NAME OF WORK:
Gosalamore to Belakoba Road from 0.00 Kmp to 18.00 Kmp Surfacing work, under Jalpaiguri
Highway Division in the district of Jalpaiguri, during the year 2019-2020.
Rate Analysis for Pakur Variety:
Lead from NJP Railway Stackyard to Work Site:
(For Stone Chips )
NJP Railway Stackyard to Sahudangi = 4.00 km.
Saudagi to Ambari = 6.00 km.
Ambari to Belakoba = 11.00 km.
Belakoba to (Work site)(18.00/2) = = 9.00 km.
Total = 30.00 km.
Say, Rs.30.00 km.
Cost of Stone Materials in connection with Pakur Variety at Work Site: (P-226 ,Table-III , 2 )
Stone dust
Type-B Stone Stone Stone Chips Stone Chips Stone Chips Stone Chips 5.60 mm
Size Type-A screening mixed wit grit Stone grit
screening metal(Gr.I) metal(Gr.II) 26.50 mm 22.40 mm 13.20 mm 11.20 mm Stone chips
Cost of
Rs.1,256.00 Rs.1,062.00 Rs.1,451.00 Rs.1,473.00 Rs.1,528.00 Rs.1,060.00 Rs.1,074.00 Rs.1,543.00 Rs.1,566.00 Rs.1,427.00 Rs.1,174.00
Materials
Cost of
Rs.374.50 Rs.374.50 Rs.374.50 Rs.374.50 Rs.374.50 Rs.374.50 Rs.374.50 Rs.374.50 Rs.374.50 Rs.374.50 Rs.374.50
Carriage
Loading,UL&S
Rs.77.00 Rs.77.00 Rs.83.00 Rs.83.00 Rs.77.00 Rs.77.00 Rs.77.00 Rs.77.00 Rs.77.00 Rs.77.00 Rs.77.00
tacking
Total ( +
Rs.1,707.50 Rs.1,513.50 Rs.1,908.50 Rs.1,930.50 Rs.1,979.50 Rs.1,511.50 Rs.1,525.50 Rs.1,994.50 Rs.2,017.50 Rs.1,878.50 Rs.1,625.50
Stacking)
(-) Stacking Rs.19.25 Rs.19.25 Rs.20.75 Rs.20.75 Rs.19.25 Rs.19.25 Rs.19.25 Rs.19.25 Rs.19.25 Rs.19.25 Rs.19.25
Total ( -
Rs.1,688.25 Rs.1,494.25 Rs.1,887.75 Rs.1,909.75 Rs.1,960.25 Rs.1,492.25 Rs.1,506.25 Rs.1,975.25 Rs.1,998.25 Rs.1,859.25 Rs.1,606.25
Stacking)
/m3. /m3. /m3. /m3. /m3. /m3. /m3. /m3. /m3. /m3.
Stone Chips 37.5 Stone Chips Stone Chips Stone Stone Chips River grit Stone Chips 5.60 mm
Size mm 20.00 mm 10.00 mm metal(Gr.II) 26.50 mm 11.20 mm Stone chips
Cost of
Rs.1,469.00 Rs.1,482.00 Rs.1,351.00 Rs.1,647.00 Rs.1,705.00 Rs.261.00 Rs.1,599.00 Rs.398.00
Materials
Cost of
Rs.374.50 Rs.374.50 Rs.374.50 #REF! #REF! #REF! Rs.374.50 Rs.374.50
Carriage
Loading,UL&S
Rs.77.00 Rs.77.00 Rs.77.00 Rs.77.00 Rs.77.00 Rs.77.00 Rs.77.00 Rs.77.00
tacking
Total ( +
Rs.1,920.50 Rs.1,933.50 Rs.1,802.50 #REF! #REF! #REF! Rs.2,050.50 Rs.849.50
Stacking)
(-) Stacking Rs.19.25 Rs.19.25 Rs.19.25 Rs.19.25 Rs.19.25 Rs.19.25 Rs.19.25 Rs.19.25
Total ( -
Rs.1,901.25 Rs.1,914.25 Rs.1,783.25 #REF! #REF! #REF! Rs.2,031.25 Rs.830.25
Stacking)
/m3. /m3. /m3. /m3. /m3. /m3. /m3. /m3.
Rate Analysis for North Bengal Variety:
Lead from Odlabari River Bed to Work Site:
(For River bed materials)
Lead from Odlabari River Bed to Work Site:
River Bed = 3.00 km.
Odlabari River Bed to Bodagunj = 31.00 km.
Bodagunj to (Work site) =(16.00/2) = 6.00 km.
Total = 40.00 km.
Say, Rs.40.00 km.
Cost of Stone Materials in connection with North bengal Variety at Work Site: (P-1 of 2 nd A & C ; P- 224 , It-1.03 , )
Boulder above Boulder Bazree R.B.M Shingle Bazree Medium 5.60 mm
Size Size course sand
225 225-150 22.40 mm 37.5mm 11.20 mm Sand Stone chips
Cost of
Cost of Materials Rs.292.00 Rs.271.00 Rs.325.00 Rs.173.00 Rs.238.00 Rs.325.00 Rs.655.00 Rs.774.00 Rs.398.00
Materials
Cost of
Cost of Carriage Rs.469.50 Rs.469.50 Rs.469.50 Rs.469.50 Rs.469.50 Rs.469.50 Rs.0.00 Rs.0.00 Rs.0.00
Carriage
Loading,UL&S
Rs.83.00 Rs.83.00 Rs.77.00 Rs.77.00 Rs.77.00 Rs.77.00 Rs.0.00 Rs.0.00 Rs.0.00
tacking
Total ( +
Rs.844.50 Rs.823.50 Rs.871.50 Rs.719.50 Rs.784.50 Rs.871.50 Rs.655.00 Rs.774.00 Rs.398.00
Stacking)
(-) Stacking Rs.20.75 Rs.20.75 Rs.19.25 Rs.19.25 Rs.19.25 Rs.19.25 Rs.0.00 Rs.0.00 Rs.0.00
Total ( -
Total Rs.823.75 Rs.802.75 Rs.852.25 Rs.700.25 Rs.765.25 Rs.852.25 Rs.655.00 Rs.774.00 Rs.398.00
Stacking)
/m .
3
/m .
3
/m .3
/m .
3
/m .
3
/m . 3
/m .3
/m .
3
/m .
3
/m3.
Unit : MT
Source - Siliguri
Carriage distance:
Siliguri to Jalpaiguri 35 km
35 km
Gosalamore to Belakoba Road from 0.00 Kmp to 18.00 Kmp Surfacing work, under
Jalpaiguri Highway Division in the district of Jalpaiguri, during the year 2019-2020.
Part A: Road Works
Site clearience
Item No: 1 Clearing grass and removal of rubbish up to a distance of 30 m outside the periphery of the area
as per Technical Specifications Clause 201 for Rural Roads of MORD.
By Manual Means
(I) By Manual Means
Ref: Item No.: 2.03 ; Page No.: ### of
P.W. (Roads) Department Schedule of Rates.
Labour cost as per item rate = Rs.11,868.00 /hec.
Final item rate = ### /hec.
Item No: 2 Clearing and grubbing road land including uprootingwild vegetation, grass, bushes, shrubs,
saplings and trees of girth upto 300 mm, removal of stumps of such trees cut earlier and
disposal of unserviceable materials and stacking of serviceable material to be used or
auctioned, upto a lead of 1000 m including removal and disposal of top organic soil not
exceeding 150 mm in thickness as per Technical
Specifications Clause 201 for Rural Roads of MORD.
(I)
(I)By
ByManual
ManualMeans
Means
a) In area of non-thorny jungle
Ref: Item No.: 2.04 a(1) ; Page No.: ### of
P.W. (Roads) Department Schedule of Rates.
Labour cost as per item rate = Rs.44,978.00 /hec.
Final item rate = ### /hec.
Roads works
Item No: 3 Patching of potholes by draining water, cutting the pothole area to rectangular shape with
vertical edges, removing all loose materials, screening and stacking the same for reuse with new
materials as per requirement, filling the pothole area with additional volume of crushed stone
materials / laterite / Jhama / broken shingles / coated stones of Pakur variety etc. and screenings
as applicable, and compacting the same with static roller as per Water Bound Macadam
Specification, including cost of all materials and machineries.
Ref: Item No.: 10.04 ; Page No.: ### of
P.W. (Roads) Department Schedule of Rates.
Cost of Material (A)
a. Cost of Stone materials.
(i) Cost of Grading-II Aggregate (53 mm to22.4mm) Pakur Variety.
1.00 m3 /m3 @ ### /m3 = Rs.1,930.50
= /m3.
(ii) Cost of Screening Ty-B(11.2mm)Pakur Variety.
0.21 m3 /m3 @ ### /m3 = Rs.317.84
= /m3.
(A) Cost of Material = Rs.2,248.34 /m3.
(B) Labour cost as per item Rate = Rs.443.00 /m3.
Final item rate= Rs.2,691.34 /m3.
Item No: 4 Providing and applying primer coat with cationic Bitumen Emulsion of approved grade
conforming to IS:8887-1978 and requisite quantity on prepared surface of granular base
including cleaning of road surface and spraying primer using Mechanical means including cost
and carriage of bitumen emulsion and all other incidental costs of work complete as per Clause
502 of Specifications for Road & Bridge Works of MoRT&H (5th Revision).
Ref: Item No.: 5.01 (i) ; Page No.: ### of
P.W. (Roads) Department Schedule of Rates.
(i) For WBM / WMM Surface (With Primer at the rate of 0.85 kg per sqm.)
