Professional Documents
Culture Documents
ACP Exam Formula Gold Cards
ACP Exam Formula Gold Cards
ACP Exam Formula Gold Cards
Future Value (FV) PV * (1 + R)^N Budget At Completion Budget assigned to complete the work
R = Rate of Interest (BAC) for the entire release. (not the iteration)
N = Number of Years
Bigger is better for FV Value of work planned to be
Planned Value (PV) accomplished at the of the iteration.
PV = PPC * BAC
Present Value (PV) FV / (1 + R)^N Earned Value (EV) Value of work actually accomplished at
Bigger is better for PV the end of the iteration.
EV = APC * BAC
Net Present Value (NPV) Bigger is better for NPV Actual Cost (AC) Actual cost incurred for work increment
(Net value right now) at the end of iteration.
NPV = Cash Inflow + Cash Outlflow
Opportunity Cost (OC) Lower is better for OC. Schedule Performance SPI = EV/PV
Index (SPI)
Velocity Sum of story points delivered SPI = 1 On Schedule
(completed) in an iteration (one SPI < 1 Behind Schedule
iteration). SPI > 1 Ahead of Schedule
1
© Satya Narayan Dash. All Rights Reserved.
All Registered Trademarks and Service Marks are the Property of the Project Management Institute.
Name Description/Formula Name Description/Formula
Prioritization of a PBI in a Priority/Rank = Work in Progress (WIP) Number of work items under process.
product backlog (PB) (Benefit score + Penalty score) /
(using Ranking Score) (Cost score + Risk score) Little’s Law Lead Time = WIP / Throughput
Value Add Time (VA) Time in operation that adds value to the
end customer.
Throughput (or Rate at which a process produces Last Responsible LRM is when Cost of Deciding Equals
Throughput completed work items, i.e., how Moment (LRM) Cost of Deferring.
Rate/Departure much work items you complete per
Rate/Processing Rate) unit of time.
Escaped Defects Cumulative Number of Defects across Variance Planned – Actual, e.g.,
all Releases as reported by the Cost Variance = Planned Cost – Actual
Users/Customer(s). Cost
Defect Cycle Time Date of Defect Remediation – Date of (+/Δ) A retrospective activity, where Plus for
Defect Injection current retrospective, Delta – future
Or Plus / Delta
retrospectives
2
© Satya Narayan Dash. All Rights Reserved.
All Registered Trademarks and Service Marks are the Property of the Project Management Institute.