Professional Documents
Culture Documents
1-Classroom (PERT-CPM and Labor)
1-Classroom (PERT-CPM and Labor)
7 7
3 8
Gravel Bed 3 E
for footing 13I13
2nd Quarter
4rth Quarter
312442.07 #DIV/0! 0 52 16 #DIV/0! #DIV/0! 3 #DIV/0! #DIV/0! CONCRETE WORKS:
242476.14 #DIV/0! 0 10 1 #DIV/0! #DIV/0! 30 #DIV/0! #DIV/0! MASONRY WORKS:
426827.85 #DIV/0! 0 3 1 #DIV/0! #DIV/0! 8 #DIV/0! #DIV/0! ROOFING WORKS:
214808.33 #DIV/0! 0 0 5 #DIV/0! #DIV/0! 10 #DIV/0! #DIV/0! DOORS & WINDOWS:
25007.77 2,500.78 10 0 10 25,007.77 #DIV/0! 2 5,001.55 0.19% TILEWORKS:
225590.99 #DIV/0! 0 0 1 #DIV/0! #DIV/0! 14 #DIV/0! #DIV/0! PAINTING WORKS:
84519.56 1,625.38 52 0 16 26,006.02 #DIV/0! 17 27,631.39 1.02% ELECTRICAL WORKS:
165,648.67 16,564.87 10 10 165,648.67 6.14% PLUMBING FIXTURES:
24,981.04 351.85 71 #DIV/0! #DIV/0! 18 6,333.22 0.23% PLUMBING WORKS:
#DIV/0! #DIV/0!
#DIV/0!
5th QUARTER
242,476.14 #DIV/0! 0 8 #DIV/0! #DIV/0! MASONRY WORKS:
25,007.77 2,500.78 10 8 20,006.21 0.74% TILEWORKS:
225,590.99 #DIV/0! 0 4 #DIV/0! #DIV/0! PAINTING WORKS:
#DIV/0! #DIV/0!
Commulati Commulative
% Planned % Actual
0 0.0% 0.00% 0
1 #DIV/0! #DIV/0! 0%
2 #DIV/0! #DIV/0! 0%
3 0.00% #DIV/0! 0%
4 #DIV/0! #DIV/0! 0%
Duration
Days Start
1 MOBILIZATION 3 1
1.1 Clearing & Grubbing: 7 4
1.2 Structural Excavation: 7 11
1.3 Backfilling and Compaction: 2 53
1.4 Gravel Bedding: 0 11
1.5 Select Fill: 12 53
1.6 Soil Poisoning: 2 16
2 CONCRETE WORKS: 0 22 43 99
3 STEEL WORKS: #REF! 11 38 54 66
4 MASONRY WORKS: 0 56 69
5 CARPENTRY WORKS: #REF! 18 102
6 ROOFING WORKS: 0 80
7 ROOF FRAMING WORKS: #REF! 65
8 DOORS & WINDOWS: 0 102
9 TILEWORKS: 10 119
10 PAINTING WORKS: 0 107
11 ELECTRICAL WORKS: 52 56
12 PLUMBING FIXTURES: 10 109
13 PLUMBING WORKS: 71 38 125
14 DEMOBILIZATION 3 128
works,Scaff.& Form oil Formworks,Scaffoldings & Form oil Plumbing and Tile Works
for Column for Beam G
D 26I27
16I17
8 75
Scaffoldings
Removal of Forms Col. J
40I
& Beam Fabrication &Inst. 41
Concreting for 4 of rebars for Concreting Preparation for Fabrication & Inst. Inst.of roofing,gutter,ridge
Footing & Col. Beam for beam F I Slab of Roof frame downspout & etc.
21I2 I K L
37I 42I42
1 37I 52I52
37
37
19 4 10 5 15 Fab.&Inst.of 9
rebars slab
Fabricattion & Ins. Masonry
of rebars for wall footing M O P
54I5 64I6 67I6
4 4 7
2 18 3
Electrical
37
17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74
0
0 0
0 0 0 0 0 0 0 0 0 0 0 0
0
###
###
###
###
###0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0###
###
######0 0 0 0 0 0 0 0 0 0 ###
### ###0 0 0 0 0 0 0 0 0 0###
###
###0 0 0 0 0 0
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
######
###
###
###
######
###
###
###
###
###
###
###
###
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### 0.00 ### 0.00 0.00 0.00 ### ### 0.00 0.00 ### ### ### ### 0.00 ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
#REF! #REF! #REF! #REF! 0.09% #REF! 2.75% #REF! #REF!