Cost of Material (A)
cost of bitumin emulsion
0.850 Kg @ Rs.35.01 /m2 Rs.29.76 /m2.
Labour cost as per item rate (B) Rs.1.50 /m2.
Final item rate Rs.31.26 /m2.
Gosalamore to Belakoba Road from 0.00 Kmp to 18.00 Kmp Surfacing work, under
Jalpaiguri Highway Division in the district of Jalpaiguri, during the year 2019-2020.
Item No: 5 Providing and applying tack coat with Cationic Bitumen Emulsion of approved grade conforming
to IS: 8887-1978 on the prepared surface cleaned with Hydraulic broom, moistening the surface
including cost and carriage of emulsion, hire charges of machinery and labour, cost of fuel and
lubricants all complete as per Clause 503 of Specifications for Road & Bridge Works of MoRT&H
(5th Revision).
Ref: Item No.: 5.02 i ; Page No.: ### of
P.W. (Roads) Department Schedule of Rates.
(i) On Bituminous Surface (Using Bitumen Emulsion at the rate of 0.25 kg per sqm.)
Cost of Material (A)
cost of bitumin emulsion
0.250 Kg @ Rs.35.01 /m2 = Rs.8.75 /m2.
Labour cost as per item rate (B) = Rs.1.30 /m2.
Final item rate = Rs.10.05 /m2.
Item No: 6 Repairing pot-holes and making up small depressions with ramming or power rolling including
screening, cleaning chips or metals and washing, drying as necessary and heating the
chips........etc. i) With premixed Chips or Bajrees with 54 kg of bitumen per m3 of loose net
volume of stone chips using concrete mixer machine. (The payment is to be made on the basis
of loose net volume of stone materials consumed in the work)
(b) Using Mobile HMP (Light duty)
Item No: 7 Providing and laying Bituminous Profile Corrective Course using Mobile Hot Mix Plant (Light Duty)
and using aggregates of Grading-2 of Table-33 premixed with 75kg of bitumen per cum,
transported to site laid over a previously prepared surface at specified laying temperature to the
required grade, level and alignment, as per specification to achieve the desired compaction
including cost and carriage of stone materials and bitumen, hire charges of machinery and
equipment, cost of fuel and lubricants and wages of operational staff, quality control complete
as per direction of Engineer-incharge.
Item No: 8 Providing and laying bituminous concrete with Hot Mix Plant using coarse aggregates, fine
aggregates, filler materials and bituminous binder of required specification including screening,
cleaning of chips and preparing a uniform and quality mix in Hot Mix Plant and ensuring a
omogeneous mix, in which all particles of the mineral aggregates are coated uniformly,
transporting the hot mix to work site, layingthe mixed materials at specified laying temperatur
with a hydrostatic paver finisher with sensor control to the required grade, level and alignment
over prepared surface coated with tack coat, rolling with smooth wheeled, vibratory and tandem
rollers for break down, inter-mediate and finished rolling to achieve the desired density of at
least 98% of that of Laboratory Marshall specimen, including cost and carriage of bitumen,
coarse and fine aggregates and filler materials and hire charges of machinery and equipment for
construction and quality control, fuels and lubricants and wages of operational staffcomplete as
per Clause 507 of Specifications for Road & Bridge Works of MoRT&H (5th Revision).
B. For Grading 2 (13.2 mm nominal size, 30mm/40 mm thick.) (i) Using Batch Type HMP of
minimum capacity 100-120 TPH.
Item No: 10 Labour for laying 150 mm to 200 mm boulder soling including rough dressing hand packing and
ramming down small pieces in the interstics including rolling and preparing the bed to proper
level and filling up all joints with sandy clay or earth.
without rolling but including ramming.
Item No: 11 Construction of Sub Base using Local Materials spreading in uniform layers with Motor grader on
prepared surface, including screening the metal as necessary, mixing by mix in place method
with Rotavator at OMC, and compacting with vibratory roller to achieve the desired density,
lighting, guarding and barricading including cost and carriage of all materials and making
necessary
earthen bundh of one metre wide on each side to protect the edges complete as per Clause 401
of Specifications for Road & ridge Works of MoRT&H (5th Revision).
(iv) For Construction of Sub Base by compacting river bed materials.
Ref: Item No.: 4.09(iv) ; Page No.: ### of
P.W.Department Schedule of Rates.
Cost of Material (A)
R.B.M 1.28 m3 @ 719.50 Rs.920.96 /m3.
Labour cost as per item rate (B) Rs.152.00 /m3.
Sub total Rs.1,072.96 /m3.
Final item rate = Rs.1,072.96 /m3.
Item No: 13 Supplying & fixing of Raised Pavement Markers / Road Studs / Cats Eye made of polycarbonate
moulded body and reflective panels with micro prismatic lens capable of providing total internal
reflection of the light entering the lens face which shall support a load of 13635 kg tested in
accordance to ASTM D 4280 Type H and complying to clause no 804 of MoRT&H's specification
for Road &Bridge Works (Fifth Rev.). Marker height shall not be less than 10 mm and shall not
exceed 20 mm, width shall not exceed 130mm
Item No: 14 Supplying and installation of delineators (road way indicators, hazard markers, object markers),
80-100 cm high above ground level, painted black and white in 15 cm wide strips, fitted with 80
x 100 mm rectangular or 75 mm dia circular reflectorised panels at the top, buried or pressed
into the ground and conforming to IRC-79 and the drawings.
Ref: Item No.: 8.11 ; Page No.: ### of
of P.W. (Roads) Schedule of Rates.
Item No: 15 Providing and fixing of retro- reflectorised cautionary, mandatory and informatory sign as per IRC
:67 made of high intensity grade sheeting vide clause 801.3, fixed over aluminium sheeting, 1.5
mm thick supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the
ground by means of properly designed foundation with M15 grade cement concrete 45 cm x 45
cm x 60 cm, 60 cm below ground level as per approved drawing and Clause 801 of
Specifications for Road & Bridge Works of MoRT&H (5th Revision).
iv) 80 mm x 60 mm rectangular
Ref: Item No.: 8.04 (iv) ; Page No.: ### of
of P.W. (Roads) Schedule of Rates.
Item No: 16 Providing and fixing of retro- reflectorised cautionary, mandatory and informatory sign as per IRC
:67 made of high intensity grade sheeting vide clause 801.3, fixed over aluminium sheeting, 1.5
mm thick supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the
ground by means of properly designed foundation with M15 grade cement concrete 45 cm x 45
cm x 60 cm, 60 cm below ground level as per approved drawing and Clause 801 of
Specifications for Road & Bridge Works of MoRT&H (5th Revision).
Item No: 17 Supplying fitting and fixing R.C. guard post 1.37m long with C.C. 1:2:4 with graded stone chips
of 13.2mm down casting ,curing complete including cost of providing 4nos.of 12mm dia. rod of
length 1.54m as main reinforcement and 6 nos. of round shaped 8mm dia rods used as binders;
the placing of the first binder should be at 75mm below the top finished surface and the other 5
nos of binders should be placed at 245mm c/c......etc
Ref: Item No.: 8.16 ; Page No.: ### of
of P.W. (Roads) Schedule of Rates.
Cost of Material (A)
Cost for Labour Charge.(B) = Rs.773.00 /each.
Sub total = Rs.773.00 /each.
Final item rate (E+F) = Rs.773.00 /each.
Item No: 18 Providing and erecting direction and place identification retro- reflectorised sign as per IRC :67
made of high intensity grade sheeting vide clause 801.3, fixed over aluminium sheeting, 2 mm
thick with area exceeding 0.9 sqm supported on a mild steel angle iron post 75 mm x 75 mm x 6
mm, 2 Nos. firmly fixed to the ground by means of properly designed foundation with M 15
grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved
drawing and Clause 801 of Specifications for Road & Bridge Works of MoRT&H (5th Revision)..
Item No: 20 Ordinary Cement concrete (mix 1:1.5:3) with graded stone chips (20 mm nominal size) excluding
shuttering and reinforcement if any, in ground floor as per relevant IS codes.
(i) Pakur Variety
Ref: Item No.: 10i ; Page No.: 26 of
of P.W.D Schedule of Rates.(3rd corrigenda)
Item No: 21 Supplying, fitting and placing un-coated HYSD bar reinforcement in Bridge Foundation including
initial straightening, straightening of coils bars, removal of loose rust (if any), cutting to requisite
length bending, binding with annealed wire not less than 1 mm in size....etc.
Ref: Item No.: 12.21 ; Page No.: ### of
of P.W.D Schedule of Rates.(3rd corrigenda)
Item No: 22 a) Supplying transporting & fabrication of welded steel girder as per approved drawing duly
made up built up sections of MS Plate, Angle, Channel of different thickness including metalizing
priming coat followed by finish coat of paints of total thickness of 165μm.
Ref: Item No.: 14.05 ; Page No.: ### of
of P.W.D Schedule of Rates.(3rd corrigenda)
(a) 10-20 mm thick & (b) 25-40 mm thick
(A) Item Rate = 42000.00
(B) Cost of Steel
1.05 x 34000.00 = 35700.00
(C ) Cost of carriage
352.00 / 1.15 = 306.09
(D) Add overhead charges
15% of (35700+306.09) = 5400.91
( E ) Add Contractor's profit
10% of (35700+306.09+5400.91) = 4140.70
Total = 87547.70 /MT
(a) Upto 200 mm size
Reference item 14.05 of page 312 of P.W. (Roads) schedule for Road and Bridge Works
(A) Item Rate = 42000.00
(B) Cost of Steel
1.05 x ### = 42630.00
(C ) Cost of carriage
352.00 / 1.15 = 306.09
(D) Add overhead charges
15% of (42630+306.09) = 6440.41
(E) Add Contractor's profit
10% of (42630+306.09+6440.41) = 4937.65
Total = 96314.15 /MT
Gosalamore to Belakoba Road from 0.00 Kmp to 18.00 Kmp Surfacing work, under
Jalpaiguri Highway Division in the district of Jalpaiguri, during the year 2019-2020.
