Professional Documents
Culture Documents
ER-670
Research Project 580
Prepared by
q
HOLT/PROCON
(A Joint Venture of The Ben Holt Co. and Procon Incorporated)
201 South Lake Avenue
Pasadena, California 91101
Principal Investigators
Ben Holt
Edward L. Ghormley
LEGAL NOTICE
This report was prepared by Holt/Procon (a Joint Venture of The Ben Holt Co. and
Procon Incorporated), as an account of work sponsored by the Electric Power Re-
search Institute, Inc. (EPRI). Neither EPRI, members of EPRI, Holt/Procon, nor
any person acting on behalf of either: (a) makes any warranty or representation,
express or implied, with respect to the accuracy, completeness, o r usefulness
of the information contained in this report, or that the use of any information,
apparatus, method, or process disclosed in this report may not infringe privately
owned rights; or (b) assumes any liabilities with respect to the use of, or
for damages resulting from the use of, any information, apparatus, method, or
process disclosed in this report.
ABSTRACT
The plant design provides flow diagrams and equipment specifications for the
"a\ energy conversion system, the cooling water system, the plant and instrument
air system, the flare system, the firewater system, the electrical system, the
2 piping system, instruments and controls, and buildings and structures.
iii
L,
TABLE OF CONTENTS
Section -
Page
1 SUMMARY 1-1
2 INTRODUCTION 2-1
.- 3-26
3-27
3-28
- BINARY PROCESS
DIAGRAM GEOTHERMAL DEMONSTRATION
START OF RUN 3-29
- BINARY PROCESS FLOW
3-30
V
TABLE OF CONTENTS
Section Page
4 DESCRIPTION OF FACILITIES 4-1
,
PLANT LAYOUT 4-2
ENERGY CONVERSION SYSTEM 4-3
COOLING WATER SYSTEM 4-5
PLANT AND INSTRUMENT AIR SYSTEM 4-6
FLARE SYSTEM 4-7
FIRE WATER SYSTEM 4-8
ELECTRICAL SYSTEM 4-9
PIPING 4-9
INSTRUMENTATION AND CONTROL 4-10
BUILDINGS AND STRUCTURES 4-12
DRAWING NO. 7523-E-3242, REV. C - BINARY PROCESS
GEOTHERMAL DEMONSTRATION PLANT PLOT PLAN 4-15
DRAWING NO. 7523-E-3215, REV. C - BINARY PROCESS P&ID
GEOTHERMAL DEMONSTRATION PLANT, HEBER,
CALIFORNIA 4-17
DRAWING NO. 7523-E-3246, REV. C - BINARY PROCESS
COOLING WATER PGID GEOTHERMAL DEMONSTRA-
TION PLANT, HEBER, CALIFORNIA 4-19
DRAWING NO. 7523-E-3221, REV. C - INSTRUMENT & PLANT
AIR P&ID GEOTHERMAL DEMONSTRATION PLANT 4-21
vi
TABLE OF CONTENTS
Section -
Page
vi i
W Section 1
SUMMARY
i
Chevron Oil Company (the field operator) predicts that the reservoir
ill decline from an initial mperature of 182 C (360 F) to a
ture of 162 C (325 F eriod of 25 years at a production
rate of 200 MWe. Accordingly, th t has been designed so that it may
economically be modified to accommodate the increased brine
and increased working fl lation at the lower reservoir
temperature while still maintaining a net output of 50 W e .
1-1
L,
A working fluid containing 20 percent i'sopentane and 80 percent isobutane was
selected for the initial operating conditions. When the fluid temperature
declines to 174 C (345 F), the working fluid is changed to a hydrocarbon
mixture containing 10 percent propane and 90 percent isobutane. This fluid
will operate efficiently in the temperature range from 174 C (345 F) to 162 C
(325 F ) .
1-2
U
mid-range plant operating condition. Piping and instrumentation diagrams
have been revised and expanded to reflect the improved plant design. Prelimi-
nary piping layout drawings have been prepared and, as a result of these
studies, the plot plan has been enlarged to provide space for future equipment
additions and the large interconnecting pipelines.
Electrical single-line drawings have been revised to reflect the latest plant
configuration. Equipment specifications have been modifed to meet the require-
ments of the new hydrocarbon mixture working fluid. Preliminary layouts and
specifications have been prepared for the buildings and structures at the
site.
An implementation plan for the design and construction of the plant has been
prepared in a separate volume which includes:
0 A schedule for applications and permits
0 A schedule for engineering and construction
0 A critical path schedule showing the time sequence of the
critical function affecting plant completion
The preliminary environmental assessment was revised and updated to show the
* effect of construction of a single 50 MWe geothermal plant, and the effect
of 4000 MWe of geothermal capacity would affect the Imperial Valley, and the
. Heber area in particular. The environmental assessment is presented in
separate volumes.
1-3
Section 2
INTRODUCT101
The conclusions reached as a result of the Part A studies were that the Heber
reservoir in the Imperial Valley is the preferred location for a demonstration
plant,
- that the binary cycle is the preferred process, that a 50 MWe plant is
the preferred size, and finally that the proposed project is feasible from a
geotechnical, technical
0 Trade-off s t u d i e s
0 Baseline configuration description
0 Plant requirements document
0 Equipment specifications
0 Capital cost estimate
0 Long lead items procurement s p e c i f i c a t i o n s
2-2
Section 3
DEVELOPMENT OF DESIGN
SITE DESCRIPTION
Location
3-1
Climate
Prevailing winds are generally below 7 m/sec. (15 miles/hour) and from t h e
west. Average d a i l y r e l a t i v e humidity ranges between 20 and 30 percent.
Topography
Geology and S o i l s
Water Supply
Access
A light-duty paved road runs north/south along the east boundary of the plant
site. Also, a Southern Pacific railroad track running north-northwest/south-
southeast lies within 1 km east of the plant site. Rail sidings presently
exist at Heber, 2 km to the north.
Transmission Lines
The Imperial Irrigation District plans to build a 33 kv substation near Heber,
about 2 km north of the plant site. A 33 kv transmission line would be built
by Imperial Irrigation District from the plant substation to the substation at
Heber to carry electrical energy in and out of the geothermal demonstration plant.
DESIGN BASIS
The previously reported feasibility studies showed that it would be techni-
cally and economically feasible to build a demonstration plant at Heber,
sing the binary conversion process to generate electric power.
d that the plant should be built in the range of SO W e elec-
trical capacity in order that the cost of power produced from the plant would
ompetitive with methods of generating electric
2
%
reported to hav temperature of 182 C (360 F).
y has predicte rature of the brine would
re to a temperature
u
3-3
The r e s e r v o i r f l u i d has a t o t a l dissolved s o l i d s content of about 15,000 ppm.
b
No accurate analysis has been made t o determine t h e quantity of noncondensable
gases i n t h e r e s e r v o i r f l u i d , but a program i s c u r r e n t l y i n progress t o d e t e r -
mine t h e quantity and analysis of such gases i f they are present. The f i e l d
tests conducted by Chevron i n d i c a t e t h a t t h e noncondensables ( i f any) w i l l
remain i n s o l u t i o n i n t h e hot water and w i l l be r e i n j e c t e d with t h e hot water
back t o t h e r e s e r v o i r .