U
Concreting 4 110I1
11
for slab Ceiling Works Septic Tank Move-out
Painting Works
N Q R V W X
64I6 79I79 98 I98 124 127l1 130l1
100 CALENDAR DAYS
I124 27
4 30
3 5 13 3 3
Plastering Works
33
75
75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125 126
000
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 ###
0 0###
0###
0###
0###
0 0 0 0 0 0 00 0 0 0 0 0 0 0 0 0 0 0 0 0
###
###
### ###0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
###
00 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0.001
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0.01 0.01 0.01 0 0 0.01 0.01 0.01 0.01 0.01
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
### ### ### ### ### 0.00 ### ### ### ### 0.00 0.00 ### ### ### ### ### ### ### ### 0.00 ### ### ### ### 0.00 ### ### ### ### ### ### 0.00 0.00 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
#REF! #REF! 0.51% 0.51% #REF! #REF! 3.77% 0.65%
0 0
0.0009 0
0.00
0
0.00 0.00 0.00 0.00 0.00 0.00 1 2 3 4 5 6 7 8
0.19% 0.22% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
#REF! 0 0.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5,001.55
#REF!
Month 5
19 20
#REF! 0.00%
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Republic of the Philippines
PROVINCE OF MISAMIS ORIENTAL
Cagayan de Oro City
Republic of the Philippines
PROVINCE OF MISAMIS ORIENTAL
Cagayan de Oro City
PROVINCIAL ENGINEERS OFFICE
Equipment: 2,310.43
- Excavator/Backhoe
22.0 cu.m x 1 hr =
15 cu.m
convert to day:
say
Add Rainfull Days:
Labor: 2,738.63
1 Foreman- 1.94 x
3 labor- 1.94 x
SLAB PREPARATION:
Backfilling: 1.94
Filling: 0.35
2.29 days
Laying of gravel: 1.00 days
additional days 2.00
for compaction: 5.29 days
Labor: 2,152.71
1 Foreman- 1.92 x
2 labor- 1.92 x
Laying of gravel: 1.00 days
additional days 2 days
for compaction: 3.00 days
Labor: 693.31
1 Foreman- 0.35 x
5 labor- 0.35 x
2 CONCRETE WORKS:
Labor: 16,181.80
1 Foreman- 4.86 x
3 mason- 4.86 x
6 labor- 4.86 x
Curing: 15
Add Rainful Days 12
32.00
Footing: 4 days
Column: 15 days
Beam: 10 days
Slab: 3 days
32
Column:
1.3 cu.m x 1 mday x
0.3 cu.m
Beam:
0.5 cu.m x 1 mday x
0.3 cu.m
Footing:
1.1 cu.m x 1 mday x
0.3 cu.m
Wall Footing:
2.7 cu.m x 1 mday x
0.3 cu.m
Slab:
6.0 cu.m x 1 mday x
0.3 cu.m
3 STEEL WORKS:
Labor: 21,958.80
1 Foreman- 6.59 x
3 Steelman 6.59 x
6 labor- 6.59 x
say
Footing: 4 days
WF: 2 days
Column: 4 days
Beam: 4 days
Slab 3 days
17
4 MASONRY WORKS:
Labor: 20,045.40
1 Foreman- 8.35 x
2 Mason 8.35 x
4 labor- 8.35 x
Add Rainful Days: 10
18.35
Wall: 15
ST: 3
18
5 CARPENTRY WORKS:
Labor: 34,780.60
1 Foreman- 19.1 x
2 Carpenter 19.1 x
2 labor- 19.1 x
RB:
Erecting forms:
16.00 sq.m x 1 hr x
1.86 sq.m
Removing Forms:
16 sq.m x 1 hr x
1.86 sq.m
Form oill application:
16 sq.ft x 0.6 mh x
100 sq.ft
Ceiling works:
Framing & Studs:
88.95 sq.m x 1 mday x
16 sq.m
Installation of Plywood:
88.954 sq.m x 1 mday x
30 sq.m
6 ROOFING WORKS:
Labor: 27,208.32
1 Foreman- 7.39 x
4 Steelman 7.39 x
6 labor- 7.39 x