Item No: 23 b) Assembling, erection I launching of fabricated steel girders in proper position, line, level,
alignment including erection of staging and scaffolding,dismantling the same after completion of
work.
Ref: Item No.: 14.05b ; Page No.: ### of
of P.W. (Roads) Schedule of Rates.
Item Rate 13000.00
Tota = 13000.00 /MT
Item No: 26 Supplying, fitting, fixing bolts with nuts, washer: (i) 20 to 25 mm dia bolt Length above 150 mm
Item No: 27 Primming one coat on steel or other metal surface with synthetic oil bound primer of approved
quality includign smoothning surfaces by sand papering etc.
Item No: 28 (A) Painting with best quality synthetic enamel paint of approved make and brand including
smoothening surface by sand papering etc.on the surface, if necessary :
(b) On steel or other metal surface :(iv) Two coats (with any shade except white)
Item 29 Earth work in excavation of foundation of structures as per drawing ...including... backfilling...
No: within a lead of 150 m …etc.
I) In all sorts of soil excluding marshy soil & rocks (soft or hard).
by manual means.
(a) Depth upto 3.0 m
(iv)Without pumping out water and shoring
Ref: Item No.: 12.01 I) a) iv) Page No.: ### of
of P.W. (Roads) Schedule of Rates.
Cost for Labour Charge.(B) Rs.114.00 /m3.
Sub total-I Rs.114.00 /m3.
Final item rate = Rs.114.00 /m3.
Item No: 30 Filling properly the empty sausage crates with boulders of any size & shape with hand packing
after preparation of bed of placement, placing the crate in position, carriage of boulders from
road stacks with a lead upto 150m etc. complete in all respect including stitching the rest of the
crate with wire (passage for filling boulders) after filling up the crate with boulders and launching
the crate in position if necessary and as directed by the Engineer-in charge.
Item No: 31 Weaving wire mattress as directed with wire of 4mm dia. and making sausage crate of required
shape after tying all intersections including joining longitudinal ends, closing ends of sausage,
carriage of wire to site of work complete in all respect as per direction of the Engineer-in-charge
including cost of supply of G.I. wire. (With 100mm x 100mm mesh.)
Item No: 32 Construction of Subgrade and Earthen Shoulders Construction of subgrade and earthen
shoulders with approved material obtained from borrow pits with all lifts and leads, transporting
to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2
with lead upto 1000 m as per Technical Specification Clause 303.1 for Rural Roads of MORD.
(Borrow pit /pre work post work measurement)
Extra for carriage of all kinds of earth by Mechanical Transport:
(c) Carriage up to total lead of 3.0 km.
Item No: 33 Providing and laying of Filter media with granular materials / stone crushed aggregates / brick
aggregates / river bed materials satisfying the requirements laid down in clause 2504.2.2 of
MoRT&H Specifications to a thickness of not less than 600 mm with smaller size towards the soil
and bigger size towards the wall and provided over the entire surface behind abutment, wing
wall and return wall to the full height compacted to a firm condition complete as per drawing
and technical specification.
Back of sausage
Ref: Item No.: 13.05 ; Page No.: ### of
of P.W. (Roads) Schedule of Rates.
Cost of R.B.M.=
0.72 m3/m3 @ Rs.700.25 /m3 Rs.504.18 /m3
Item No: 34 Providing and laying Design Mix concrete for plain / reinforced concrete work in any part of
bridge (excluding bottom plugging) with coarse aggregates of appropriate nominal size and
grading, fine aggregate (sand) conforming to proper grading zone, both of approved quality and
cement, as necessary, including labour, cost and carriage of all materials and including
preparation of design mix, approval of the same by the Engineer-in-Charge and cost for quality
control, sampling, testing etc. all complete but excluding cost of labour and materials for
formwork & reinforcement works.
(a) M-15 Grade
Using concrete mixer.
for slope protection
Ref: Item No.: 18.07 ; Page No.: ### of
P.W. (Roads) Schedule of Rates.
Cost of 20mm stone chips =
60.00% of 0.90 m3/m3 @ ### /m3 Rs.1,033.70 /m3
Cost of 10mm stone chips =
40.00% of 0.90 m3/m3 @ ### /m3 Rs.641.97 /m3
Cost of cement 5.873 /kg @ 350.00 kg/ Rs.2,055.55 /m3
(A)Cost of Material m3= Rs.3,731.22 /m3
(B)Item Rate = Rs.1,406.00 /m3
Total = Rs.5,137.22 /m3
Item No: 35 Hire and labour charges for Shuttering with or without staging upto 4.0 m height using approved
stout props with wooden planks/ply wood/steel sheet plate with required bracing.......etc.
(b) Where staging is not required.
(i) For WBM / WMM Surface (With Primer at the rate of 0.85 kg per sqm.)
For WBM Surface 236.250 m3 / 0.075 m = 3150.00 m2
Total= 3150.00 m2
B. For Grading 2 (13.2 mm nominal size, 30mm/40 mm thick.) (i) Using Batch Type HMP of minimum capacity 100-120 TPH.
Gosalamore to Belakoba-bazar.
0.00 kmp to 18.00 kmp
1 x 18.00 km x 1000.0 m x 7.00 m = 126000.00 m2
For Bell mouth both side .
Gosalamore,Randhamali & Belakoba junction widening portion
2x 8.00% of 126000.00 m2. = 20160.00 m2.
For market Danguajhar portion .
3x 6.00% of 126000.00 m2. = 22680.00 m2.
Deduction for (Under D.L.P.) Total area = 168840.00 m2
i)Neopati Bridge & Approaches 380.00 x 7.00 = 2660.00 m2
ii)Monthony Bridge & Approaches 390.00 x 7.00 = 2730.00 m2
Total area = 163450.00 m2
TotalVoll. = 163450.00 m2 X 0.03 m = 4903.50 m3
19.0 Ordinary Cement concrete (mix 1:2:4) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement,
if any, in ground floor as per relevant IS codes.
a) Pakur Variety
2.0 x 3.0 x 3.0 x 0.1 Total = 1.80 m3
20.0 Ordinary Cement concrete (mix 1:1.5:3) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement if
any, in ground floor as per relevant IS codes.
(i) Pakur Variety
2.0 x 3.0 x 3.0 x 0.4 = 7.20 m3
2.0 x 0.8 x 0.8 x 2.6 = 3.33 m3
Total = 10.53 m3
21.0 Supplying, fitting and placing un-coated HYSD bar reinforcement in Bridge Foundation including initial straightening, straightening
of coils bars, removal of loose rust (if any), cutting to requisite length bending, binding with annealed wire not less than 1 mm in
size....etc.
0.750% x 10.53 m3 x 7850.0 Kg/m3 Total = 0.62 MT
22.0 a) Supplying transporting & fabrication of welded steel girder as per approved drawing duly made up built up sections of MS
Plate, Angle, Channel of different thickness including metalizing priming coat followed by finish coat of paints of total thickness of
165μm.
(i) Steel plates:(F-250 conforms to IS:2062-2006)
461750802.xls
Sl. Item Page
Description of Item Quantity Unit
No. No. No.
(a) 10-20 mm thick & (b) 25-40 mm thick
Weight
Descript Surface Unit
Size Length Width per No of
Sl No. ion of Area Weigh No Total Weight
mm m m numbe Member
Item (Sqm) t
r
For Column
1) For 1 No Over Head Gantry
Base
Plate
(25mm 25 0.650 0.650 1.690 196.250 2 ### 165.831
Thick)
Stiffner
Plate
(10mm 10 0.400 0.163 2.086 78.500 16 5.118 81.891
Thick)
Cap
Plate
(12mm 12 0.650 0.825 4.290 78.500 4 ### 202.059
thick)
Stiffner
Plate
(10mm 10 0.300 0.305 1.464 78.500 8 7.183 57.462
Thick)
(ii) Structural Steel (MS) angles, joist, pipe, channel, flats, etc.(F250 conforms to IS:2062 & 808)
(a) Upto 200 mm size
Gantry
1) For 1 No Overhead Gantry
Main
Pipe
End 80 NB 12.649 12.71 8.36 4 105.75 1 423.00
Vertical
Pipe 80 NB 1.020 1.025 8.36 4 8.53 1 34.12
End
Horizont
al Pipe 80 NB 0.630 0.633 8.36 4 5.27 1 21.08
Vertical
Pipe 32 NB 1.020 2.46 3.10 24 3.16 1 75.84
Vertical
Pipe
Diagona
l 32 NB 1.428 2.583 3.10 18 4.43 1 79.74
Vertical
Pipe(dig
nl) 32 NB 1.250 0.502 3.10 4 3.88 1 15.52
Vertical
Pipe(dig
nl) 32 NB 1.160 0.932 3.10 8 3.6 1 28.80
Horizont
al Pipe 25NB 0.668 1.259 2.41 24 1.61 1 38.64
Horizont
al
Pipe(dig
nl) 25NB 1.180 1.667 2.41 18 2.84 1 51.12
Horizont
al
Pipe(dig
nl) 25NB 0.950 0.298 2.41 4 2.29 1 9.16
Horizont
al
Pipe(dig
nl) 25NB 0.835 0.262 2.41 4 2.01 1 8.04
Internal
Diagnoa
l Pipe 25NB 0.835 1.573 2.41 24 2.01 1 48.24
Total Surface Area (B) = 25.904 m2
461750802.xls
Sl. Item Page
Description of Item Quantity Unit
No. No. No.
