Professional Documents
Culture Documents
Project Mine Econ
Project Mine Econ
If P6,500 will be needed after 5 years, how much should be invested now if the interest
rate is 7.5% per annum compounded annually?
Solution:
A
Present Value = -----------
(1 + i)n
P6,500
Present Value = --------------
(1 + 0.075)5
2. The projected earnings or net cash flow of a newly developed mine is as follows:
Year 1 - P 3.0 million
Year 2 - P 3.0 million
Year 3 - P 3.5 million
Year 4 - P 3.0 million
Year 5 - P 2.5 million
If the mine is constructed at the cost of P 10 million which will be funded from a loan
borrowed at 12% interest per annum, what is the net present value (NPV) of the
mine?
Solution:
1
Year 1 P 3.0 million ------- = 0.893 P 2.7
(1.12)1
1
Year 2 P 3.0 million ------- = 0.797 P 2.4
(1.12)2
1
Year 3 P 3.5 million ------- = 0.712 P 2.5
(1.12)3
1
Year 4 P 3.0 million ------- = 0.636 P 1.9
(1.12)4
1
Year 5 P 2.5 million ------- = 0.567 P 1.4
(1.12)5
--------------
P 10.9
Year 1 2 3 4 5 6
Profits in million 7.19 7.22 7.69 8.20 8.73 13.31
What is the present value of the mineral property if the cost of money is 18% compounded
annually? The discount factor at 18% is:
Year 0 1 2 3 4 5 6
Factor 1 0.847 0.718 0.609 0.516 0.473 0.370
Solution:
Therefore:
Not advisable to buy the property for P20 million since the NPV is only P18.63
million.
4. Consider a mining project which requires an economic evaluation. If the yearly net cash
flow to be generated by the proposed operation over an expected life span of mine of nine
(9) years are as shown in the table, Calculate:
1. DCFROR to be generated by the project using as guides the present value
factors given for 30% and 35%.
2. The net present value to be generated by the project assuming that the cost of
capital is 12% compounded annually.
Year NCF (in millions) PV factor @ 30% PV factor @ 35% PV factor @ 12%
1 (10.1120) 0.7692 0.7407
0.8929
2 5.636 0.5917 0.5487
0.7972
3 3.693 0.4552 0.4064
0.7118
4 3.111 0.3501 0.3011
0.6355
5 3.444 0.2693 0.2230
0.5674
6 3.313 0.2072 0.1652
0.5066
7 3.046 0.1594 0.1224
0.4523
8 (0.121) 0.1226 0.0906
0.4039
9 (0.974) 0.0943 0.0671
0.3006
Solution:
1. DCFROR:
Year NCF PV factor Present PV factor Present
(in millions) @ 30% Value @ 30% @ 35% Value @ 35%
35% = -0.348
DCFROR = 0
30% = +0.319
35 – DCFROR -0.348 – 0
---------------- = --------------
35 – 30 -0.348 – 0.319
DCFROR = 32.4%
Solution:
1. Project in Mindanao
Solution:
First Cost – 0
Annual Depreciation Cost = -----------------
10
First Cost
Annual Depreciation Cost = ----------- (Equation 1)
10
First Cost
Annual Depreciation Cost x 2 = ------------
n
First Cost
Annual depreciation Cost = ------------ (Equation 2)
2n
2n = 10
n = 5 years
What is the book value of a fixed asset originally purchased at 10 million pesos being
depreciated on straight line basis at 20% per annum at the end of the 3 rd year?
a. 2 million b. 4 million c. 6 million d. 8 million
Solution:
Solution:
8. What is the net annual foreign exchange savings for the country by using production
from a local coal mine producing 3,000 tons per day, operating 300 days per year,
displacing 10,000 barrels of oil per day, assuming 25 dollars per barrel of imported oil and
the cost of producing the coal is 500 pesos per ton of which 20% is in US dollars to pay
for foreign loans and the exchange rate is 50 pesos to one US dollar?