Heat exchanger tests performed by t h e San Diego Gas & Electric Company a t
Heber showed t h a t t h e s a l t s present i n t h e f l u i d form s c a l e a t a n e g l i g i b l e
r a t e a t temperatures above 132 C (270 F), but below t h a t temperature fouling
occurs a t an increased rate. From t h e i r d a t a w e estimated t h e following tube-
s i d e fouling f a c t o r s which were used i n t h e design of brine/working f l u i d heat
exchangers:
The previous exchanger t e s t s were conducted using titanium, 90% cupro nickel
and mild steel exchangertubes. No corrosion was observed on t h e titanium
tubes a f t e r 560 hours' exposure; some corrosion occurred t o t h e cupro nickel
tubes a f t e r 200 hours' t e s t i n g ; and s l i g h t p i t t i n g and surface decarbonization
were observed on t h e carbon steel tubes a f t e r 560 hours of t e s t i n g . It is
possible t h a t t h e s l i g h t corrosion of t h e steel tubes had occurred p r i o r t o
t h e t e s t program. Chevron has indicated t h a t corrosion during t h e i r test work
was negligible. Accordingly, we have specified t h e use of steel i n a l l
Lid
3-4
LiiJ ' equipment exposed to brine. A final decision on materials will be made on the
basis of the test program currently in progress.
Summer time dry bulb ambient temperatures vary up to 49 C (120 F). One per-
cent of the time during the summer months, the wet bulb temperature reaches
or exceeds 27 C (80 F). This wet bulb temperature was used for design.
PROCESS DESIGN
3-5
Thermodynamic Cycle Studies
The initial phases of the.processdesign are reported in detail in the
"Thermodynamic Cycle Analysis" section of "Energy Conversion and Economics
for Geothermal Power Generation at Heber, California; Valles Caldera, New
Mexico; and Raft River, Idaho - Case Studies" (Energy Conversion Study). The
selection of the final working fluids for Heber was done in the same general
manner as the initial screening study, described in the Energy Conversion
Study.
Figure 3-1 provides a summary of the procedures which led to the selection of
the final process design. This figure shows graphically the relationship
between reservoir temperature and net power output for a number of working
fluid compositions. Each of these curves has been optimized with respect to
turbine inlet pressure and temperature.
Curve A represents the thermodynamic performance of the best fluid for the
start-of-run conditions as a result of the initial study for the Energy
Conversion Study. This cycle is favored at 182 C (360 F) but the performance
drops off sharply at lower temperatures. Likewise, Curve B shows the per-
formance of the preferred end-of-run case in the Energy Conversion Study.
u
3-6
Li This cycle, which is optimum for 163 C (325 F), performs poorly at higher
temperatures. Curve C shows the performance of the 6est three-component cycle
that we studied. It shows significantly lower performance than most of the
two-component cycles. Curve D illustrates the performance of the best case
we found in our study. However, it was rejected because the expansion would
have precipitated excessive liquid in the turbine. (Parenthetically, it
appears that the development of a turbine capable of operating in the two-
phase region without loss of efficiency is a worthwhile objective.)
The process design of plants for mid-run and "off design" conditions involves
t a great deal of complexity. First, the design must be optimum at the given
brine temperature of interest. Second, the process must perform well at
brine temperatures on either side of the optimum. Third, the cycle must
with cycles on either side. This means that flow rates, operating
llmeshll
pressures, heat exchanger surface areas, etc. must be consistent so that in
operating a geothermal plant, a smooth transition can be made from one
process to the next. It was found that the entire desired operating range from
182 C (360 F) to 163 C (325 F) could be accommodated by two cycles with a
switchover occurring when the brine was at 174 C (345 F).
Curves E and F show the performance of the two cycles for the start-of-run
and end-of-run designs which were finally adopted. The discontinuity of
these curves at 174 C (345 F) is an artifact of the assumptions used in the
5
In actual practice, the heat exc surface requirements for the
-run case actually decrea g brine temperature due to a
in the log-mean t difference (LMTD). Since the
c
will not be reduced in size from the initial installation,
the lower temperatures, an excess of hea sfer surface.
a more effective utilization of the brine will allow a
rs as heat ex
temperature approach was also investigated. These studies are described in
detail in the section of this report dealing with the trade-off studies.
3-7
Process Flow Diagrams
Drawing 7523-D-3260 is a process flow diagram for this plant at the start-of-
run conditions. The process flow diagram shows principal items of equipment
and presents heat and material balances for the hydrocarbon working fluid and
reservoir fluid.
Reservoir Fluid
Temperature 182 C (360 F)
Flow Rate 3.05 x 106 kg/hr (6.72 x 106 lbs/hr)
The hydrocarbon liquid is preheated and vaporized by heat exchange with the
brine reservoir fluid at a pressure of 3447 kPa (500 psia) and to a tempera-
ture of 146 C (295 F). The super-critical vapor drives an expansion turbine
connected to an electrical generator. Exhaust vapor from the turbine is con-
densed in a group of water-cooled exchangers and collected in accumulators.
The liquid hydrocarbon is pumped at elevated pressure back through the heat
exchangers, completing the cycle.
3-8
LJ We s e l e c t e d a hydrocarbon mixture consisting of 10%propane and 90% isobutane
f o r t h e middle-of-run condition. Drawing 7523-D-3275 i s a process flow dia-
gram showing t h e operation of t h e p l a n t using t h e middle-of-run f l u i d . Perti-
nent design d a t a are as follows:
Reservoir Fluid
Temperature 174 C (345 F)
Flow Rate 6
3.48 x 10 kg/hr
(7.66 x lo6 lbs/hr)
Hydrocarbon Working Fluid
Composition 90% isobutane
(Mole basis) 10%propane
Flow Rate 6
4.09 x 10 kg/hr
6
9.03 x 10 lbs/hr)
Gross Generator Output 65 MWe
In-plant Load 15 MWe
-
N e t Power Output 50 M
W e
I
f i e l d t o handle t h e increased flow. In addition, one condenser w i l l be added
and t h e cooling tower enlarged by 43%. These modifications w i l l be s u f f i c i e n t
f o r t h e remaining l i f e of t h e ect and no f u r t h e r equipment additions w i l l
be necessary.
3- 9
6 6
increase to 4 . 4 7 x 10 kg/hr (9.86 x 10 lbs/hr). However, the rate of circu-
ti
lation of the working fluid remains constant.
TRADE-OFF STUDIES
Sufficient design work was performed in Part A of this project to show that
the binary process was the optimum process for generation of power at the
Heber reservoir. In Part B of this project detailed trade-off studies have
been performed to define the effect of the following variables on the cost
of power produced:
0 Minimum temperature difference (pinch) in the brine/hydro-
carbon exchangers
0 Log mean temperature difference in the hydrocarbon condenser
0 Cooling tower approach to the atmospheric wet bulb temper-
ature
0 Cooling water temperature rise
0 Selection of motor or turbine drives for process pumps
Method of Approach
Each of the above variables was studied over the expected range of operating
feasibility. The method of approach was to estimate capital and operating
costs for the plant and for the field installation at each assumed condition.
These costs were then used as input data to the economic analysis program
developed as part of the Energy Conversion Study. The selected variable
which gave the lowest power cost was deemed to be the optimum.
To obtain estimates of plant costs, the following sections of the cost esti-
mate presented in the Energy Conversion Study were selected for estimation:
major equipment, concrete, piping and electrical. The other sections, site
preparation, structural, instrumentation, insulation and painting are rela-
tively insensitive to changes in process conditions and are assumed to be
constant.
3-10
Total p l a n t c o s t s were estimated by employing f a c t o r s developed i n t h e base
c o s t estimate.
