Republic of the Philippines

Department of Education
Region V
DIVISION OF CAMARINES SUR
BINANUAANAN HIGH SCHOOL
Binanuaanan, Pili, Camarines Sur

HOMEROOM PTA PROJECT PROPOSAL FOR s/y 2019-2020


A Project Title: B Schedule of Implementation: C Proponent:
Double Walling of Classroom Partition July 10,2019 Grade 7 - Rizal
and repainting Homeroom PTA
Purchase of Wall Fan
D Project Location
(Building No.5: Room No.1 – Rizal Classroom), Binanuaanan High School, Pili, Camarines Sur
E Participants:
Homeroom PTA, Adviser and Students of Grade 7 – Rizal
F Overview, Rationale and Objectives
1. To improve the wall of the classroom that separates Grade 7 –Rizal from another section.
2. To enhance the beauty and orderliness of the classroom.
3. To promote conduciveness in learning.
G Goal and Scope/ BENEFICIARIES
1. Students of Grade 7 - Rizal
H Work Programs/ Activities
Preliminary Activities Actual Activities Post construction Activities
Planning proposal drafting, Monitor the procurement/repair by Invite the school’s inspectorate
submission of proposal for approval, the PTA President and Class Adviser. team/personnel to conduct post-
and to canvass the materials evaluation.
needed. Preparation of pertinent papers/
documents for liquidation.
Turn-over of the facilities to the assigned
in-charge for the proper care and
maintenance.
I Funding Source
Homeroom PTA Voluntary Donations s/y 2019-2020
J Budgetary Requirements (Details)
Quantity Unit Description Unit Price Total
A. Material Cost
6 pcs Marine plywood(Y4) 330 1,980
½ Kl Nail(1 inch) 64 32
½ Kl Nail (1 ½ inches) 64 32
½ Kl Nail (2 inches) 62 31
4 Liters/ 380 380
Latex paint white
1 (can)

SUB-TOTAL 2, 455

B. Labor Cost 30% of Material Cost

1 1/5 Days Labor for walling & repainting 450 675

B. Wall fan

2 Pcs. Wall fan 750 1,500

Grand Total P 4,630.00


(A+B+C)

K Reporting and Evaluation


The project will be strictly monitored by the school head, the school physical facilities coordinator and the
faculty. There will also be a request for post inspection and submission of liquidation reports on time.
L Enclosures Notes on Pictures:
1. Implementation Agreement 1 Pre-Repair/Construction to be attached to project Proposal/repost
2. Project Locator Map 2 Picture for On-going and Completed projects together with the Pre-
3. Pictures (Front, Side and Back) repair/construction picture shall be attached to accomplishment report and
liquidation documents.
4. Perspective, Plans & Specs and Program Of Work
5. Others
Proponent: Noted:
___ BLIZELDA R. BETCHAYDA_______________ ___ _WINSTON T. YUTA__________________
HRPTA President Class Adviser

Concurred: Approved:

JERIC A. ADIZAS HERNANI A. MAYOR


Physical Facilities Coordinator Secondary School Principal I