Tenants Construction Status-3-3-20
Tenants Construction Status-3-3-20
OITC-1
1.0 G/F Tinytoots
I. Submission of Documents -
III. a. Ongoing fit-out status - 75% (Ongoing wall partitioning and ceiling works)
b. Architectural - 75% (Painting works ongoing)
c. Mechanical - 70% (AC Indoor unit installed, ongoing wiring and piping)
d. Electrical - 85% (Wiring installation and devices ongoing)
e. Plumbing -80% (Piping works ongoing)
IV. Others:
a. For follow-up schedule for initial leak testing of plumbing
b. For follow-up schedule for initial leak testing of aircon drain
c. Schedule of megger testing 1-week before operation
I. Submission of Documents -
IV. Others:
a. For follow-up schedule for initial leak testing of plumbing
b. For follow-up schedule for initial leak testing of aircon drain
c. Schedule of megger testing 1-week before operation
For recommendations:
a sprinkler heads for adjustment/ actual is in upright position
b Provision of gas leak detector @ kitchen
c. Provision of drain pan of ACCU condenser @ front side
d. Re-schedule of megger testing 1-ckt#13 failed
OITC-2
1.0 5/F-unit 2-504A DONG FEI
IV. Others:
a. For follow-up schedule for initial leak testing of aircon drain
b. Schedule of megger testing 1-week before operation
IV. Others:
a. For follow-up schedule for initial leak testing of aircon drain
b. Schedule of megger testing 1-week before operation
IV. Others:
a. For follow-up schedule for initial leak testing of aircon drain
b. Schedule of megger testing 1-week before operation
IV. Others: