Professional Documents
Culture Documents
S-TR-GEN-PSTS (Planning & Scheduling TechSpec) (Rev 0-2009)
S-TR-GEN-PSTS (Planning & Scheduling TechSpec) (Rev 0-2009)
GENERAL REQUIREMENTS
( SPECIFICATION )
CONTENTS
1 GENERAL
The Principal rights and duties of the parties with respect to planning and scheduling are set forth
under any contract however, the following detailed requirements and procedures shall govern the
planning and scheduling activities under this contract:
2 SCOPE
The scope of this procedure includes the following:
• The development of schedules which represent the plan for execution of the services
consistent with TRANSCO requirement and reflecting the total scope.
• A monitoring system which continually compares actual performance with planned
performance and allows early review and corrective/preventive actions on deviations.
3 CONSULTANT/CONTRACTOR RESPONSIBILITIES
Consultant/Contractor shall be responsible for the overall scheduling system within the
guidelines set forth below. Consultant/Contractor shall utilize a suitable and professional
standard computer system/software package (e.g. Primavera, MS Project) for formulation,
update, reviewing and reporting of schedules and progress reports through out the duration of the
project, including the accommodation of any changes in the scope of work.
Consultant/Contractor may also utilized his in-house developed package(s) suitable for specific
applications (e.g. document control, procurement control, etc.). TRANSCO shall have the right
to review and approve all formats planning package such as, schedules, procedures, Tracking and
commented them to suite its requirements. Consultant/Contractor shall maintain a database
systems which shall be capable of tracking deliverables, assessing progress, producing
manpower histograms and “S” curves by discipline/Area, identifying problems areas and
supporting the decision making process for corrective actions.
The systems shall enable production of all normal exceptional reports as may be required by
TRANSCO.
4 DEFINITIONS:
Each activity in the network shall be assigned with appropriate resources and weight factors
based on which manpower histograms and progress “S” curves will be generated and
subsequently monitored. The control schedule is explained in further detail under paragraph 4.3
below.
The progression of works shall be guided by and controlled against the approved plans and
schedules which are prepared in line with TRANSCO requirements.
The schedule should out line the estimated duration for the main activities covering each phase
by discipline and the project control milestones.
The control schedule shall also clearly indicate the preparation and approval of project co-
ordination procedures, planning dossier, HSE philosophy and plan, vendor manual pre-
commissioning and commissioning manual, etc.
The activity coding structure shall provide reference to project phase/discipline/area…etc, as per
the agreed work breakdown structure (WBS) for ease of identification and report sorting. The
control schedule, after approval by TRANSCO, serve as the management schedule should be
adjusted to comply with the resources levels/levelling by rescheduling the activities within its
slack. Also any schedule adjustments to allow for uniform progress i.e. smooth progress “S”
Curves have to be considered. The control network/control bar charts shall be updated on a
monthly basis.
For updating of the data, percent complete (PC) may be used. Based on the actual progress,
following the network updating, a critical and near critical listing of activities shall be produced.
The critical activity listing shall be reviewed to identify problem areas and ensure timely
effective actions. The critical activity listing shall be included in the monthly progress report
with suggested corrective actions. Early start, early finish, predecessors, successors and float
details shall be indicated in the bar chart for all activities of the control network.
The base bars and milestones targets will be retained for comparison with update.
The histograms shall be produced to depict the scheduled manpower planned and shall be
compared with actual manpower deployed on a weekly basis for the entire project duration.
The histogram shall be developed for the entire duration of the contract.
The Schedules and all documents related to the planning dossier, once approved, shall not be
changed by consultant/contractor without prior approval by TRANSCO.
Consultant/Contractor shall submit along with any variation proposal a detailed evaluation of
schedule impact, if any, due to change in scope/sequence of work. Justification for schedule
impact should be accompanied by a logic network clearly highlighting the impact of such
changes on the completion of intermediate milestones as well as the overall project completion,
if any.
Consultant/Contractor shall note that the submission of any revised program/extension time
request and subsequent approval of same by TRANSCO, during the contract period shall not
relieve the consultant/contractor from his contractual obligations. All such revisions shall only be
treated as a part of the control mechanism for effective monitoring so as to arrest/reduce progress
slippage.
8 PROGRESS MEASUREMENT.
8.1 Responsibility:
The assessment and reporting of progress shall be the responsibility of consultant/contractor.
Basis Progress Measurements are shown in the following part of the Standard Technical
Specification, Part 1:
The supporting documents, charts & photos relevant to the measurements of the actual field
progress are to be provided by consultant/contractor and shall be attached to the relevant monthly
report.
Progress Calculations are shown in the following part of the Standard Technical Specification,
Part 1:
9 PROGRESS REPORTING
Consultant/Contractor shall prepare and maintain a comprehensive set of controls for
documentation. These controls shall enable exception reports to be prepared speedily and to
support management reporting as required by TRANSCO from time to time. Details of various
reports to be submitted by consultant/contractor are given below:
In addition, consultant/contractor shall submit the following as part of the monthly progress
report:
a) Updated level II control schedule showing planned/actual/forecast dates.
b) Progress “S” Curves for each phase (Engineering, procurement or construction)
by discipline/area/system etc. separately.
c) Updated deliverables/control register indicating plan versus actual/forecast
completion dates along with progress status.
Weekly progress report shall also include, but not be limited to the following details;
d) Progress statistics (weekly & cumulative) along with reasons for backlog if any,
separately for each area/system/discipline/facility…etc and overall progress.
e) Activities awaiting TRANSCO action/approval.
f) Updated S curve showing planned vs. actual progress (weekly & cumulative) at
the overall project level.
g) Procurement status report.
h) 3 weeks look – ahead program.
A deviation from the agreed schedule shall be identified and two (2) copies of this report shall be
submitted by the contractor to TRANSCO and consultant.
This log shall be prepared and maintained daily at site and a copy shall be delivered to
Consultant Residence Engineer next morning.
10 COORDINATION PROCEDURE.
10.1 Communication:
The English Language shall be used for all correspondence, reports, instruction, drawings,
specifications etc.
As far as possible, all written communication shall be SITE level directly between Consultant
and contractor. All efforts shall be made to keep the correspondence to the minimum. If for
expediency, telephonic conversation shall be used; this shall be confirmed in writing two (2)
working days, by both PARTIES.
Consultant shall prepare and issue the Minutes of all his meetings with TRANSCO & Contractor
and shall be responsible for obtaining approval of these minutes prior to release within two (2)
working days.
Any delay or expenses for securing necessary permission/permits/passes from the concerned
authorities shall not entitle Contractor to any claim for extension of completion date or payment.
The end user (ADDC/AADC/TRANSCO) representative shall attend the progress review
meeting as an observer.
The minutes of meeting shall be prepared by the consultant and submitted to TRANSCO for
review and approval prior distribution to all attendees.
13 GENERAL REQUIREMENTS.
TRANSCO reserves the right to add/delete/modify any or all of the scheduling and reporting
requirements if deemed necessary to ensure effective control and monitoring. TRANSCO shall
discuss/explain all such changes/requirement and consultant/contractors shall implement the
same at all times until contract completion.
Consultant/contractor shall submit to TRANSCO electronic file(s) of the schedules and reports at
regular intervals for review & approval as applicable.