Professional Documents
Culture Documents
334WE6UJH
334WE6UJH
334WE6UJH
Resource assignments
Labor Resources – are used to calculate Units % Complete
Nonlabor Resources – are used to calculate Units % Complete
Material Resources – are not used to calculate Units % Complete
Expense assignments – are not used to calculate Units %
Complete
If you are familiar with the Microsoft Project, it might help to say that
P6’s units are similar to MSP’s work, and P6’s Units % Complete is
similar to MSP’s % Work Complete.
Actual units is the sum of the labor units and nonlabor units, and
remaining units is equal to the sum of the remaining labor units and
remaining nonlabor units.
It simply shows that how much of the units are actualized so far. The
following figure shows a sample calculation.
As you can see in the previous figure, when the units are not distributed
uniformly, the resulting Units % Complete will not be equal to the ratio of
the actual duration to the total duration.
The following figure shows a sample executing which does not follow
the plan. The redistribution of the units is based on an imaginary
tracking method and you should not worry about that; the only purpose
of this figure is to show the calculation of Units % Complete with
changing values.
Units % Complete VS. Duration % Complete
Samples
Now that you know the formula behind the Units % Complete, let’s have
a final review by looking at some sample screenshots of the Primavera
P6.
This plan has only one activity. This activity has three resources, two
labor and one nonlabor resource. Each assignment has 32 units. One
assignment’s curve is “Early Peak”, another is “At Start” and the third
one’s curve field is empty, which is equal to uniform distribution.
Let’s open the Activity Usage Spreadsheet in bottom:
Here we can see the amount of units planned for each period. Now
assume that one day is passed according to plan. I check the Actual
Start checkbox of the activity, reschedule it for the second day, and
input 3 days for the Remaining Duration. This would be the result:
As you can see, we have some actual units in the first day and some
remaining units in the remaining three days. I’ll calculate the parameters
based on the data from the above figure:
Now let’s put the Gantt chart away and check the Units % Complete
field in the table:
The current Units % Complete is, as we calculated before, 48.33%,
which is much higher than the current Duration % Complete (25%).
That’s because our units were not uniform. We can check the units’
distribution in the Activity Usage Profile view:
The above figure shows the distribution of the Labor units. Nonlabor
units are shown in the next figure:
Aggregation of these two profiles is still front loaded, which causes the
Units % Complete to have a higher value in the first day.
Summary