Lecture 2 - WBS Gantt Chart
Lecture 2 - WBS Gantt Chart
SCHEDULING
2
3
GANTT CHART
▫ a Gantt chart is a visual view of tasks scheduled over time. Gantt
charts are used for planning projects of all sizes and they are a
useful way of showing what work is scheduled to be done on a
specific day.
8
MS PROJECT
9
PERT/CPM
▫ ACTIVITY – IS THE WORK
OPERATIONS REQUIRED TO
COMPLETE THE TASK.
▫ EVENTS – IS A POINT IN TIME
SIGNIFYING THE BEGINNING OR
END OF ONE OR MORE ACTIVITIES.
▫ DUMMY ACTIVITY – IS AN ARROW
ON A NETWORK SWHOWING THE
DEPENDENT RELATIONSHIP
BETWEEN TWO ACTIVITIES.
▫ DURATION – IS THE TIME IT TAKES
AN ACTIVITY TO FINISHED.
▫ PATH – A SEQUENCE OF ACTIVITIES
THAT LEADS FROM STARTING
NODE TO THE FINISHED NODE
10
DEFINITIONS
▫ CRITICAL PATH – IS THE LONGEST ROUTE IN THE NETWORK OF
ACTIVITIES.
▫ EARLY START (ES) – EARLIEST ANY ACTIVITY CAN START
▫ EARLY FINISH (EF) - EARLIEST ANY ACTIVITY CAN FINISH
▫ LATE START (LS) – LATEST TIME THE ACTIVITY CAN START AND NOT
DELAY THE PROJECT
▫ LATE FINISH (LF) - LATEST TIME THE ACTIVITY CAN FINISH AND NOT
DELAY THE PROJECT