Title page

Alcatel-Lucent
Base Station | B12
Add TRE to Equipped BTS
9YZ-03803-0450-RJZZA
Issue 7 | September 2014
Legal notice

Legal notice

Alcatel, Lucent, Alcatel-Lucent and the Alcatel-Lucent logo are trademarks of Alcatel-Lucent. All other trademarks are the property of their respective
owners.

The information presented is subject to change without notice. Alcatel-Lucent assumes no responsibility for inaccuracies contained herein.
Copyright © 2014 Alcatel-Lucent. All rights reserved.

Note:

Not to be used or disclosed except in accordance with applicable agreements.


Contents

About this document


Purpose ............................................................................................................................................................................................ vii
vii

Reason for reissue ....................................................................................................................................................................... vii


vii

New in this release .................................................................................................................................................................... viii


viii

Intended audience ...................................................................................................................................................................... viii


viii

Supported systems ..................................................................................................................................................................... viii


viii

How to use this document ....................................................................................................................................................... viii


viii

Prerequisites ................................................................................................................................................................................. viii


viii

Conventions used ....................................................................................................................................................................... viii


viii

Related information ..................................................................................................................................................................... ix


ix

Document support ........................................................................................................................................................................ ix


ix

Technical support .......................................................................................................................................................................... ix


ix

How to order ................................................................................................................................................................................... ix


ix

How to comment ............................................................................................................................................................................ x


x

1 Overview

Overview ...................................................................................................................................................................................... 1-1


1-1

Presentation ................................................................................................................................................................................. 1-1


1-1

Preparation .................................................................................................................................................................................. 1-3


1-3

Scheduling ................................................................................................................................................................................... 1-5


1-5

Telecom/Supervision Outage and Operating Impact ................................................................................................... 1-6


1-6

Resources ..................................................................................................................................................................................... 1-7


1-7

2 Scenario

Overview ...................................................................................................................................................................................... 2-1


2-1

....................................................................................................................................................................................................................................
Alcatel-Lucent BTS iii
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Contents

....................................................................................................................................................................................................................................
Before Going Onsite

Preparation Before Going Onsite ........................................................................................................................................ 2-3


2-3

Before You Start

Preparation Before You Start ................................................................................................................................................ 2-4


2-4

Scenario Description

Scenario Description Overview ........................................................................................................................................... 2-5


2-5

Initial Checks .............................................................................................................................................................................. 2-6


2-6

Prepare Add TRE Logical ...................................................................................................................................................... 2-7


2-7

Activate PRC ............................................................................................................................................................................ 2-11


2-11

Install TRE Hardware ........................................................................................................................................................... 2-13


2-13

Activate PRC ........................................................................................................................................................................... 2-18


2-18

Call Tests ................................................................................................................................................................................... 2-20


2-20

Lock Test Frequency ............................................................................................................................................................. 2-21


2-21

Final Checks ............................................................................................................................................................................. 2-22


2-22

Reverse Procedure

Activate Backup PRC ........................................................................................................................................................... 2-23


2-23

Uninstall TRE Hardware ..................................................................................................................................................... 2-25


2-25

Call Tests ................................................................................................................................................................................... 2-29


2-29

Final Checks ............................................................................................................................................................................. 2-30


2-30

Index

....................................................................................................................................................................................................................................
iv Alcatel-Lucent BTS
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
List of figures

1-1 Add TRE to Equipped BTS ................................................................................................................................... 1-3

....................................................................................................................................................................................................................................
Alcatel-Lucent BTS v
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
List of figures

....................................................................................................................................................................................................................................

....................................................................................................................................................................................................................................
vi Alcatel-Lucent BTS
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
About this document
About this document

Purpose
This document describes how to add a TRE/TWIN TRA/MC TRE to an equipped 9100
BTS, lightRadio 9711/9712 Base Station.

Reason for reissue

Issue number Reason for reissue


7 The following section was updated:“Presentation”
(p. 1-1)
6 The following sections were updated:
• “Preparation” (p. 1-3)
• “Activate PRC” (p. 2-11)

5 The following sections were updated:


• “Presentation” (p. 1-1)
• “Scenario Description Overview” (p. 2-5)

4 The following sections were updated:


• “Presentation” (p. 1-1)
• “Scenario Description Overview” (p. 2-5).
3 “Prerequisites” (p. 1-3) section was updated.
2 The following sections were updated:
• “Prerequisites” (p. 1-3)
• “Install TRE Hardware” (p. 2-13)
• “Activate PRC” (p. 2-11).
1 First official release of the document for B12.

...................................................................................................................................................................................................................................
Alcatel-Lucent BTS vii
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
About this document

....................................................................................................................................................................................................................................
New in this release
This section contains information about changes to the current document.
New features
None.
Other changes
None.

Intended audience
This document is intended for:
• Field service technicians
• Specialists
• Project managers
• Foremen.

Supported systems
This document applies to Release B12 of the BSS.

How to use this document


No specific recommendation applies regarding the way readers should read this
document.

Prerequisites
You must have a basic understanding of the following:
• Planning
Including:
– Network architecture and reshuffling principles
– Scheduling.
• Implementation
Including:
– Alcatel-Lucent operations and maintenance (O&M) concepts for the BSS
– 9153 OMC-R operation
– Equipment (BSC, BTS, MFS) hardware configurations
– Windows environment.

Conventions used
This section gives information on conventions.

....................................................................................................................................................................................................................................
viii Alcatel-Lucent BTS
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
About this document

....................................................................................................................................................................................................................................
Vocabulary conventions
None.
Typographical conventions
The following typographical conventions are used in this document:

Appearance Description
Italicized text Emphasized information.
graphical user interface text Text that is displayed in a graphical user interface or in a
hardware label.
Document reference, reference Related document that is referenced in the document.
number

Related information
None.

