Professional Documents
Culture Documents
Lec 5 - Options For Contract Price
Lec 5 - Options For Contract Price
INTRODUCTION
The decision made on the most appropriate option of project
delivery will be closely followed by a decision on the most
appropriate option for the contract price.
The price payable under the contract to members of a project
team for specific work and services may either be pre-ascertained
in the form of a lump sum or price rates, or determined when a
project has been completed. The former approach is known as a
fixed-price contract while the latter is usually cost-plus. These two
options for a contract price will now be discussed in more detail.
There are other options that are used less often. In some forms of
contract, for example BOOT, the price may depend on the earnings
from the completed project or on a lease arrangement or another
formula quite unrelated to the cost of construction.
FIXED-PRICE CONTRACTS
In fixed-price contracts a contract price for specific work and
services is ascertained before any work is carried out. This
price is said to be fixed at the start of the contract but it may
change during its execution if the contract conditions allow
cost adjustment.
The most common contract conditions that allow cost to be
adjusted are variations, latent site conditions, provisional or
prime cost items, and clauses for other risks beyond the
control of the contract party claiming such cost adjustments.
In this scenario, the original contract price will be different
(generally less) than the final contract cost.
If the client wants, for example, to fix the contract price of the
main contractor for the entire contract period, the client
would need to delete from the contract any conditions that
the contractor might otherwise use to claim for cost
adjustments. The client’s intent is to shift the risk of cost
overruns onto the contractor. This practice may be justified in
some situations but only when: