Professional Documents
Culture Documents
E 1 - Cabedo2014
E 1 - Cabedo2014
E 1 - Cabedo2014
Manuel Cabedo, Civil Eng., Isolux Corsán Group—Corsán Corviam Construcción, Madrid, Spain; Jaime Gracia,
Geologist, Copisa, Teruel, Spain; Bernardo Roldán, Civil Eng., Isolux Corsán Group—Corsán Corviam Construcción, Teruel, Spain.
Contact: jsa@isoluxcorsan.com
DOI: 10.2749/101686614X13830788506369
601,00 (ASL)
596,00
594,30 Conventional concrete (CC)
PA-10
PA-20
PA-30
PA-40
PA-50
Stilling basin
Dam axis of original project
R 50
Left stilling basin 27°
0,2 Roller 0,6 Right stilling basin
601
compacted
1 1 575,50 565
concrete Concreted
(RCC) rockfill
572,50 569
CC
2,00
2,70
570,00
565,00 CC Spillway
1,80
Perimetric gallery 33 m
557,00 Bottom outlet
2
1,50
1
1,00
Infill
Anchorages RCC
Fig. 1: Cross section at the spillway (left) and ground plan (right)1
Hosepipe
R2,1
595,10
follows: Conventional 0,28 0,12 × 0,09 Downstream
5
0,30 0,12 × 0,095
0,23
concrete face
• Quality improvement by simplify- Upstream 594,30 0,33 0,12 × 0,10
0,27
face
0,32
0,36 0,12 × 0,11
ing the stepped and beveled creager 0,39 0,12 × 0,12
0,37
execution. Vibration is always per- 0,43 0,12 × 0,13
0,45
formed in an “open air” condition 0,2 0,48
0,54
0,12 × 0,14
against formwork, improving face 0,54
0,66
1
finish, avoiding horizontal joints, 0,12 × 0,15
0,85
Roller
• Economic and time saving by allow- compacted
0,12 × 0,17
1,03
one dam abutment to the other and 0,12 × 0,19
1,20
1,20
(6 m). This procedure helped to avoid 0,6
the common gap left by CC spillway y
= 0,5 · x
in the RCC area, which would have 4 4 0,6 1
prevented the entrance of pouring,
spreading, and compacting machin- Fig. 6: Creager profile cross section showing the RCC advancement until the last step1
ery on the other side of the spillway.
• Economic and time saving in basin
foundation by avoiding the com-
mon phases associated with form-
work joints to prevent cracks due to
shrinkage in CC (3200 m3 of RCC
was poured in 3 days).
• Mixture saving and lesser shrinkage
when changing from CC to RCC by
increasing the cementitious fly ash
proportion from 50 to 70%.
Technical Achievements
To meet the rest of the challenges men-
tioned under the Introduction section—
high speed of execution, and adaptation
to adverse weather conditions—some
of the measures adopted could be con-
sidered as major technical achievements. Fig. 7: RCC blanket protection at night and RCC stepped creager allowing machinery pass
between abutments
Mixture Design Variation Depending
on Cold or Hot Weather Conditions
and covering time lasted 16 h. This is 16 h generate hot joint with each other.
The mixture design was fixed after the key for RCC dam quality because RCC dam is made of layers of 300 mm
the test slab as summarized in Table 2, spreading the next layer and covering thickness, and to guarantee the hot
Vebe time was settled from 8 to 12 s, completely the previous one before joints (i.e., right bonding) between
www.iabse.org/madrid2014