CULVERTS DETAIL SUMMARY

MODIFICATION DETAILS DETAILS:

Extra Added As Location


Description As Per Old Not Required (As Cancelled As per per Site Decision Changed As per Present
Alignment per new Alignment) Site Condition Requirement Pending Site Condition Status
Slab Culverts 4 0 0 0 0 0 4
Box Culverts 18 2 1 1 0 1 16
Pipe Culvert 53 3 7 1 3 1 44
TOTAL 75 5 8 2 3 2 64

CANCELLED DETAILS:
Cancelled Not Required Total
Slab Culverts 0 0 0
Box Culverts 1 2 3
Pipe Culvert 7 3 9
TOTAL 8 5 13

CURRENT DETAILS:
Decision Co-Ordinates
Completed Under Construction Pending Not Finalized Local Problem Yet to be Started Total
Slab Culverts 4 0 0 0 0 0 4
Box Culverts 12 0 0 3 0 0 15
Pipe Culvert 33 0 4 5 1 2 45
TOTAL 49 0 4 8 1 2 64

24
List of CD Structures As Per Design
S. Culvert ID Type of Size/ Dia (M) Present Status Remark-1 Remark-2
No. Culvert
For Main Road
1 116 SC 3 Completed Relief Culvert
2 269 PC 1 Completed
3 323 PC 1 Completed
4 659 PC 1 Completed
5 750 BC 2x2 Completed
6 876 BC 2x2 Completed
7 1175 PC 1 Completed
8 2331 SC 2 Completed
9 2580 PC 1 Completed
10 2750 PC 1 Completed
11 2930 PC 1 Completed
12 3172 BC 2x2 Completed Relief Culvert
13 3392 DPC 2x1 Completed
14 3640 PC 1 Completed
15 3970 PC 1 Completed
16 4198 PC 1 Completed
17 4262 TBC 2x2x2 Completed
18 4421 PC 1 Completed
19 4895 PC 1 Completed
20 4960 SC 3 Completed
21 5351 SC 2 Completed

22 5581 PC 1 Decision Pending CCPL/SHEP/STR-597 Dated 25-


Aug-2011
23 5961 PC 1 Completed
24 6143 PC 1 Completed
25 6506 PC 1 Completed
26 6621 PC 1 Completed
27 6803 TBC 2x2x2 Completed

28 6900 PC 1 Decision Pending CCPL/SHEP/STR-597 Dated 25-


Relief Culvert Aug-2011
29 7056 PC 1 Completed
30 7248 BC 6x4 Completed
31 7284 BC 6x4 Completed

32 7353 PC 1 Cancelled Chief Engineer Visit on 7th June


2011
33 7532 PC 1 Completed

34 8012 BC 3x3 Completed Location Shifted to 8018

35 8220 BC 3x3 Completed

36 8383 BC 2x2 Cancelled CCPL/SHEP/CA/L&T-498 Dated 7-


Apr-2011

37 8544 PC 1 Cancelled CCPL/SHEP/CA/L&T-498 Dated 7-


Apr-2011
38 8612 PC 1 Completed

39 8661 PC 1 Cancelled CCPL/SHEP/CA/L&T-498 Dated 7-


Apr-2011
40 8884 PC 1 Completed
41 9040 PC 1 Yet to be Started Relief Culvert
42 9211 PC 1 Completed
43 9682 PC 1 Completed
44 9790 PC 1 Cancelled Cancelled at Site by BA Wani
45 9898 BC 3x3 Completed
46 10031 BC 3x3 Completed

47 10196 PC 1 Cancelled Chief Engineer Visit on 7th June


2011
48 10394 BC 3x3 Completed
49 10578 PC 1 Completed
50 10662 PC 1 Completed

51 10935 PC 1 Cancelled Chief Engineer & XEN Visits in


Nov'11
52 11073 PC 1 Yet to be Started
53 11214 PC 1 Coardinates not Finalized Relief Culvert
54 11785 BC 2x2 CTC Submitted
55 12071 BC 2x2 Coardinates not Finalized Relief Culvert Revised to 12074
56 12275 PC 1 Coardinates not Finalized Revised to 12297
57 12725 PC 1 Coardinates not Finalized Revised to 12733
58 13040 PC 1 Coardinates not Finalized Revised to 13042
List of CD Structures As Per Design
S. Culvert ID Type of Size/ Dia (M) Present Status Remark-1 Remark-2
No. Culvert
59 13110 BC 2x2 Coardinates not Finalized Revised to 13114
60 13490 PC 1 Coardinates not Finalized Revised to 13364
61 13970 BC 3x3 Not Required
62 14175 BC 3x3 Not Required
63 14320 PC 1 Not Required
64 14550 PC 1 Not Required
65 14630 PC 1 Not Required
For Right Bank Portal Road

66 120 PC 1 Cancelled With out any letter, Reason is Not


Relief Culvert Necessary.
67 378 PC 1 Completed

68 955 DPC 2x1 Decision Pending CCPL/SHEP/STR-597 Dated 25-


Aug-2011

69 1055 DPC 2x1 Completed Location Shifted to 1096

70 1255 PC 1 Yet to be Started


71 1453 PC 1 Completed
72 1721 PC 1 Completed
73 1923 PC 1 Completed
74 2201 PC 1 Completed
75 2368 PC 1 Completed
New Culverts Incorporated as per Site requirement
76 2432 RBP DPC 2x1 Completed
77 13653 BC 2x2 Coardinates not Finalized Relief Culvert

Note. 1. BC = Box Culvert Cancelled


2. PC = Pipe Culvert Decision Pending
3. SC = Slab Culvert Location Shifted
4. TBC = Twin Box Culvert Extra Added
5. DPC = Double Pipe Culvert Not Required

You might also like