3-11
Ld
t h e pinch temperature difference i s increased by r a i s i n g t h e r e t u r n temper-
a t u r e of t h e brine t o t h e f i e l d , t h e c o s t of t h e brine-hydrocarbon exchangers
decreases a t t h e expense of higher b r i n e rates. As shown i n Table 3-1, with
an increase from 5.5 C pinch t o 11.1 C pinch, t h e cost of t h e exchangers
drops from $1,570,000 t o $815,000 reducing by 4.4 percent t h e c a p i t a l c o s t of
t h e plant. The brine requirements increase 10.5 percent, r a i s i n g t h e t o t a l
f i e l d cost from 6.5 percent, from $11,460,000 t o $12,210,000. Power conver-
sion c o s t s reflect t h e lower p l a n t c o s t s , while energy ( f i e l d r e l a t e d ) c o s t s
go up. The additional energy c o s t s o f f s e t t h e savings i n p l a n t r e l a t e d
expenses, r e s u l t i n g i n increased t o t a l power c o s t s as t h e temperature pinch
increases.
The reduction in the turbine outlet temperature from 56.1 C (133 F) to 54.4 C
(130 F) increases the power output from every pound of working fluid used,
causing a 4 percent reduction in both hydrocarbon circulation and brine rate.
The cooling water circulation drops by 5.4 percent. As shown in Table 4,
these changes have relatively little effect on related equipment costs. At
the same time, the closer approach to wet bulb causes the cooling tower cost
to increase 65 percent, from $1,000,000 to $1,650,000. The net effect is a
significant increase in plant cost and a slightly more than compensating
decrease in field cost. We conclude that the small saving (0.14 mills/kwh)
W
3-13
i n power c o s t as t h e approach t o wet bulb i s reduced involves a measure of
r i s k i n t h a t we are requiring superior performance of t h e cooling tower
r a t h e r than normal performance. For t h i s reason w e s e l e c t e d a 5.5 C (10 F)
approach f o r preliminary design.
3-14
The f a c t o r s involved i n t h e determination of t h e optimum included c o s t ,
a v a i l a b i l i t y and operational f l e x i b i l i t y . Five a l t e r n a t e pump systems com-
bining t h e above v a r i a b l e s were s e l e c t e d f o r t h e study. Piping schematics
of t h e a l t e r n a t e s a r e shown on Figure 3-2. A b r i e f description of t h e a l t e r -
n a t e s follows:
3-15
Turbine d r i v e r s were considered as operating i n p a r a l l e l with t h e plant
turbine-generator set handling t h e hydrocarbon vapor a t t h e same i n l e t and
o u t l e t conditions, thus reducing t h e required size of t h e turbine-generator
set.
3-16
due t o fewer number of systems i n p a r a l l e l . I n cases where two pumps are
connected i n series, a f a i l u r e of e i t h e r pump would remove t h e other from
operation.
ECONOMIC ANALYSIS
Capital Cost
?
The updated i n i t i a l c a p i t a l c o s t is presented i n Figure 3-3. The estimated
c o s t is $29,634,000 as compared with t h e earlier estimate of $28,500,000.
b
This estimate is prepared on t h e same b a s i s as t h e earlier one. I t reflects
changes i n design and i n some cases improved accuracy. The major differences
between t h e two estimates are as follows:
3-17
!
c,
0 Construction items increased by about $750,000. This reflects
a reduction in the cost of pipe, valves and fittings and an
increase in the cost of concrete, both changes resulting from
a more accurate material take-off than before.
0 Fee, contingency and escalation were increased in proportion
to total plant cost.
I
This estimate, like the earlier one, is for a battery limits plant. Excluded
from the cost are the following:
0 Cost of field collection and reinjection facilities
0 Cost of electrical transmission facilities to a load-
center
0 Cost of land
0 Costs incurred by the Owner for managing the project and for
obtaining the necessary permits to construct.
0 Cost of royalties, if any
0 Interest and taxes during construction
As before, the estimate assumes that the project will be completed by late
1979 and escalation is estimated on this basis.
Cost of Power
The performance of the plant has been improved slightly over the base case
that was reported in.the Energy Conversion Study. As a result, the geothermal
fluid requirement of the plant is reduced, and consequently, the fuel cost
at the plant is reduced. Because of the increase in capital, the
3-18
conversion cost increases over the base case. A comparison of the base case
and the preliminary design case is as follows:
This Case Base Case
Mi11s/kwh Mi11s/kwh
Cost of Energy 16.53 16.60
Cost of Power Conversion 19.03 18.25
Cost of Transmission 0.28 0.28
Total Cost 35.84 35.22
3-19
A - 50/50 ISOBUTANE-ISOPENTANE
Li
B - 35/55 PROPANE-ISOBUTANE
C - 20/60/20 PROPANE-ISOBUTANE-ISOPENTANE
D - 80/20 ISOBUTANE-ISOPENTANE
E - 80/20 ISOBUTANE-ISOPENTANE
F - 10/90 PROPANE-ISOBUTANE
1 I I I
165 170 175 180
3-20
CAPACITY:
9700 GPM
CAPACITY 9700 GPM €A
4r c
1252 GPM
CAPACIT*
ALTERNATE
fi CAPACITY:
145006PI.l
boooclp
I I
I
ALTEKNATE P
3-21
CUSTOMERElectric Power Research Institute
LOCATION- REV. NO. DATE 10/1/76
ACCOUNT Materials Subcontract Labor TOTAL
I100 Columns (incl. trays)
1200 Pressure Vessels 230,000 230,000
1300 Heat Exchangers 3,252,000 3,252,000
1400 Furnace/Heaters
1500 Pumps 1,144,000 1,144,000
1600 Boilers
1'100 Cooling Towers 1,150,000 1,150,000
I800 Turbine-generator 3,593,000 3,593,000
1900 Water Treatment 201,000 201,000
2800 Other 134,000 134,000
Labor 143,000 143,000
Freight 350,000 34,000 384,000
iU6-TOTAL 23,523,000
Escalation 2,700,000
3-22
U
Table 3- 1
-~
PINCH POINT 5.5 C (10 F) 8 . 3 C (15 F) 11.1 C (20 F)
3-23
Table 3-2
LOG MEAN TEMPERATURE DIFFERENCE 6.1 C (11 F) 11.7 C (21 F) 17.2 C (31 F]
3-24
Table 3-3
3-25
i
Table 3-4
3-26
Table 3-5
COOLING WATER TEMPERATURE RISE 6.1 C (11 F) 11.7 C (21 F) 18.3 C (33 F)
k,
3-27
I - -
I
Table 3-6
HYDROCARBON CIRCULATION PUMP STUDY
NOTES :
ALTERNATE I - six vertical pumps in parallel, motor drive
ALTERNATE I1 - three vertical pumps in parallel, motor drive
ALTERNATE I11 - three vertical pumps in parallel, one motor drive and two turbine drive
ALTERNATE IV - (a) motor driven vertical pump in series with motor driven horizontal pump and turbine driven horizontal pump in
para1le1
(b) motor driven vertical pump in series with turbine driven horizontal pump
ALTERNATE V - motor driven vertical pump in series with motor driven horizontal pump, two systems in parallel
6- C'
c
Y
RCPERENCC DRAW1110
E2 !k! C 3 -ID. "ru
rumewe GENERATOR CONDENSCR YC. ACCUHULATOR COOLlNO l D W E R I
w
I 1
I
h)
rD
E!
