Download as pdf or txt
Download as pdf or txt
You are on page 1of 8

PRODUCTION AND OPERATIONS

MANAGEMENT

IMT - 15

(Assignment Questions)

Institute of Management Technology


Centre for Distance Learning
Ghaziabad
2
IMT CENTRE FOR DISTANCE LEARNING
GHAZIABAD
Distance Learning Programme

PRODUCTION AND OPERATIONS MANAGEMENT

Notes:
a. Write answers in your own words as far as possible and refrain from copying from text books/handouts.
b. All answers should be of 200 words.
c. Write on one side of the paper.
d. Answers of Assignments I, II, III and IV (Case Study) must be sent together.
e. Mail the answer sheet along with the copy of the assignment for evaluation and return.

FIRST SET OF ASSIGNMENTS Assignment-I = 5 Marks

ASSIGNMENT-I

1. What are production/operation systems? Discuss its components, giving examples from both service and non-
service organizations.
2. What do you understand by product design?
3. What are the competitive priorities of a firm?
4. Why is layout planning necessary?
5. Explain any three of the following terms:
(a) Aggregate production planning
(b) Master production plan
(c) Rough cut capacity
(d) Scheduling

3
SECOND SET OF ASSIGNMENTS Assignment-II = 5 Marks

ASSIGNMENT-II

1. Write short notes on following:


(a) Acceptance sampling.
(b) OC Curve.
2. What do you mean by PERT?
3. Draw a diagram of MRP II.
4. What is the need for a maintenance management system?
5. What do you mean by linear programming?

4
THIRD SET OF ASSIGNMENTS Assignment-III = 5 Marks

ASSIGNMENT-III

1. The table below shows a job consisting of 3 sub-jobs a, b and c, along with their time estimates

Job 1-2 1-6 2-3 2-4 3-5 4-5 6-7 5-8 7-8
a(days) 1 2 2 2 7 5 5 3 8
b(days) 7 5 14 5 10 5 8 3 17
c(days) 13 14 26 8 19 17 29 9 32

Draw the project network diagram for each of the jobs. Find the critical path and minimum time taken for each
sub-job. Can the total project be completed in 40 days?

2. Perform ABC analysis on the following sample of items in an inventory.

Item Annual Consumption Price/Unit


A 400 20
B 2900 30
C 40 20
D 1200 10
E 40 10
F 320 02
G 250 10
H 900 10
I 700 30
J 90 20

3. Jaycee potteries manufactures ceramic bowls and mugs. Two main resources used by the company are skilled
labour and clay. The resources required and the profit per unit of each product is tabulated below:

Product Resource Requirement Profit/unit


Labour (hrs/unit) Clay (kg/unit)
Bowl 1 4 40
Clay 2 3 50

There are 40 hours of skilled labour and 120 kg of clay available each day. Formulate the problem for maximization
of profit as a linear programming problem and find the solution graphically using iso-profit lines.

5
4. The processing time (in hours) of seven jobs to be processed on three machines
M1, M2, M3 in the order M1, M2 and M3 are tabulated below:

Job M1 M2 M3
A 1 7 8
B 3 3 10
C 7 8 9
D 9 2 11
E 4 8 9
F 5 6 14 G 2 1 12
Sequence these jobs using Johnson’s method and find the overall processing time. Find also the waiting time of
the jobs and idle times of the three machines.

6
FOURTH SET OF ASSIGNMENTS Case Studies = 5 Marks

CASE STUDY - I

The table below gives details about the various tasks in assembly operation.

Task Precedence Task Time


Requirement (S) (min)
A - 10
B C 20
C A 30
D A, C 15
E A 10
F B 20
G D 10
H G 15
I G, H 15

Questions
(a) Explain the heuristic steps involved.
(b) Find the theoretical minimum cycle time.
(c) Find the theoretical number of work stations.
(d) Assign tasks to the work stations using the LOT rule.
(e) Calculate the efficiency of the assembly line.
(f) Determine the balance delay.

7
CASE STUDY - II

A company is setting up an assembly line to produce 192 units per 8 hours shift. The following table identifies the work
elements, times and immediate predecessors.

Work Element Time(seconds) Immediate


predecessor(s)
A 40
B 80 A
C 30 D,E,F
D 25 B
E 20 B
F 15 B
G 120 A
H 145 G
I 130 H
J 115 C,I

Total = 720 seconds

Questions:
1. What is the cycle time?
2. What is the theoretical minimum number of work stations?
3. Draw the precedence diagram.
4. Determine the idle time, efficiency, and balance delay.

You might also like