Document support
For support in using this or any other Alcatel-Lucent document, contact Alcatel-Lucent at
the following telephone numbers.
From United States
• If you are using a landline, a cellular phone or VoIP, dial this number: 1-888-582-3688
From other countries
• If you are using a cellular phone or VoIP, dial this number: +1-630-224-2485
• If you are using a landline (phone without a plus [+] character), replace the plus sign
with your country's exit code. Dial this number: Exit code for the country of origin:
1-630-224-2485. See the country-specific exit codes listed here.
These numbers apply for document support only. Please see the section “Technical
support” for details about product hardware, software, and technical support.

Technical support
For technical support, contact your local Alcatel-Lucent customer support team. See the
Alcatel-Lucent Support web site (http://www.alcatel-lucent.com/support/) for contact
information.

How to order
To order Alcatel-Lucent documents, contact your local sales representative or use Online
Customer Support (OLCS) (http://support.alcatel-lucent.com)

....................................................................................................................................................................................................................................
Alcatel-Lucent BTS ix
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
About this document

....................................................................................................................................................................................................................................
How to comment
To comment on this document, go to the Online Comment Form (http://infodoc.alcatel-
lucent.com/comments/) or e-mail your comments to the Comments Hotline
(comments@alcatel-lucent.com).

....................................................................................................................................................................................................................................
x Alcatel-Lucent BTS
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
1 Overview
1

Overview
Purpose
This Overview gives information needed by project managers and foremen, for
presentation to the customer and for site planning.

Contents

Presentation 1-1
Preparation 1-3
Scheduling 1-5
Telecom/Supervision Outage and Operating Impact 1-6
Resources 1-7

Presentation
Overview
The equipped value of the equipped status status attribute indicates the presence of the
transcoding rate, adaptation, and radio transmission capacity in the BTS, which shows
that the required BTS equipment is present.
HR Flexibility allows the user to define the speech-coding rate at the TRE/TWIN
TRA/MC TRE and TRX level. Full Rate TREs/TWIN TRAs/MC TREs are treated before
Dual Rate TREs/TWIN TRAs/MC TREs.
If a TRE/TWIN TRAs/MC TREs are added to a cell split on two BTSs, the TRX attribute
is set to main or secondary, depending on where the TRE/TWIN TRA/MC TRE is
added.
The scenario uses configuration management rules specific to the 9153 OMC-R.

...................................................................................................................................................................................................................................
Alcatel-Lucent BTS 1-1
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Overview Presentation

....................................................................................................................................................................................................................................
In order to create a required configuration, it is possible to add more than one TRE/TWIN
TRA/MC TRE.

Cases
The following cases apply:
• C1: BTS with frequency hopping system declared
• C2: New TRE/TWIN TRA does not have a frequency allocated and after the
operation it remains OPR
• C3: Only G3 and G4 TRE are added
• C4: Add new TWIN TRA/MC TRE modules
• C5: Add new MC TRE modules dedicated for other standards usage.
Note: The default TRE/TWIN TRA allocation mode is automatic mode.

Options
The following options apply. Note that the default is a BTS without frequency hopping
where the frequency for the new TRE/TWIN TRA is known and the TRE/TWIN TRA
remains in traffic after the operation.
• O1: TRE allocation mode: on demand
• O2: TWIN TRA allocation mode: on demand
This option applies also if antenna hopping is configured on the cell.
As follows:
– O2.1: TWIN TRA is configured as 1 TRX, Non-TX-Div, 2 RX-Div
– O2.2: TWIN TRA is configured as 1 TRX, TX-Div, 4 RX-Div
– O2.3: TWIN TRA is configured as 2 TRX, Non-TX-Div, 2 RX-Div
• O3: MC TRE allocation mode: on demand
• O4: MC TRE software preload.

Restrictions
The following restrictions apply:
• This procedure does not cover adding a TRE to a low loss configuration, which
implies antenna reconfiguration.
• The addition of a MC TRE is not possible if the BTS is equipped with ANX or ANY
because of the higher RF power of MC TRE.

Grouped Task Sequence


The following figure shows the task sequence for adding a TRE, TWIN TRA, MC TRE to
an equipped 9100 BTS, lightRadio 9711/9712 Base Station.

....................................................................................................................................................................................................................................
1-2 Alcatel-Lucent BTS
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Overview Presentation

....................................................................................................................................................................................................................................

Figure 1-1 Add TRE to Equipped BTS

Preparation
Prerequisites
The following prerequisites apply:
• BTS sites are clean, tidy, and easily reachable
• The OMC-R is in Release B12. The BSC must be operational and running in Release
B12.
• There are enough resources (Abis timeslots and TCUCs) to handle new TREs/TWIN
TRAs/MC TREs (TCH, SDDCH, LAPD)
If there are not enough, perform Alcatel-Lucent Base Station - Attach Secondary Abis.
• Test frequencies must be available
• When adding a TWIN TRA/MC TRE, ensure that the BTS is equipped with
SUMA/SUMX
• To have 3G capability on the MC TRE 900 modules of the BTS, the cabinet must be
equipped with d2u board
• To have 4G capability on the MC TRE 900 and the MC TRE 1800 modules of the
BTS, the cabinet must be equipped with BBU board
• The BTS must not contain any G3 TREs for a configuration with more than 12 TREs

....................................................................................................................................................................................................................................
Alcatel-Lucent BTS 1-3
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Overview Preparation

....................................................................................................................................................................................................................................
• The BTS logical configuration must not exceed a maximum number of 24 TRXs.
Refer to Alcatel-Lucent 9100 Base Station - Hardware Description for the
recommended hardware configurations.
• For new MC TRE modules take into account the cable set needed according to the AN
it will be connected to. See Alcatel-Lucent 9100 Base Station - Hardware Description.
• MC-Modules are licensed separately using a LKDI license file installed at Centralized
License Manager Server. Make sure the LKDI license is installed and enough licenses
are availlable in case of adding MC-Modules. Contact the Customer License Manager
(CLM) representative person for any issues related to MC-Modules LKDI license.
• For O4 the MC TRE software to be loaded must be available on the BTS NEM PC
together with an Ethernet cable used for the connection between PC and MC TRE.
The BTS NEM PC IP address needs to be set to 192.168.0.1.
The MC TRE software files can be retrieved from one of the following:
– OMC-R location /alcatel/var/share/oef/SDPPackage/<SDP Name>
– original source of the OMC-R SDP package.
– BTS Post-commissioning SW Package
Note: The source folder must contain files with the y0snxxxx.zzz format, where:
• y is W for MC TRE 900, Y for MC TRE 1800, X for MC RRH 900 and Z for MC
RRH 1800
• s is W for the MC TRE TDM operational software files, I for MC TRE IP
operational software files and O for the origin software files
• n is a unique number for each file
• xxxx.zzz depends on the release version.

