ID Task Name Duration Start Finish January 2020 February 2020

4 7 10 13 16 19 22 25 28 31 3 6 9 12
1 RENOVASI KAMAR MANDI BU IIS 21 days Mon 1/13/20 Mon 2/10/20
2 Pekerjaan Renovasi Rumah 21 days Mon 1/13/20 Mon 2/10/20
3 PERSIAPAN 3 days Mon 1/13/20 Wed 1/15/20
4 - Mobilisasi material & Pekerja 1 day Mon 1/13/20 Mon 1/13/20
5 - Pekerjaan Bobokan Keramik Lantai 1 day Tue 1/14/20 Tue 1/14/20
6 - Pekerjaan Galian Pipa Air Bekas 1 day Wed 1/15/20 Wed 1/15/20
7 PEKERJAAN PLUMBING 5 days Thu 1/16/20 Wed 1/22/20
8 - Pipa dia. 25 mm2 2 days Thu 1/16/20 Fri 1/17/20
9 - Pipa dia. 15 mm2 2 days Thu 1/16/20 Fri 1/17/20
10 - Fitting & Material Bantu 2 days Thu 1/16/20 Fri 1/17/20
11 - Pipa dia. 100 mm2 3 days Mon 1/20/20 Wed 1/22/20
12 - Pipa dia. 80 mm2 3 days Mon 1/20/20 Wed 1/22/20
13 - Pipa dia. 50 mm2 3 days Mon 1/20/20 Wed 1/22/20
14 - Fitting & Material bantu 3 days Mon 1/20/20 Wed 1/22/20
15 Pekerjaan Sanitary 3 days Tue 2/4/20 Thu 2/6/20
16 - Pemasangan Wastafel 1 day Tue 2/4/20 Tue 2/4/20
17 - Pemasangan Closet 2 days Tue 2/4/20 Wed 2/5/20
18 - Pemasangan Bathub 3 days Tue 2/4/20 Thu 2/6/20
19 - Pemasangan Floor Drain 1 day Tue 2/4/20 Tue 2/4/20
20 - Material Bantu 1 day Tue 2/4/20 Tue 2/4/20
21 PEKERJAAN ELEKTRIKAL 2 days Thu 1/23/20 Fri 1/24/20
22 - Instalasi Penerangan 2 days Thu 1/23/20 Fri 1/24/20
23 - Instalasi Power Exhaust Fan 2 days Thu 1/23/20 Fri 1/24/20
24 - Pemasangan Exhaust Fan Dinding 2 days Thu 1/23/20 Fri 1/24/20
25 - Pemasangan Lampu 2 days Thu 1/23/20 Fri 1/24/20
26 PEKERJAAN PLAFOND 15 days Tue 1/14/20 Mon 2/3/20
27 - Pembongkaran Plafond Existing 1 day Tue 1/14/20 Tue 1/14/20
28 - Pemasangan Plafond gypsum 1 day Mon 2/3/20 Mon 2/3/20
29 - Pemasangan List plafond 1 day Mon 2/3/20 Mon 2/3/20
30 PEKERJAAN DINDING DAN LANTAI 11 days Mon 1/27/20 Mon 2/10/20
31 - Pekerjaan Kolom Praktis 1 day Mon 1/27/20 Mon 1/27/20
32 - Pemasangan Dinding Bata 2 days Mon 1/27/20 Tue 1/28/20
33 - Pemasangan Bata dudukan Bathub 2 days Mon 1/27/20 Tue 1/28/20
34 - Pekerjaan Plesteran 2 days Mon 1/27/20 Tue 1/28/20
35 - Pekerjaan Acian 2 days Mon 1/27/20 Tue 1/28/20
36 - Pekerjaan Pemasangan Keramik Dinding 5 days Mon 1/27/20 Fri 1/31/20

37 - Pekerjaan Pemasangan Keramik Lantai 5 days Tue 2/4/20 Mon 2/10/20

38 Pekerjaan Pengecatan 1 day Tue 2/4/20 Tue 2/4/20


39 - Pengecatan Plafond 1 day Tue 2/4/20 Tue 2/4/20
40 - Pengecatan Dinding 1 day Tue 2/4/20 Tue 2/4/20
41 - Material Bantu 1 day Tue 2/4/20 Tue 2/4/20
42 PEKERJAAN LAIN-LAIN 9 days Thu 1/23/20 Tue 2/4/20
43 - Pemasangan Pintu Sliding 1 day Tue 2/4/20 Tue 2/4/20
44 - Pembuatan Bak Kontrol 1 day Tue 2/4/20 Tue 2/4/20
45 - Pekerjaan pembersihan Area kerja 1 day Tue 2/4/20 Tue 2/4/20
46 Pekerjaan tambah level lantai kamar 1 day Thu 1/23/20 Thu 1/23/20
mandi

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project1
Summary Manual Summary Rollup Progress
Date: Thu 1/9/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1