Professional Documents
Culture Documents
Tang, Mitri, Bouteldja - 2000 - Finite-Element Modelling of Rock Anchors
Tang, Mitri, Bouteldja - 2000 - Finite-Element Modelling of Rock Anchors
This paper describes a generalized modelling technique Cet article preÂsente une technique geÂneÂraliseÂe de modeÂli-
for the simulation of rock anchors, including mechanically sation numeÂrique pour la simulation des boulons d'anc-
anchored rock bolts, grouted rebars and cable bolts. The rage, incluant des boulons meÂcaniques, des armatures
proposed technique is implemented in a two-dimensional, cimenteÂs et des caÃbles d'ancrage. La technique proposeÂe
®nite-element method. A rock anchor system is modelled est effectueÂe par la meÂthode des eÂleÂments ®nis. Le systeÁme
by a series of bar elements, representing the anchor, which d'ancrage est modeÂlise par une seÂrie d'eÂleÂments lineÂaires,
are connected along their length to the rock mass by qui repreÂsentent l'ancrage, et qui est connecteÂe au massif
continuous shear springs, representing the shear bond rocheux par des ressorts de cisaillement aÁ l'interface roche-
stiffness of the grout and the rock±anchor interface. boulon. On peut modeÂliser l'effet d'ancrage de teÃte du
Surface anchorage, anchor tensioning and full or partial- boulon, et les boulons qui sont partiellement ou compleÁte-
length grouting can be modelled. The versatility of the ment cimenteÂs. La polyvalence du modeÁle proposeÂe est
proposed model is illustrated by a simple example of a illustreÂe par un exemple simple d'une excavation rectangu-
rectangular excavation, and the application of the model is laire. Une application pratique du modeÁle est preÂsenteÂe
demonstrated by a case study of an underground mine dans le cas d'un chantier d'abattage souterrain supporteÂ
stope in hard rock, supported by cable bolts. par des caÃbles d'ancrage dans une mine de roche dure.
Load
for underground-excavation design today. In hard-rock
mining, the stability graph method developed by Mathews
et al. (1981) and later modi®ed by Potvin (1988) is actually
based on the Q method of classi®cation. It is used to
evaluate the stability of mine stope walls and help determine P
the need for ground support. Grouted ∆L
With the rapid advancement of computer hardware tech- anchor
nology in the last two decades, the use of numerical modell-
ing software as a design tool in geotechnical engineering has
become both affordable and popular. Methods such as ®nite
elements, boundary elements and distinct elements have all S Slip Slip S
been used extensively in the design and analysis of geotech-
nical structures. Numerical methods have certain advantages k = P /S /∆L: kN/m3
Load P
over other methods; notably, they can account for the
complex geometry of an excavation, the deformation proper- Fig. 2. De®nition of shear bond stiffness k of a grouted rock anchor of
ties of the rock and the presence of in situ (virgin) stresses. short length ÄL
A number of numerical models were developed especially
for the simulation of rock bolts and cable bolts, such as those nected to quadrilateral isoparametric elements repre-
reported by Mitri and Rajaie (1990), Wang and Garga (1992), senting the host rock via the shear springs; see Fig. 1.
Peng and Guo (1992) and Tan et al. (1993). This paper (d) When the rock bolt is anchored at its head, for example
presents a generalized ®nite-element modelling technique with a plate and a nut, or with a grip as in the case of
developed to simulate the mechanical behaviour of the cable bolts, the two nodes representing the anchor head
performance of rock anchors. The technique is implemented and the adjacent rock are forced to move together, to
in a ®nite-element code (e-z tools) developed at McGill simulate such an anchorage effect.
University by the authors. (e) On the basis of this formulation, only the axial load
exerted on the rock anchor is considered. Bending load
that may develop along a fully grouted anchor is not
Finite-element formulation accounted for.
( f ) The formulation is based on small-deformation theory.
The rock anchor formulation presented here employs the Large-deformation effects such as cable stretch due to
following assumptions. lateral loads are not accounted for.
(a) A rock anchor can be represented by any number of
A four-node quadrilateral, isoparametric element is used
two-node bar elements. The cross-sectional area and
to represent the rock domain. The stiffness matrix K is given
modulus of elasticity of the bar element are those of the
by
rock anchor material (Fig. 1).
