(For Printing) Progress Billing 001 - (POGO 19 and DORM 23 PSW) PDF
(For Printing) Progress Billing 001 - (POGO 19 and DORM 23 PSW) PDF
Architecture
Interior Design
(Bidder's Logo) Office Space Planning
I N C O R P O R A T E D Office Systems Furniture
Design Build
MAIN SUMMARY
TOTAL MAIN SUMMARY 7,200,000.00 - 0% 2,457,340.11 34% 2,457,340.11 34% 4,742,659.89 66%
BILLING HISTORY
No. Gross Amount Net Amount
1 2,457,340.11 1,474,404.06
2,457,340.11 1,474,404.06
Unit Rate
Item Description Unit Quantity Amount Quantity Amount % Quantity Amount % Quantity Amount % Quantity Amount %
Material Labor Others Total
Mobilization and Demobilization lot 1.00 40,000.00 40,000.00 - - 0% 0.75 30,000.00 75% 0.75 30,000.00 75% 0.25 10,000.00 25%
Bonds and Insurances lot 1.00 40,000.00 40,000.00 - - 0% 0.75 30,000.00 75% 0.75 30,000.00 75% 0.25 10,000.00 25%
Surety Bond lot
Performance Bond lot
Guarantee Bond lot
Workers Compensartion Insurance lot
As-built Drawings and Shop drawing lot 1.00 20,000.00 20,000.00 - - 0% 0.75 15,000.00 75% 0.75 15,000.00 75% 0.25 5,000.00 25%
Signed and sealed As-built drawings lot
Shopdrawings lot
Setting out
Surveyors lot 1.00 15,000.00 15,000.00
Site Management Personnel lot 1.00 180,000.00 180,000.00 - - 0% 0.75 135,000.00 75% 0.75 135,000.00 75% 0.25 45,000.00 25%
Operations Group (Project Director, Project Manager, Site Engineers) lot
QA/QC Group lot
Project Conrol (Field Engineering, Planning, Cost, Docs Control, QS) lot
Safety Precautions lot 1.00 75,000.00 75,000.00 - - 0% 0.75 56,250.00 75% 0.75 56,250.00 75% 0.25 18,750.00 25%
PPE''s lot
Medical Services Medicines lot
Safety Personnel lot
Security
Security Guards lot
Lighting, Power, Water, Telephone, Fire Protection,Ventillation and Air lot 1.00 21,967.10 21,967.10 - - 0% 0.75 16,475.33 75% 0.75 16,475.33 75% 0.25 5,491.78 25%
Conditioning etc. lot
Temporary Electrical Materials and Fixtures lot
Standby Gensets lot
Power Consumption lot
Water Consumption
lot 1.00 - - 0% 0.75 - 75% 0.75 - 75% 0.25 - #DIV/0!
Temporary Plant, Equipment and Scaffolding. lot
Service Vehicle lot
Mini Truck Dropside lot
Boom Truck
Annex D.1 Pricing Summary Plumbing and Sanitary Works_POGO.XLSX - Bill No.1 Page 2 of 15
DESIGN.SAGA INC.
Architecture
Interior Design
(Bidder's Logo) Office Space Planning
I N C O R P O R A T E D Office Systems Furniture
Design Build
Unit Rate
Item Description Unit Quantity Amount Quantity Amount % Quantity Amount % Quantity Amount % Quantity Amount %
Material Labor Others Total
Bill No. 01 - PRELIMINARIES AND GENERAL REQUIREMENTS 486,967.10 - 308,975.33 308,975.33 102,991.78
Annex D.1 Pricing Summary Plumbing and Sanitary Works_POGO.XLSX - Bill No.1 Page 3 of 15
DESIGN.SAGA INC.