Roof installation:
note: 35 pcs/man - days
Convert to Area: 2.16 sq.m
Labor: 37,157.68
1 Foreman- 15.48 x
2 steelman- 15.48 x
4 labor- 15.48 x
8 DOORS & WINDOWS:
Labor: 7,118.80
1 Foreman- 3.91 x
2 Skilled Installer 3.91 x
2 labor- 3.91 x
9 TILEWORKS:
Labor: 2,144.60
1 Foreman- 0.89 x
2 Skilled Installer- 0.89 x
4 labor- 0.89 x
10 PAINTING WORKS:
Labor: 12,097.04
1 Foreman- 5.04 x
2 Painter- 5.04 x
4 labor- 5.04 x
Add Rainful days: 8
13.04
11 ELECTRICAL WORKS:
Labor: 4,445.60
1 Foreman- 1.85 x
2 Electrician- 1.85 x
4 labor- 1.85 x
12 PLUMBING FIXTURES:
PLUMBING WORKS:
Labor: 3,701.88
1 Foreman- 2.52 x
1 Skilled Installer- 2.52 x
2 labor- 2.52 x
Forman
1.468 hr 2,310.43 ( 1x d x 538.4 )
2,310.43 = ( d 538.4 )
0.18 2,310.43 = 1411.4 d
0.50 days 1.64 = d
6.50
7.00 days
Forman
538.35 1,044.63 2,738.63 ( 1x d x 538.4 )
291.00 1,693.99 2,738.63 = ( d 538.4 )
2,738.63 2,738.63 = 1411.4 d
1.94 = d
Forman
538.35 1,034.42 2,152.71 ( 1x d x 538.4 )
291.00 1,118.29 2,152.71 = ( d 538.4 )
2,152.71 2,152.71 = 1120.4 d
1.92 = d
Forman
538.35 187.24 693.31 ( 1x d x 538.4 )
291.00 506.07 693.31 = ( d 538.4 )
693.31 693.31 = 1993.4 d
0.35 = d
Forman
538.35 2,614.53 16,181.80 ( 1x d x 538.4 )
349.20 5,087.73 16,181.80 = ( d 538.4 )
291.00 8,479.55 16,181.80 = 3332.0 d
16,181.80 4.86 = d
1 days = 0.6
8 mday
1 days = 0.2
8 mday
1 days = 0.5
8 mday
1 days = 1.1
8 mday
1 days = 2.5
8 mday
4.8 days
Forman
538.35 3,547.93 21,958.80 ( 1x d x 538.4 )
349.20 6,904.08 21,958.80 = ( d 538.4 )
291.00 11,506.79 21,958.80 = 3332.0 d
21,958.80 6.59 = d
1.06 day
1.47 day
15.00
16.5 days
17.00 days
Forman
538.35 4,495.03 20,045.40 ( 1x d x 538.4 )
349.20 5,831.39 20,045.40 = ( d 538.4 )
291.00 9,718.98 20,045.40 = 2400.8 d
20,045.40 8.35 = d
0
Forman
538.35 10,295.06 34,780.60 ( 1x d x 538.4 )
349.20 13,355.75 34,780.60 = ( d 538.4 )
291.00 11,129.79 34,780.60 = 1818.8 d
34,780.60 19.12 = d
Forman
538.35 3,979.08 27,208.32 ( 1x d x 538.4 )
349.20 10,324.11 27,208.32 = ( d 538.4 )
291.00 12,905.13 27,208.32 = 3681.2 d
27,208.32 7.39 = d
1 days = 1 day
10 mday
1.59 day
Forman
538.35 8,332.33 37,157.68 ( 1x d x 538.4 )
349.20 10,809.51 37,157.68 = ( d 538.4 )
291.00 18,015.84 37,157.68 = 2400.8 d
37,157.68 15.48 = d
Forman
538.35 2,107.16 7,118.80 ( 1x d x 538.4 )
349.20 2,733.62 7,118.80 = ( d 538.4 )
291.00 2,278.02 7,118.80 = 1818.8 d
7,118.80 3.91 = d
Forman
538.35 480.91 2,144.60 ( 1x d x 538.4 )
349.20 623.88 2,144.60 = ( d 538.4 )
291.00 1,039.81 2,144.60 = 2400.8 d
2,144.60 0.89 = d
Forman
538.35 2,712.67 12,097.04 ( 1x d x 538.4 )
349.20 3,519.14 12,097.04 = ( d 538.4 )
291.00 5,865.23 12,097.04 = 2400.8 d
12,097.04 5.04 = d
Forman
538.35 996.89 4,445.60 ( 1x d x 538.4 )
349.20 1,293.27 4,445.60 = ( d 538.4 )
291.00 2,155.44 4,445.60 = 2400.8 d
4,445.60 1.85 = d
Forman
538.35 1,356.13 3,701.88 ( 1x d x 538.4 )
349.20 879.65 3,701.88 = ( d 538.4 )
291.00 1,466.09 3,701.88 = 1469.6 d
3,701.88 2.52 = d
Total Labor:
-
#VALUE!
