Professional Documents
Culture Documents
Design Basis Report-Main Bridge-Comments
Design Basis Report-Main Bridge-Comments
with approaches parallel to existing 2-lae Bridge over Ganga River at Phaphamau,
Allahabad in Uttar Pradesh
Basis Report
The purpose of this report is to present the design basis to be followed for the detailed
design for different construction stages of proposed Extradosed Bridge (main bridge)
across Ganga River starting from Ch. 144+400 on Phaphamau Side and ending at CH.
148+100, Allahabad side.
1.0 Design Standards
1.1 Concept of Extradosed Bridge
Extradosed bridges are similar in appearance to cable-stayed bridges but their
structural behavior is quite different and more akin to that of pre-stressed
concrete box girder bridges. Extradosed bridges are externally pre-stressed by
the installation of stay cables outside the deck. The stay cables pass over
saddles at the head of the towers and are anchored in the deck at low angles of
inclination thus inducing significant compression in the deck. Optimum span to
depth ratio for extradosed bridge ranges between 30 to 35 of the main span
near pier and near mid span 50 to 55. The bridge decks with extradosed cables
are constructed as balanced cantilever type construction using precast/cast in
situ span segments and cast-in-situ concrete pier table and stitches.
1.2 Bridge Configurations
1.2.1 Main Bridge
Span arrangement (Extradosed) = 130m +3 x 200m+ 130m
Median = 3.1m/1.2m for extradosed unit and 3/4 span Commented [VR2]: 3 or 4 span
continuous unit respectively.
Total deck width =33.00m/30.2m for extradosed unit and 3/4 span Commented [VR3]: 3 or 4
continuous unit respectively.
Carriageway = 2 X 10.50m
Median = 1.20m
Total width = 30.20m
1.2.5 Bearings
POT/PTFE Bearings/Spherical Bearings shall be provided.
1.2.7 Navigational Clearance Commented [VR4]: This para may be shifted to other location.
For Pylon, substructure and foundation design, Staad Pro and manual
calculation using Excel sheet are usedwill be carried out.
Confirmatory pile load test should be carried out before execution of work to
ascertain load carrying capacity of pile.
1.2.3.1 FOUNDATION
Bored cast-in-situ piling is done. Depending upon the soil condition, grouting of
pile is done if required. And RCC Pile Cap to be constructed over pile.
1.2.3.2 ABUTMENTS/PIERS
Construction of reinforced concrete piers with limited height of pier less than
10-12m will be carried out using traditional formwork with concreting in different
stages. For larger height piers, climbing formwork or slip forms with jack
controlled vertical sliding movement will be used.
1.2.3.3 PYLONS
Construction of reinforced concrete PYLON will be achieved by climbing
formwork or slip forms with jack controlled vertical sliding movement.
1.3.5 Miscellaneous
Access to different parts of structures shall be provided for inspection and
maintenance. All bearings at expansion joint pier locations shall be replaceable
and jacking points and jacking loads shall be shown on the drawings.
2 MATERIAL SPECIFICATIONS
• M70 – For Extradosed Span – Pile, Pile cap, substructure and superstructure
Location Cover
mm
Note
Where bundled or paired bars are used then the equivalent diameter shall be
considered in determining cover requirements.
Cover to pre-stressing ducts for post-tensioning shall neither be less than that
specified for main reinforcement nor one-half duct diameter
• Maximum jacking Stress: 0.729 fpu = 1356 MPa; (for Cables other than extradosed
Stay cables)
• Maximum jacking Stress: 0.55 fpu = 1023 MPa; (for extradosed Stay cables)
3 DESIGN LOADS
For design purposes 65mm thick of asphalt wearing course shall be considered. Its
weight is considered as 2.0 kN/m2
Concrete crash barrier with a weight of 8.0kN/m will be considered for both
unsupported longitudinal edges of the deck
The weight of known utilities carried by the bridge shall be taken into consideration.
As future utilities are unknown then an allowance of 1 kN/m per carriageway shall
be considered for this purpose
3.3 LIVE LOADS
Live loads are to be considered in accordance with provision of IRC: 6-2014. Bridge
has two carriageways of 10.5m14.00m? width. Each carriageway will be loaded 4
lanes with wheeled Class A & Class 70R loadings with the following live load
combinations:
One lane of Class IRC 70R for every 2-lanes with one lane of Class-A for the
remaining lanes or one lane of Class-A for each lane whichever is severe. The
above loads will be increased by appropriate impact factors as per provision of
Cl: 208 of IRC: 6-2014.
The Class A trains are spaced every 20m whereas Class 70R are spaced every 30m
between axles for wheeled vehicles, and every 30 m from tail to nose for tracked
vehicles. A reduction factor of 10% is applied when 3 lanes are loaded and 20% when
4 lanes are loaded.
Class A Train
2790
Length of segment ??
3.3.5 Effect of Vehicle Impact for longitudinal and transverse analysis (IM)
Vertical impact for Class A loading shall be as per figure given below:
Class 70 R – wheeled vehicles, impact shall be taken equal to 25 % for spans less
than12m, and in accordance with above figure for spans in excess of 12 m.