Architecture
Interior Design
(Bidder's Logo) Office Space Planning
I N C O R P O R A T E D Office Systems Furniture
Design Build
WATER DISTRIBUTION
20mm diameter including fittings m 121.00 207.13 78.71 2.98 288.82 34,947.54 - - 0% 48.40 13,979.02 40% 48.40 13,979.02 40% 72.60 20,968.52 60%
25mm diameter including fittings m 31.00 278.00 105.64 8.45 392.09 12,154.83 - - 0% 12.40 4,861.93 40% 12.40 4,861.93 40% 18.60 7,292.90 60%
32mm diameter including fittings m 28.00 386.00 146.68 11.73 544.41 15,243.60 - - 0% 11.20 6,097.44 40% 11.20 6,097.44 40% 16.80 9,146.16 60%
40mm diameter including fittings m 68.00 597.00 226.86 18.15 842.01 57,256.60 - - 0% 27.20 22,902.64 40% 27.20 22,902.64 40% 40.80 34,353.96 60%
65mm diameter m 40.00 772.00 293.36 42.72 1,108.08 44,323.20
SEWER LINE
Supply and installation of Polyvinyl Chloride (PVC) Pipes Series
1000, including fittings, sleeves, painting, supports, hangers,
excavation, backfilling, filter cloth and other miscellaneous items as
shown and as required to complete the system.
50mm diameter m 60.00 215.00 81.70 6.54 303.24 18,194.40 - - 0% 45.60 13,827.74 76% 45.60 13,827.74 76% 14.40 4,366.66 24%
100mm diameter m 214.00 395.79 150.40 9.50 555.69 118,917.66 - - 0% 162.64 90,377.42 76% 162.64 90,377.42 76% 51.36 28,540.24 24%
150mm diameter m 56.00 837.50 318.25 15.30 1,171.05 65,578.80 - - 0% 42.56 49,839.89 76% 42.56 49,839.89 76% 13.44 15,738.91 24%
200mm diameter m 20.00 895.05 340.12 27.21 1,262.38 25,247.60 - - 0% 15.20 19,188.18 76% 15.20 19,188.18 76% 4.80 6,059.42 24%
Annex D.1 Pricing Summary Plumbing and Sanitary Works_POGO.XLSX - Bill No.2 Page 4 of 15
DESIGN.SAGA INC.
Architecture
Interior Design
(Bidder's Logo) Office Space Planning
I N C O R P O R A T E D Office Systems Furniture
Design Build
VENT LINE
Supply and installation of Polyvinyl Chloride (PVC) Pipes Series
1000, including fittings, sleeves, painting, supports, hangers,
excavation, backfilling, filter cloth and other miscellaneous items as
shown and as required to complete the system.
50mm diameter m 220.00 215.00 81.70 6.54 303.24 66,712.80 - - 0% 191.40 58,040.14 87% 191.40 58,040.14 87% 28.60 8,672.66 13%
75mm diameter m 28.00 372.53 149.01 8.94 530.48 14,853.44 - - 0% 24.36 12,922.49 87% 24.36 12,922.49 87% 3.64 1,930.95 13%
100mm diameter m 9.00 395.79 150.40 9.50 555.69 5,001.21 - - 0% 7.83 4,351.05 87% 7.83 4,351.05 87% 1.17 650.16 13%
Accessories
Vent stack thru wall, 100mm diameter no 1.00 1,500.00 675.00 109.00 2,284.00 2,284.00 - - 0% 0.87 1,987.08 87% 0.87 1,987.08 87% 0.13 296.92 13%
DRAINAGE LINE
Supply and installation of Polyvinyl Chloride (PVC) Pipes Series
1000, including fittings, sleeves, painting, supports, hangers,
excavation, backfilling, filter cloth and other miscellaneous items as
shown and as required to complete the system.
100mm diameter m 234.00 395.79 150.40 9.50 555.69 130,031.46 - - 0% 175.50 97,523.60 75% 175.50 97,523.60 75% 58.50 32,507.87 25%
Accessories
Annex D.1 Pricing Summary Plumbing and Sanitary Works_POGO.XLSX - Bill No.2 Page 5 of 15
DESIGN.SAGA INC.