Site Specific Information


You must have the following specific information to complete the scenario:
• BTS name and hardware characteristics
• Customer report about BTS and cell configurations
• TRE/TWIN TRA/MC TRE auto-allocation mode status (automatic / on demand)
• FHS to be defined, if necessary
• Number of TRE/TWIN TRA/MC TRE to add
• Frequency Allocation Plan, or the frequency, to be created for the new TRE/TWIN
TRA/MC TRE(s) and test frequency.

External Tasks
None.

....................................................................................................................................................................................................................................
1-4 Alcatel-Lucent BTS
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Overview Scheduling

....................................................................................................................................................................................................................................

Scheduling
Time based on technical constraints
The number of resources shown in the following table does not take into account
individual customer or safety requirements.

Grouped Task Site / Resource Time / Task


Initial Checks OMC-R / 1 ope. 20 min.
Prepare Add TRE/TWIN OMC-R / 1 ope. 15 min. + 4 min./ cell + 1 min./ TRX + 3 min./ C1
TRA/MC TRE Logical
Activate PRC(1) OMC-R / 1 ope. 5 min./cell
Install TRE/TWIN BTS / 1 team 15.5 min. + 12 min./TRE + 5 min. + 1 min./ O1, O2 +
TRA/MC TRE Hardware 5 min./TRE/ O4
Activate PRC(2)(3) OMC-R / 1 ope. 5 min./cell
Final Checks BTS / 1 team 25 min. +1 min./ C2
OMC-R / 1 ope.
TOTAL TIME BTS / 1 team 1h 15.5 min. + 12 min./ TRE + 9 min./ cell + 1 min. /
OMC-R / 1 ope. TRX + 5 min.
C1: + 3 min.
C2: + 1 min.
O1, O2: + 1 min.
O4: + 5 min./TRE

Notes:
1. (1) In case of BTS attached to an 9120 BSC with Radio Hopping or No Hopping defined on the impacted
cell.
2. (2) In case of BTS attached to an 9120 BSC with Base Band Hopping defined on the impacted cell.
3. (3) In case of BTS attached to an 9130 BSC Evolution.
4. ope. OMC-R Operator
5. team BTS Commissioning Team

....................................................................................................................................................................................................................................
Alcatel-Lucent BTS 1-5
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Overview Telecom/Supervision Outage and Operating Impact

....................................................................................................................................................................................................................................

Telecom/Supervision Outage and Operating Impact


Overview
The following table describes the traffic outage and loss of supervision caused by each
grouped task.

Out.
Ref. Grouped Task Outage / Impacts...
- Initial Checks. None.
- Prepare Add TRE/TWIN None.
TRA Logical
1 Activate PRC (1) Telecom and GPRS 1 min./ cell
Outage
Supervision Outage 1.5 min.
During PRC activation: Supervision Outage
2 Install TRE/TWIN Telecom and GPRS None or 24 sec.
TRA/MC TRE Hardware Outage Outage if added TRE/TWIN TRA/MC TRE(s)
are multiplexed with the existing TRE/TWIN
TRA/MC TRE(s). This means moving existing
TRE/TWIN TRA/MC TRE(s) from the initial
TCUC.
1 Activate PRC(2)(3) Telecom and GPRS 1 min./ cell
Outage
Supervision Outage 1.5 min.
During PRC activation: Supervision Outage
- Final Checks None.
TOTAL Telecom and GPRS None or 24 sec.
Outage + 1 min./ cell
Supervision Outage 1.5 min.

Notes:
1. (1) In case of BTS attached to an 9120 BSC with Radio Hopping or No Hopping defined on the impacted
cell.
2. (2) In case of BTS attached to an 9120 BSC with Base Band Hopping defined on the impacted cell.
3. (3) In case of BTS attached to an 9130 BSC Evolution.

....................................................................................................................................................................................................................................
1-6 Alcatel-Lucent BTS
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Overview Resources

....................................................................................................................................................................................................................................

Resources
Tools
The following tables describe the necessary hardware tools, software tools, and forms.
Hardware Tools

Item Use at....


PC Terminal with CD drive and associated cable. BTS
RS-232 Cable. BTS
Trace mobiles equipped with SIM cards. BTS
Installation Tools. BTS
Commissioning Tools. BTS

Software Tools

Item Use at...


BTS NEM in Release B12. BTS
LMT Terminal. BTS
Customer documentation CD with the version associated with the current document BTS, BSC, OMC-R
edition. Remember that the document you are reading cannot be used as a paper version.
It is online documentation using hypertext links which take you to other parts of a
document on the same CD-ROM. All words in italics are hypertext links.

Forms
None.

Supplies
The following table describes the necessary supplies.

Item Contents Use at...