Y.C CIRCULATION PUMP
b 1
E-1
3
P
w
I
w
0 I I I
-
P-I
Y.C. CIRCULATION PUMP
-
P-2
C.W. U R C U L I T I O N PUWP
WI 1111- oL (* mTGEOTHERMAL
8IUARY PROCE59 FLr 'I D I A 6 R A M
'In'
DIMOLISTRAATIOU P L A N T
A IMMD CDR PRIYUIU4RY OnIOU IW P Y D N V
I I I ,I- ,-am"
MIDDLE OF RUU
c
Section 4
DESCRIPTION OF FACILITIES
Plant layout
Energy conversion system
Cooling water system
Plant and instrument air system
Flare system
Fire water system
Electrical system
Piping
Instrumentation and control
Building and structures
The following preliminary design drawings are included as a part of the re-
port.
Plot plan
Piping and instrumentation diagrams for the following systems:
4- 1
PLANT LAYOUT
The p l o t plan f o r Heber i s shown i n Drawing No. 7523-E-3242. The tlNorthll
d i r e c t i o n shown on t h i s drawing i s a plant-north. The a c t u a l o r i e n t a t i o n of
t h e p l a n t w i l l not be determined u n t i l a s p e c i f i c p l a n t s i t e is selected.
The p l a n t contains four major, c l e a r l y defined functional areas as follows:
4-2
u When additional geothermal p l a n t s are constructed, each p l a n t w i l l be located
adjacent t o i t s own producing wells. The p l a n t s w i l l be adequately separated
so t h a t t h e r e w i l l be no interference between adjacent p l a n t s .
4-3
The generator i s designed t o produce 65 W e with an estimated e f f i c i e n c y o f
98%. This capacity i s adequate t o meet t h e end-of-run power requirements o f
t h e p l a n t and s t i l l produce 50 W e o f n e t power.
\
4 -4
ti Hydrocarbon Condensers -1 exchanger s h e l l i n p a r a l l e l
Hydrocarbon c i r c u l a t i o n pumps -1 pump i n p a r a l l e l
The cooling water system i s shown on piping and instrument flow sheet No. 7523-
E-3246. The major equipment c o n s i s t s o f t h e c i r c u l a t i o n pumps, cooling tower,
basin, and t h e make-up water puplps. The water treatment s e c t i o n c o n s i s t s of
sand f i l t e r , f a c i l i t i e s t o add a c i d , chlorine, corrosion i n h i b i t o r , and disper-
s a n t , and an automatic control t h a t monitors and maintains t h e q u a l i t y of t h e
c i r c u l a t i n g water. The individual equipment s p e c i f i c a t i o n s can be found under
S p e c i f i c a t i o n s , Section 5 of t h i s r e p o r t .
4-5
e r a t u r e decreases and t h e process conditions change, a fourth pump w i l l be
added. The pump p i t has been designed f o r t h e addition of t h e f o u r t h pump.
A v e r t i c a l type make-up water pump has been selected. The water w i l l be taken
out of an i r r i g a t i o n canal and, a f t e r a preliminary screen f i l t r a t i o n , w i l l be
pumped through sand f i l t e r s on i t s way t o t h e cooling tower basin. The make-
up water rate was determined based on evaporative and d r i f t l o s s estimates and
a blowdown rate consistant with a four f o l d concentration of s o l i d s i n t h e
cooling water.
The plant and instrument a i r system is shown on piping and instrumentation flow
sheet No. 7523-D-3221. Separate a i r systems are provided f o r p l a n t and i n s t r u -
ment a i r . A manual cross over i s provided between t h e systems so t h a t an
I operator could use plant a i r i n t h e instrument a i r system i f t h e instrument
a i r system should f a i l .
4 -6
U
The compressed instrument a i r w i l l be cooled and condensables removed before
it flows t o a surge drum. Further separation of condensables occurs i n t h i s
drum. The a i r then flows through an all-purpose f i l t e r t o remove other foreign
materials. The a i r i s then d r i e d t o a -4OC dewpoint i n regenerative s o l i d des-
iccant beds, and f i l t e r e d before being used.
FLARE SYSTEM
D
ispersion of t h e gaseous
e f f l u e n t s , such t h a t ground level concentrations of any p o l l u t a n t generated
w i l l be below regulatory l i m i t a t i o n s .
W
4-7
To prevent accumulation o f hydrocarbons heavier than air, a hydrocarbon analy-
Li
zer with alarm mounted on t h e control panel, w i l l be i n s t a l l e d a t t h e foot of
t h e flare stack.
The f i r e water supply i s taken from t h e cooling tower basin. This supply w i l l
l a s t about t h r e e hours a t t h e maximum f i r e water flow rate without make-up.
The rate of t h e water make-up t o t h e cooling tower i s about equal t o t h e con-
sumption of t h e f i r e water system.
4-8
'6) ELECTRICAL SYSTEM
The 3 phase 480V, 2500 KVA in-plant system i s outlined i n Drawing No. 7523-D-
3603 and D-3604. A 13.8 KV/480V transformer, Substation C y feeds power t o t h e
480V switchgear. Two motor control centers, MCC-A and MCC-B are fed from t h e
480V switchgear. Power from MCC-A and -B w i l l d r i v e cooling tower fans, water
treatment system motors, a i r compressors and make-up pumps, provide indoor
and outdoor l i g h t i n g and instrumentation and control power.
PIPING
4-9
The above piping drawings were prepared i n order t o e s t a b l i s h major equipment LJ
and piping locations which provide a b a s i s f o r estimating p l a n t construction
costs. The drawings are preliminary i n nature, therefore, piping and equip-
ment locations established during f i n a l design may vary somewhat from those
shown.
i
Piping design s p e c i f i c a t i o n s are included i n Section 6 of t h i s report.
Instruments for supervision of the plant will be centralized at the main con-
trol panel. The panel will have a semi-graphic section with color-coded sym-
bols illustrating the complete process. Indicators, recorders, controllers,
motor control stations, etc., will be arranged logically to facilitate overall
control of the plant operations from this location.
arbon analyzers will be instal d in the heat exchan brine outlet and
arbon condenser cooling water et t o check fo
1eakage.
ss instrument systems wile electronic with 4 to 20 m
mission signals. Panel mounted instruments for these systems will be miniature
types.
The control panel will be a vertical free-standing unit of welded steel con-
struction. It will be shop-fabricated and tested completely before shipment
4-11
Li
to the jobsite. No process fluids will enter the panel. Electrical power at
the panel will be limited to nominal 120 volts.
Low voltage DC signal wires (4-20 ma, thermocouples, etc.,) will be twisted
pairs and will be run in separate conduit and raceways from AC wiring. Thermo-
couple extension wires will be continuous from the primary element to the cold
junction.
There will be three buildings in the plant. The largest will be the office
and control building measuring 85' x 50' and approximately 15' high. The
interior will be paritioned into a control room measuring 40' x 35', and add-
itional rooms housing the switchgear, office, instrument and electronic main-
tenance, and laboratory areas. The building will be located next to the
turbine/generator area, will have a door opening to the operating area, and
have windows located so that the operators can maintain visual contact with
the major equipment areas. A heat pump will supply heating and cooling for
all the areas in the building.
As the office and control building will have many visitors, special attention
will be given to its appearance through the use of architectural treatment.
i
4-12
The o f f i c e and control building w i l l have walls of concrete block. The roof
w i l l be bondable build-up type over insulation.