Architecture
Interior Design
(Bidder's Logo) Office Space Planning
I N C O R P O R A T E D Office Systems Furniture
Design Build
Supply and installation of catch basin no 12.00 5,000.00 1,500.00 325.00 6,825.00 81,900.00 - - 0% 9.00 61,425.00 75% 9.00 61,425.00 75% 3.00 20,475.00 25%
Plumbing Fixtures
Water Closet no 36.00 OSM 950.00 50.00 1,000.00 36,000.00 - - 0% - - 0% - - 0% 36.00 36,000.00 100%
Trough sink no 4.00 OSM 1,200.00 45.00 1,245.00 4,980.00 - - 0% - - 0% - - 0% 4.00 4,980.00 100%
Urinal no 20.00 OSM 950.00 45.00 995.00 19,900.00 - - 0% - - 0% - - 0% 20.00 19,900.00 100%
Mix Faucet no 26.00 OSM 750.00 20.00 770.00 20,020.00 - - 0% - - 0% - - 0% 26.00 20,020.00 100%
SUNDRIES
Allow for any other items for which the Contractor requires payment
to comply in all respect with the provisions of the relevant
Conditions of Contract, the Particular Specifications and Drawings
and which are not in the rates contained in these Bill of Quantities,
Details of each item shall be inserted below:
Bill No. 02 - PLUMBING AND SANITARY WORKS 1,113,032.90 - 693,156.07 62% 693,156.07 375,561.76
Annex D.1 Pricing Summary Plumbing and Sanitary Works_POGO.XLSX - Bill No.2 Page 6 of 15
DESIGN.SAGA INC.
Architecture
Interior Design
(Bidder's Logo) Office Space Planning
I N C O R P O R A T E D Office Systems Furniture
Design Build
1 Mobilization and Demobilization lot 1.00 80,000.00 80,000.00 - - 0% 0.75 60,000.00 75% 0.75 60,000.00 75% 0.25 20,000.00 25%
2 Bonds and Insurances lot 1.00 45,000.00 45,000.00 - - 0% 0.75 33,750.00 75% 0.75 33,750.00 75% 0.25 11,250.00 25%
4 As-built Drawings and Shop drawing lot 1.00 25,000.00 25,000.00 - - 0% 0.75 18,750.00 75% 0.75 18,750.00 75% 0.25 6,250.00 25%
Shopdrawings lot
5 Setting out
Surveyors lot
6 Site Management Personnel lot 1.00 180,000.00 180,000.00 - - 0% 0.75 135,000.00 75% 0.75 135,000.00 75% 0.25 45,000.00 25%
Project Conrol (Field Engineering, Planning, Cost, Docs Control, QS) lot
7 Safety Precautions lot 1.00 50,000.00 50,000.00 - - 0% 0.75 37,500.00 75% 0.75 37,500.00 75% 0.25 12,500.00 25%
PPE''s lot
8 Security
Warehouse Facility lot 1.00 70,000.00 70,000.00 - - 0% 0.75 52,500.00 75% 0.75 52,500.00 75% 0.25 17,500.00 25%
7 of 15
Previous This Week To Date Remaining
Unit Rate
ITEM DESCRIPTION Unit Qty Amount
Quantity Amount % Quantity Amount % Quantity Amount % Quantity Amount %
Materials Labor Others Total
Temporary Electrical Materials and Fixtures lot
11 Temporary Plant, Equipment and Scaffolding. lot 1.00 70,000.00 70,000.00 - - 0% 0.75 52,500.00 75% 0.75 52,500.00 75% 0.25 17,500.00 25%
Dewatering lot
15 Testing and Commissioning lot 1.00 75,000.00 75,000.00 - - 0% 0.75 56,250.00 75% 0.75 56,250.00 75% 0.25 18,750.00 25%
Bill No. 01 - PRELIMINARIES AND GENERAL REQUIREMENTS 647,044.38 - - 0% - 485,283.29 75% - 485,283.29 75% - 161,761.10 25%
8 of 15
DESIGN.SAGA INC.
