Façade Systems

Gerd Hönicke, Director Pre-Construction Services

August 2017
Content

1.  Clarification Façade Systems

2.  Stick System Façades

3.  Unitized Window Walls

4.  Mitred Unitized Façades

5.  Butt Jointed Unitized Façades


2 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services
Façade Systems
1.  Clarification

3 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services


Façade Systems
1. Clarification

Unitized Curtain Wall = Unitized Façade = glazed externally


European Window Wall = Unitized Facade = glazed internally
American Window Wall = Horizontal Ribbon Facade
= glazed externally or internally
European Curtain Wall = Window Wall or Stick System
American Curtain Wall = Could be everything
American Unitized System = Butt Jointed = Chicken Head
European Unitized System = Mitered = Spigot Connection
4 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services
Façade Systems
1. Clarification
Traditional Facade Unitized Facade

Stick Installation Ladder Installation

Time in Workshop

Time on site

5 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services


Façade Systems
2.  Stick System Façades

6 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services


Façade Systems
2. Stick System Façades

•  Individual components installed in the


field

7 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services


Façade Systems
2. Stick System Façades

•  Ventilation and Drainage System FW 50

8 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services


Façade Systems
2. Stick System Façade

Column
Floor slab •  Differential deformation varies from mullion to mullion
Mullion during floor slab deflection
Transom
•  No stiff transom/mullion connection

•  No longer rectangular corners

•  Glass floating in glazing rebate

•  Larger rebates for warping needed

Differential deformation

9 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services


Façade Systems
2. Stick System Façades
The most accurate way to calculate screen movement is by using a break down of
individual mullion movement rather than a single mid span figure.

5
Mid span deflection 1.2 3.8
Mullion differential Mullion differential

10 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services


Façade Systems
2. Stick System Façades
2,36 in

Glass height

Glass width
„Leeway“ in the rebate

11 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services


ZVE Fraunhofer Institute
London
Stuttgart, Germany
Victoria and Albert Museum
ZVE Fraunhofer Institute
London
Stuttgart, Germany
Victoria and Albert Museum
ZVE Fraunhofer Institute
London
Stuttgart, Germany
Piccadilly
ZVE Fraunhofer Institute
London
Stuttgart, Germany
Bond Street
ZVE Fraunhofer Institute
London
Stuttgart, Germany
Bond Street
ZVE Fraunhofer Institute
London
Stuttgart, Germany
London
Picadelly
Rathbone Passage
ZVE Fraunhofer Institute
London
Stuttgart, Germany
London
Picadelly
Brewer Street
ZVE Fraunhofer Institute
London
Stuttgart, Germany
London
Picadelly
Rathbone Passage
London
Brewer Street
London
Brewer Street
London
Brewer Street
London
Brewer Street
London
Brewer Street
ZVE Fraunhofer Institute
London
Stuttgart, Germany
London
Picadelly
Brewer Street
ZVE Fraunhofer Institute
London
Stuttgart, Germany
London
Picadelly
Brewer Street
ZVE Fraunhofer Institute
London
Stuttgart, Germany
London
Picadelly
Broadwick Street
ZVE Fraunhofer Institute
London
Stuttgart, Germany
London
Picadelly
Broadwick Street
Façade Systems
3.  Unitized Window Walls

29 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services


Façade Systems
3. Unitized Window Walls

30 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services


Façade System
3. Unitized Window Walls

31 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services


ZVE Fraunhofer Institute
London
Stuttgart, Germany
Central St. Giles
ZVE Fraunhofer Institute
London
Stuttgart, Germany
Central St. Giles
ZVE Fraunhofer Institute
London
Stuttgart, Germany
Central St. Giles
ZVE Fraunhofer Institute
London
Stuttgart, Germany
Central St. Giles
ZVE Fraunhofer Institute
London
Stuttgart, Germany
Central St. Giles
ZVE Fraunhofer Institute
London
Stuttgart, Germany
Central St. Giles
ZVE Fraunhofer Institute
London
Stuttgart, Germany
Central St. Giles
ZVE Fraunhofer Institute
London
Stuttgart, Germany
Central St. Giles
ZVE Fraunhofer Institute
London
Stuttgart, Germany
Central St. Giles
Façade Systems
4. Mitered Unitized Façades
I.  Cover Caped System
II.  Structural Bonded System
III. Structural Taped System

41 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services


Façade Systems
4.I Cover Caped System

2,95 in
Vertical unit joint
Horizontal unit joint

42 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services


Façade Systems
4.I Cover Caped System
65mm

Glass support Rebate Saddle


& packer gasket gasket

Vertical
Glazing coupling
gasket (bullet)
gasket
Glazing
bead
Connectors
Front weather
seal gasket