4-13
/
1' .
c
I
I
I
q--
I
I
1
I
I
I
I
I
I
I
I
I
I
F
1 %
I:
li
I
I
I
1
1
I I
I I
I I
I I
I I
I I
I I
I I
I I
I I
I I
I I
I I
I I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
9
3
8' I
-- - . _
REFERENCE D R A W I N G
)I DRAWlNG NO. TITLE
TACK
14o?O'aJmALL I
UCICI~T
8
.
I
1
I
I
t
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I 'k'
//
:
:
95
'
Y- OrC"
W W AP :I24 H I
E
4-23
REFERENCE D R A W I N G
I
I
I
I
I
I
tI I t
I
1
I
I"
I S
I I ! I
.-
I
e I i
4-25
i
I
1
. I- __-
--- 1
I
I
I
I
I----
1
I
u I
D
P z
I -I
N
I
I
I
,
I
i
1
I
,
j
I
REFERENCE DRAWING
DRAWINGNO I TITLE
I I
I
'
I
P
4-29
\
E
w II
!!
I
I
---1
M
M
I
e
t
-
--I._-
I r---
i
\
:
3
Ln
M
I
d
I'
11
uon- I
I
I
L-.!
- 1
I
I
I
I
I
I
I
I
I
I
1
b
M
I
d
1 1 1
I '
i I
------
6- j-- # - i
i
I
I
I
I
I
I
--I I I
I
I J l !
Q p'-'*
.
I I 1:o
I
I
t
LE
I
M
d
I
d
J
.u
I
L=
i
L
1
r--
I
i
-4
I
I
I
I
I
I
1
I
I
I
I
I
1
I
I
I
I -
I
I
I
I
I
I
I
I
I
I
l l
Ln
d
I
d
I I@-- - -
.0-,11
.--I
- - . ---- - _ _ I _
-I- ‘ €
I 1 P
c INSTRUMENT SYMBOLS PtPlNG ANDEQU1PMENTSYMBOI.S
5 AIR COOLCDUUIT
'eurTWP
rnmuuam.
REFERENCE DRAWING
nw
Y
iDu)wDowu
RUPWPa DISC ilU
4mm
IU
DHD
XIION
XCMOOWU VALVE
5wuTbovvU
@ iumcAm*l(i COUTWUC~R
& *mew PUMP
&
FLOW
I
R t C I P O a T I U Q WMP
@ hbw ORIFICE (RESTRICTION)
e
@
FLOW MCtOP WITH IUDICA;K)R
~ ~ s ~ onJRncanwt
n v e
PWWPeCORDCR
&- B U R PUMP
eoKco DWWDOWU OR
Y- R 4 W R U VALVE
8 FLOW PtCOPOlUG COWROLLER SUMP PUMP
6 FLOW JwlrcH
.-Y CORLYW
L CORWW
!AKCR
Q ROTARY PUMP
JHN
- UtW LWI
.--- CrnURE
RLVIYI
;SUED FOR
c
Section 5
EQUIPMENT SPECIFICATIONS
bd EQUIPMENT LIST
SHEET
REvsion
1
DATE
OF .7
S-1
SHEET OF 3
5-2
3 -~
3
W
SHEET OF
5-3
EQUIPMENT LIST
SHEET
REVISION DATE
OF 7
c
CONTRACT No. 7571 CUSTOMER Electric Power Research Institute
Pressure Gage w/
~-~
Pressure Transmi
Pressure Transmit
P r e s s u r e - R A MVal=-
Pressure Relief Valve,
5-4
W SHEET * OF
5 -5
SHEET 3 OF
i'
c
5-6
OF 7
-
W EQUIPMENT LIST
SHEET
REVISION DATE
5-7
SHEET
5 OF
Flow
-
FS ~- ~
Flow Switch, In-line 1 - __ __
5 -8
SHEET OF 7
EQUIPMENT LIST REVISION DATE
5-9
EQUIPMENT LIST REVOION DATE
5-10
hd
~~~
HORIZONTAL VESSEL DESIGN DATA
~~ ~
1 NOZZLE SCHEDULE
CODE STAMP AW qpCt VIII MARK SIZE RATING SERVICE
OTHER SPECS.: Nl 18" 150# RF HC In
DESIGN PRESS.AT TEMP. 165 PSI AT450 OF N2 18" 150# RF HC In
OPER. PRESS. AT TEMP. 56 PSI AT104 OF
STRESS RELIEVINO per Code
WELD EXAMINATION 4" 150# RF HC Makeup
1508 RF PSV
3000# Cplg I PI
3000# Cplg ,";y;,";&!
3000# Cplrr Level Alan
150# RF HC Out
3000# Cplg ' TI
3000# Cplg lev vel Indic
PT
Equalizing
-# RF Manwav
REMARKS Geothermal Demonstration Plant
Heber, California
Hydrocarbon Accumulator
V-201A,B,C,D
VESSELS
5-12
VESSELS
VERTICAL VESSEL DESIGN DATA
CODE STAMP ASME Section VI11
OTHER SPECS.:
DESIGN PRESS.AT TEMP. 165PSI AT 450 O F
OPER. PRESS. AT TEMP. 134 PSI AT 120 OF
STRESS RELIEVING Per Code
WELD EXAMINATION
INSULATION None
C0RR 0 S ION ALL0WA NCE 1116"
MATERIALS
SHELL
HEADS
INTERNALS
SUPPORTS C.S.
LINING
TRAYS
NOZZLE SCHEDULE
610"
MARK SIZE RATING FACING
N1 3" 150# RF HC Vapor Inlzt
N2 3" 150# RF HC Vapor Inlet
!
N3 1" E O # RF Drain
14 (A,B) 1" 3000# Cplg Level Gage
1 1/4" 3000# Cplg Calrod
I I I 1
i
REMARKS
5-13
r >
JOB NO. 7523
CUSTOM E R Electric Power Research Institute ITEM NO. E-201A,B - E-204A,B
PLANT Geothermal Demonstration Plant REV. NO. DATE 7/17/76
L O C A T l ON Heber, California QUOTE NO.
SERVICE Hydrocarbon/Brine Heat Exchanzer REFERENCE
SIZE 60" dia. x 59' (est. over%1# E CEN CONNECTED IN SERIES/PARALLEL
L
S H E L L SIDE TUBE SIDE
FLU1D C I R C U L A T E D 80% Isobutane - 20% 1sOpentaI.e Brine (14,600 PPM Tots
TOTAL FLUID ENTERING 7.687 (10") lb/hr Dissolved Solid
VAPOR
I I ioiiin I 7.687 110") lb/hr 6.722 (loo] lb/hr
5-14
ST-s
e # PI
w
0 0 0
0 0 0
0
6
0
E
m
F
-I?
c
4
W
d
P
0
r-
Ip
gor
0
2
3
r
JOB NO.
ITEM No. E-205A-G
7523 i
CUSTOMER Electric Power Research Institute
PLANT Geothermal Demonstration Plant REV. NO. DATE7/17/76
LOCATION Heber, California QUOTE NO.
SERVICE Hydrocarbon Condenser REFERENCE
S I Z E 81" dia. x 52' (est.
overa
I IE CJN CONNECTED IN SERIES/PARALLEL 1/7
SURFACE PER SHELL 157,286ftL NO. OF SHELLS 7 TOTAL SURFACE 1 101 000 ftL
(est -J i
NON-CONDENS ABL ES I
FLUID VAPORJZED OR CONDENSED I 7.687(10°) lb/hr
-
BAFFLE LONG
TUBE SUPPORTS
GASKETS
C.S.