Architecture
Interior Design
(Bidder's Logo) Office Space Planning
I N C O R P O R A T E D Office Systems Furniture
Design Build
Unit Rate
ITEM DESCRIPTION Unit Qty Amount Quantity Amount % Quantity Amount % Quantity Amount % Quantity Amount %
diameter considered)
15mm diameter m 592.00 195.75 56.48 2.98 255.22 151,088.15 - - 0% - - 0% - - 0% 592.00 151,088.15 100%
20mm diameter m 604.00 207.13 59.77 3.16 270.06 163,114.48 - - 0% - - 0% - - 0% 604.00 163,114.48 100%
25mm diameter m 220.00 278.00 81.41 8.45 367.86 80,930.29 - - 0% - - 0% - - 0% 220.00 80,930.29 100%
32mm diameter m 32.00 386.00 113.04 11.73 510.78 16,344.85 - - 0% - - 0% - - 0% 32.00 16,344.85 100%
40mm diameter m 33.00 597.00 174.83 18.15 789.98 26,069.45 - - 0% - - 0% - - 0% 33.00 26,069.45 100%
50mm diameter m 32.00 750.60 219.82 22.82 993.24 31,783.53 - - 0% - - 0% - - 0% 32.00 31,783.53 100%
65mm diameter m 32.00 1,405.30 411.55 42.72 1,859.57 59,506.26 - - 0% - - 0% - - 0% 32.00 59,506.26 100%
75mm diameter m 16.00 1,501.20 439.63 45.64 1,986.47 31,783.53 - - 0% - - 0% - - 0% 16.00 31,783.53 100%
100mm diameter m 12.00 1,876.50 549.54 57.05 2,483.09 29,797.06 - - 0% - - 0% - - 0% 12.00 29,797.06 100%
-
Supply and installation of elbow, 90deg -
100mm diameter no 8.00 701.50 205.44 21.33 928.26 7,426.11 - - 0% - - 0% - - 0% 8.00 7,426.11 100%
75mm diameter no 2.00 613.48 182.10 27.22 822.80 1,645.60 - - 0% - - 0% - - 0% 2.00 1,645.60 100%
100mm diameter no 1.00 895.33 273.31 66.30 1,234.94 1,234.94 - - 0% - - 0% - - 0% 1.00 1,234.94 100%
-
Supply and installation of tee reducer -
65mm diameter no 2.00 941.85 275.83 28.63 1,246.31 2,492.62 - - 0% - - 0% - - 0% 2.00 2,492.62 100%
75mm diameter no 9.00 1,083.13 317.20 32.93 1,433.25 12,899.29 - - 0% - - 0% - - 0% 9.00 12,899.29 100%
DESIGN.SAGA INC.
Architecture
Interior Design
(Bidder's Logo) Office Space Planning
I N C O R P O R A T E D Office Systems Furniture
Design Build
Unit Rate
ITEM DESCRIPTION Unit Qty Amount Quantity Amount % Quantity Amount % Quantity Amount % Quantity Amount %
100mm diameter no 2.00 1,245.60 364.78 37.87 1,648.24 3,296.48 - - 0% - - 0% - - 0% 2.00 3,296.48 100%
-
Supply and installation of coupling -
65mm diameter no 4.00 1,620.00 483.45 81.00 2,184.45 8,737.80 - - 0% - - 0% - - 0% 4.00 8,737.80 100%
75mm diameter no 3.00 1,801.84 537.72 90.09 2,429.65 7,288.94 - - 0% - - 0% - - 0% 3.00 7,288.94 100%
100mm diameter no 1.00 1,985.88 592.64 99.29 2,677.81 2,677.81 - - 0% - - 0% - - 0% 1.00 2,677.81 100%
100mm diameter no 2.00 1,744.00 520.45 87.20 2,351.65 4,703.31 - - 0% - - 0% - - 0% 2.00 4,703.31 100%
-
Supply and installation of gate valve -
20mm diameter no 118.00 837.82 250.03 41.89 1,129.74 133,309.74 - - 0% - - 0% - - 0% 118.00 133,309.74 100%
25mm diameter no 28.00 846.40 252.59 42.32 1,141.31 31,956.61 - - 0% - - 0% - - 0% 28.00 31,956.61 100%
Supply andSupply
installation
Supply
andand
installation
ofinstallation
hose bibof hose
of hose
bibbib -
100mm diameter no 5.00 7,200.00 2,148.67 360.00 9,708.67 48,543.33 - - 0% - - 0% - - 0% 5.00 48,543.33 100%
100mm diameter no 1.00 60,000.00 17,905.55 3,000.00 80,905.55 80,905.55 - - 0% - - 0% - - 0% 1.00 80,905.55 100%
diameter considered)
15mm diameter m 80.00 195.75 56.48 2.98 255.22 20,417.32 - - 0% - - 0% - - 0% 80.00 20,417.32 100%
15mm diameter no 115.00 828.00 247.10 41.40 1,116.50 128,397.11 - - 0% - - 0% - - 0% 115.00 128,397.11 100%
DESIGN.SAGA INC.