Solution:
Foreign Expenses (Oil) = 10,000 barrels/day x $25/barrel x 300 days/year
Foreign Expenses (Oil) = $75,000,000 / year
Therefore:
Net Annual Foreign Exchange Savings = Foreign Expenses – Local
Expenses
Net Annual Foreign Exchange Savings = $75,000,000 - $1,800,000
Net Annual Foreign Exchange Savings = $73,200,000
9. Assuming you are operating a second hand 10 megawatt power plant at the mine for
300 days a year and are able to save 2 pesos per kilowatt hour by not buying from the
grid, how long will it take you to fully recover your investments if you bought the plant at
288 million pesos?
Solution:
Then:
Acquisition Cost
Return on Investment (ROI) = ----------------------
Savings
P288,000,000
ROI = --------------------
P144,000,000/year
ROI = 2 years
10. You manage a small high grade (3%) copper operations at a capacity of 100 short
tons per day at 300 days per year. Your mill recovery is 90% and your selling price is US
$1.00 per pound of copper, net of smelter charges. If your fixed cost total 30 million pesos
per year, what should your average annual variable cost per ton in order to breakeven,
assuming 40 pesos per dollar.
a. P2,160 /ton b. P1,160 /ton c. P2,000 /ton d. P1,000 /ton
Solution:
To Breakeven:
Then:
P34,800,000
Variable Cost/ton = ----------------
30,000 tons
Solution:
12. The recent chromite export shipment of Heritage Resources to China was surveyed
by SGS. The survey report shows the shipment to contain 12,350 WMT, 8% moisture,
51% Cr2O3, 6% MgO, 18% FeO, 12% Al2O3, 0.25% SiO2, 0.06% P, 0.004% S. The
market contract of Heritage shows the price conditions to be USD 42 per DMT FOB ST
at base grade of 43% Cr2O3 with bonus/penalty of USD 1.50 per unit Cr 2O3 over and
above base grade, fraction pro-rata. What is the total Excise Tax due on the shipment?
Solution:
Solution:
Production = 15,000 Mt x 6 gms/MT
Production = 90,000 grams
Total Sales
% Recovery = --------------
Production
100,000,000 tons
% Recovery = --------------------- x 100 % Recovery = 80%
125,000,000 tons
15. The corporate income tax of a gold mine is 35% and the local government unit
receives 40% share and the barangay receives 10% of LGU share. The generated profit
of the mine is P12,387,673.09 and the excise tax is set at P1,079,340.27.
1. How many percent will the Barangay receive from the corporate income tax?
a. 2% b. 1.4% c. 1.25% d. 1.88%
2. Amount the Barangay receives from the corporate income tax?
a. P57,654.00 b. P59,774.89 c. P60,699.60 d. P64,539.11
3. Amount the Government will receive?
a. P5,415,026.13 b. P4,945,600.26 c. P5,335,011.21 d. P4,623,977.00
Solution:
1. % Barangay Share = 10% x 40% x 35%
% Barangay Share = 1.4%
Solution:
900,000 tons/year
Mine Production = -------------------
0.60
17. How many days per year will a local coal mine producing 10,000 tons per day have
to operate to supply a power plant requiring 1 million tons a year of which 70% is
imported?
Solution:
Local requirement/year
N = ----------------------------
Production/day
300,000 tons/year
N = ------------------------
10,000 tons/day
N = 30 days
18. An open pit coal mine has an overall stripping ratio of 10 cubic meters to 1 ton of coal.
If the owner decides to contract out both the waste stripping and coal mining at a price
per cubic meter of material, what should be the minimum contract price for the mine to
breakeven assuming a selling price of coal of 1,000 pesos per ton ex-mine and a coal
specific gravity of 1.25.
Solution:
Assume:
Therefore:
Gross Sales = 1 ton x P1,000/ton
Gross Sales = P1,000.00
And:
Cost of Mining Waste = 10 cu.m x a (P/cu.m.)