(b) If the rock anchor is partially or fully grouted, the K BT DB dV (1)
bonding effect of the grout, as well as the shear slip V
occurring at the rock±grout and grout±anchor inter-
where B is the strain±displacement matrix and D is the
faces, can be represented by continuous shear springs
stress±strain elasticity matrix. In rock mechanics problems,
acting along the anchor length. The stiffness of those
the load vector P is generally de®ned as follows:
springs, k, represents the shear bond stiffness per unit
length of the grouted rock anchor (Fig. 2). P ÿ BT ó 0 dV ãN T dV (2)
(c) The bar element representing the rock anchor is con- V V
0
where V is the element volume, ó is the initial stress vector,
N is the shape function matrix and ã is the unit weight of
the rock. Details of the above-mentioned equations can be
found in any textbook on ®nite elements (e.g. Cook, 1995).
For the new anchor elements, the total stiffness matrix Ka
is obtained by adding up the stiffness contributions from the
bar element Kb and the shear springs Ks . Thus,
Ka Kb Ks (3)
where
2 3
Ea Aa Ea Aa
6 ÿ
Kb 6 l l 77 (4)
4 Ea Aa Ea Aa 5
ÿ
l l
In the above, Ea is the modulus of elasticity of the anchor,
Aa is its cross-sectional area and l is the element length.
The shear spring stiffness, ks , is assumed to vary linearly
along the anchor element. This variation can be expressed in
terms of the nodal values ki and kj as follows:
66
Downloaded by [ University of Waterloo] on [15/06/16]. Copyright © ICE Publishing, all rights reserved.
Finite-element modelling of rock anchors
where 0 < æ x=l < 1: Likewise, the spring displacement, Rock bolts
1 2 3 4 5 6
us , can be expressed in terms of the nodal values as Competent
rock 0·6 m
us (1 ÿ æ)usi us j (6)
The shear spring stiffness matrix is calculated from the Weak roof
0·9 m
strain energy stored in the shear springs of stiffness ks over 1·8 m
the element length l, as follows.
l l
Us ks u2s dæ (7)
2 0
67
Downloaded by [ University of Waterloo] on [15/06/16]. Copyright © ICE Publishing, all rights reserved.
Tang et al.
to case 1, and the shear bond stiffness along the ungrouted this case, the maximum load on bolt 3 is only 1´1 t, as shown
length was zero. The results are shown in Fig. 5. As can be in Fig. 6(c).
seen, the axial load distribution is uniform along the free
length of the bolt, with a value of 6´02 t for bolt 3. The axial
load decays to zero over the resin-grouted portion. Discussion
The axial-load distributions along bolt 3 for all ®ve cases
simulated are shown in Fig. 7 and the numerical results are
Fully grouted rock bolts given in Table 2. Some remarks can be made in the light of
When the anchor is cement-grouted over the entire length these results. It is evident that the proposed numerical
of the bolt, the load distribution exhibits a consistent modelling technique is sensitive to variations of load and
increase in axial load to a maximum value at the bolt head; boundary conditions. More speci®cally, it can noted that
see Fig. 6(a). Bolt 3 attained a maximum load of 3´25 t.
(a) head and toe anchorage causes an increase in the bolt
Tensioning of fully grouted bolts can be made possible with
load
the help of a fast-setting resin grout. Figure 6(b) shows the
(b) bolt tensioning increases the bolt load
results of such a simulation (case 4), where resin grout was
(c) resin grout results in higher bolt load than cement grout
applied over a length of 0´6 m and cement grout over the
(d) when the bolt is not anchored at either end, the
remaining length of 1´8 m, and a tension load of 2´5 t was
maximum axial load develops somewhere in the mid-
applied. The maximum bolt load is found at its head and is
dle.
6´5 t, for bolt 3. The third simulation (case 5) was one in
which the bolt was not anchored at either end. This situation
is found in some applications of cable bolts in mining. In
Case study
8 Figure 8 shows a cross-section of a mine stope in an
underground, hard-rock mine made using a sublevel stoping
6
Load: t
4
Bolt 1 8
2 Bolt 2
Bolt 3
6
0
Case 5
Load: t
0
8 0 0·3 0·6 0·9 1·2 1·5 1·8 2·1 2·4
Bolt 1 Distance: m
6 Bolt 2
Fig. 7. Axial-load distribution along bolt 3 for all cases analysed
Load: t
Bolt 3
4
2
Ore body
0 4·2 m 17 m
(a)
Cable 1
8
3·6 m
2
6
3
Load: t
4 4
Bolt 1 5
2 Bolt 2 6
7
Bolt 3
8
0
(b) Mine
8 stope
Footwall
6 Bolt 1 hanging wall
Load: t
Bolt 2
4 Bolt 3
2 80˚
0
0 0·3 0·6 0·9 1·2 1·5 1·8 2·1 2·4
Distance: m 1170 m below surface
(c)
68
Downloaded by [ University of Waterloo] on [15/06/16]. Copyright © ICE Publishing, all rights reserved.