#VALUE!
From Roofing giadjust
Earth Works:
- = #VALUE!
- = #VALUE!
#VALUE! = x
Forman
#VALUE! ( 1x d x 538.4 )
#VALUE! = ( d 538.4 )
#VALUE! = 3332.0 d
#VALUE! = d
#VALUE!
Steelman Labor
+ ( x dx ) + ( 3x d x 291.00 )
+ ( d 0 ) + ( d 873 )
Steelman Labor
+ ( x dx ) + ( 3x d x 291.00 )
+ ( d 0 ) + ( d 873 )
Steelman Labor
+ ( x dx ) + ( 2x d x 291.00 )
+ ( d 0 ) + ( d 582 )
Steelman Labor
+ ( x dx ) + ( 5x d x 291.00 )
+ ( d 0 ) + ( d 1455 )
Skilled Labor
+ ( 3x dx 349.20 ) + ( 6x d x 291.00 )
+ ( d 1047.6 ) + ( d 1746 )
Skilled Labor
+ ( 3x dx 349.20 ) + ( 6x d x 291.00 )
+ ( d 1047.6 ) + ( d 1746 )
Column:
Skilled Labor
+ ( 2x dx 349.20 ) + ( 4x d x 291.00 ) - (
+ ( d 698.4 ) + ( d 1164 ) - =
- =
- =
Beam:
- (
- =
- =
Skilled Labor - =
+ ( 2x dx 349.20 ) + ( 2x d x 291.00 )
+ ( d 698.4 ) + ( d 582 )
skilled Labor
+ ( 4x dx 349.20 ) + ( 6x d x 291.00 )
+ ( d 1396.8 ) + ( d 1746 )
Steelman Labor
+ ( 2x dx 349.20 ) + ( 4x d x 291.00 )
+ ( d 698.4 ) + ( d 1164 )
Steelman Labor
+ ( 2x dx 349.20 ) + ( 4x d x 291.00 )
+ ( d 698.4 ) + ( d 1164 )
Steelman Labor
+ ( 2x dx 349.20 ) + ( 4x d x 291.00 )
+ ( d 698.4 ) + ( d 1164 )
Steelman Labor
+ ( 1x dx 349.20 ) + ( 2x d x 291.00 )
+ ( d 349.2 ) + ( d 582 )
mason- Labor
+ ( 3x dx 349.20 ) + ( 6x d x 291.00 )
+ ( d 1047.6 ) + ( d 1746 )
Forman Skilled
1x d x 538.4 ) + ( 2x
( d 538.4 ) + ( d 698.4
2400.8 d
d
Forman Skilled
1x d x 538.4 ) + ( 2x
( d 538.4 ) + ( d 698.4
2400.8 d
d
Masonry
x d x #REF! )
#REF! )
CARPENTRY WORKS: ROOFING WORKS: ROOF FRAMING WORKS: DOORS & WINDOWS:
### + 27,208.32 + 37,157.68 + 7,118.80
Skilled Labor
d x 349.20 ) + ( 4x d x
698.4 ) + ( d 1164
Skilled Labor
d x 349.20 ) + ( 4x d x
698.4 ) + ( d 1164
TILEWORKS: PAINTING WORKS: ELECTRICAL WORKS:
+ 2,144.60 + 12,097.04 + 4,445.60 +
291.00 )
164 )
291.00 )
164 )
PLUMBING FIXTURES:
3,701.88
DIRECT
SCOPE OF WORKS QTY UNIT UNIT COST COST
A MOBILIZATION
N DEMOBILIZATION
757,763.73
WEEKLY PHYSICAL ACCOMPLISHMENT (%)
Move-in/
Mobilization
0 1
0 0 3 3
3.00
TOTAL WEEK 1
OCM(12% of PROFIT VAT 12% (DC Relative No. of
DC) ( 10% OF DC) +IC) COST Weight days 1 2 3 4 5
3.00
4.0
62
Formworks,Scaff. Formworks,Scaff.
