ACP Exam Formula Gold Cards

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

ACP Formula Gold Cards

Name Description/Formula Name Description/Formula

Future Value (FV) PV * (1 + R)^N Budget At Completion Budget assigned to complete the work
R = Rate of Interest (BAC) for the entire release. (not the iteration)
N = Number of Years
Bigger is better for FV Value of work planned to be
Planned Value (PV) accomplished at the of the iteration.
PV = PPC * BAC

Present Value (PV) FV / (1 + R)^N Earned Value (EV) Value of work actually accomplished at
Bigger is better for PV the end of the iteration.
EV = APC * BAC

Net Present Value (NPV) Bigger is better for NPV Actual Cost (AC) Actual cost incurred for work increment
(Net value right now) at the end of iteration.
NPV = Cash Inflow + Cash Outlflow

Internal Rate of Return Rate at which NPV = 0 Schedule Variance (SV) SV = EV – PV


(IRR) Bigger is better for IRR
SV = 0  On Schedule
SV = negative  Behind Schedule
Benefit Cost Ratio (BCR) BCR = Benefit / Cost
SV = Positive  Ahead of Schedule
Bigger is better for BCR

Return on Investment ROI = (Benefit – Cost) / Cost Cost Variance (CV) CV = EV – AC


(ROI) Bigger is better for ROI. CV = 0  On Budget
CV = negative  Over budget
Payback Period (PP) How quickly monies can be paid CV = Positive  Under budget
back. Lesser is better for PP.

Opportunity Cost (OC) Lower is better for OC. Schedule Performance SPI = EV/PV
Index (SPI)
Velocity Sum of story points delivered SPI = 1  On Schedule
(completed) in an iteration (one SPI < 1  Behind Schedule
iteration). SPI > 1  Ahead of Schedule

Average Velocity Cumulative Velocity over


iterations/Number of Iterations

Cost Performance Index


Planned Percent Number of Current Iteration/Total CPI = EV/PV
(CPI)
Complete (PPC) Number of Iteration CPI = 1  On Budget
CPI < 1  Over Budget
CPI > 1  Under Budget
Pro
Actual Percent Complete Total Number of Story Points
Expected Monetary
(APC) Completed/Total Number Story Pro Probability (P) * Impact (I)
Value (EMV)
Points Planned

1
© Satya Narayan Dash. All Rights Reserved.
All Registered Trademarks and Service Marks are the Property of the Project Management Institute.
Name Description/Formula Name Description/Formula

Prioritization of a PBI in a Priority/Rank = Work in Progress (WIP) Number of work items under process.
product backlog (PB) (Benefit score + Penalty score) /
(using Ranking Score) (Cost score + Risk score) Little’s Law Lead Time = WIP / Throughput

Value Add Time (VA) Time in operation that adds value to the
end customer.

Time a work item takes to go through


Lead time (LT) Non-value Add time Time in operation that does not add
the entire process.
(NVA) value to the end customer

Time a work item takes to go through


Cycle time (CT) Total Cycle time Value-add time + Non-value-add time
part of the process.
= VA + NVA

Time between two success delivery of


Takt Time (TT) Process Cycle Efficiency Value Added Time/Total Cycle Time
a feature or bug or a story

Throughput (or Rate at which a process produces Last Responsible LRM is when Cost of Deciding Equals
Throughput completed work items, i.e., how Moment (LRM) Cost of Deferring.
Rate/Departure much work items you complete per
Rate/Processing Rate) unit of time.

Escaped Defects Cumulative Number of Defects across Variance Planned – Actual, e.g.,
all Releases as reported by the Cost Variance = Planned Cost – Actual
Users/Customer(s). Cost

Defect Cycle Time Date of Defect Remediation – Date of (+/Δ) A retrospective activity, where Plus for
Defect Injection current retrospective, Delta – future
Or Plus / Delta
retrospectives

2
© Satya Narayan Dash. All Rights Reserved.
All Registered Trademarks and Service Marks are the Property of the Project Management Institute.

You might also like