Architecture
Interior Design
(Bidder's Logo) Office Space Planning
I N C O R P O R A T E D Office Systems Furniture
Design Build
Unit Rate
ITEM DESCRIPTION Unit Qty Amount Quantity Amount % Quantity Amount % Quantity Amount % Quantity Amount %
Equipment
Electric water heater, EWH 1, Instantaneous single point, 2.5 lpm, 230 V, 1Ph, no 115.00 OSM 5.68 20.00 25.68 2,953.69 - - 0% - - 0% - - 0% 115.00 2,953.69 100%
60Hz
SEWER LINE
Supply and installation of Polyvinyl Chloride (PVC) Pipes Series 1000, including
system.
50mm diameter including fittings m 517.00 215.00 62.96 6.54 284.50 147,086.44 - - 0% 206.80 58,834.57 40% 206.80 58,834.57 40% 310.20 88,251.86 60%
100mm diameter m 996.00 395.79 115.19 9.50 520.48 518,399.71 - - 0% 398.40 207,359.88 40% 398.40 207,359.88 40% 597.60 311,039.83 60%
150mm diameter m 132.00 837.50 242.38 15.30 1,095.18 144,563.58 - - 0% 52.80 57,825.43 40% 52.80 57,825.43 40% 79.20 86,738.15 60%
200mm diameter m 12.00 895.05 262.12 27.21 1,184.38 14,212.56 - - 0% 4.80 5,685.02 40% 4.80 5,685.02 40% 7.20 8,527.53 60%
100mm diameter no 578.00 178.50 51.47 2.60 232.57 134,428.05 - - 0% 231.20 53,771.22 40% 231.20 53,771.22 40% 346.80 80,656.83 60%
150mm diameter no 7.00 477.36 138.77 10.88 627.01 4,389.07 - - 0% 2.80 1,755.63 40% 2.80 1,755.63 40% 4.20 2,633.44 60%
100mm diameter no 180.00 195.83 56.99 4.70 257.53 46,355.12 - - 0% 72.00 18,542.05 40% 72.00 18,542.05 40% 108.00 27,813.07 60%
150mm diameter no 1.00 1,162.80 338.02 26.51 1,527.33 1,527.33 - - 0% 0.40 610.93 40% 0.40 610.93 40% 0.60 916.40 60%
100x50mm diameter no 460.00 187.10 54.25 3.77 245.12 112,754.11 - - 0% 184.00 45,101.64 40% 184.00 45,101.64 40% 276.00 67,652.46 60%
DESIGN.SAGA INC.