Site Documentation. - BTS, OMC-R
Topology regarding operation. Must be provided by customer. BTS, OMC-R
TRE Extension Kit and connection cables. 1 kit per added TRE. BTS

....................................................................................................................................................................................................................................
Alcatel-Lucent BTS 1-7
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Overview Resources

....................................................................................................................................................................................................................................
Applicable Documents
You must have the following documents or have electronic access to the following
documents:
• Alcatel-Lucent Base Station Subsystem - BSS Methods Handbook
• Alcatel-Lucent Base Station Subsystem - BSS Configuration Handbook
• Alcatel-Lucent Base Station Subsystem - BSS Surveillance Handbook
• Alcatel-Lucent Base Station Subsystem - Network Reconfiguration
Recommendations
• Alcatel-Lucent Base Station - BTS NEM User Guide
• Alcatel-Lucent 9100 Base Station - Hardware Description.

....................................................................................................................................................................................................................................
1-8 Alcatel-Lucent BTS
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
2 Scenario
2

Overview
Purpose
This scenario presents all checks needed before beginning the scenario, and all detailed
tasks to be performed on each site.

Contents

Before Going Onsite 2-3


Preparation Before Going Onsite 2-3
Before You Start 2-4
Preparation Before You Start 2-4
Scenario Description 2-5
Scenario Description Overview 2-5
Initial Checks 2-6
Prepare Add TRE Logical 2-7
Activate PRC 2-11
Install TRE Hardware 2-13
Activate PRC 2-18
Call Tests 2-20
Lock Test Frequency 2-21
Final Checks 2-22
Reverse Procedure 2-23
Activate Backup PRC 2-23
Uninstall TRE Hardware 2-25
Call Tests 2-29

...................................................................................................................................................................................................................................
Alcatel-Lucent BTS 2-1
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Scenario Overview

....................................................................................................................................................................................................................................

Final Checks 2-30

....................................................................................................................................................................................................................................
2-2 Alcatel-Lucent BTS
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Scenario Preparation Before Going Onsite
Before Going Onsite
....................................................................................................................................................................................................................................

Before Going Onsite

Preparation Before Going Onsite


Overview
Before going onsite, you must check that the following information and supplies are
available:
• All “Prerequisites” (p. 1-3) are met
• The customer has been informed of the following information.
You must indicate:
– Date and time
– Site name and address
– Purpose of operation.
• Personnel are available (refer to “Scheduling” (p. 1-5))
• “Site Specific Information” (p. 1-4) is available
• “Tools” (p. 1-7) are available and ready for operation
• “Supplies” (p. 1-7) are available and ready for operation
• “Applicable Documents” (p. 1-8) is available.
Ensure that the technical release level of the delivered board is in accordance with the
BSS hardware technical release document.
Ensure that the method used at the BSS site is at the same level as at the OMC-R.

....................................................................................................................................................................................................................................
Alcatel-Lucent BTS 2-3
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Scenario Preparation Before You Start
Before You Start
....................................................................................................................................................................................................................................

Before You Start

Preparation Before You Start


Checks
Perform the following operations:
• Check that all “Prerequisites” (p. 1-3) are met
• Check the availability of all necessary “Tools” (p. 1-7) and “Supplies” (p. 1-7)
• Inform the operator.
Attention: Among the “Cases” (p. 1-2) and the “Options” (p. 1-2), identify which
cases and options apply to you.

Required Knowledge
You must be familiar with the following:
• Safety Rules and Precautions
• “Telecom/Supervision Outage and Operating Impact” (p. 1-6)
• Reverse Procedure
• “Grouped Task Sequence” (p. 1-2)
• Operating Hints
• How to document Faults and Anomalies.

....................................................................................................................................................................................................................................
2-4 Alcatel-Lucent BTS
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Scenario Scenario Description Overview
Scenario Description
....................................................................................................................................................................................................................................

Scenario Description

Scenario Description Overview


Overview
This section describes how to add a TRE to an equipped 9100 BTS, lightRadio 9711/9712
Base Station.

....................................................................................................................................................................................................................................
Alcatel-Lucent BTS 2-5
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Scenario Initial Checks
Scenario Description
....................................................................................................................................................................................................................................

Initial Checks
Procedure
Perform the following checks:
...................................................................................................................................................................................................

1 Perform an Audit Alarm/State for the BSS.


Case/Option C1 C2 C3 C4
Site OMC-R
Time/Task 10 min.
Outage None.
...................................................................................................................................................................................................

2 View Status of Managed Objects and Alarms for impacted BTS.


Note: Print the report.
Case/Option C1 C2 C3 C4
Site OMC-R
Time/Task 5 min.
Outage None.
E...................................................................................................................................................................................................
N D O F S T E P S

....................................................................................................................................................................................................................................
2-6 Alcatel-Lucent BTS
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Scenario Prepare Add TRE Logical
Scenario Description
....................................................................................................................................................................................................................................

Prepare Add TRE Logical


Overview
Attention: For C2: Use a test frequency.
In order to create a required configuration, it is possible to add more than one TRX. In
this case, modify all the logical parameters at the same time in the same PRC.

Create Backup PRC


Create the backup PRC:
...................................................................................................................................................................................................

1 Create PRC backup in restricted mode.


Note: The PRC backup is necessary for the “Reverse Procedure” (p. 2-23).
The PRC opens automatically.
Case/Option C1 C2 C3 C4
Site OMC-R
Time/Task 30 sec.
Outage None.
...................................................................................................................................................................................................

2 Copy OMC Cells to PRC backup.


Note: Only copy the impacted cells.
Case/Option C1 C2 C3 C4
Site OMC-R
Time/Task 1 min. 30 sec./ cell
Outage None.
...................................................................................................................................................................................................

3 Check PRC (without forcing Administrative State).


Case/Option C1 C2 C3 C4
Site OMC-R
Time/Task 2 min.
Outage None.
...................................................................................................................................................................................................

4 Close PRC backup.


....................................................................................................................................................................................................................................
Alcatel-Lucent BTS 2-7
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Scenario Prepare Add TRE Logical
Scenario Description
....................................................................................................................................................................................................................................
Case/Option C1 C2 C3 C4
Site OMC-R
Time/Task 30 sec.
Outage None.
E...................................................................................................................................................................................................
N D O F S T E P S

Configure Cells
Configure the cells:
...................................................................................................................................................................................................

