KURVA S PEKERJAAN

No Pekerjaan Harga Pekerjaan durasi Bobot hari


% 1 2 3 4 5 6 7 8

1 Galian Tanah Rp 4,410,000.00 8 38.65 4.83 4.83 4.83 4.83 4.83 4.83 4.83 4.83

2 Lantai Kerja Rp 1,500,000.00 2 13.15 6.57 6.57

3 Pasangan Batu Kali Rp 4,500,000.00 4 39.44 13.15 13.15 13.00 0.15

4 Urugan Pasir Rp 1,000,000.00 2 8.76 4.38 4.38


Jumlah Rp 11,410,000.00 100.00 4.83 9.21 15.79 11.40 17.98 17.98 17.83 4.98
Jumlah komulatif ### 4.83 14.04 29.83 41.24 59.21 77.19 95.02 100.00