Architecture
Interior Design
(Bidder's Logo) Office Space Planning
I N C O R P O R A T E D Office Systems Furniture
Design Build
Unit Rate
ITEM DESCRIPTION Unit Qty Amount Quantity Amount % Quantity Amount % Quantity Amount % Quantity Amount %
200x100mm diameter no 1.00 1,641.29 474.64 28.72 2,144.66 2,144.66 - - 0% 0.40 857.86 40% 0.40 857.86 40% 0.60 1,286.79 60%
200x150mm diameter no 2.00 1,810.00 523.95 33.49 2,367.43 4,734.86 - - 0% 0.80 1,893.95 40% 0.80 1,893.95 40% 1.20 2,840.92 60%
200x150mm diameter no 1.00 1,763.27 513.74 44.29 2,321.30 2,321.30 - - 0% 0.40 928.52 40% 0.40 928.52 40% 0.60 1,392.78 60%
50mm diameter no 230.00 1,064.98 308.13 19.17 1,392.29 320,226.16 - - 0% - - 0% - - 0% 230.00 320,226.16 100%
50mm diameter no 115.00 1,064.98 308.13 19.17 1,392.29 160,113.08 - - 0% - - 0% - - 0% 115.00 160,113.08 100%
100mm diameter no 174.00 1,315.75 382.93 31.58 1,730.25 301,064.30 - - 0% - - 0% - - 0% 174.00 301,064.30 100%
150mm diameter no 3.00 3,627.74 1,047.55 58.04 4,733.33 14,200.00 - - 0% - - 0% - - 0% 3.00 14,200.00 100%
100mm diameter no 28.00 826.80 239.92 17.36 1,084.09 30,354.43 - - 0% - - 0% - - 0% 28.00 30,354.43 100%
50mm diameter no 4.00 2,098.78 615.46 66.68 2,780.92 11,123.69 - - 0% - - 0% - - 0% 4.00 11,123.69 100%
Supply and installation of trench grating no 4.00 3,220.00 920.86 20.00 4,160.86 16,643.43 - - 0% - - 0% - - 0% 4.00 16,643.43 100%
VENT LINE
Supply and installation of Polyvinyl Chloride (PVC) Pipes Series 1000, including
system.
50mm diameter including fittings m 1584.00 215.00 62.96 6.54 284.50 450,647.80 - - 0% 475.20 135,194.34 30% 475.20 135,194.34 30% ####### 315,453.46 70%
75mm diameter including fittings m 540.00 372.53 108.42 8.94 489.89 264,540.85 - - 0% 162.00 79,362.25 30% 162.00 79,362.25 30% 378.00 185,178.59 70%
DESIGN.SAGA INC.
Architecture
Interior Design
(Bidder's Logo) Office Space Planning
I N C O R P O R A T E D Office Systems Furniture
Design Build
Unit Rate
ITEM DESCRIPTION Unit Qty Amount Quantity Amount % Quantity Amount % Quantity Amount % Quantity Amount %
Vent stack thru wall, 50mm diameter no 3.00 900.00 268.58 45.00 1,213.58 3,640.75 - - 0% 0.90 1,092.22 30% 0.90 1,092.22 30% 2.10 2,548.52 70%
Vent stack thru wall, 75mm diameter no 16.00 1,500.00 447.64 75.00 2,022.64 32,362.22 - - 0% 4.80 9,708.67 30% 4.80 9,708.67 30% 11.20 22,653.55 70%
Supply and installation of Polyvinyl Chloride (PVC) Pipes Series 1000, including
system.
100mm diameter m 267.00 395.79 118.11 19.79 533.70 142,497.10 - - 0% 80.10 42,749.13 30% 80.10 42,749.13 30% 186.90 99,747.97 70%
100mm diameter no 36.00 370.00 110.42 18.50 498.92 17,961.03 - - 0% 10.80 5,388.31 30% 10.80 5,388.31 30% 25.20 12,572.72 70%
100mm diameter no 61.00 178.50 51.47 2.60 232.57 14,187.04 - - 0% 18.30 4,256.11 30% 18.30 4,256.11 30% 42.70 9,930.93 70%
100mm diameter no 8.00 195.83 56.99 4.70 257.53 2,060.23 - - 0% 2.40 618.07 30% 2.40 618.07 30% 5.60 1,442.16 70%
Accessories
100mm diameter no 18.00 2,500.00 746.06 125.00 3,371.06 60,679.16 - - 0% 5.40 18,203.75 30% 5.40 18,203.75 30% 12.60 42,475.41 70%
100mm diameter no 8.00 210.00 60.43 2.60 273.03 2,184.23 - - 0% 2.40 655.27 30% 2.40 655.27 30% 5.60 1,528.96 70%
Supply and installation of Catch basin no 12.00 10,000.00 3,026.89 650.00 13,676.89 164,122.69 - - 0% 3.60 49,236.81 30% 3.60 49,236.81 30% 8.40 114,885.88 70%
Supply and installation of Polyvinyl Chloride (PVC) Pipes Series 1000, including
DESIGN.SAGA INC.