1 Create PRC (PRC1).


Case/Option C1 C2 C3 C4
Site OMC-R
Time/Task 1 min.
Outage None.
...................................................................................................................................................................................................

2 Copy OMC Cells to PRC.


Note: Copy the impacted cells.
Case/Option C1 C2 C3 C4
Site OMC-R
Time/Task 1.5 min./ cell
Outage None.
...................................................................................................................................................................................................

3 Change Cell Type for the existing cell to concentric, if necessary.


Case/Option C1 C2 C3 C4
Site OMC-R
Time/Task 0.5 min./ cell
Outage None.
...................................................................................................................................................................................................

4 Set Cell Telecom Parameters, change the frequency range from p_gsm to p_gsm_dcs, if
necessary.

....................................................................................................................................................................................................................................
2-8 Alcatel-Lucent BTS
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Scenario Prepare Add TRE Logical
Scenario Description
....................................................................................................................................................................................................................................
Note: Check the PC parameters minutes toggle and change the parameters, if
necessary.
Set the parameter EN_ANTENNA_HOPPING to enable, if required.
Case/Option C1 C2 C3 C4
Site OMC-R
Time/Task 0.5 min./ cell
Outage None.
...................................................................................................................................................................................................

5 Create Radio Frequency.


Add a new frequency according to the Frequency Plan.
Case/Option C1 C2 C3 C4
Site OMC-R
Time/Task 1 min.
Outage None.
...................................................................................................................................................................................................

6 Modify Frequency Hopping System.


Case/Option C1
Site OMC-R
Time/Task 2 min.
Outage None.
...................................................................................................................................................................................................

7 Create TRX.
Case/Option C1 C2 C3 C4
Site OMC-R
Time/Task 0.5 min./ TRX
Outage None.
...................................................................................................................................................................................................

8 Configure TRX.
Set TRX attributes to main or secondary and inner or outer, depending on the BTS and
cell zone where the TRE is added.
Also set the value of TRX_PREF_MARK, if needed.

....................................................................................................................................................................................................................................
Alcatel-Lucent BTS 2-9
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Scenario Prepare Add TRE Logical
Scenario Description
....................................................................................................................................................................................................................................
Case/Option C1 C2 C3 C4
Site OMC-R
Time/Task 0.5 min./ TRX
Outage None.
...................................................................................................................................................................................................

9 Configure Logical Channels.


Case/Option C1 C2 C3 C4
Site OMC-R
Time/Task 2 min.
Outage None.
...................................................................................................................................................................................................

10 Configure TRX Channel Hopping Law.


Case/Option C1
Site OMC-R
Time/Task 1 min.
Outage None.
...................................................................................................................................................................................................

11 Synchronize PRC with SC.


Case/Option C1 C2 C3 C4
Site OMC-R
Time/Task 1 min.
Outage None.
...................................................................................................................................................................................................

12 Check PRC without forcing Administrative State.


Case/Option C1 C2 C3 C4
Site OMC-R
Time/Task 2 min.
Outage None.
E...................................................................................................................................................................................................
N D O F S T E P S

....................................................................................................................................................................................................................................
2-10 Alcatel-Lucent BTS
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Scenario Activate PRC
Scenario Description
....................................................................................................................................................................................................................................

Activate PRC
Overview
Attention: Perform this section only in case BTS is attached to an 9120 BSC with
Radio Hopping or No Hopping defined on the impacted cell.

Procedure
Activate the PRC:
...................................................................................................................................................................................................

1 If Radio Hopping or No Hopping has been defined on the impacted cell and BTS is
attached to an 9120 BSC,activate PRC (PRC1).
Choose to activate using these options:
• Queued Activation
• With Cell cleanup
• Without forcing Administrative State.
Display Pending Activations List, to see when the activation is finished.
Note: The activation time depends on the number of cells.
During the activation, there is a supervision outage for 1.5 min.
Telecom and GPRS outage: 1 min./cell only for C1.
As there is a new TRX, if it has a higher priority than the old TRX, calls and packet
traffic are cut on the lower priority TRX.
Attention: During the activation, the impacted cell(s) become(s) yellow and the GSM
Alarm is Loss-of-TCH. This alarm disappears when the TRE hardware installation is
finished.
Case/Option C1 C2 C3 C4
Site OMC-R
Time/Task 5 min./ cell
Outage START1
END1
Refer to the“Telecom/Supervision Outage and Operating Impact” (p. 1-6).
...................................................................................................................................................................................................

2 Optionally, View Last PRC log Activation.

....................................................................................................................................................................................................................................
Alcatel-Lucent BTS 2-11
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Scenario Activate PRC
Scenario Description
....................................................................................................................................................................................................................................
Case/Option C1 C2 C3 C4
Site OMC-R
Time/Task 1 min.
Outage None.
...................................................................................................................................................................................................

3 Close PRC (PRC1).


Case/Option C1 C2 C3 C4
Site OMC-R
Time/Task 1 min.
Outage None.
...................................................................................................................................................................................................

4 Note: C5
3G/4G logical configuration impacting the MC TREs must be performed before
continuing with the procedure. See Alcatel-Lucent 9353 Wireless Management System -
MC-TRX Configuration and Activation or Alcatel-Lucent LTE FDD - Configuration and
Management for LTE.
Case/Option C5
Site -
Time/Task -
Outage -
...................................................................................................................................................................................................

5 Inform the BTS site when the PRC activation (or configuration for other standard) is
finished.
Case/Option All (EXCH)
Site OMC-R
Time/Task 1 min.
Outage None.
E...................................................................................................................................................................................................
N D O F S T E P S

....................................................................................................................................................................................................................................
2-12 Alcatel-Lucent BTS
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Scenario Install TRE Hardware
Scenario Description
....................................................................................................................................................................................................................................

