Strykers Bay Neighborhood Council V Karlen 444 US 223 1980

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

Strycker's Bay Neighborhood Council, Inc. v.

Karlen
444 U.S. 223 (1980)

The US Department of Housing and Urban Development (HUD) approved a project to build low-income
housing in Manhattan. A local citizen group, Stryker's Bay, opposed the project and sued.

Stryker's Bay argued that HUD had not properly considered environmental impacts of the project as
they were required to under the National Environmental Policy Act (NEPA).

The Trial Court found for HUD. Stryker's Bay appealed.

The Trial Court found that HUD's decision-making process was adequate.

The Appellate Court reversed and remanded back to HUD.

The Appellate Court found that NEPA required consideration of alternatives to the project.

HUD prepared a lengthy report asserting that they had considered all of the relevant factors and still
found that the project was not unacceptable. Stryker's Bay sued again.

The main reason HUD found the project to be acceptable was that relocating the project would result in
"unacceptable delay."

The Trial Court found for HUD. Stryker's Bay appealed.

The Trial Court found that HUD had properly and in good faith considered the alternatives and
environmental impacts of the project, thereby meeting their requirements under NEPA.

The Appellate Court reversed. HUD appealed.

The Appellate Court found that "unacceptable delay" was a capricious reason for finding the project
acceptable. Instead, the Appellate Court suggested that HUD actually consider environmental factors.

The US Supreme Court reversed the Appellate Court and found HUDs assessment to be acceptable.

The US Supreme Court found that NEPA requires "a fully informed and well-considered decision" but not
necessarily "a decision the judges of the Appellate Court would have reached had they been members of
the decision-making process."

Basically, as long as the agency considers the environmental consequences of the project, NEPA is
satisfied. There are no specific rules on how an agency should weigh the factors influencing their
decision.

In a dissent it was argued that the Court has a role in determining whether the decision was "arbitrary or
capricious," and if so, they had a responsibility to overturn it.
What if after considering the environmental impacts, an agency decided to permit a project solely
because they thought the people who opposed it were all dirty hippies? Would the Court feel they were
empowered to overturn the decision?

You might also like