Architecture
Interior Design
(Bidder's Logo) Office Space Planning
I N C O R P O R A T E D Office Systems Furniture
Design Build
Unit Rate
ITEM DESCRIPTION Unit Qty Amount Quantity Amount % Quantity Amount % Quantity Amount % Quantity Amount %
25mm diameter m 366.00 48.00 14.07 1.51 63.58 23,271.77 - - 0% 109.80 6,981.53 30% 109.80 6,981.53 30% 256.20 16,290.24 70%
32mm diameter m 524.00 57.00 16.74 1.90 75.64 39,634.22 - - 0% 157.20 11,890.27 30% 157.20 11,890.27 30% 366.80 27,743.96 70%
instruction
25mm diameter m 366.00 108.90 32.73 6.27 147.90 54,130.33 - - 0% 109.80 16,239.10 30% 109.80 16,239.10 30% 256.20 37,891.23 70%
32mm diameter m 524.00 417.50 122.61 13.90 554.01 290,302.17 - - 0% 157.20 87,090.65 30% 157.20 87,090.65 30% 366.80 203,211.52 70%
32mm diameter no 4.00 519.44 158.43 38.00 715.87 2,863.49 - - 0% 1.20 859.05 30% 1.20 859.05 30% 2.80 2,004.44 70%
32mm diameter no 31.00 519.44 158.43 38.00 715.87 22,192.06 - - 0% 9.30 6,657.62 30% 9.30 6,657.62 30% 21.70 15,534.44 70%
20mm diameter no 28.00 150.00 45.76 11.00 206.76 5,789.24 - - 0% 8.40 1,736.77 30% 8.40 1,736.77 30% 19.60 4,052.47 70%
25mm diameter no 28.00 178.90 52.16 4.63 235.70 6,599.50 - - 0% 8.40 1,979.85 30% 8.40 1,979.85 30% 19.60 4,619.65 70%
PLUMBING FIXTURES
the system.
Water Closet no 115.00 OSM 71.05 250.00 321.05 36,921.18 - - 0% - - 0% - - 0% 115.00 36,921.18 100%
Lavatory with faucet no 115.00 OSM 71.05 250.00 321.05 36,921.18 - - 0% - - 0% - - 0% 115.00 36,921.18 100%
Shower head including faucet no 115.00 OSM 71.05 250.00 321.05 36,921.18 - - 0% - - 0% - - 0% 115.00 36,921.18 100%
DESIGN.SAGA INC.
Architecture
Interior Design
(Bidder's Logo) Office Space Planning
I N C O R P O R A T E D Office Systems Furniture
Design Build
Unit Rate
ITEM DESCRIPTION Unit Qty Amount Quantity Amount % Quantity Amount % Quantity Amount % Quantity Amount %
SUNDRIES
Allow for any other items for which the Contractor requires payment to comply
in all respect with the provisions of the relevant Conditions of Contract, the
Particular Specifications and Drawings and which are not in the rates contained
Bill No. 02 - PLUMBING AND SANITARY WORKS 4,952,955.62 - - 0% - 969,925.42 20% - 969,925.42 20% - 3,983,030.20 80%
POGO 19 – PLUMBING AND SANITARY WORKS
LEGEND:
- ACCOMPLISHED
- REMAINING
- ACCOMPLISHED
- REMAINING
WATERLINE SYSTEM
POGO 19 – PLUMBING AND SANITARY WORKS
LEGEND:
- ACCOMPLISHED
- REMAINING
MALE TOILET
FEMALE TOILET
- ACCOMPLISHED
- REMAINING