For Display Support
1) For 1 No Over Head Gantry
Support
6.8 1 54.40
Angle 75x75x6 1.000 2.33 6.8 8
Back
Frame 18.85 1 37.70
Angle 25x25x4 12.649 7.36 1.49 2
Total Surface Area (C ) = 9.69 Total in Kg = 925.40
0.925 MT Total = 0.925 MT
ii) Structural steel (MS) angles, joist, pipe, channels, flats, etc.(F 250 conforms to
IS:2062 & 808)
(b) Above 200 mm & upto 400 mm size
Column
1) For 1 No Over Head Gantry
Main
10.362
Pipe 300 NB 5.500 62.8 2 345.40 690.8
Total Surface Area (D) = 10.362 Total in Kg = 690.8
0.691 MT Total = 0.691 MT
23.0 b) Assembling, erection I launching of fabricated steel girders in proper position, line, level, alignment including erection of
staging and scaffolding,dismantling the same after completion of work.
0.51+0.925+0.691 Total = 2.13 MT
26.0 Supplying, fitting, fixing bolts with nuts, washer: (i) 20 to 25 mm dia bolt Length above 150 mm
27.0 Primming one coat on steel or other metal surface with synthetic oil bound primer of approved quality includign smoothning
surfaces by sand papering etc.
Primming area for the structures = (A+B+C+D) surface area (9.530+25.904+9.69+10.362) = 55.486 M2
Add 10% Extra (9.530+25.904+9.69+10.362 x 10% = 5.549 M2
Total = 61.040 M2
28.0 (A) Painting with best quality synthetic enamel paint of approved make and brand including smoothening surface by sand
papering etc.on the surface, if necessary :
(b) On steel or other metal surface :(iv) Two coats (with any shade except white)
painting area for the structures = (A+B+C+D) surface area (9.530+25.904+9.69+10.362) = 55.486 M2
Add 10% Extra (9.530+25.904+9.69+10.362 x 10% = 5.549 M2
Total = 61.040 M2
at ch 0.9 km L/S
Top layer 55.00 x (0.9+1.2)/2 x 1.2 = 69.30 m3
Middle layer 55.00 x (1.2+1.5)/2 x 1.0 = 74.25 m3
Bottom layer 55.00 x 2.2 x 0.7 = 84.70 m3
at ch 0.9 km L/S
Top layer 60.00 x (0.9+1.2)/2 x 1.2 = 75.60 m3
Middle layer 60.00 x (1.2+1.5)/2 x 1.0 = 81.00 m3
Bottom layer 60.00 x 2.2 x 0.7 = 92.40 m3
at ch 1.1 km L/S
at 1.2 km L/s
Top layer 55.00 x (0.9+1.2)/2 x 1.2 = 69.30 m3
Bottom layer 55.00 x 1.7 x 0.7 = 65.45 m3
at ch .2.00 km.R/S
Top layer 30.00 x (0.9+1.2)/2 x 1.2 = 37.80 m3
Bottom layer 30.00 x 1.7 x 0.7 = 35.70 m3
at ch .2.0 km.L/S
Top layer 20.00 x (0.9+1.2)/2 x 1.2 = 25.20 m3
Bottom layer 20.00 x 1.7 x 0.7 = 23.80 m3
at ch .2.10 km.L/S
Top layer 30.00 x (0.9+1.2)/2 x 1.2 = 37.80 m3
Bottom layer 30.00 x 1.7 x 0.7 = 35.70 m3
at ch .2.20 km.L/S
Top layer 35.00 x (0.9+1.2)/2 x 1.2 = 44.10 m3
Bottom layer 35.00 x 1.7 x 0.7 = 41.65 m3
at ch 2.4 km R/S
Top layer 25.00 x (0.9+1.2)/2 x 1.2 = 31.50 m3
Middle layer 25.00 x (1.2+1.1.5)/2 x 1.0 = 33.75 m3
Bottom layer 25.00 x 2.2 x 0.7 = 38.50 m3
at ch 2.6 km L/S
Top layer 55.00 x (0.9+1.2)/2 x 1.2 = 69.30 m3
Middle layer 55.00 x (1.2+1.1.5)/2 x 1.0 = 74.25 m3
Bottom layer 55.00 x 2.2 x 0.7 = 84.70 m3
at ch 2.6 km R/S
at 2.8 km L/s
Top layer 20.00 x (0.9+1.2)/2 x 1.2 = 25.20 m3
Bottom layer 20.00 x 1.7 x 0.7 = 23.80 m3
at ch .2.80 km.R/S
Top layer 30.00 x (0.9+1.2)/2 x 1.2 = 37.80 m3
Bottom layer 30.00 x 1.7 x 0.7 = 35.70 m3
at ch .2.9 km.L/S
Top layer 40.00 x (0.9+1.2)/2 x 1.2 = 50.40 m3
Bottom layer 40.00 x 1.7 x 0.7 = 47.60 m3
at ch .3.0 km.L/S
at ch .3.20 km.L/S
Top layer 35.00 x (0.9+1.2)/2 x 1.2 = 44.10 m3
Bottom layer 35.00 x 1.7 x 0.7 = 41.65 m3
at ch 3.3 km R/S
Top layer 25.00 x (0.9+1.2)/2 x 1.2 = 31.50 m3
Middle layer 25.00 x (1.2+1.1.5)/2 x 1.0 = 33.75 m3
Bottom layer 25.00 x 2.2 x 0.7 = 38.50 m3
at ch 3.8 km L/S
Top layer 25.00 x (0.9+1.2)/2 x 1.2 = 31.50 m3
Middle layer 25.00 x (1.2+1.1.5)/2 x 1.0 = 33.75 m3
Bottom layer 25.00 x 2.2 x 0.7 = 38.50 m3
at ch 3.9 km L/S
Top layer 30.00 x (0.9+1.2)/2 x 1.2 = 37.80 m3
Middle layer 30.00 x (1.2+1.1.5)/2 x 1.0 = 40.50 m3
Bottom layer 30.00 x 2.2 x 0.7 = 46.20 m3
at 4.0 km L/s
Top layer 30.00 x (0.9+1.2)/2 x 1.2 = 37.80 m3
Bottom layer 30.00 x 1.7 x 0.7 = 35.70 m3
at ch 4.3 km L/S
Top layer 30.00 x (0.9+1.2)/2 x 1.2 = 37.80 m3
Middle layer 30.00 x (1.2+1.1.5)/2 x 1.0 = 40.50 m3
Bottom layer 30.00 x 2.2 x 0.7 = 46.20 m3
at ch 4.4 km L/S
Top layer 35.00 x (0.9+1.2)/2 x 1.2 = 44.10 m3
Middle layer 35.00 x (1.2+1.1.5)/2 x 1.0 = 47.25 m3
Bottom layer 35.00 x 2.2 x 0.7 = 53.90 m3
at ch 4.6 km R/S
Top layer 30.00 x (0.9+1.2)/2 x 1.2 = 37.80 m3
Middle layer 30.00 x (1.2+1.1.5)/2 x 1.0 = 40.50 m3
Bottom layer 30.00 x 2.2 x 0.7 = 46.20 m3
at 4.80 km R/s
Top layer 40.00 x (0.9+1.2)/2 x 1.2 = 50.40 m3
Bottom layer 40.00 x 1.7 x 0.7 = 47.60 m3
at ch 5.0 km R/S
Top layer 30.00 x (0.9+1.2)/2 x 1.2 = 37.80 m3
Middle layer 30.00 x (1.2+1.1.5)/2 x 1.0 = 40.50 m3
Bottom layer 30.00 x 2.2 x 0.7 = 46.20 m3
at ch 5.2 km R/S
Top layer 50.00 x (0.9+1.2)/2 x 1.2 = 63.00 m3
Middle layer 50.00 x (1.2+1.1.5)/2 x 1.0 = 67.50 m3
Bottom layer 50.00 x 2.2 x 0.7 = 77.00 m3
461750802.xls
Sl. Item Page
Description of Item Quantity Unit
No. No. No.
at 5.40 km L/s
Top layer 25.00 x (0.9+1.2)/2 x 1.2 = 31.50 m3
Bottom layer 25.00 x 1.7 x 0.7 = 29.75 m3
at ch 5.8 km L/S
Top layer 65.00 x (0.9+1.2)/2 x 1.2 = 81.90 m3
Middle layer 65.00 x (1.2+1.1.5)/2 x 1.0 = 87.75 m3
Bottom layer 65.00 x 2.2 x 0.7 = 100.10 m3
at ch 5.9 km L/S
Top layer 35.00 x (0.9+1.2)/2 x 1.2 = 44.10 m3
Middle layer 35.00 x (1.2+1.1.5)/2 x 1.0 = 47.25 m3
Bottom layer 35.00 x 2.2 x 0.7 = 53.90 m3
at ch 6.0 km R/S
Top layer 45.00 x (0.9+1.2)/2 x 1.2 = 56.70 m3
Middle layer 45.00 x (1.2+1.1.5)/2 x 1.0 = 60.75 m3
Bottom layer 45.00 x 2.2 x 0.7 = 69.30 m3
at 6.6 km R/s
Top layer 35.00 x (0.9+1.2)/2 x 1.2 = 44.10 m3
Bottom layer 35.00 x 1.7 x 0.7 = 41.65 m3
at 6.80 km L/s
Top layer 40.00 x (0.9+1.2)/2 x 1.2 = 50.40 m3
Bottom layer 40.00 x 1.7 x 0.7 = 47.60 m3
at ch 6.8 km R/S
Top layer 20.00 x (0.9+1.2)/2 x 1.2 = 25.20 m3
Middle layer 20.00 x (1.2+1.1.5)/2 x 1.0 = 27.00 m3
Bottom layer 20.00 x 2.2 x 0.7 = 30.80 m3
at ch 16.2 km R/S
Top layer 40.00 x (0.9+1.2)/2 x 1.2 = 50.40 m3
Middle layer 40.00 x (1.2+1.1.5)/2 x 1.0 = 54.00 m3
Bottom layer 40.00 x 2.2 x 0.7 = 61.60 m3
at ch 16.8 km R/S
Top layer 45.00 x (0.9+1.2)/2 x 1.2 = 56.70 m3
Middle layer 45.00 x (1.2+1.1.5)/2 x 1.0 = 60.75 m3
Bottom layer 45.00 x 2.2 x 0.7 = 69.30 m3
at ch 17.67 km R/s
Top layer 50.00 x (0.9+1.2)/2 x 1.2 = 63.00 m3
Bottom layer 50.00 x 1.7 x 0.7 = 59.50 m3
Total= = 4815.50 m3
at ch 0.8 km.