TYPE THICKNESS
THICKN E S S
I
CONNECTIONS- SHELL- I N 001 SERIES 150 lb RF
CHANNEL -
IN OUT SERIES 150 1b RF
-
CORROSION ALLOWANCE S H E L L S I D E TUBE SIDE 1/16"
CODE REQUIREMENTS ASME Sect. VI11 TEMA C L A S S C (1)
WEIGHTS- EACH S H E L L BUNDLE F U L L O F WATER
(11 W/o cross baffles
5-16
hd
JOB NO. 7523
CUSTOMER Electric Power Research Institute ITEM NO. P-201A- F
PLANT& NO. R E Q U I R E D 6 REV. N O . L D A T E 7 -
5-17
CENTRIFUGAL PUMP SPECIFICATION
JOB N O . 3 3
5-18
b, JOBNO. 7523
C-STO~ER Electric Power Research Institute ITEM NO. P-204AsBsC
re
sp‘-RJV.
PLANT G e o t h e r m a l t r a t ion P1ant NO. REQUIRED- NO.-DATE7117/76
~
STEAM EXHAUST P.S.I.G. OF
MOTOR LE.
5-19
RECIPROCATING PUMP S PEClFlCATlON
GENERAL JOB NO. 7523
CUSTOMER Ele- Power R e s e h Insaute ITEM NO P-206
PLANT G
-o
e- NO REQUIRED REV. NO. DATE-
LOCATION Heber. California DIRECT ACT1 NG - QUOTE NO.
SERVICE Cooline Water Dispersant POWER FRAME -- REFERENCE
PISTONS TYPE
P I S T O N RODS -
LUBRICATOR M A K E -
VALVES- MTL. TYPE COMP. CAP'Y - FEEDS
VALVE SEATS HYDROSTATIC TEST-FLUID END -PSlG
HYDROSTATIC T E S T -STEAM END-PSlG
5-20
GENERAL JOB NO. 7523
CUSTOMER Electric Power Research I n s t i t u t e ITEM NO. p-207
PLANT G e o t h e r m a l i n n P l a n NO REQUIRED REV. NO. DATE- 7-17-'
LOCATION H e b e r r C a l l f o r n i a DIRECT ACTING- QUOTE NO.
SERVICE c O O 1 1 - b
..POWER FRAME -- REFERENCE
DIAMETER RODS
SIZE OF PACKING
PING WEIGHT
PUMP, BASE
MOTOR -LB
Special Instructions or Featuras
GENERAL JOB NO. 7523
CUSTOMER E l e c t r i c Power Research I n s t i t u t e ITEM NO. p-208
PLANT Geothermal Demonstration Plant NO REWIRED REV. NO. DATE 7- 17 - 7(
LOCATION Heber, California DIRECT ACTING- QUOTE NO.
SERVICE Cooling Water Acid POWER FRAME ---- REFERENCE
PUMP SPECIFICATIONS
MANUFACTURER PUMP TYPE
SIZE DRIVE -LIO. -- STROKE
SPEED FT./MIN. - EFF.
BHI? DESIGN MAX. BHP. REQD RECOMMENDED DRIVER HF!
CIRCULAR NO. DIMENSION P R I N T SECTION DWG.
5-22
JOBNO. 7523
CUSTOMER Electrical Power Research Institute I T E M NO.' 210 A E
PLANT Geothermal Demonstration Plant 7-17-76
NO. R E Q U I R E D ~ ( SPS+@V.
~~~ NO.-DATE-
LOCATION Heber, California MOTORDRIVE QUOTE NO.
SERVICE Make-up Water TURBINE DRIVE- REFERENCE
P.S.I.G.
OF
OF
MOTOR LE.
Special Instructions w F e a t u r e s - to meet API 610 sDecification
5-23
JOBNO. 7523
CUSTOMERU~~ ic Power Research Institute I T E M NO. p-2001
Binary Process-Geothermal Demonstration Plant
PLANT NO. REQUIRED One REV. NO.-DATE-
5-24
CENTRIFUGAL PUMP SPECIFICATION
IJoBNO. 7523
CUSTOMER Electric Power Research Institute I T E M NO. P-2002 IA-C)
Binary Process-Geothermal Demonstration Plant
PLANT- - - - - NO. R E Q U I R E D - ~ ~ ~ S G P ~ 0 . ~ ~ ~ ~ ~ 7 - 2 1 - 7 6
LOCATION Heber. California MOTOR DRIVE One QUOTE NO.
S E R ~ ~ C E Firewater
Diesel Enpine
ltvfiP!NEhFfw= REFERENCE
I1
I M P E L L E R RINGS WATERJACKET: 0 YES 0 NO
SHAFT A1 lov INTERNAL EXTERNAL
SHAFT S L E E V E SINGLE- D OU B LE- BA L A N C E D U N B A L A N C E D -
PACKING G L A N D BEARINGS WATER JACKETED: 0 YES 0 NO
PACKING Graphite Impreg ASB LUBRICATION O I L GREASE
S E A L CAGE F L E X I B L E COUPLIpJG: MAKE TYPE
BASE P L A T E r $ COUPLINGGUARD: 0 YES 0 NO
DRIVER DATA
MAKE
- MOTOR
TYPE TEFC R.P.M. 1770 R.P.M. 1770
PHASE 2C Y C L E L V O L T S d h n A T E @ DESIGN L O A D _______ L B S / H R . BHP.
P.S.I.G. - OF
STEAM EXHAUST P.S.I.G. OF
SHIPPING WEIGHT
structions or Features
5-25
c 1
JOBNO. 7523
CUSTOMER Electric Power Research Institute I T E M NO. p-2003
Binary Process-Geothermal Demonstration P,18p&EQu, RED
PLANT T)np REV. NO.-DATE-
I MOTOR
I
LE.
5-26
THE BEN HOLT CO.
COOLING TOWER SPECIFICATIONS
s - i
cusfohim Electric Power Reserach Institute ITEM NO. CT-291
PLANT Geothermal Demonstratinn Plant REV. NO.
Heber , Ca 1ifornia
LOCATION
REFERENCE
I
Woter Circuloting Rote: 137.0 85 gpm. Temp. In: 108.7 OF Temp. Out: , A . O F
Cooling Duty 1 2 4 3 . 3 [ i n6 )~ Bb/Hr.; PetfonrcTost Code.
* A t Option of Owner
S ELECTK)N -
Manufacturer: Model:
Type: No. of Calls:
DESIGN
Wet Bulb Temp: 80 OF; Static Pumpin9 Hd. 35 (max> Ft. Eff. Cool. Vat. cu. Ft.
Fill Wetted Surf. Sq. Ft; Total Wetted Surf. Sq. Ft; Eff. Splosh S u r f j t . Ft.
No. of Fans Req*d. ChdFan ;Static Pros. In. HzO; Normal DHP/Fon
REMARKS
P.O. TO: I
5-27
STANDARD DATA SHEET FOR RECIPROCATING COMPRESSORS
P l a n t Binary Process - ~pothprmalDemo- t i h b No. 7523
Location Heber, California No. Reqd. ONE -
Item No. K-LUl Manufacturer
A -SERVICE G-CONTROLS: TYPE &i DESCRlPTION
Type Gas Handled H v- Mix a E t a r t i n g unloader furnished
Normal Capacity S. C. F. M. b )Capacity Control:( VarSpeed)(on-off )
Number of Stages (multi-speed unloade r)f dua1)etc.
