GALAXY ENTERTAINMENT GROUP

银河娱乐集团有限公司
To : WONG & OUYANG (HK) LTD From: 上海建工集团(澳门)有限公司 Shanghai Construction Group(Macau)Limited
Name: Zhou Yi Dong /Zhou Gong Jun
Attn.: Wayne So/ Winson Liem Signature:

 w/ encl.  w/o encl. Date: 3-Feb-20


CONTRACTOR SUBMISSION
Material Method Statement Others: Inspection & Test Plan
Contract No.: 3C005N077 Ref. No.: 3C005N077-HWT-ITP-00-0002 Revision: 01

Spec./ BQ/ Drawings Ref.: Attachment :  Yes, 1 page


pages  No
Contractor's alternative proposal:  Yes  No
Involve extra time/ cost under the contract  Yes  No

Subject : Inspection & Test Plan for Drywall


Description :
Inspection & Test Plan for Drywall

 WONG & OUYANG


Party expected to  RLB
reply:  ARUP (Struct)  Others, pls specify:-
 AURECON
Initial of : Expected approval date:_____________________
For Materials Submission Only:
 Brand/ Manufacturer:___________________________________________  Info. from Manufacturer

 Supplier:____________  Country of Origin:______________  Job Ref.

 Catalogue  Certificate  Sample to:  Site  Office:  Ref. Letter from Authorities

Purpose of Submission : Previous Ref.:

 For Review/ Approval  For Record  For Endorsement

COMMENT FROM THE CONSULTANT


Consultant: Ref. no.: Attachment:  Yes, ___ Pages  No
 WONG & OUYANG  ARUP(Struct)  AURECON  RLB  Other, pls specify:
 Approved Approved with Comment  Reject and Re-submit Consultant Name : WONG & OUYANG / ARUP / AURECON Date:
COMMENT: Signature :

WONG & OUYANG Galaxy - (Endorse if approved)


Name : Name:
Signature : Date: Signature : Date:

cc: External Internal


w/e w/o w/e w/o w/e w/o w/e w/o
  Galaxy   WONG & OUYANG (Site)    
  ARUP (Struct)   ARUP (Site)    
  AURECON   AURECON (Site)    
  RLB   RLB    
w/e - with enclosure w/o - without enclosure
Galaxy Resort Casino Development, Cotai City, Macau Phase 2
3C005N077 – Nominated Sub‐Contract for
Hotel Tower(West) Fit Out

Inspection Test Plan
Drywall Construction
Verifying Document Inspection Code
Item Particular / Activity Inspection Stage Inspection / Testing Activities Required Controlling Document Description NSC MC RSS M&E Remarks
Cont
A. Pre‐construction Stage
Method Statement ,Shop Drawing & Prior work commencement Approval by consultant  ‐Approved MethodStatement Approval by consultant
1 Calculation  ‐Approved Sh口p Drawing R HP HP N/A

Inspection & Test  Plan Prior work commencement Approval by consultant  ‐Approved Inspection & Test Plan Approval by consultant


2 R HP HP N/A

Material Approval Prior work commencement Approval by consultant  ‐Submission Form Approval by consultant


3 ‐ Product Data Sheet R HP HP N/A

B. Construction Stage
Receipt of material Material delivery Check material conforming to approval record Delivery note Check list
1 IV RI RI N/A

Setting out Prior installation of hanger and Ensure correct drywall alignment and demarcation Approved shop drawing Check list


2 frame IV CP RI RI

Installation of drywall frame (Before board Prior rockwool filling Check spacing and workmanship of stud frame Method statement Check list


3 installation) IV CP RI N/A

Get confirmation from Main Contractor for the Prior drywall closeup Check if clash with existing MEP services and rock wool Confirmation from Main RIN & Check list


4 completion of E&M services (conduit inside infill completed Contractor IV HP HP RI
drywall)
Wall boarding to both side of dry wall Prior finishes application Ensure smooth board surface Method statement Check list
5 IV RI RI N/A

Completion of drywall prior to finishes application After drywall close‐up Check quality of joint taping, applied sealant and Method statement RIN & Check list


6 surface condition of painting works IV HP HP N/A

Verification Code:
Legend:
IV: Inspection & Verification NSC: Nominated Sub-Contractor
RI: Random Inspection MC: Main Contractor
T: Test RSS: Resident Site Staff of the Supervision
RIN: Request for Inspection Form
CP: Control Point
HP: Hold Point