Then:
Total Operating Cost = Cost of Mining Coal + Cost of Mining
Waste
To Breakeven:
10.80a = 1,000
a= P92.59/cu.m.
19. Semirara Coal Corporation supplies coal to NPC plants on the basis of import parity
(delivered price + tariff ) on an equivalent BTU basis. If NPC can buy imported coal of
10,000 BTU per pound at 20 USD per ton delivered and pays a tariff of 10% on the FOB
price of 15 USD per ton, how much will SCC have to produce and deliver its 8,000 BTU
per pound coal to breakeven, assuming an exchange rate of 40 pesos to one USD?
a. P688 / ton b. P704 / ton c. P640 / ton d. P800 / ton
Solution:
To Breakeven:
20. A coal basin underlain by a one-meter thick continuous horizontal coal seam is open
for concession applications. What is the minimum number of coal blocks one has to apply
for to supply the 25-year requirement of a 300 megawatt power plant which requires one
million tons of run-of-mine coal a year assuming a specific gravity of 1.25 for the coal as
mined. One block consisting of 1000 hectares and a mining recovery of 100%.
a. 2 blocks b. 20 blocks c. 200 blocks d. 30 blocks
Solution:
25,000,000 tons
No. of blocks = --------------------
12,500,000 tons/block
Solution:
Area x Grade
Average Grade = ----------------
Area unoxidized
320,000
Average Grade = ------------
400,000
Solution:
Under
Ground
Workers 400 25 10,000 0 0 10,000
400 25 10,000 2 hrs 2,500 12,500
Support
Personnel 100 25 2,500 4 hrs 1,250 3,750
Supervisors 50 25 1,250 0 0 1,250
---------
Total Manshift 27,500
Production
Overall Productivity = --------------
Manshift
30,000 tons
Overall Productivity = --------------------
27,500 manshift
23. An underground mine has developed an incentive bonus scheme which provides for
a 50% bonus for development advance beyond the standard of 3 meters per day per
crew. If the crew achieves said standard, they get 300 pesos per day. What is the total
compensation due a crew that made an advance of 105 meters during a 25 working day
month, assuming there were no holidays and no night work?
Solution:
Total Compensation:
Solution:
At Breakeven:
Operating Costs = Revenue from sale of metal
14,000 tons
Dozing ore period = -----------------------------------
166.4 bcm/hr x 2.2 tons/bcm
= P61,053
W tons
Dozing waste period = ----------------------------------------
166.4 bcm/hr x 2.2 tons/bcm
W
Dozing waste period = ------ hr
366
A.
Milling Cost = P168/ton x 14,000 tons = P2,352,000.00
B.
Other Costs = P300/ton x 14,000 tons = P4,200,000.00
C.
Total Operating Cost = Mining Cost + Milling Cost + Other Cost
Total Operating Cost = (P1,046,386.00 + P13.729W) + P2,352,000.00 + P4,200,000.00
Total Operating Cost = P7,598,386 + 13.729W
Then;
Revenue = 1,071.262 oz x $470/oz x P20.50/$
Revenue = P10,321,610.00
But:
Operating Cost = Revenue
P7,598,386 + P13.729W = P10,321,610
P13.729W = P2,723,224
W = 198,356 tons
Therefore:
Wt. of waste
Breakeven Stripping Ratio = ---------------------
Wt. of ore
198,356 tons
Breakeven Stripping Ratio = ------------------
14,000 tons
25. You are the manager of the company contracted to do pre-stripping of a large copper
deposit minable by open pit with total minable reserves of 15 million tons and an overall
stripping ratio of 2 to 1 which the mine owner wants to reduce to 1 to 1 during operations.
At what average daily rate will you have to pre-strip the mine if you are given only 6
months and you have 25 working days per month.
Solution:
Then:
15,000,000 MT
Stripping rate= --------------------------------
6 months x 25 days/month