Top layer 45.0 x 0.90 x 0.10 = 4.05 m3
side face 45.0 x 1.237 x 0.10 = 5.57 m3
middle layer 45.0 x 0.3 x 0.10 = 1.35 m3
side face 45.0 x 1.044 x 0.10 = 4.70 m3
bottom layer 45.0 x 1.00 x 0.10 = 4.50 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.35 x 1.00 x 0.10 = 0.27 m3
at ch 0.9 km ch.
Top layer 55.0 x 0.90 x 0.10 = 4.95 m3
side face 55.0 x 1.237 x 0.10 = 6.80 m3
middle layer 55.0 x 0.3 x 0.10 = 1.65 m3
side face 55.0 x 1.044 x 0.10 = 5.74 m3
bottom layer 55.0 x 1.00 x 0.10 = 5.50 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.35 x 1.00 x 0.10 = 0.27 m3
at ch 0.9 km.
Top layer 60.0 x 0.90 x 0.10 = 5.40 m3
side face 60.0 x 1.237 x 0.10 = 7.42 m3
middle layer 60.0 x 0.3 x 0.10 = 1.80 m3
side face 60.0 x 1.044 x 0.10 = 6.26 m3
bottom layer 60.0 x 1.00 x 0.10 = 6.00 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.35 x 1.00 x 0.10 = 0.27 m3
at 1.1 km ch.
Top layer 40.0 x 0.90 x 0.10 = 3.60 m3
side face 40.0 x 1.237 x 0.10 = 4.95 m3
middle layer 40.0 x 0.3 x 0.10 = 1.20 m3
side face 40.0 x 1.044 x 0.10 = 4.18 m3
bottom layer 40.0 x 1.00 x 0.10 = 4.00 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.35 x 1.00 x 0.10 = 0.27 m3
at 1.2 km ch.
Top layer 55.0 x 0.90 x 0.10 = 4.95 m3
side face 55.0 x 1.237 x 0.10 = 6.80 m3
Bottom layer 55.0 x 0.8 x 0.10 = 4.40 m3
side face 55.0 x 0.3 x 0.10 = 1.65 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
at 2.0 km ch.
Top layer 30.0 x 0.90 x 0.10 = 2.70 m3
side face 30.0 x 1.237 x 0.10 = 3.71 m3
Bottom layer 30.0 x 0.8 x 0.10 = 2.40 m3
side face 30.0 x 0.3 x 0.10 = 0.90 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
461750802.xls
Sl. Item Page
Description of Item Quantity Unit
No. No. No.
at 2.0 km ch.
Top layer 20.0 x 0.90 x 0.10 = 1.80 m3
side face 20.0 x 1.237 x 0.10 = 2.47 m3
Bottom layer 20.0 x 0.8 x 0.10 = 1.60 m3
side face 20.0 x 0.3 x 0.10 = 0.60 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
at 2.1 km ch.
Top layer 30.0 x 0.90 x 0.10 = 2.70 m3
side face 30.0 x 1.237 x 0.10 = 3.71 m3
Bottom layer 30.0 x 0.8 x 0.10 = 2.40 m3
side face 30.0 x 0.3 x 0.10 = 0.90 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
at 2.2 km ch.
Top layer 35.0 x 0.90 x 0.10 = 3.15 m3
side face 35.0 x 1.237 x 0.10 = 4.33 m3
Bottom layer 35.0 x 0.8 x 0.10 = 2.80 m3
side face 35.0 x 0.3 x 0.10 = 1.05 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
at 2.4 km ch.
Top layer 25.0 x 0.90 x 0.10 = 2.25 m3
side face 25.0 x 1.237 x 0.10 = 3.09 m3
middle layer 25.0 x 0.3 x 0.10 = 0.75 m3
side face 25.0 x 1.044 x 0.10 = 2.61 m3
bottom layer 25.0 x 1.00 x 0.10 = 2.50 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.35 x 1.00 x 0.10 = 0.27 m3
at 2.6 km ch.
Top layer 55.0 x 0.90 x 0.10 = 4.95 m3
side face 55.0 x 1.237 x 0.10 = 6.80 m3
middle layer 55.0 x 0.3 x 0.10 = 1.65 m3
side face 55.0 x 1.044 x 0.10 = 5.74 m3
bottom layer 55.0 x 1.00 x 0.10 = 5.50 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.35 x 1.00 x 0.10 = 0.27 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
at 2.6km ch.
Top layer 30.0 x 0.90 x 0.10 = 2.70 m3
side face 30.0 x 1.237 x 0.10 = 3.71 m3
middle layer 30.0 x 0.3 x 0.10 = 0.90 m3
side face 30.0 x 1.044 x 0.10 = 3.13 m3
bottom layer 30.0 x 1.00 x 0.10 = 3.00 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.35 x 1.00 x 0.10 = 0.27 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
at 2.7 km ch.
Top layer 40.0 x 0.90 x 0.10 = 3.60 m3
side face 40.0 x 1.237 x 0.10 = 4.95 m3
Bottom layer 40.0 x 0.8 x 0.10 = 3.20 m3
side face 40.0 x 0.3 x 0.10 = 1.20 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
at 2.8km ch.
Top layer 30.0 x 0.90 x 0.10 = 2.70 m3
side face 30.0 x 1.237 x 0.10 = 3.71 m3
Bottom layer 30.0 x 0.8 x 0.10 = 2.40 m3
side face 30.0 x 0.3 x 0.10 = 0.90 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
461750802.xls
Sl. Item Page
Description of Item Quantity Unit
No. No. No.
at 2.9 km ch.
Top layer 40.0 x 0.90 x 0.10 = 3.60 m3
side face 40.0 x 1.237 x 0.10 = 4.95 m3
Bottom layer 40.0 x 0.8 x 0.10 = 3.20 m3
side face 40.0 x 0.3 x 0.10 = 1.20 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
at 3.20 km ch.
Top layer 35.0 x 0.90 x 0.10 = 3.15 m3
side face 35.0 x 1.237 x 0.10 = 4.33 m3
Bottom layer 35.0 x 0.8 x 0.10 = 2.80 m3
side face 35.0 x 0.3 x 0.10 = 1.05 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
at 3.3 km ch.
Top layer 25.0 x 0.90 x 0.10 = 2.25 m3
side face 25.0 x 1.237 x 0.10 = 3.09 m3
Bottom layer 25.0 x 0.8 x 0.10 = 2.00 m3
side face 25.0 x 0.3 x 0.10 = 0.75 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
at 3.8 km ch.
Top layer 25.0 x 0.90 x 0.10 = 2.25 m3
side face 25.0 x 1.237 x 0.10 = 3.09 m3
middle layer 25.0 x 0.3 x 0.10 = 0.75 m3
side face 25.0 x 1.044 x 0.10 = 2.61 m3
bottom layer 25.0 x 1.00 x 0.10 = 2.50 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.35 x 1.00 x 0.10 = 0.27 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
at 3.9 km ch.
Top layer 30.0 x 0.90 x 0.10 = 2.70 m3
side face 30.0 x 1.237 x 0.10 = 3.71 m3
middle layer 30.0 x 0.3 x 0.10 = 0.90 m3
side face 30.0 x 1.044 x 0.10 = 3.13 m3
bottom layer 30.0 x 1.00 x 0.10 = 3.00 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.35 x 1.00 x 0.10 = 0.27 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
at 4.0 km ch.
Top layer 30.0 x 0.90 x 0.10 = 2.70 m3
side face 30.0 x 1.237 x 0.10 = 3.71 m3
middle layer 30.0 x 0.3 x 0.10 = 0.90 m3
side face 30.0 x 1.044 x 0.10 = 3.13 m3
bottom layer 30.0 x 1.00 x 0.10 = 3.00 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.35 x 1.00 x 0.10 = 0.27 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
at 4.3 km ch.
Top layer 30.0 x 0.90 x 0.10 = 2.70 m3
side face 30.0 x 1.237 x 0.10 = 3.71 m3
middle layer 30.0 x 0.3 x 0.10 = 0.90 m3
side face 30.0 x 1.044 x 0.10 = 3.13 m3
bottom layer 30.0 x 1.00 x 0.10 = 3.00 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.35 x 1.00 x 0.10 = 0.27 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
461750802.xls
Sl. Item Page
Description of Item Quantity Unit
No. No. No.
at 4.4 km ch.
Top layer 35.0 x 0.90 x 0.10 = 3.15 m3
side face 35.0 x 1.237 x 0.10 = 4.33 m3
middle layer 35.0 x 0.3 x 0.10 = 1.05 m3
side face 35.0 x 1.044 x 0.10 = 3.65 m3
bottom layer 35.0 x 1.00 x 0.10 = 3.50 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.35 x 1.00 x 0.10 = 0.27 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
at 4.6 km ch.
