Jsa No-01 Container Unloading

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 4

Project: CMB JOB SAFETY ANALYSIS FOR CONTAINER UNLOADING AND SHIFTING JSA No.

01
1 Defination To identify the hazard before starting the work to avoid incident & accident.

2 Scope As per safety rules and standards

To provide safe working environment & promote a safety awarness for staff / Workers. To Protect public from injury and to damage
Objectives
3 properties . To ensure Safe works without disruption & to complete them within target in terms of safety and time.

To identify probable hazards & risk, then the Risks are ranked. Find out counter measures & Safety key points to minimize probability of
Procedure
4 hazards.

5 LTI-Lost Time Injuries,MTC-Medical Treatment Cases, FAC-First Aid Cases

Risk Revis
SR Probable
Activity Risk By Counter Measures Safety key Points ed Job Responsibility
No. Hazard rank risk

1) Workers should be 1) Site Engineer


Hooking of experienced & trained 2) Site Supervisor
container for with safety induction. 3) Site safety Officer
Damage of
1 unloading. (Use Fatal P1 1. Certified lifting gear (Chain, Belts, D’Shackle etc.) 2) Tool box talk done by P4
lifting tackles.
ceiling , concerned supervisor.
D’Shackle)
3) Use proper PPE'S
1) Workers should be 1) Site Engineer
experienced & trained
with safety induction. 2) Site Supervisor
1. Permit to work shall be obtained & Safely Tool 2) Tool box talk done by
Box Talk shall be performed by the concerned supervisor. 3) Site safety Officer
foreman/engineer to his group before commencing
to work. 3) Use proper PPE'S
2. Only trained operators shall be allowed to
operate equipments.
Hooking of Injury to
2 container by persons,Property Slipery P2 3. Area to be barricaded and signs posted. P4
4. Personnel carrying-out the job shall wear
trained persons. damage.
suitable eye protection, safety gloves and proper
PPE.
5. Full time supervision
6. Only physically fit persons are allowed to do the
work.

1. Permit to work shall be obtained & Safety Tools 1) Machine movement area 1) Site Engineer
Box Talk shall be performed by the foreman / will be cleared from all
engineer to his group before commencing to work. unwanted materials and
traffic. 2) Site Supervisor
2. Personnel carrying-out the job shall wear safety
2) Vehicle should be
gloves and proper PPE. checked along with the 3) Site safety Officer
3. Only trained person to carry out the job. chcklist and pre-entry check
4. Only an experienced operator with signal man list swill be displayed on the
will be allowed to operate the hydra. vehicle.
Human injury. 5. All lifting equipments such as Farana, 3) Proper leveled area
Hit / Trip /Cut Ceiling,D’Shackle etc. shall be certified. should be used for machine
Equipments 6. Safe Work load to be followed to avoid wire movement and signal man
damage rope/ boom snapping and lower collapsing. should be guided properly
Lifting by 4) Tool box talk to be done
3 Improper Fatal P1 7. Physical check up for the machine will be done before starts the work. P4
Farana by daily basis.
unloading. 5)Work can be carried out
Fall of Man & 8. Area to be barricaded by means of warning tape under the strict suprevision
10. Full time supervision.
material. 11. Access routs should be cleared
01. Proper Ladder should be provided. 1) Operator& workers 1) Site Engineer
02. Full body Harness with double lanyard will be should be experienced &
provided to all who are involved with working at trained with safety 2) Site Supervisor
height induction.
Human injury. 03. Do not attempt climb on container until it has 2) Tool box talk done by
Hit / Trip /Cut, been inspected and considered safe by your concerned supervisor.
3) Site safety Officer
Hit / Trip
Work at slip. supervisor. 3)people should aware
4 Height. Fall of both Man /Cut, P2 P4
slip. 06. Area to be barricaded by means of warning about PPE's
& material tape
07. Remove unwanted material at work site.

1. Permit to work shall be obtained & Safety Tools 1) Workers should be 1) Site Engineer
Box Talk shall be performed by the foreman / experienced & trained
engineer to his group before commencing to work. with safety induction. 2) Site Supervisor
2 .Personnel carrying out the job shall wear 2) Tool box talk done by
suitable safety gloves and proper PPE. concerned supervisor. 3) Site safety Officer
3.Only trained person to carry out the job .
4. Full Time Supervision. 3) Use proper PPE'S
5. All lifting equipments such as Hydra and ,
D.Shackle ,sling, belt, wire rope, etc. shall be
certified
Human injury. 6. Safe Work load to be followed to avoid wire
5. Container Hit & Cut by angle rope/ boom snapping and lower collapsing.
shifting and channel Hit / Trip 7. .Nylon rope will be provided for controlling the
unloading to Fall of Equipment,
5 exact location Improper loading, /Cut, P2 container when shifting process.
8. All lifting equipments such as Farana, Ceiling
P4
slip. etc. shall be certified
Hook latch failure
9. Physical check up for the machine will be done
before starting the job.
10. Should not allow unauthorized person in the
lifting area

RISK CLASS -
P1 Potential Death, Permanent Disability or Major Structural Damage
P2 Potential Temporary Disability or Minor Structural Damage
P3 Reportable Injuries /Environmental Hazards
P4 FAC
JSA Prepared by Contractor - EHS Officer JSA Reviewed by EHS - CUSHMAN JSA Approved by EHS - HEUBACH