Professional Documents
Culture Documents
Daily Report Template
Daily Report Template
From: To:
FOR THE DAY PL. Next Cum.
ACTIVITY DESCRIPTION LOCATION Unit Total QTY % COMP
Planned Achieved day Achieved
Formworks first floor slab Zone 3 m2 2000 500 300 200 1200 60.0%
WORK PROGRESS
MANPOWER EQUIPMENT
Formworks first floor slab Zone 3 500 300 200 1200 60.0%
STARTED ACTIVITIES
m2 2000
Formworks drop beams -1st flr Zone 3 m2
Post tension duct installation -1st flr Zone 3 nos
Plumbing sleeve installation -1st flr Zone 3 nos
Scaffolding erection for first flor slab Zone 2 m3
Formworks column - Grnd floor Zone 1 m2
JM JM Project Manager
Page 1 of 1