Top layer 30.0 x 0.90 x 0.10 = 2.70 m3
side face 30.0 x 1.237 x 0.10 = 3.71 m3
middle layer 30.0 x 0.3 x 0.10 = 0.90 m3
side face 30.0 x 1.044 x 0.10 = 3.13 m3
bottom layer 30.0 x 1.00 x 0.10 = 3.00 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.35 x 1.00 x 0.10 = 0.27 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
at 4.8 km ch.
Top layer 40.0 x 0.90 x 0.10 = 3.60 m3
side face 40.0 x 1.237 x 0.10 = 4.95 m3
Bottom layer 40.0 x 0.8 x 0.10 = 3.20 m3
side face 40.0 x 0.3 x 0.10 = 1.20 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
at 5.0 km ch.
Top layer 30.0 x 0.90 x 0.10 = 2.70 m3
side face 30.0 x 1.237 x 0.10 = 3.71 m3
middle layer 30.0 x 0.3 x 0.10 = 0.90 m3
side face 30.0 x 1.044 x 0.10 = 3.13 m3
bottom layer 30.0 x 1.00 x 0.10 = 3.00 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.35 x 1.00 x 0.10 = 0.27 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
at 5.2 km ch.
Top layer 50.0 x 0.90 x 0.10 = 4.50 m3
side face 50.0 x 1.237 x 0.10 = 6.19 m3
middle layer 50.0 x 0.3 x 0.10 = 1.50 m3
side face 50.0 x 1.044 x 0.10 = 5.22 m3
bottom layer 50.0 x 1.00 x 0.10 = 5.00 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.35 x 1.00 x 0.10 = 0.27 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
at 5.4 km ch.
Top layer 25.0 x 0.90 x 0.10 = 2.25 m3
side face 25.0 x 1.237 x 0.10 = 3.09 m3
Bottom layer 25.0 x 0.8 x 0.10 = 2.00 m3
side face 25.0 x 0.3 x 0.10 = 0.75 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
at 5.8 km ch.
Top layer 65.0 x 0.90 x 0.10 = 5.85 m3
side face 65.0 x 1.237 x 0.10 = 8.04 m3
middle layer 65.0 x 0.3 x 0.10 = 1.95 m3
side face 65.0 x 1.044 x 0.10 = 6.79 m3
bottom layer 65.0 x 1.00 x 0.10 = 6.50 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.35 x 1.00 x 0.10 = 0.27 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
461750802.xls
Sl. Item Page
Description of Item Quantity Unit
No. No. No.
at 5.9 km ch.
Top layer 35.0 x 0.90 x 0.10 = 3.15 m3
side face 35.0 x 1.237 x 0.10 = 4.33 m3
middle layer 35.0 x 0.3 x 0.10 = 1.05 m3
side face 35.0 x 1.044 x 0.10 = 3.65 m3
bottom layer 35.0 x 1.00 x 0.10 = 3.50 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.35 x 1.00 x 0.10 = 0.27 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
at 6.0 km ch.
Top layer 45.0 x 0.90 x 0.10 = 4.05 m3
side face 45.0 x 1.237 x 0.10 = 5.57 m3
middle layer 45.0 x 0.3 x 0.10 = 1.35 m3
side face 45.0 x 1.044 x 0.10 = 4.70 m3
bottom layer 45.0 x 1.00 x 0.10 = 4.50 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.35 x 1.00 x 0.10 = 0.27 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
at 6.6 km ch.
Top layer 35.0 x 0.90 x 0.10 = 3.15 m3
side face 35.0 x 1.237 x 0.10 = 4.33 m3
middle layer 35.0 x 0.3 x 0.10 = 1.05 m3
side face 35.0 x 1.044 x 0.10 = 3.65 m3
bottom layer 35.0 x 1.00 x 0.10 = 3.50 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.35 x 1.00 x 0.10 = 0.27 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
at 6.8 km ch.
Top layer 40.0 x 0.90 x 0.10 = 3.60 m3
side face 40.0 x 1.237 x 0.10 = 4.95 m3
middle layer 40.0 x 0.3 x 0.10 = 1.20 m3
side face 40.0 x 1.044 x 0.10 = 4.18 m3
bottom layer 40.0 x 1.00 x 0.10 = 4.00 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.35 x 1.00 x 0.10 = 0.27 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
at 6.8 km ch.
Top layer 20.0 x 0.90 x 0.10 = 1.80 m3
side face 20.0 x 1.237 x 0.10 = 2.47 m3
Bottom layer 20.0 x 0.8 x 0.10 = 1.60 m3
side face 20.0 x 0.3 x 0.10 = 0.60 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
at 6.8 km ch.
Top layer 20.0 x 0.90 x 0.10 = 1.80 m3
side face 20.0 x 1.237 x 0.10 = 2.47 m3
middle layer 20.0 x 0.3 x 0.10 = 0.60 m3
side face 20.0 x 1.044 x 0.10 = 2.09 m3
bottom layer 20.0 x 1.00 x 0.10 = 2.00 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.35 x 1.00 x 0.10 = 0.27 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
at 16.2 km ch.
Top layer 40.0 x 0.90 x 0.10 = 3.60 m3
side face 40.0 x 1.237 x 0.10 = 4.95 m3
middle layer 40.0 x 0.3 x 0.10 = 1.20 m3
side face 40.0 x 1.044 x 0.10 = 4.18 m3
bottom layer 40.0 x 1.00 x 0.10 = 4.00 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.35 x 1.00 x 0.10 = 0.27 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
461750802.xls
Sl. Item Page
Description of Item Quantity Unit
No. No. No.
at 16.8 km ch.
Top layer 45.0 x 0.90 x 0.10 = 4.05 m3
side face 45.0 x 1.237 x 0.10 = 5.57 m3
middle layer 45.0 x 0.3 x 0.10 = 1.35 m3
side face 45.0 x 1.044 x 0.10 = 4.70 m3
bottom layer 45.0 x 1.00 x 0.10 = 4.50 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.35 x 1.00 x 0.10 = 0.27 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
at 17.67 km ch.
Top layer 50.0 x 0.90 x 0.10 = 4.50 m3
side face 50.0 x 1.237 x 0.10 = 6.19 m3
middle layer 50.0 x 0.3 x 0.10 = 1.50 m3
side face 50.0 x 1.044 x 0.10 = 5.22 m3
bottom layer 50.0 x 1.00 x 0.10 = 5.00 m3
End face 2.0 1.05 x 1.2 x 0.10 = 0.252 m3
End face 2.0 1.35 x 1.00 x 0.10 = 0.27 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
End face 2.0 1.7 x 0.3 x 0.10 = 0.10 m3
Total = 582.99 m3
at sausage work
at ch .0.8 km l/s
side face 1.0 45.0 x 1.237 = 55.7 m2
side face 1.0 45.0 x 1.044 = 47.0 m2
End face 2.0 1.05 x 1.2 = 2.5 m2
End face 2.0 1.35 x 1.0 = 2.7 m2
at ch .0.9 km l/s
side face 1.0 55.0 x 1.237 = 68.0 m2
side face 1.0 55.0 x 1.044 = 57.4 m2
End face 2.0 1.05 x 1.2 = 2.5 m2
End face 2.0 1.35 x 1.0 = 2.7 m2
at ch .0.9 km l/s
side face 1.0 60.0 x 1.237 = 74.2 m2
side face 1.0 60.0 x 1.044 = 62.6 m2
End face 2.0 1.05 x 1.2 = 2.5 m2
End face 2.0 1.35 x 1.0 = 2.7 m2
at ch .1.1 km l/s
side face 1.0 40.0 x 1.237 = 49.5 m2
side face 1.0 40.0 x 1.044 = 41.8 m2
End face 2.0 1.05 x 1.2 = 2.5 m2
End face 2.0 1.35 x 1.0 = 2.7 m2
at ch .1.2 km l/s
side face 1.0 55.0 x 1.237 = 68.0 m2
side face 1.0 55.0 x 0.300 = 16.5 m2
End face 2.0 1.05 x 1.2 = 2.5 m2
End face 2.0 1.70 x 0.3 = 1.0 m2
at ch .2.0 km R/s
side face 1.0 30.0 x 1.237 = 37.1 m2
side face 1.0 30.0 x 0.300 = 9.0 m2
End face 2.0 1.05 x 1.2 = 2.5 m2
End face 2.0 1.70 x 0.3 = 1.0 m2
461750802.xls
Sl. Item Page
Description of Item Quantity Unit
No. No. No.