Outer profile
Horizontal coupling
Isolator Head transom gasket Insulating foam insert

43 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services


Façade Systems
4.I Cover Caped System

44 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services


Façade Systems
4.I Cover Caped System Vertical vapor barrier

Saddle gasket

Horizontal vapor
barrier

45 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services


Façade Systems
4.I Cover Caped System
level-1
level-0 level-0 level-0

direction of force
unit height

unit height
level-0 level-0 level-0 level-0
unit width unit width

46 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services


Façade Systems
4.I Cover Caped System

•  Unit corners are fabricated using cleats


in the same manner as window vents/frames

•  Cleats can be crimped or nailed, and are filled with


2-part adhesive to complete the bonding process

•  A Schueco 4-head crimper is the best crimping


machine to use, as it will even out any slight
inaccuracies across all 4 corners

47 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services


Façade Systems
4.I Cover Caped System

48 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services


Façade Systems
4.I Cover Caped System

49 8/14/17 Title of presentation (edit with ‘Insert > Header and Footer’)
Façade Systems
4.I Cover Caped System

50 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services


Spigot

Façade Systems
4.I Cover Caped System
Hook

•  One bracket will be fixed bearing point


•  Next bracket to allow sliding bearing point
•  Height adjustments to be “locked”
Bracketry

Spigot

Bracketry

Hook

51 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services


Façade Systems
4.I Cover Caped System

52 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services


Façade Systems
4.I Cover Caped System

53 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services


Façade Systems
4.I Cover Caped System

54 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services


Façade Systems
4.I Cover Caped System

•  No rotaion of units possible


•  During slab deflection, vertical racking of units occurs
•  Units move closer to each other
•  Vertical joints remain parallel
•  Horizontal joint staggering
•  Saddle gasket to compensate for staggering effect

55 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services


Façade System
4.1. Cover Capped System

56 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services


ZVE Fraunhofer Institute
London
Stuttgart, Germany
Bankside 123
ZVE Fraunhofer Institute
London
Stuttgart, Germany
Bankside 123
ZVE Fraunhofer Institute
London
Stuttgart, Germany
Bankside 123
ZVE Fraunhofer Institute
London
Stuttgart, Germany
Bank Street
ZVE Fraunhofer Institute
London
Stuttgart, Germany
New Cavendish Street
ZVE Fraunhofer Institute
London
Stuttgart, Germany
Leman Street
ZVE Fraunhofer Institute
London
Stuttgart, Germany
Leman Street
ZVE Fraunhofer Institute
London
Stuttgart, Germany
Cambridge
Leman Street
Fakulty of English
Façade Systems
4. Mitered Unitized Façades
II. Structural Bonded System

65 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services


Façade Systems
4.II Structural Bonded System

•  Fully Structurally Glazed, vertically and horizontally


•  Project specific solution due to glass bonding
•  Glass thickness 26 to 36mm
•  Horizontal gap of 10 or 20mm

66 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services


Façade Systems
4.II Structural Bonded System

67 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services


Façade Systems
4.II Structural Bonded System

68 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services


Façade Systems
4. Mitered Unitized Façades
III.  Structural Taped System

69 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services


ZVE Fraunhofer Institute
London
Stuttgart, Germany
Picadelly
ZVE Fraunhofer Institute
London
Stuttgart, Germany
Picadelly
ZVE Fraunhofer Institute
London
Stuttgart, Germany
Picadelly
ZVE Fraunhofer Institute
London
Stuttgart, Germany
Picadelly
ZVE Fraunhofer Institute
London
Stuttgart, Germany
Picadelly
Façade Systems
5.  Butt Jointed Unitized Façade System

75 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services


Façade Systems
5. Butt Jointed Unitized Façades

76 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services


Façade Systems
5. Butt Jointed Unitized Façades

Male/female connection
Seal at junit joint

77 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services


Façade Systems
5. Butt Jointed Unitized Façades

•  Units rotate at bracketry


•  Vertical joint no longer parallel, will
become triangular
•  Mullions butting top or bottom
•  When mullions butt, units lift up from
brackets and rotate
•  Units start to stagger

78 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services


Façade Systems
5. Butt Jointed Unitized Façades

79 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services


Façade Systems
5. Butt Jointed Unitized Façades

80 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services


Thank you for your attention.

81 8/14/17 Façade Systems, Gerd Hönicke, Director Pre-Construction Services