JHA - Installation of Pipe & Support For Fire Protection 1
JHA - Installation of Pipe & Support For Fire Protection 1
JHA - Installation of Pipe & Support For Fire Protection 1
Job: Hook-up & allignment of pumps & Tapping of blow down for CHW / COW
Analysis by: Reviewed By: Approved By:
4. Hook-up & allignment of pumps & A. Fall of materials * Ensure materials was tie-off
Tapping of blow down for CHW / * Buddy buddy system is applied.
COW
B. using welding machine electric * Inspection of electrical tools prior to start
drill/ grinder & electrical tools the activities.
* Use Panel/Extension with GFCI
* Hot work permit shall be obtained
* Fire Watchman, Fire Extinguisher shall
be available
* Buddy buddy system is applied.
C. Struck by flying object * Use face shield and spectacles
* Provide and install protective covering
* Install warning sign and barricade into
afected area.
A, Slip, Trip and Fall * Make sure all unnecessary materials will be
5, Housekeeping pull-out of work area and place to designated
area.
B. Excess materials & waste * 5's must be implemented.
Note : The JHA will be discussed in the Pre-job work planning meeting between Contractor's work group & AGA Safety team.
ENVIRONMENT HEALTH AND SAFETY
JOB HAZARD ANALYSIS FORMSHEET
AGA-EHS-FS-0016
The work supervisor or Safety officer shall take into account step by step identification and analysis of the task to be performed to identify
hazards in the workplace and find ways to elliminate hazards prior to commencement of work.