Install TRE Hardware


Overview
Attention: In order to create the required configuration, it is possible to add more
than one TRE/TWIN TRA/MC TRE.
Check if O1/O2/O3/O4/C1 apply.

Procedure
Install the TRE hardware:
...................................................................................................................................................................................................

1 Begin HW Modification.
Case/Option C1 C2 C3 C4 C5
Site BTS
Time/Task 1 min.
Outage None.
...................................................................................................................................................................................................

2 Install and cable the TRE/TWIN TRA/MC TRE accordingly.


Wait until the new MC TRE/TWIN TRA modules are displayed in the BTS NEM. To
refresh the list of modules displayed perform Reload BTS Data. For MC TREs to be used
for other standards connect also the CPRI link.
Note: Use the Alcatel-Lucent 9100 Base Station - Hardware Description for the
appropriate BTS type.
Case/Option C1 C2 C3 C4 C5
Site BTS
Time/Task 3 min./ board
Outage None.
...................................................................................................................................................................................................

3 Initialize Single TRE (the added TRE).


Note: Do not perform this task for TWIN TRA or MC TRE.

....................................................................................................................................................................................................................................
Alcatel-Lucent BTS 2-13
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Scenario Install TRE Hardware
Scenario Description
....................................................................................................................................................................................................................................
Case/Option C1 C2 C3
Site BTS
Time/Task 2 min./ TRE
Outage None.
...................................................................................................................................................................................................

4 For the impacted MC TREs perform:


• Connect the Ethernet cable between NEM PC and TEST interface of the impacted MC
TRE
• Open BTS Commissioning window and launch Multicarrier SW Preload
Note: The PC used for BTS NEM must have the Windows Firewall disabled during
this step.
Case/Option O4
Site BTS
Time/Task 5 min./ TRE
Outage None.
...................................................................................................................................................................................................

5 End HW Modification.
Select the TWIN TRA Settings if the BTS is equipped with TWIN TRA.
Select the Multicarrier Settings if the BTS is equipped with MC TREs.
End Commissioning is automatically launched. For commissioning take into account only
the impacted modules.
Note: If a new MC TRE module is present in the BTS cabinet and O4 doesn't apply,
the task can take up to 115 min.
The TWIN TRA Settings and Multicarrier Settings windows automatically open if the
BTS is equipped with a TWIN TRA/MC TRE modules.
No operator action is allowed until the hardware modifications are accepted.
This triggers the BTS to poll equipment.

....................................................................................................................................................................................................................................
2-14 Alcatel-Lucent BTS
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Scenario Install TRE Hardware
Scenario Description
....................................................................................................................................................................................................................................
Case/Option C1 C2 C3 C4 C5
Site BTS
Time/Task 12 min.
Outage None.
...................................................................................................................................................................................................

6 The BSC sends a report to the OMC-R.


Note: Automatic action. Concurrent with the action below.
Case/Option C1 C2 C3 C4 C5
Site -
Time/Task -
Outage -
...................................................................................................................................................................................................

7 The BTS triggers a hardware audit.


Note: Automatic action. Concurrent with the action above.
Case/Option C1 C2 C3 C4 C5
Site -
Time/Task -
Outage -
...................................................................................................................................................................................................

8 Create BTS Sector and/or TRE (add TRE/TWIN TRA on the selected sector).
Case/Option O1 O2.1 O2.2
Site OMC-R
Time/Task 1 min.
Outage None.
...................................................................................................................................................................................................

9 Create BTS Sector and/or TRE (add two TREs for each TWIN TRA added on the selected
sectors)

....................................................................................................................................................................................................................................
Alcatel-Lucent BTS 2-15
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Scenario Install TRE Hardware
Scenario Description
....................................................................................................................................................................................................................................
Case/Option O2.3
Site OMC-R
Time/Task 1 min.
Outage None.
...................................................................................................................................................................................................

10 Create BTS Sector and/or TRE (add the same number of TREs according to the
configuration of each MC TRE added on the selected sectors)
Case/Option O3
Site OMC-R
Time/Task 1 min.
Outage None.
...................................................................................................................................................................................................

11 If the number of TWIN TRAs/MC TREs is more than 6/ MBO cabinet, Add PM12
module.
Case/Option C4
Site BTS
Time/Task 5 min.
Outage None.
...................................................................................................................................................................................................

12 The BSC allocates TCU and Abis timeslots.


Note: Automatic action.
If moving existing TREs from the initial 9120 BSC TCUC, there is 24 sec. Telecom
Outage for the impacted TREs.
Case/Option C1 C2 C3 C4
Site -
Time/Task 2 min. for 9120 BSC.
15 sec. for 9130 BSC Evolution.
Outage None.
...................................................................................................................................................................................................

13 The BSC configures the BSC transmission settings.


Note: Automatic action.

....................................................................................................................................................................................................................................
2-16 Alcatel-Lucent BTS
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Scenario Install TRE Hardware
Scenario Description
....................................................................................................................................................................................................................................
Case/Option C1 C2 C3 C4
Site -
Time/Task 6 min. for 9120 BSC.
15 sec. for 9130 BSC Evolution.
Outage START2
END2
Refer to the “Telecom/Supervision Outage and Operating Impact” (p. 1-6).
...................................................................................................................................................................................................

14 The BSC configures the BTS transmission settings.


Note: Automatic action.
Case/Option C1 C2 C3 C4
Site -
Time/Task 2 min. for 9120 BSC.
15 sec. for 9130 BSC Evolution.
Outage None.
...................................................................................................................................................................................................

15 On the BTS site, wait 15 minutes from the last operator action (from End HW
Modification).
Case/Option C1 C2 C3 C4 C5
Site BTS
Time/Task -
Outage -
...................................................................................................................................................................................................