at ch .2.0 km l/s
side face 1.0 20.0 x 1.237 = 24.7 m2
side face 1.0 20.0 x 0.300 = 6.0 m2
End face 2.0 1.05 x 1.2 = 2.5 m2
End face 2.0 1.70 x 0.3 = 1.0 m2
at ch .2.1 km l/s
side face 1.0 30.0 x 1.237 = 37.1 m2
side face 1.0 30.0 x 0.300 = 9.0 m2
End face 2.0 1.05 x 1.2 = 2.5 m2
End face 2.0 1.70 x 0.3 = 1.0 m2
at ch .2.2 km l/s
side face 1.0 35.0 x 1.237 = 43.3 m2
side face 1.0 35.0 x 1.044 = 36.5 m2
End face 2.0 1.05 x 1.2 = 2.5 m2
End face 2.0 1.35 x 1.0 = 2.7 m2
at ch .2.4 km R/s
side face 1.0 25.0 x 1.237 = 30.9 m2
side face 1.0 25.0 x 1.044 = 26.1 m2
End face 2.0 1.05 x 1.2 = 2.5 m2
End face 2.0 1.35 x 1.0 = 2.7 m2
at ch .2.6 km l/s
side face 1.0 55.0 x 1.237 = 68.0 m2
side face 1.0 55.0 x 1.044 = 57.4 m2
End face 2.0 1.05 x 1.2 = 2.5 m2
End face 2.0 1.35 x 1.0 = 2.7 m2
at ch .2.6 km R/s
side face 1.0 30.0 x 1.237 = 37.1 m2
side face 1.0 30.0 x 1.044 = 31.3 m2
End face 2.0 1.05 x 1.2 = 2.5 m2
End face 2.0 1.35 x 1.0 = 2.7 m2
at ch .2.7 km l/s
side face 1.0 40.0 x 1.237 = 49.5 m2
side face 1.0 40.0 x 0.300 = 12.0 m2
End face 2.0 1.05 x 1.2 = 2.5 m2
End face 2.0 1.70 x 0.3 = 1.0 m2
at ch .2.8 km R/s
side face 1.0 30.0 x 1.237 = 37.1 m2
side face 1.0 30.0 x 0.300 = 9.0 m2
End face 2.0 1.05 x 1.2 = 2.5 m2
End face 2.0 1.70 x 0.3 = 1.0 m2
at ch .2.8 km R/s
side face 1.0 30.0 x 1.237 = 37.1 m2
side face 1.0 30.0 x 0.300 = 9.0 m2
End face 2.0 1.05 x 1.2 = 2.5 m2
End face 2.0 1.70 x 0.3 = 1.0 m2
at ch .2.9 km L/s
side face 1.0 40.0 x 1.237 = 49.5 m2
side face 1.0 40.0 x 0.300 = 12.0 m2
End face 2.0 1.05 x 1.2 = 2.5 m2
End face 2.0 1.70 x 0.3 = 1.0 m2
at ch .3.20 km l/s
side face 1.0 35.0 x 1.237 = 43.3 m2
side face 1.0 35.0 x 0.300 = 10.5 m2
End face 2.0 1.05 x 1.2 = 2.5 m2
End face 2.0 1.70 x 0.3 = 1.0 m2
at ch .3.2 km l/s
side face 1.0 35.0 x 1.237 = 43.3 m2
side face 1.0 35.0 x 0.300 = 10.5 m2
End face 2.0 1.05 x 1.2 = 2.5 m2
End face 2.0 1.70 x 0.3 = 1.0 m2
at ch .3.3 km r/s
side face 1.0 25.0 x 1.237 = 30.9 m2
side face 1.0 25.0 x 1.044 = 26.1 m2
End face 2.0 1.05 x 1.2 = 2.5 m2
End face 2.0 1.35 x 1.0 = 2.7 m2
461750802.xls
Sl. Item Page
Description of Item Quantity Unit
No. No. No.
at ch .3.8 km l/s
side face 1.0 25.0 x 1.237 = 30.9 m2
side face 1.0 x 25.0 x 1.044 = 26.1 m2
End face 2.0 x 1.05 x 1.2 = 2.5 m2
End face 2.0 x 1.35 x 1.0 = 2.7 m2
at ch .3.9 km l/s
side face 1.0 30.0 x 1.237 = 37.1 m2
side face 1.0 30.0 x 0.300 = 9.0 m2
End face 2.0 1.05 x 1.2 = 2.5 m2
End face 2.0 1.70 x 0.3 = 1.0 m2
at ch .4.0 km l/s
side face 1.0 30.0 x 1.237 = 37.1 m2
side face 1.0 30.0 x 0.300 = 9.0 m2
End face 2.0 1.05 x 1.2 = 2.5 m2
End face 2.0 1.70 x 0.3 = 1.0 m2
at ch .4.3 km L/s
side face 1.0 30.0 x 1.237 = 37.1 m2
side face 1.0 30.0 x 0.300 = 9.0 m2
End face 2.0 1.05 x 1.2 = 2.5 m2
End face 2.0 1.70 x 0.3 = 1.0 m2
at ch .4.4 km l/s
side face 1.0 35.0 x 1.237 = 43.3 m2
side face 1.0 35.0 x 0.300 = 10.5 m2
End face 2.0 1.05 x 1.2 = 2.5 m2
End face 2.0 1.70 x 0.3 = 1.0 m2
at ch .4.6 km l/s
side face 1.0 30.0 x 1.237 = 37.1 m2
side face 1.0 30.0 x 0.300 = 9.0 m2
End face 2.0 1.05 x 1.2 = 2.5 m2
End face 2.0 1.70 x 0.3 = 1.0 m2
at ch .4.8 km r/s
side face 1.0 40.0 x 1.237 = 49.5 m2
side face 1.0 40.0 x 1.044 = 41.8 m2
End face 2.0 1.05 x 1.2 = 2.5 m2
End face 2.0 1.35 x 1.0 = 2.7 m2
at ch .5.0 km l/s
side face 1.0 30.0 x 1.237 = 37.1 m2
side face 1.0 x 30.0 x 1.044 = 31.3 m2
End face 2.0 x 1.05 x 1.2 = 2.5 m2
End face 2.0 x 1.35 x 1.0 = 2.7 m2
at ch .5.2 km l/s
side face 1.0 50.0 x 1.237 = 61.9 m2
side face 1.0 50.0 x 0.300 = 15.0 m2
End face 2.0 1.05 x 1.2 = 2.5 m2
End face 2.0 1.70 x 0.3 = 1.0 m2
at ch .5.4 km l/s
side face 1.0 25.0 x 1.237 = 30.9 m2
side face 1.0 25.0 x 0.300 = 7.5 m2
End face 2.0 1.05 x 1.2 = 2.5 m2
End face 2.0 1.70 x 0.3 = 1.0 m2
at ch .5.8 km L/s
side face 1.0 65.0 x 1.237 = 80.4 m2
side face 1.0 65.0 x 0.300 = 19.5 m2
End face 2.0 1.05 x 1.2 = 2.5 m2
End face 2.0 1.70 x 0.3 = 1.0 m2
at ch .5.9 km l/s
side face 1.0 35.0 x 1.237 = 43.3 m2
side face 1.0 35.0 x 0.300 = 10.5 m2
End face 2.0 1.05 x 1.2 = 2.5 m2
End face 2.0 1.70 x 0.3 = 1.0 m2
at ch .6.0 km l/s
side face 1.0 45.0 x 1.237 = 55.7 m2
side face 1.0 45.0 x 0.300 = 13.5 m2
End face 2.0 1.05 x 1.2 = 2.5 m2
End face 2.0 1.70 x 0.3 = 1.0 m2
at ch .6.6 km r/s
side face 1.0 35.0 x 1.237 = 43.3 m2
side face 1.0 35.0 x 1.044 = 36.5 m2
End face 2.0 1.05 x 1.2 = 2.5 m2
461750802.xls
Sl. Item Page
Description of Item Quantity Unit
No. No. No.
End face 2.0 1.35 x 1.0 = 2.7 m2
461750802.xls
Sl. Item Page
Description of Item Quantity Unit
No. No. No.
at ch .6.8 km l/s
side face 1.0 x 40.0 x 1.237 = 49.5 m2
side face 1.0 x 40.0 x 1.044 = 41.8 m2
End face 2.0 x 1.05 x 1.2 = 2.5 m2
End face 2.0 x 1.35 x 1.0 = 2.7 m2
at ch .6.8 km l/s
side face 1.0 20.0 x 1.237 = 24.7 m2
side face 1.0 20.0 x 0.300 = 6.0 m2
End face 2.0 1.05 x 1.2 = 2.5 m2
End face 2.0 1.70 x 0.3 = 1.0 m2
at ch .6.8 km l/s
side face 1.0 20.0 x 1.237 = 24.7 m2
side face 1.0 20.0 x 0.300 = 6.0 m2
End face 2.0 1.05 x 1.2 = 2.5 m2
End face 2.0 1.70 x 0.3 = 1.0 m2
at ch .16.20 km l/s
side face 1.0 40.0 x 1.237 = 49.5 m2
side face 1.0 40.0 x 0.300 = 12.0 m2
End face 2.0 1.05 x 1.2 = 2.5 m2
End face 2.0 1.70 x 0.3 = 1.0 m2
at ch .16.8 km l/s
side face 1.0 45.0 x 1.237 = 55.7 m2
side face 1.0 45.0 x 0.300 = 13.5 m2
End face 2.0 1.05 x 1.2 = 2.5 m2
End face 2.0 1.70 x 0.3 = 1.0 m2
at ch .17.67 km R/s
side face 1.0 50.0 x 1.237 = 61.9 m2
side face 1.0 50.0 x 0.300 = 15.0 m2
End face 2.0 1.05 x 1.2 = 2.5 m2
End face 2.0 1.70 x 0.3 = 1.0 m2
Total = 2770.14 m2
Sl
Description of Items Quantity Unit Rate Amount
No
Part A: Road Works
1.0 Clearing grass and removal of rubbish up to a distance of 30 m
outside the periphery of the area as per Technical Specifications
Clause 201 for Rural Roads of MORD.
By Manual Means
(I) By Manual Means 3.51 Hect 11868.00 Rs. 41,656.68
2.0 Clearing and grubbing road land including uprootingwild
vegetation, grass, bushes, shrubs, saplings and trees of girth upto
300 mm, removal of stumps of such trees cut earlier and disposal
of unserviceable materials and stacking of serviceable material to
be used or auctioned, upto a lead of 1000 m including removal
and disposal of top organic soil not exceeding 150 mm in 2.69 hectore 44978.00 Rs. 120,990.82
thickness as per Technical
Specifications Clause 201 for Rural Roads of MORD.
