Professional Documents
Culture Documents
Terminology Explained - P10, P50 and P90 - DNV GL - Software
Terminology Explained - P10, P50 and P90 - DNV GL - Software
Terminology Explained - P10, P50 and P90 - DNV GL - Software
The P10, P50 and P90 are useful parameters to understand how the numbers
are distributed in a sample. Let’s try to explain that using an example.
1. 95
2. 95
3. 96
4. 95
5. 97
6. 93
7. 94
8. 95
9. 96
10. 94
There are several options to display this data. You could decide to group the
observations within a certain range and create a frequency table (i.e. how
frequently an observation appears in the sample). This is calculated by counting
the observations with a specific value and dividing by the total number of
observations (e.g. 93 appears one time in a sample which has ten observations
so its frequency is 10%):
The frequency can also be used to create the famous “bell” curve:
With this distribution, there is no need to have access to all the data points in the
sample to start the inference work. We can tell, by looking at the graph, that most
observations are around 95.
What is Cumulative Frequency and probability of
Exceedance and Non-Exceedance?
Another option to display this distribution is using a “Cumulative Frequency”
graph. This table is calculated by adding each frequency from a frequency
distribution table to the sum of its predecessors.
One will notice that you can start from either the lower observation values to
higher observation values or the opposite. So, we must introduce two new
concepts:
Probability of exceedance: If you start from the left (i.e. lower observation
values) of the bell curve to the right (i.e. higher observation values), you
are building-up a probability of exceedance curve.
Probability non-exceedance: If you start from the right (i.e. higher
observation values) of the bell curve to the left (i.e. lower observation
values), you are building-up a probability of non-exceedance curve.
Probability of Exceedance
Again, this graph adds up the frequency of occurrence as the value of the
observation decreases i.e. 30% of our observations will be equal exceed the
value of 96. This is what is called the probability of exceedance.
Probability of Non-Exceedance
So, in our sample, P10 would be 96 – 10% of our observation will exceed the
value of 96. And P90 will be 94 – 90% of our observation will exceed the value of
94.
Note that it does not mean that the estimate has a 90% chance of occurring –
that is a very different concept. P50 is more likely to occur because it is closer to
the mean. For this sample of observations, our P50 would be 95 which is exactly
the mean (i.e. 95). There is a reason for this which is explained later in this
article.
We can never be sure exactly (this is an important word which is the core reason
of why we use probabilistic approach) how much crude oil is available for
production in the reserves. However, we can have a good estimate (another
important word). Geologists and Reservoir Engineers working for the oil and gas
industry have developed numerous methods and tools to calculate the potential
production and get estimates of production rates from oil and gas reservoirs to
obtain a high economic recovery.
The Securities and Exchange Commission (SEC) define the reserves and
resources estimates in terms of P90/P50/P10 ranges as:
Translating all these terms, the amount thought to be in the reserves is generally
estimated as three figures:
Proved (P90): The lowest figure. It means that 90% of the calculated
estimates will be equal or exceed P90 estimate.
Median (P50): This is the median.
Possible (P10): The highest figure, it means that 10% of the calculated
estimates will be equal or exceed P10 estimate.