16 Init OSF for the added MC TREs.


Case/Option C5
Site BTS
Time/Task 4 min.
Outage None.
E...................................................................................................................................................................................................
N D O F S T E P S

....................................................................................................................................................................................................................................
Alcatel-Lucent BTS 2-17
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Scenario Activate PRC
Scenario Description
....................................................................................................................................................................................................................................

Activate PRC
Overview
Attention: Perform this section only:
• In case BTS is attached to an 9120 BSC with Base Band Hopping defined on the
impacted cell.
• In case BTS is attached to an 9130 BSC Evolution, whatever the hopping mode
defined on the impacted cell.

Procedure
Activate the PRC:
...................................................................................................................................................................................................

1 Open PRC (PRC1), if not already opened.


Case/Option C1 C2 C3 C4
Site OMC-R
Time/Task 1 min.
Outage None.
...................................................................................................................................................................................................

2 Activate PRC (PRC1).


Choose to activate using these options:
• Queued Activation
• With Cell cleanup
• Without forcing Administrative State.
Display Pending Activations List, to see when the activation is finished.
Note: The activation time depends on the number of cells.
During the activation, there is a supervision outage for 1.5 min.
Telecom and GPRS outage: 1 min./cell only for C1.
In case BTS O&M remains locked at the end of the activation perform unlock BTS
O&M Capability.

....................................................................................................................................................................................................................................
2-18 Alcatel-Lucent BTS
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Scenario Activate PRC
Scenario Description
....................................................................................................................................................................................................................................
Case/Option C1 C2 C3 C4
Site OMC-R
Time/Task 5 min./ cell
Outage START1
END1
Refer to the “Telecom/Supervision Outage and Operating Impact” (p. 1-6).
...................................................................................................................................................................................................

3 Close PRC (PRC1).


Case/Option C1 C2 C3 C4
Site OMC-R
Time/Task 1 min.
Outage None.
E...................................................................................................................................................................................................
N D O F S T E P S

....................................................................................................................................................................................................................................
Alcatel-Lucent BTS 2-19
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Scenario Call Tests
Scenario Description
....................................................................................................................................................................................................................................

Call Tests
Procedure
Perform the call tests:
...................................................................................................................................................................................................

1 Call Test on the BTS.


Perform this task in parallel with the OMC-R tasks in order to save time. Unlock Cell
from the Call Test task is not necessary.
Case/Option C1 C2 C3 C4
Site BTS
Time/Task 5 min./ cell
Outage -
...................................................................................................................................................................................................

2 Display USD Detailed Cell Information to check if calls are made on impacted cells.
Case/Option All (CHECK)
Site OMC-R
Time/Task 5 min./ cell
Outage -
E...................................................................................................................................................................................................
N D O F S T E P S

....................................................................................................................................................................................................................................
2-20 Alcatel-Lucent BTS
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Scenario Lock Test Frequency
Scenario Description
....................................................................................................................................................................................................................................

Lock Test Frequency


Procedure
Lock the test frequency:
...................................................................................................................................................................................................

1 Lock the TRE/TWIN TRA using


Lock BSC or BTS Function
Case/Option O2
Site OMC-R
Time/Task 1 min.
Outage None.
...................................................................................................................................................................................................

2 Check that the test frequency is locked.


E...................................................................................................................................................................................................
N D O F S T E P S

....................................................................................................................................................................................................................................
Alcatel-Lucent BTS 2-21
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Scenario Final Checks
Scenario Description
....................................................................................................................................................................................................................................

Final Checks
Procedure
Perform the final checks:
...................................................................................................................................................................................................

1 Perform an Audit/Alarm State for the BSS.


Case/Option C1 C2 C3 C4
Site OMC-R
Time/Task 10 min.
Outage None.
...................................................................................................................................................................................................

2 View Status of Managed Objects and Alarms for the impacted BTS.
Display Cell Report for the impacted cells.
Note: Compare the status of Managed Objects and alarms with the results printed in
the “Initial Checks” (p. 2-6).
Case/Option C1 C2 C3 C4
Site OMC-R
Time/Task 10 min.
Outage None.
E...................................................................................................................................................................................................
N D O F S T E P S

....................................................................................................................................................................................................................................
2-22 Alcatel-Lucent BTS
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Scenario Activate Backup PRC
Reverse Procedure
....................................................................................................................................................................................................................................

Reverse Procedure

Activate Backup PRC


Procedure
Activate the backup PRC:
...................................................................................................................................................................................................

1 Open PRC backup.


Case/Option C1 C2 C3 C4
Site OMC-R
Time/Task 1 min.
Outage None.
...................................................................................................................................................................................................

2 Activate PRC.
Activate the PRC backup using the options:
• Queued Activation
• Without Cell cleanup
• Without forcing Administrative State.
Display Pending Activations List, to see when the activation is finished.
Case/Option C1 C2 C3 C4
Site OMC-R
Time/Task 5 min./ cell
Activation time is 5 minutes for one cell. Total time depends on the number of cells.
Outage None.
...................................................................................................................................................................................................

3 Close PRC backup.

....................................................................................................................................................................................................................................
Alcatel-Lucent BTS 2-23
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Scenario Activate Backup PRC
Reverse Procedure
....................................................................................................................................................................................................................................
Case/Option C1 C2 C3 C4
Site OMC-R
Time/Task 1 min.
Outage None.
...................................................................................................................................................................................................

4 Inform the BTS site when the PRC activation (or configuration for other standard) is
finished.
Case/Option All (EXCH)
Site OMC-R
Time/Task 1 min.
Outage None.
E...................................................................................................................................................................................................
N D O F S T E P S

....................................................................................................................................................................................................................................
2-24 Alcatel-Lucent BTS
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Scenario Uninstall TRE Hardware
Reverse Procedure
....................................................................................................................................................................................................................................

Uninstall TRE Hardware


Procedure
Uninstall the TRE hardware:
...................................................................................................................................................................................................