(I) By Manual Means
a) In area of non-thorny jungle
Page 34 Abstract
Sl
Description of Items Quantity Unit Rate Amount
No
8.0 Providing and laying bituminous concrete with Hot Mix Plant using
coarse aggregates, fine aggregates, filler materials and
bituminous binder of required specification including screening,
cleaning of chips and preparing a uniform and quality mix in Hot
Mix Plant and ensuring a omogeneous mix, in which all particles
of the mineral aggregates are coated uniformly, transporting the
hot mix to work site, layingthe mixed materials at specified laying
temperatur with a hydrostatic paver finisher with sensor control to
the required grade, level and alignment over prepared surface
coated with tack coat, rolling with smooth wheeled, vibratory and
tandem rollers for break down, inter-mediate and finished rolling
to achieve the desired density of at least 98% of that of
Laboratory Marshall specimen, including cost and carriage of
bitumen, coarse and fine aggregates and filler materials and hire
charges of machinery and equipment for construction and quality
control, fuels and lubricants and wages of operational
staffcomplete as per Clause 507 of Specifications for Road &
Bridge Works of MoRT&H (5th Revision).
13.0 Providing and fixing of road stud 100x 100 mm, diecast in
aluminium, resistant to corrosive effect of salt and grit, fitted with
lens reflectors, installed in concrete or asphaltic surface by drilling 9002.00 Each 255.00 Rs. 2,295,510.00
hole 30 mm upto a depth of 60 mm and bedded in a suitable
bituminous grout or epoxy mortar, all as per BIS 873 part
4:1973 ....etc
14.0 Supplying and installation of delineators (road way indicators,
hazard markers, object markers), 80-100 cm high above ground
level, painted black and white in 15 cm wide strips, fitted with 80 525.00 Each 386.00 Rs. 202,650.00
x 100 mm rectangular or 75 mm dia circular reflectorised panels
at the top, buried or pressed into the ground and conforming to
IRC-79 and the drawings.
15.0 Providing and fixing of retro- reflectorised cautionary, mandatory
and informatory sign as per IRC :67 made of high intensity grade
sheeting vide clause 801.3, fixed over aluminium sheeting, 1.5
mm thick supported on a mild steel angle iron post 75 mm x 75
mm x 6 mm firmly fixed to the ground by means of properly
designed foundation with M15 grade cement concrete 45 cm x 45
cm x 60 cm, 60 cm below ground level as per approved drawing
and Clause 801 of Specifications for Road & Bridge Works of
MoRT&H (5th Revision).
iv) 80 mm x 60 mm rectangular 20.00 Each 5208.00 Rs. 104,160.00
Page 35 Abstract
Sl
Description of Items Quantity Unit Rate Amount
No
16.0 Providing and fixing of retro- reflectorised cautionary, mandatory
and informatory sign as per IRC :67 made of high intensity grade
sheeting vide clause 801.3, fixed over aluminium sheeting, 1.5
mm thick supported on a mild steel angle iron post 75 mm x 75
mm x 6 mm firmly fixed to the ground by means of properly
designed foundation with M15 grade cement concrete 45 cm x 45
cm x 60 cm, 60 cm below ground level as per approved drawing
and Clause 801 of Specifications for Road & Bridge Works of
MoRT&H (5th Revision).
ii) 60 cm equilateral triangle 20.00 Each 2811.00 Rs. 56,220.00
17.0 Supplying fitting and fixing R.C. guard post 1.37m long with C.C.
1:2:4 with graded stone chips of 13.2mm down casting ,curing
complete including cost of providing 4nos.of 12mm dia. rod of
length 1.54m as main reinforcement and 6 nos. of round shaped 120.00 Each 773.00 Rs. 92,760.00
8mm dia rods used as binders; the placing of the first binder
should be at 75mm below the top finished surface and the other 5
nos of binders should be placed at 245mm c/c......etc
20.0 Ordinary Cement concrete (mix 1:1.5:3) with graded stone chips
(20 mm nominal size) excluding shuttering and reinforcement if
any, in ground floor as per relevant IS codes. 10.53 m3 5295.37 Rs. 55,760.27
(i) Pakur Variety
(ii) Structural Steel (MS) angles, joist, pipe, channel, flats, etc.
(F250 conforms to IS:2062 & 808)(a) Upto 200 mm size 0.925 MT 96314.15 Rs. 89,090.59
ii) Structural steel (MS) angles, joist, pipe, channels, flats, etc.(F
250 conforms to IS:2062 & 808) 0.69 MT 102955.40 Rs. 71,142.18
(b) Above 200 mm & upto 400 mm size
24.0 Alluminium Alloy Plate for Over Head Sign 29.97 M2 333.60 Rs. 9,998.66
25.0 Retro Reflectorised 2 mm thick high intensity grade sheeting Rs. 554,252.66
38.10 M2 14547.31
27.0 Primming one coat on steel or other metal surface with synthetic
oil bound primer of approved quality includign smoothning
surfaces by sand papering etc. 61.04 M2 29.00 Rs. 1,770.16
28.0 (A) Painting with best quality synthetic enamel paint of approved
make and brand including smoothening surface by sand papering 61.04 M2 79.00 Rs. 4,822.16
etc.on the surface, if necessary :
(b) On steel or other metal surface :(iv) Two coats (with any shade
except white)
Page 36 Abstract
Sl
Description of Items Quantity Unit Rate Amount
No
34.0 Providing and laying Design Mix concrete for plain / reinforced
concrete work in any part of bridge (excluding bottom plugging)
with coarse aggregates of appropriate nominal size and grading,
fine aggregate (sand) conforming to proper grading zone, both of
approved quality and cement, as necessary, including labour, cost
and carriage of all materials and including preparation of design
mix, approval of the same by the Engineer-in-Charge and cost for 582.99 m3 5137.22 Rs. 2,994,947.89
quality control, sampling, testing etc. all complete but excluding
cost of labour and materials for formwork & reinforcement works.
(a) M-15 Grade
Using concrete mixer.
35.0 Hire and labour charges for Shuttering with or without staging
upto 4.0 m height using approved stout props with wooden
planks/ply wood/steel sheet plate with required bracing.......etc. 2770.14 m2 214.00 Rs. 592,809.96
(b) Where staging is not required.
Sl.
Description of Items Cost in Rupees
No.
1.0 COST FOR ROAD WORKS Rs. 62,430,756.00
2.0 COST FOR ROAD FURNITURE Rs. 8,280,477.00
3.0 COST FOR PROTECTION WORK Rs. 14,875,344.00
4.0 COST FOR REPAIRING OF CD STRUCTURES Rs. 0.00
5.0 (A) Sub-Total = Rs. 85,586,577.00
6.0 (B) GST,as applicable on (A) @ 12% = Rs. 10,270,389.00
7.0 (C) Cost of Civil work excluding labour welfare Cess Rs. 95,856,966.00
8.0 [A+B] = 1.0% L.W cess on (C) =
(D) Add: Rs. 958,570.00
9.0 (E) Cost of Civil work including GST & labour welfare Rs. 96,815,536.00
10.0 Cess [C+D]
(F)Add: =
Contigency Charges @ 3.00% on C Rs. 2,875,709.00
11.0 Grand Total = {E+F} Rs. 99,691,245.00
Junior Engineer
Jalpaiguri Highway Section-II
Jalpaiguri
Executive Engineer
Assistant Engineer JalpaiguriHighway Division
Jalpaiguri Highway Sub Division Jalpaiguri
Jalpaiguri
COMMENTS
1) Objective and necessity of the project:
This road has been taken over from North Bengal Development Department in the year 2017-18.
This road is very important road in the district of Jalpaiguri with clasification of major district road
(MDR) . The total length of the road is 16.50 km and carriageway width of the road is 5.50 m.
This road is serves as an alternate route from Jalpaiguri to Siliguri. Daily thousand of vehicle
passes through this road to go to siliguri and NJP Station. This road is also connectivity with the
Gajaldoba Project(Bhorer Alo).
At present it is seen that the condition of the road is at a moderate stage as the top most
wearing course which is SDBC has become hungry and worn out, due to wear & tear along with
small depressions at some place. It can be predicted that the road might get more damaged
during this rainy season ,if not taken care off immediately, might lead to damaged of the base
course as a result creation of potholes may come into existence and finally give rise to fatal
accidents and insecurity of precious life. So, considering the importance of this road and
present situation ,surfacing work is required through out the road leaving out the mastic portion
area so as to provide a smooth running condition over the road.
As the mastic portion of the road from CH- 0.00kmp, 4.60kmp, 5.10kmp, 5.80kmp,
6.20kmp,7.00kmp, 8.90kmp, 10.50kmp, 10.70kmp, 14.20kmp, 14.80kmp, 15.60kmp,
15.90kmp,16.50kmp is in good condition, so this portion of the road is not included in this project
work.
At ch. 1.50kmp, 2.40 kmp and ch.6.80kmp has been considered p.c.c. guard wall for protection
of the flank. Details of which is provided in the table no 10 below, which has been considered in
this estimate and also hard shoulder is provided 60% of the total length of the road shoulder.
4)Technical details:
Category of the road #REF!
a) Land acquisition
Sl.No. Chainage Area to be acquired/purchased Value including Remark
structures s
NA
b) Removal of trees:
Sl.No. Chainage No. Of trees to be relocated
NA
c) Encroachment Removal:
No. Of Remark
Sl. No. Chain age encroachment Type of encroachment s
NA
d) Utility Service:
Sl.No. Chainage Length Type of Utility Authority Estimated Remark
Services concerned Amount s
NA
Profile 25 mm
corrective thick
course (10% of SDBC
the project
length)
Add: Contingency @
3% on B (C) 28.76
Add: Quality Control
(1%)/Supervision 0.00
Consultancy(2.5%)