Construction Daily Report

Checklist
conducted for

Ground Breaking Zone 1

Date and Time


15 Oct 2018 10:29 AM

Prepared by
Antonio Iglesias

Location
509 Grand Blvd
Venice, CA 90291
United States
(33.9883634073794, -118.466816814894)
Completed on
17 Oct 2018 06:02 PM

Score
3/6.0 - 50.00%
Audit - 3/6 50.00%

Question Response Details

Job Description

Job Name Ground Breaking

Job No. 00001

Weather Information

Weather Report Clear / A bit windy but clear sky.


Sunny

Appendix 1

Temperature 20 °C

Winds (MPH) 2

Precipitation AM

Precipitation PM

Job Workforce

Enter Workforce

Crew 1

Title Laborers

No. of Crew 10

Total No. of Hrs 80

Enter Subcontractor Manpower

Subcontractor 1

Name of Subcontractor Ground Breaking Services

No. of Crew 10

Total No. of Hrs 80

Ground Breaking Zone 1 / 15 Oct 2018 / Antonio Iglesias


Score (3/6) 50.00% -2-
Question Response Details

Daily Activities

Describe the Daily Activities and Phase of First working day. Groundbreaking.
the Project

Photo/s

More Information Score (0/2) 0.00%

Was worked delayed for any reason? No

Was stoppage order in writing? N/A

Were verbal instructions recieved? Yes

Describe Verbal instructions were give to secure the perimeter.

Has the directions been put in writing? No

Has any verbal or written direction been


given to a Subcontractor? Yes

Describe Verbal instruction to secure the perimeter and assist the


visitor.

Has the directions been put in writing? No

Were any field work orders received or


implemented today? No

Was any Subcontractor scheduled to start


or material to arrive but didn't appear? No

Describe or List Subcontractors arrived early.

Were you required to do any extra work? No

Safety Score (2/2) 100.00%

Was a job site inspection performed


today? Yes

Were there any job site hazards observed


or incidents that occured today? No

Are all Subcontractors compliant to THG


Safety Management Program? Yes

Describe

Ground Breaking Zone 1 / 15 Oct 2018 / Antonio Iglesias


Score (3/6) 50.00% -3-
Question Response Details

QA/QC Score (0/1) 0.00%

Was any QA/QC inspections done today? No

Visitor Information Score (1/1) 100.00%

Was there any visitors today? Yes

List Names The City mayor for a photo op.

Completion

Foreman or Site Antonio Iglesias 17 Oct 2018 05:43 PM


Supervisor: Name and
Signature

Ground Breaking Zone 1 / 15 Oct 2018 / Antonio Iglesias


Score (3/6) 50.00% -4-
Media

Appendix 1

Ground Breaking Zone 1 / 15 Oct 2018 / Antonio Iglesias -5-