Operating Speed, RPM c ) Unloade r ope ration(E l e c t P n e u. Comb)
. Direction of Rotation, F r o m Driver End H-CONSTRUCTION MATERIALS
Total B. H. P. Cyls P Heads
Type of D r i v e r Electric Motor
B-OPERATING CONDITIONS - - - Pistons
Stages Piston Rines a
Size
Mfrs. Type & Designation Crosshead Guide Brgs. Type
No. of C o m p r e s s o r Cylinders Crosshead P i n Brgs. Type
Cylinder Arrangement Size
Single o r Double Acting Lubrication of Bearings ., 4
I n e r t i a F o r c e s & Couples Lubrication of C r o s s h e a d 4 NONE
Max. Safe Operating Speed Lubrication of Cvlinders 1
E -DRIVER( Motor)(Turbine)(Engine) Cooling W a t e r , GPM. F o r Intercoolers
D r i v e r R. P. M.
D r i v e r H. P. 10 Hd. Loss thru Cyl. J a c k e t s Ft.
NO. of Motor, Data Sheet Hd. Loss t h r u I n t e r c o o l e r Ft.
Type of Drive(direct)(GearrV-belt)
Size & Type of Gear o r Belt J -GENERAL
Normal & T h e r m a l Rating of Drive P r i c e , Each (FOB) ( F R T Allowed) I
Type of Coupling Extra for Driver
Size of Coupling E x t r a f o r Gear, Belts, Cplgs, etc.
Extra for
F-PRESSURE RATING O F CYL. (Max. )PSIG Weight. Unit onlv
v . I
M a x Differential P r e s s u r e Weight, D r i v e r
Suction Nozzle Size & Rating Weight
Disch. Nozzle Size & Rating Shipment f r o m Receipt of O r d e r , Wks. ,
THE BEN HOLT CO. ---
Engineers-Constructors
201 So. Lake Avenue
Pasadena, California 91101 NO. Date Revisions By
5-28
TURBINE-GENERATOR ~ ' Specification No. 2801
Electric Power Research Institute Holt Job No. 7523
Palo Alto, California March 1977
Geothermal Demonstration Plant Page 1 of 23 Pages
GENERAL REQUIREMENTS
1. SCOPE
4. ,
tative reserv
spect fully all phases of the manufacture of the turbine and the generator
to insure that the manufacturer is complying with the specifications. Any
item found to be not in accordance with the specification will be rejected
at no additional cost to the Purchaser. The Purchaser's inspection shall
not relieve conformance to the specifications or release from warranty.
5-29
Lid
TURBINE-GENERATOR Specification No. 2801
Electric Power Research Institute Holt Job No. 7523
Palo Alto, California March 1977
Geothermal Demonstration Plant Page 2 of 23 Pages
I1 TURBINE
8. TYPE AND DESIGN REQUIREMENTS
The turbine, which shall be rated in accordance with the requirements of
these specifications, shall be directly connected to and shall drive the
generator described herein.
When in normal operation the unit and its associated equipment shall be
sufficiently strong to withstand without injury, any strain that might
result from sudden application or withdrawal of normal load, or from any
transient speed to 120 percent of rated speed. The unit shall be designed
to conform to all API mechanical specifications for equipment handling
highly flammable fluids, i.e., API Standard 617.
A system torsional and lateral critical speed analysis shall be made.
The design flow requirements for the turbine at rated throttle conditions
are as specified below:
5-30
W TURBINE-GENERATOR Specification No. 2801
Electric Power Research Institute Holt Job No. 7523
Palo Alto, California March 1977
Geothermal Demonstration Plant Page 3 of 23 Pages
9.1 General
All parts which are subject to temperature c,.anges shall be des-,pel
and supported so as to permit free expansion and contraction in an
effort to minimize harmful distortion or misalignment.
9.2 Turbine Casings and Diaphragms
Turbine casings shall conform to API Standard 617, Section 2.3 and
Section 3. Provisions shall be made in the design of the turbine
to control thermal stresses in the turbine casing. The main hori-
zontal joint and/or the main vertical joint in the turbine shell
shall be metal to metal. The turbine shells and diaphragms shall
be supported so that their movement relative to the shaft be mini-
mized. Their design shall be made to minimize the time required
for an inspection or a repair. A design which permits bearing
inspection or removal without removal of the turbine shells is
required. The casing shall be equipped with suitable drains.
5-31
TURBINE-GENERATOR Specification No. 2801
Electric Power Research Institute Holt Job No. 7523
Palo Alto, California March 1977
Geothermal Demonstration Plant Page 4 of 23 Pages
All of the valves, valve stems, and valve seats shall be made of
corrosion and erosion-resistant materials which have been proven
suitable for successful operation and durability in other existing
applications.
9.7 Turbine Governors
An automatic speed governor shall be supplied which will regulate
the flow to the turbine through a suitable governing mechanism. It
shall prevent the unit from reaching the overspeed tripping point
in the event of an instantaneous change in load from full to no
load. The governor shall be furnished with a means of manually
limiting the turbine-generator output. The governor shall be fur-
nished with an adjustment for regulating the speed and/or load of
the turbine-generator manually from a remote location.
In addition to the automatic speed governor, a separate quick acting
emergency governor will be furnished that will cause flow to be shut
off to the unit when it reaches approximately 10 percent overspeed,
but can be reset when the speed is reduced to approximately normal,
thus permitting the unit to be synchronized with other units. This
governor shall be of a type which can be tested at no load.
9.8 Hydraulic, Lubrication and Seal Oil System
A complete hydraulic fluid system shall be furnished to provide hy-
draulic fluid to the turbine control valve gear and emergency trip
system. This system may be combined with the lubricating oil and
Oil reservoir
Oil coolers
Oil filters
5-33
TURBINE-GENERATOR Specification No. 2801
hi
Electric Power Research I n s t i t u t e Holt Job No. 7523
Palo Alto, California March 1977
Geothermal Demonstration Plant Page 6 of 23 Pages
9.9 Bearings
5-34
u TURBINE-GENERATOR Specification No. 2801
Electric Power Research Institute Holt Job No. 7523
Palo Alto, California March 1977
Geothermal Demonstration Plant Page 7 of 23 Pages
The turbine design and testing shall conform to Section 2.18 of API
Standard 617.
Vibration and position detectors shall be provided in accordance
with Section 2.14 of API Standard 617. Paragraphs 2.14.3 and 2.14.4
of this standard shall not apply.
10. MOTORS
10.1 All AC motors shall be in accordance with Specification No. 3600-2.
10.2 All wiring shall be in accordance with electrical components Speci-
fication No. 3600-3.
11. ACCESSORIES
In addition to those accessories already mentioned in these specifications,
the following shall be included:
An electric type speed indicating device will be furnished consisting of
a tachometer generator and an indicating instrument.
Industrail dial-type thermometers and wells shall be provided for all main
bearings and thrust bearing oil drains and for the oil cooler outlet tem-
peratures.
A thrust failure trip device shall be provided
- for both active and inactive
sides of thrust bearing.
5- 35
TURBINE-GENERATOR Specification No. 2801
Electric Power Research Institute Holt Job No. 7523
Palo Alto, California March 1977
Geothermal Demonstration Plant Page 8 of 23 Pages
I11 GENERATOR
12. TYPE AND DESIGN REOUIREMENTS
The generator shall be an alternating current synchronous generator,
rated in accordance with the requirements of these specifications, and
shall be directly connected to and driven by the turbine described herein.