1 Disable SBLs Other than BTS_TEL (TRE/TWIN TRA/MC TRE).


Case/Option C1 C2 C3 C4 C5
Site BTS
Note: Action performed at the BTS NEM.
For a two TRX configuration, disable both SBLs related to the TWIN TRA.
Time/Task 1 min.
Outage None.
...................................................................................................................................................................................................

2 Begin HW Modification.
Case/Option C1 C2 C3 C4 C5
Site BTS
Time/Task 1 min.
Outage None.
...................................................................................................................................................................................................

3 Uninstall TRE/TWIN TRA/MC TRE hardware from the BTS.


Case/Option C1 C2 C3 C4 C5
Site BTS
Time/Task 3 min./ board
Outage None.
...................................................................................................................................................................................................

4 Remove HW.

....................................................................................................................................................................................................................................
Alcatel-Lucent BTS 2-25
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Scenario Uninstall TRE Hardware
Reverse Procedure
....................................................................................................................................................................................................................................
Case/Option C1 C2 C3 C4
Site BTS
Time/Task 1 min.
Outage None.
...................................................................................................................................................................................................

5 End HW Modification.
Case/Option C1 C2 C3 C4 C5
Site BTS
Time/Task 5 min.
Outage None.
...................................................................................................................................................................................................

6 The BSC sends a report to the OMC-R.


Note: Automatic action. Concurrent with the action below.
Case/Option All (EXCH)
Site -
Time/Task -
Outage None.
...................................................................................................................................................................................................

7 The BTS triggers a hardware audit.


Note: Automatic action.
Case/Option C1 C2 C3 C4
Site BTS
Time/Task -
Outage None.
...................................................................................................................................................................................................

8 Delete BTS Sector and/or TRE (delete TRE/TWIN TRA/MC TRE on the selected sector).

....................................................................................................................................................................................................................................
2-26 Alcatel-Lucent BTS
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Scenario Uninstall TRE Hardware
Reverse Procedure
....................................................................................................................................................................................................................................
Case/Option O1 O2.1 O2.2
Site OMC-R
Time/Task 1 min.
Outage None.
...................................................................................................................................................................................................

9 Delete BTS Sector and/or TRE (delete both TREs from the selected sectors).
Case/Option O2.3
Site OMC-R
Time/Task 1 min.
Outage None.
...................................................................................................................................................................................................

10 Delete BTS Sector and/or TRE (delete all TREs corresponding to the MC TRE from the
selected sectors).
Case/Option O3
Site OMC-R
Time/Task 1 min.
Outage None.
...................................................................................................................................................................................................

11 If needed Remove PM12


Case/Option C4
Site BTS
Time/Task 5 min.
Outage None.
...................................................................................................................................................................................................

12 The BSC allocates TCU and Abis timeslots.


Note: Automatic action.
Case/Option C1 C2 C3 C4
Site -
Time/Task 2 min. for the 9120 BSC.
15 sec. for the 9130 BSC Evolution.

....................................................................................................................................................................................................................................
Alcatel-Lucent BTS 2-27
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Scenario Uninstall TRE Hardware
Reverse Procedure
....................................................................................................................................................................................................................................
Outage None.
...................................................................................................................................................................................................

13 The BSC reconfigures BSC transmission settings.


Note: Automatic action.
If moving existing TREs from the initial 9120 BSC TCUC, there is a 24 minute
Telecom Outage for the impacted TREs.
Case/Option C1 C2 C3 C4
Site -
Time/Task 2 min. for the 9120 BSC.
15 sec. for the 9130 BSC Evolution.
Outage None.
...................................................................................................................................................................................................

14 The BSC configures the BTS transmission settings.


Note: Automatic action.
Case/Option C1 C2 C3 C4
Site -
Time/Task 2 min. for the 9120 BSC.
15 sec. for the 9130 BSC Evolution.
Outage None.
E...................................................................................................................................................................................................
N D O F S T E P S

....................................................................................................................................................................................................................................
2-28 Alcatel-Lucent BTS
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Scenario Call Tests
Reverse Procedure
....................................................................................................................................................................................................................................

Call Tests
Procedure
Perform the call tests:
...................................................................................................................................................................................................

1 Call Test on the BTS.


Perform this task in parallel with the OMC-R tasks in order to save time. Unlock Cell
from the Call Test task is not necessary.
Case/Option C1 C2 C3 C4
Site BTS
Time/Task 5 min./ cell
Outage -
...................................................................................................................................................................................................

2 Display USD Detailed Cell Information to check if calls are made on impacted cells.
Case/Option All (CHECK)
Site OMC-R
Time/Task 5 min./ cell
Outage -
E...................................................................................................................................................................................................
N D O F S T E P S

....................................................................................................................................................................................................................................
Alcatel-Lucent BTS 2-29
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Scenario Final Checks
Reverse Procedure
....................................................................................................................................................................................................................................

Final Checks
Procedure
Perform the final checks:
...................................................................................................................................................................................................

1 Perform an Audit/Alarm State for the BSS.


Case/Option C1 C2 C3 C4
Site OMC-R
Time/Task 10 min.
Outage None.
...................................................................................................................................................................................................

2 View Status of Managed Objects and Alarms for the impacted BTS.Display Cell Report
for the impacted cells.
Note: Compare the status of Managed Objects and alarms with the results printed in
the “Initial Checks” (p. 2-6).
Case/Option C1 C2 C3 C4
Site OMC-R
Time/Task 10 min.
Outage None.
E...................................................................................................................................................................................................
N D O F S T E P S

....................................................................................................................................................................................................................................
2-30 Alcatel-Lucent BTS
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Index

D document support, ix

.............................................................

P phone numbers

for document support, ix

....................................................................................................................................................................................................................................
Alcatel-Lucent BTS IN-1
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014
Index

....................................................................................................................................................................................................................................

....................................................................................................................................................................................................................................
IN-2 Alcatel-Lucent BTS
9YZ-03803-0450-RJZZA B12
Issue 7 September 2014