Excavation Footing,wall footing & Form oil for column & Form oil for Beam
& Septic tank
2 10 13 3
7.00 7 8
10 10 17 17 25 25
Removal of form
for col. & beam
Fabr.&Installation Pouring of Concrete 2
of Reinforcement bar for Footing Pouring of Concrete
for Footing & Col. for Column
1 5 6 9
3 10 10 14 14 29
6 10
0 0 0 0 0 0
0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0.01 0.01 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0
0 0 0 0 0.01 0 0.01 0.01 0.01 0.012 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0 0 0 0.01
5.03% 6.69% 8.58% 6.74% 6.32%
5.03% 11.73% 20.31% 27.04% 33.36%
52,103.88 69,317.24 88,820.32 69,736.87 6
52,103.88 121,421.12 210,241.44 279,978.31 34
Month 1
1 2 3 4 5
0.00% 0.00% 0.00% 0.00% 0.00%
Installation of Plumbing Pipes,
Fixtures & Tile Works
71
12
emoval of form 31 17
r col. & beam Fabr.&Installation
of Reinforcement bar
for Roof Beams Fabrication & Installation of
Pouring of Concrete Slab Preparation Roof Frame
11 for Roof Beam
9 12 13
4 10 5
29 29 33 33 43.0 43.0 48 48
15
Fabricattion & Ins.
of rebars for wall footing
2
15
45 45
0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0.01 0
0.01 0 0 0 0
0.01 0 0 0 0 0
0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0.018 0.02 0.01 0 0.003 0 0 0 0 0 0 0 0 0 0.01 0.01 0.01 0.01 0.015 0.01 0.01 0.01 0.01 0.01
6.32% 2.13% 6.72% 10.39%
33.36% 35.49% 42.21% 52.60%
65,446.17 22,028.26 69,610.13 107,581.99
345,424.48 367,452.74 437,062.86 544,644.85
Month 2
5 6 7 8
0.00% 0.00% 0.00% 1.19%
Scaffoldings
21
Installation of Doors
& Windows 4
Inst.of roofing,gutter,ridge
abrication & Installation of downspout & etc. Slab Concreting
Ceiling Works
14 17 20
63 63 72 72 75 75
15 3 33
60 72 63 75
Electrical Works
34
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0
0 0 0
0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0
0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.01 0.01 0.01 0.02 0.02 0.01 0.01
10.39% 11.68% 12.47% 10.86% 6.42%
52.60% 64.29% 76.76% 87.62% 94.04%
107,581.99 120,981.99 129,110.82 112,437.50
544,644.85 665,626.84 794,737.66 907,175.16
Month 3
8 9 10 11 12
1.19% 1.19% 0.00% 0.00% 0.00%
21
76 96
Construction
of Septic Tank Demobilization
Ceiling Works Painting Works
22 23 24 26
13 3 4
80 80 93 93 96 96 100
lastering Works
33
0.01
0 0
0.01
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0.004 0 0 0 0 0 0 0 0
0.012 0.007 0.01 0.01 0 0.0066 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.002 0 0 0.012 ### ### 101.00
6.42% 4.63% 3.22% 71400.00%
94.04% 98.67% 101.89% 71501.89%
66,514.40 47,979.90 33,328.17 7,898
973,689.56 1,021,669.46 1,054,997.63 8,953
Month 4
12 13 14 15
0.00% 0.00% 0.00% 0.00%
26 100 CALENDAR DAYS
100
b.1
b.2
b.3
b.4
2nd Quarter
277
694
Item 200
3rd Quarter
8,133
12437.202
per day no.of day no of days total %
in qrter
#REF! #REF!
- #DIV/0! -
#REF! #REF!