The generator shall be of the nonsalient pole revolving field type.
The telephone influence factors of the generator shall be in accordance
with the latest ANSI and NEMA standards.
Lid
5-36
W TURBINE-GENERATOR Specification No. 2801
Electric Power Research Institute Holt Job No. 7523
Palo Alto, California March 1977
Geothermal Demonstration Plant Page 9 of 23 Pages
The deviation factor of the open circuit terminal voltage wave of the
generator shall not exceed 10 percent as defined by ANSI and NEMA
standards.
The generator armature shall be capable of operating at 13 percent of
rated armature current for at least one minute, starting from stabi-
lized temperatures at rated conditions.
The generator field windings shall be capable of operating at a field
voltage of 125 percent of rated load field voltage for at least one min-
ute starting from stablized temperatures at rated conditions.
The generator will be capable of withstanding, without injury, the thermal
effects of unbalanced faults at the generator terminals, including the
decaying effects of field current (where protection is provided by causing
field current reduction, such as with a field breaker or equivalent) and
the d-c component of the stator current, for times up to 120 seconds, pro-
vided the integrated product (Iz2t) of generator negative phase sequence
current (Iz) and time (t) does not exceed 30.
The generator shall be capable of withstanding without mechanical injury,
any type of short circuit at its terminals for times not exceeding the
short time thermal capabilities, when operating at rated KVA and power
factor and five percent overvoltage, provided the maximum phase current
is limited by external means to a value which does not exceed the mxi-
mum phase current obtained from the three-phase fault.
rdance with
mance establ ormal ratin
t full load
ent temperature
stator coils and 125OC for the field when operating at full load or below.
The stator and rotor insulation shall be Class F.
5- 37
TURBINE-GENERATOR Snecification No. 2801
5-38
b) TURBINE-GENERATOR Specification No. 2801
Electric Power Research Institute Holt Job No. 7523
Palo Alto, California March 1977
Geothermal Demonstration Plant Page 11 of 23 Pages
IV EXCITER
15. TYPE
The exciter shall be of the nonrotating type and rated in accordance with
the requirements of these specifications. The exciter shall supply gen-
erator field excitation by utilizing power from the armature terminals of
the generator. The excitation system shall regulate and maintain the de-
sired terminal voltage as specified herein. The excitation system shall
consist of power transformers, rectifiers,
- --- and excitation controls.
16. CONSTRUCTION AND DESIGN CONSIDERATIONS
The exciter shall be wide range stablized to permit stable operation down
to 25 percent of rated exciter voltage on manual control. The exciter
5-33
TURBINE-GENERATOR Specification No. 2801 id
Electric Power Research I n s t i t u t e Holt Job No. 7523
Palo Alto, California March 1977
Geothermal Demonstration Plant Page 1 2 of 23 Pages
17. TESTS
17.1 Turbine
T e s t of o i l pumps.
Assembly of turbine.
Heat s t a b i l i z a t i o n of r o t o r .
Ultrasonic t e s t on r o t o r .
5-40
I) TURBINE-GENERATOR Specification No. 2801
Electric Power Research Institute Holt Job No. 7523
Palo Alto, California March 1977
Geothermal Demonstration Plant Page 13 of 23 Pages
17.2 Generator
Mechanical Inspection.
Mechanical balance and high speed run to 110 percent of rated speed.
Measurement of cold resistance of armature and field windings.
Di-electric tests:
Armature - The standard test voltage shall be an alternating
voltage whose effective value is 1,000 V plus twice the rated
voltage of the generator. Test shall be applied for 60 seconds
duration.
Field -
The standard test voltage shall be an alternating volt-
effective Val ill be ten times the field rated
excitation voltage but not less than 1,500 V. The test shall
be applied for 60 seconds duration.
Air leakage test of stator frame.
Resistance temperature detector tests.
Physical and chemical analysis of major rotating parts.
17.3
Transformers
Polarity test.
5-41
TURBINE-GENERATOR Specification No. 2801 b
Electric Power Research Institute Holt Job No. 7523
Palo Alto, California March 1977
Geothermal Demonstration Plant Page 14 of 23 Pages
Rectifiers
Voltage drop at reduced current.
Reverse leakage test.
General
Voltage regulator gain test.
High potential tests on all circuits to ground.
Test to insure operation of all services associated with the
excitation system.
5-42
TURBINE-GENERATOR Specification No. 2801
Electric Power Research Institute ' Holt Job No. 7523
Palo Alto, California March 1977
Geothermal Demonstration Plant Page 15 of 23 Pages
18.2 Turbine
Guaranteed hydrocarbon rates at 100 percent load point, and an esti-
mate performance curve for 0 percent - 105 percent of full load.
Description of the type of turbine rotor construction.
Description of the type of inlet valve gear and advise approximate
number of valves included in each set of gear.
Description of turbine shaft sealing system.
Description of method of fastening blades to turbine wheels or fab-
rication of impellers.
Description of lubrication and hydraulic oil system.
Description of the control system.
Description of the turbine stop valve.
Description of emergency trip system.
Description of emergency overspeed governor.
18.3 Generator
The following curves for the generator size and rating specified
herein.
Typical saturation and synchronous impedance curves.
Typical reactive capability curves.
Typical excitation Vee" curves.
Transient and subtransient reactances.
Required cooling water flow rate at 95'F maximum cooling water
temperature.
Description of method of cooling stator and rotor.
5-43
Lid
TURBINE-GENERATOR Specification No. 2801
,
Length (above floor)
Width
Height above floor
Minimum distance required from floorline
to CL crane hood to lift largest piece.
During erection
(Specify which piece)
After erection
(Specify which piece)
How far forward from front end of turbine
below floor does oil tank extend?
Lit#
5 -44
LJ
TURBINE-GENERATOR Specification No. 2801
Electric Power Research Institute Holt Job No. 7523
Palo Alto, California March 1977
Geothermal Demonstration Plant Page 17 of 23 Pages
without external a
Shipped assemble
during erection
Heaviest piece and weight to be handled
LJ after erection
5-45
L,
, TURBINE-GENERATOR Specification No. 2801
Electric Power Research Institute Holt Job No. 7523
Palo Alto, California March 1977
Geothermal Demonstration Plant Page 18 of 23 Pages
Blading material
Banding of blading (yes or no)
Stationary hydrocarbon path
Blade rings or diaphragms
Nozzle material
Method of support
Type of interstage seals
Shaft Sealing System
Type of system
Sealing Fluid
Bearings
Number of journal bearings
Turbine
Generator
Type of journal bearings
Type of thrust bearing
Dummy piston required Yes No
If dummy piston required, is there pro-
vision to move rotor axially under load Yes No
Are sight flows provided Yes No
Oil System
Capacity of oil tank (gals)
5-47
L,
TURBINE-GENERATOR Specification No. 2801
Electric Power Research Institute Holt Job No. 7523
Palo Alto, California March 1977
Geothermal Demonstration Plant Page 20 of 23 Pages
5-48
W
TURBINE-GENERATOR Specification No. 2801
Electric Power Research Institute Holt Job No. 7523
Palo Alto, California March 1977
Geothermal Demonstration Plant Page 21 of 23 Pages
5-50
TURBINE-GENERATOR Specification No. 2801
Electric Power Research Institute Holt Job No. 7523
Palo Alto, California March 1977
Geothermal Demonstration Plant Page 23 of 23 Pages
5-51