Finite-element modelling of rock anchors
Table 2. Summary of results of the numerical example Table 3. Geomechanical data for the case study
Case Anchor Tension: t Maximum load: t Sulphide ore
1 Mechanical rock bolt 2´5 5´32 Material property Hanging wall Footwall body
2 Resin anchor (0´6 m) 2´5 6´02 ã: MN=m3 0´027 0´027 0´027
3 Fully cement-grouted 0 3´25 E: MPa 54000 75000 125000
4 Resin-anchored (0´6 m) 2´5 6´5 RMR 50 55 75
cement-grouted ERM : MPa 31000 49000 115000
5 Fully cement-grouted 0 1´15 í 0´21 0´15 0´1
method. The stope, located 1170 m below the surface, was E ð(RMR)
ERM 1 ÿ cos (13)
30 m high and 7 m wide. The ore body was a stiff, massive 2 100
sulphide, sandwiched between softer schistose host walls.
As a result, in such a case, ore extraction causes signi®cant
stress relief in the walls, which can result in signi®cant Preliminary analysis and delineation of hanging-
caving-in of walls into the stope (or ore dilution) when the wall weak rock
walls are not supported. To remedy the situation, cable bolts A ®nite-element model was constructed with a dense,
were installed, prior to stope mining, from a hanging-wall graded mesh in the hanging wall to examine the stress levels
drift in a fanning pattern, as shown in Fig. 9. This pattern around the mine stope (refer to Fig. 10). The results of the
was repeated every 1´5 m in the strike direction of the ore preliminary analysis showed high stress concentration,
body. The geomechanical data are listed in Table 3. The in reaching up to 183 MPa in the top and bottom corners of the
situ stresses are given (in MPa) by ó 0y ã H (vertical stress), stope. It also showed a signi®cant stress relief zone both in
ó 0x 2:26ã H (horizontal stress perpendicular to the strike) the hanging wall and the footwall, with relief or tensile
and ó 0z 1:52ã H (horizontal stress parallel to the strike), stresses reaching up to 41 MPa. Before a cable bolt analysis
where H is the depth below the surface (1170 m) and ã is was carried out, it was important to delineate the area in the
the average unit weight of the rock mass (0:027 MN=m3 ). hanging wall requiring support. To do so, the elements
The deformation modulus of the rock mass ERM , reported having tensile stresses in the hanging wall were identi®ed as
in Table 3, was calculated in terms of the Young's modulus the weak rock zone (see Fig. 11). These were modelled in the
of elasticity of the intact rock material and the rock mass ®nal analysis with lower mechanical properties than the
rating RMR as follows (Mitri et al., 1996): hanging-wall rock. The treatment of the hanging-wall rock
Bolt
0 33·20 m
x fixed y fixed
69
Downloaded by [ University of Waterloo] on [15/06/16]. Copyright © ICE Publishing, all rights reserved.
Tang et al.
5
Analysis with cable bolts and model validation
0
The analysis with cable bolts was conducted with the 1 3 5 7 9 11 13 15
cable-bolting pattern shown in Fig. 8. A total of eight Nodes along the cable bolt
standard seven-wire, 5=8 in dia. cable bolts were used. These
cables had a tensile strength capacity of 26 t each. The Fig. 12. Axial-load distribution along cable bolts
70
Downloaded by [ University of Waterloo] on [15/06/16]. Copyright © ICE Publishing, all rights reserved.
Finite-element modelling of rock anchors
Table 4. Peak axial loads in cable bolts Bawden W. F., Hyett A. J., Lausch P., Moosavi M., De Graaf P.
Cable 1 2 3 4 5 6 7 8 and Ruest M. (1997) The S.M.A.R.T. cable bolt: results from two
initial ®eld trials. Proceedings of the Annual General Meeting of
Peak load: t 22´34 24´75 22´16 17´39 16´21 14´14 17´76 12´87 the Canadian Institute of MiningÐRock Mechanics Division, pp.
245±255.