For Class 70 R – tracked vehicles, impact shall be taken equal to 25 % for spans upto
5 m, linearly reducing to 10 % for spans of 9 m. 10 % for spans up to 40 m and in
accordance with above figure for spans in excess of 40 m.
Total braking force will be computed based on the number of design lanes in the same
direction. Braking forces will not be increased for impact allowance and assumed to act
horizontally at a height of 1.2m above the roadway surface and distributed equally on all
bearings. Cl. No ???
3.3.11.1 General
Time dependent effects of creep and shrinkage for precast and in-situ portion of the
bridge shall be computed using program ADAPT-ABI with the ACI-209 model.
A range of ± 20% shall be considered on the creep factor for both pre-cast and in-
situ design.
Minimum and maximum air shade temperatures in the region of bridge are respectively
equal to +0°C & 50.0 °C. Therefore the mean of maximum and minimum air shade
temperature is equal to 25.0 °C.
As the bridge location has a difference between maximum and minimum shade
temperature greater than 20 °C; the bridge temperature to be assumed when the
structure is effectively restrained as per the table shown in IRC-6 § 215, is equal to
mean of maximum and minimum air shade temperature + 10° whichever is critical,
which corresponds in this case to 25.0 °C or 35.0 °C.
Then, lowering of temperature will be in the range of 35.0 - 0 = 35.0°C and temperature
increase equal to 50.0 – 25.0 = 25.0 °C. Uniform temperature variation is considered as
a long term loading. The elastic modulus for uniform temperature effects will be taken
as 0.5 times the instantaneous elastic modulus .
6.6
With:
With:
R = 4.0 response modification factor for concrete prestressed bridge with ductile
detailing;
The seismic force (modal mass) due to live load shall not be considered when acting in
the direction of traffic, but shall be considered in the direction perpendicular to traffic.
Parts of the structure embedded in soil shall not be considered to produce any seismic
forces. Only 20% of Live Load on the deck will be considered in transverse seismic
case.
3.3.17 Vessel Collision Force (Ship/Barge Impact on the Bridge) Cl.220 of IRC:6-
2014
3.3.18 Bearing Replacement Commented [VR6]: This para may be shifted to other location
The bridge deck, substructure and bearings shall be designed and detailed to permit
future bearing replacement of each and every bearing and jacking points shall be
clearly shown on the drawings.
Cable Replacement : Replacement of one cable during service stage will be verified. Formatted: Underline
Cable snap condition :One cable snap condition during construction/service stage will
be verified.
Construction agency will be responsible for ensuring that his the proposed handling,
erection methods and sequences of construction do not overstress the permanent
works.
Transverse stressing of the top slabs of the larger boxes through the use of
internal bonded tendons, located in flat elongated sheathing. This stressing will
be undertaken in the pre-casting yard shortly after casting.
Internal tendons located in the top slab and used for balanced cantilevering.
These tendons will be restricted in size to 12/15.2mm and typically two tendons
per web will be used for each segment. The tendons will be anchored on the
face of the segments.
Internal tendons located in the top and bottom slabs and will be used to provide
first stage continuity across the mid span in situ-concrete stitches between
cantilever tips. These tendons will be in size of 12/15.2mm or 19/15.2mm and
will generally be anchored at internal top and bottom blisters within the box
sections.
Extradosed tendons of size 22/15.2mm will be used to provide the external
prestressing by the installation of stay cables outside of the deck. The stay
cables pass over a saddle at the head of the tower and are anchored in the
Short line casting method will be adopted. The essence of this method is that each
segment is cast directly against the segment that it will be erected next to (match-cast
face) on one face and against a fixed form (bulkhead) on the other face.
The match-cast segment is positioned to act as one face of the mould, the
other face being the bulkhead. The curvature of the span is controlled through
the orientation of the match-cast segment relative to the bulkhead.
The mould is cleaned and the exterior forms are closed up. The prefabricated
reinforcement cage is lifted into position in the mould. The inner void form is
placed and sealed against the outer forms and the match-cast face.
The deck side forms are placed, cast-in features are secured and after a final
survey check the wet-cast segment is cast.
After the wet-cast segment has gained sufficient strength the forms are stripped
and the transverse tendons are stressed to about 20% design pre-stress level.
The match-cast segment is then carefully separated from the wet-cast segment
and removed to storage.
The wet-cast segment is moved to the match-cast position and the sequence is
repeated.
5. MISCELLANEOUS
The part of anchorage is required sufficient resistance against partial bending moment
and shear force at once, providing prestresssing from stay cable to girder smoothly.
The 3-D FEM analysis will be carried out to estimate the stress of critical parts of
segments adjoining the anchorages. According to the FEM analysis, anchor parts of
stay cables will be reinforced.
Dywidag-Systems International markets an Extradosed Anchorage, Type XD (-E for
epoxy coated strands), that is purposefully designed to combine the anchor head of an
external tendon with the protection details found on their DYNA-Grip and DYNA-Bond
Stay Cables (Dywidag-2006 Commented [VR9]: Do we need this para
Anchorage Anchorage
5.6 Bearings
POT cum PTFE bearings will be designed according to the provision of IRC: 83 (Part-III)
– 2002