WOSKED FIREFLY 2019

9M – FYK ATR 72-500 REV 28 01 SEPTEMBER 2019

PARTICIPATED IN CARRYING OUT OPERATION TEST OF FLIGHT COMPARTMENT

SEAT HARNESS DURING C CHECK.

AMM: JIC 251100-OPT-10000

JN:CA2-6-006

ASSISTED IN CARRYING OUT FUNCTIONAL TEST OF FREE FALL EXTENSION SYSTEM

DURING C CHECK.

AMM :JIC 323300-FUT-10000 (9M-MWD)

JN:323300-FUT-10000-01

9M MWE ATR 72-500 REV 28 01 SEP 2019


PARTICIPATED IN CARRYING OUT REMOVAL OF TORQUE TUBE ASSEMBLY

ON ENGINE NO 2 DURING C CHECK

AMM: JIC 712361-RAI-10000

JN: ( 13-12-19)

9M-MWE

PARTICIPATED IN CARRYING OUT AIRCRAFT JACKING DUE TO

FRAME 44 REPLACEMENT DURING C CHECK.

AMM: JIC 07-11-00 JUP 10000

JN: H29510 (12 DEC 19)

ASSISTED IN CARRYING OUT OPERATIONAL TEST OF FLIGHT

COMPARTMENT OVERHEAD HATCH DURING C CHECK

AMM : 522200-OPT-10010

JN : H029510 OR 522200-OPT-10010-01/ITEM-1
ASSISTED IN CARRYING OUT DRAINING OF PROPELLER HUB OIL

ON RIGH HAND PROPELLER DUE TO PROPELLER REMOVAL

DURING C CHECK.

AMM: 611100-DRN-10000

JN:MW-005/RH PROPELLER

ASSISTED IN CARRYING OUT ADJUSTMENT OF POWER CONTROL

CABLE TENSION DUE TO CONTROL CABLE REMOVAL DURING

C CHECK.

AMM: 761121 ADJ 10000

JN: IRC 00126 (16/12/19)

ASSISTED IN CARRYING OUT OPERATIONAL TEST OF ENGINE AIR

INTAKE DE-ICING SYSTEM ON ENGINE NO 2 DURING C CHECK

AMM:30-21-00 OPT 10000

JN: H029510 OR 302100OPT10000-1/#2 ENG

9M-MWF ATR 72-500 (JN : H040944 )

PARTICIPATED IN CARRYING OUT RAM AIR CHECK VALVE OPERATIONAL CHECK

FOR WEAR AND FREE MOVEMENT DURING A CHECK

AMM : 215159-CHK-10000

JN : ….(3/1/2020) mus
FOUND REAR STROBE LIGHT NOT ILLUMINATE.

TROUBLESHOOT CARRIED OUT FOUND REAR STROBE LIGHT

UNSERVICEABLE. REAR STROBE LIGHT REPLACEMENT CARRIED OUT

AS PER JIC 33-43-72 RAI 10000 DURING A CHECK. OPERATIONAL TEST

CARRIED OUT AND FOUND SATISFACTORY.

JN:IRC-00001 (22/1/2020) B2

PARTICIPATED IN CARRYING OUT TENSION CHECK OF ELEVATOR

CONTROL CABLE DURING A CHECK

AMM: 273100-CHK-10010

JN:IRC-00032 (20/1/20) mus

ASSISTED IN CARRYING OUT NOSE LANDING GEAR ABSORBER

NITROGEN CHARGING DUE TO FOUND NOSE LANDING GEAR TOO LOW

DURING A CHECK.

AMM: 121432 SRV 10020

JN:IRC00039 (18/1/20)

FOUND ENGINE NO 1 HP BLEED VALVE INTERMITTENLY OPEN AND CLOSE DURING EGR

TROUBLESHOOT CARRIED OUT FOUND HP BLEED VALVE AIR TEMPERATURE SENSOR

UNSERVICEABLE AND REPLACEMENT BE CARRIED OUT AS PER AMM JIC 361164 RAI 10010.