Bieniawski Z. T. (1973) Engineering classi®cation of jointed rock
masses. Transactions of the South African Institute of Civil Engin-
subject of a ®eld investigation by Bawden et al. (1997). In eers, 15, 335±344.
that study, the axial displacements in selected cables were Cook R. D. (1995) Finite Element Modeling for Stress Analysis. Wiley,
monitored at six anchor points along the cable from the time New York.
of their installation, prior to mining, to the time when stope Diakite O. (1998) Assessment of Ore Dilution in Sublevel Open Stope
Mining. MSc thesis, McGill University, Montreal.
blasts were completed and the stope was completely mined
Hoek E. and Brown E. T. (1980) Underground Excavations in Rock.
out (as shown in Fig. 8). Knowing the axial stretch between Institution of Mining and Metallurgy, London.
two anchor points along the cable, the strains were calcu- Hutchinson D. J. and Diederichs M. S. (1996) Cablebolting in
lated and hence the average axial load of the cable for that Underground Mines. BiTech Publishers, Richmond, BC.
segment. The results and observations reported by Bawden Mathews K. E., Hoek E., Wyllie D. C. and Stewart S. B. V. (1981)
et al. serve to validate the present model. First, it was Prediction of Stable Excavation Spans for Mining at Depths below
reported that the cable loads were negligible in the lower 1000 m in Hard Rock Mines. CANMET, Ottawa, Report DSS OSQ
80-00081.
holes, an observation which substantiates the numerical Mitri H. S. and Rajaie H. (1990) Stress analysis of rockmass with
results obtained here, for example for cables 7 and 8. cable bolt supportÐa ®nite element approach. CANMET:
Secondly, the cables in the upper holes attained maximum Stresses in Underground Structures, Ottawa, pp. 110±119.
loads of nearly 250 kN (or 25 t), which correlates very well Mitri H. S., Edrissi R. and Henning J. (1996) Finite element
with the computed maximum loads in cables 1, 2 and 3 modelling of cablebolted stopes in hard rock underground
(22´16 to 24´75 t). mines. Transactions of the Society for Mining, Metallurgy, and
Exploration Inc., 298, 1897±1902.
Mitri H. S., Mohammed M. and Bouteldja M. (1999) Recent
advances in cable bolting technology. Proceedings of the 6th
Conclusion International Conference on Mining, Petroleum and Metallurgy,
Cairo, 168±179.
A generalized ®nite-element modelling technique for the Peng S. S. and Guo S. (1992) An improved numerical model of
simulation of rock anchors has been presented. The formula- grouted bolt±roof rock interaction in underground openings.
Proceedings of Rock Support in Mining and Underground Construc-
tion is based on the assumption that only the axial load is
tion (eds P. K. Kaiser and D. R. McCreath). Balkema, Rotterdam,
transmitted to the anchor, by shear springs acting along its pp. 67±74.
length. Such springs represent the shear bonding effect Potvin Y. (1988) Empirical Open Stope Design in Canada. PhD thesis,
between the bolt and the host rock. The versatility of the University of British Columbia.
new method for modelling rock bolts has been demonstrated Scott J. J. (1976) Friction rock stabilizersÐa new rock reinforcement
through a simple excavation example. It has been shown method. In Monograph on Rock Mechanics Applications in Mining.
(eds W. S. Brown, S. J. Green and W. M. Hustrulid). Society of
that the proposed modelling technique is capable of repre-
Mining Engineers, AIMMPE, New York, pp. 242±249.
senting a wide range of load and boundary conditions, such Scott J. J. (1983) Friction rock stabilizer impact upon anchor design
as the effect of an expansion shell, bolt tensioning, grouting and ground control practices. In Rock Bolting: Theory and
(fully or partially) and head anchorage. A mining engineer- Application in Underground Construction (ed. O. Stephansson).
ing case study of an underground stope in hard rock has Balkema, Rotterdam, pp. 407±418.
been presented. The stope was supported by fully grouted, Stillborg B. (1994) Professional Users Handbook for Rock Bolting.
non-tensioned, non-anchored cable bolts from a hanging- Trans Tech Publications, Clausthal-Zellerfeld, 2nd edn.
Tan G., Bawden W. F. and Pelley C. (1993) A cable bolt model and
wall drift. It has been shown that the cable bolts that were
its implementation into UDEC and FLAC. Proceedings of the First
nearly perpendicular to the stope face were more effective. Canadian Symposium on Numerical Modelling Applications in Min-
The proposed modelling technique can equally well be used ing and Geomechanics, Montreal, 240±252.
in design and back analysis. Wang B. and Garga V. K. (1992) A numerical model for rock bolts.
Proceedings of Rock Support in Mining and Underground Construc-
tion (eds P. K. Kaiser and D. R. McCreath). Balkema, Rotterdam,
pp. 57±66.
References
Barton N., Lien R. and Lunde J. (1974) Engineering classi®cation
of rockmasses for the design of tunnel support. Rock Mechanics, Discussion contributions on this paper should reach the
May, 189±236. editor by 31 August 2000
71
Downloaded by [ University of Waterloo] on [15/06/16]. Copyright © ICE Publishing, all rights reserved.