0020 R NDT Personnel and Procedures Verify valid personnel qualification and procedures.
0030 R Procedures and Personnel for Metal Coating if Specified in the Verify valid personnel qualification and procedures.
P.O.
0020
0010
*** R X
In process inspection & test requirement
Non-Destructive Testing
Specification Details / Notes:
Shall be done for all welds and material as required by the
material spec. & P.O. spec. and per ASME Sec VIII, Div 1.
0020 R X Post Weld Heat Treatment After major weld repairs if required by applicable ASTM
specification.
0030 R X Welding repairs As per applicable material specification. If weld procedure is not
covered by the material spec, use ASME IX or EN 288.
0040 R X Hardness Testing For parts exposed to sour service and shall meet ISO 15156. Or
If requested in P.O. and shell meet P.O. specifications.
0030
0010
*** R X
Final inspection & test requirements
Dimensional Inspection
Specification Details / Notes:
Dimensional compliance to drawings and P.O. specifications.
Verify compliance of run out and concentricity readings.
0020 H R X Hydrostatic Test for Pressure Retaining Parts (Note 3) Duration 30 minutes at 1.5 times maximum allowable pressure
at ambient temperature.
0040 R X Product test certificate Verify mechanical and chemical data compliance to P.O.
specifications
Notes:
(1) Refer detailed instruction sheet 175 - 000003 of inspection and testing requirements for ideal use of this form.
(2) All documents must be available for the purchaser inspector review upon his request.
(3) Most parts under this 9COM are not pressure retaining parts. Hydrostatic test shall only be applicable for pressure retaining parts such as vertical
IR791100 Continued...
INSPECTION & TESTING REQUIREMENTS REVISION: 10/21/2016 CODE NUMBER: PAGE:
SAUDI ARAMCO FORM-175 REPLACES: 04/24/2016 IR791100 2 of 2
(1).VISUAL INSPECTION BY BUYER INSPECTION REPRESENTATIVE
(2) REVIEW AND VERIFICATION OF MATERIAL CERTIFICATES AND INSPECTION RECORDS
(3) SUBMISSION OF MANUFACTURING, INSPECTION AND QUALITY RECORDS
pump column and head.
End of IR791100