OPERATIONAL TEST CARRIED OUT AND FOUND SATISFACTORY

JN:IRC 00048 (22/1/20) NIK

PARTICIPATED IN CARRYING OUT RIGGING AND TENSION CHECK ON ENGINE NO 1

POWER LEVER CONTROL CABLE DUE TO CONTROL CABLE INSTALLATION DURING

A CHECK.

AMM: 761121 ADJ 10000

JN: IRC-00065 (20/1/20)


FOUND OIL LEAK AT DRAIN MAST ON ENGINE NO 1

TROUBLESHOOT CARRIED OUT FOUND ACW GENERATOR PACKING BADLY

WORN. ACW GENERATOR PACKING REPLACEMENT CARRY OUT AS PER

AMM JIC 242261 RAI 10000. OPERATIONAL TEST AND LEAK TEST FOUND

SATISFACTORY.

JN:IRC 00078 (22/1/20) NIK

9M-FYK 2D+2C+4A

ASSISTED IN CARRYING OUT FORWARD SIDE FLIGHT

COMPARTMENT WINDOW INSTALLATION DUE TO AIRWORTHINESS

DIRECTIVE DURING D CHECK.

AMM : 56-12-00 RAI 10000

JN :1YK1819261 (SUNNY) 11/12/2019

PARTICIPATED IN CARRYING OUT REMOVAL OF PASSENGER SEATS

BETWEEN FRAME 29 TO 44 DURING D CHECK

AMM : 25-21-21 RAI 10000

JN : SIPCM-2-013 (SUN) 1/12/19

PARTICIPATED IN CARRYING TENSION CHECKING OF

RUDDER CONTROL CABLE DURING D CHECK

AMM : 272100 CHK 10010

JN:SIPA2-4-005 (MUS/SUNNY) 21/12/19

ASSISTED IN CARRYING OUT OPERATIONAL TEST OF ENGINE FIRE

EXTINGUISHING SYSTEM DUE TO ENGINE FIRE BOTTLE REPLACEMENT

DURING D CHECK.

AMM: 262100 OPT 10000

JN:IRC-00013 (30/1/20) SUNNY


FOUND FLOORBOARD 261BF DELAMINATED

PARTICIPATED IN CARRYING OUT REPLACEMENT OF FLOOR PANEL

261BF. TASK CARRIED OUT IN ACCORDANCE WITH APPROVED

AIRCRAFT MAINTENANCE MANUAL.

REF: AMM JIC 20-41-13.

JN: IRC -00149 (SUNNY)

FOUND REAR NAVIGATION LIGHT BLINKING DURING POWER UP

TROUBLESHOOT CARRIED OUT FOUND REAR NAVIGATION LIGHT

UNSERVICEABLE. REPLACEMENT OF REAR NAVIGATION LIGHT CARRY

OUT AS PER AMM JIC 334132 RAI 10000. OPERATIONAL TEST CARRIED OUT

FOUND SATISFACTORY.

JN: IRC-00246 (B2)


9M-FYK
OBSERVED IN CARRYING OUT OPERATIONAL TEST ON ADF SYSTEM DURING D CHECK.
REF : AMM JIC 345300 OPT 10000
JN: IRC-00038 (B2)
OBSERVED IN CARRYING OUT REMOVAL OF MARKER BEACON ANTENNA DURING D CHECK
JIC : 343321 RAI 10000 JN: SIPXR2-2-002 3/12/20
OBSERVED IN CARRYING OUT REMOVAL OF TCAS BOTTOM ANTENNA DURING D CHECK..
JIC : 344321 RAI 10010 JN:SIPXR2-2-002 3/12/20

PARTICIPATED IN CARRYING OUT VISUAL INSPECTION ON OF REFUELLING DUCT


DURING D CHECK.
AMM 282000 DVI 10000
JN:SIPA2-4-007 (SUNNY)

9M-MWH
PARTICIPATED IN CARRYING OUT REPLACEMENT OF AFT SHOCK MOUNT ON ENGINE NO 2
DUE TO CRACK FOUND DURING D CHECK.
AMM 712261 RAI 10000
JN : IRC 00125 (RAFIQ) 3/2/20