Repetitive Manufacturing
Repetitive Manufacturing
Repetitive manufacturing is period based planning and not based on orders. Normally same
products will be manufactured over longer period of time. Products will not change frequently.
Confirmation is from back flushing and settlement is through from product cost collector for the
period. Confirmation will be without ref to planned orders. Planned orders are sufficient to carry
out shop floor activity. In master data production versions and cost collector is must where this is
not mandatory in discrete.
Purpose:
The products produced are not manufactured in individually defined lots. Instead, a total
quantity is produced over a certain period at a certain rate per part-period.
2. Master Data
a. Creating Material Master using T-code MM01
Maintain selection method as 2, check repetitive manufacturing and maintain REM profile as
REM1 in MRP View 4 for header material.
Repetitive Manufacturing
MRP4 View
Maintain production version which is mandatory for repetitive manufacturing in MRP view 4.
Production version is mainly used when the alternate BOM and ROUTING is exist or header Click on Here
material.
Enter the version and text as shown in screen shot and double click on the version
Repetitive Manufacturing
Double Click
on Here
Click on
Here
Confirm Here
Repetitive Manufacturing
6. Run MRP
Repetitive Manufacturing
After MRP Run system generate 1 planned order for finished material & 1 purchase
requisition for raw material as shown in below screen.
Repetitive Manufacturing
Repetitive Manufacturing
7. REM Confirmation using T-code MFBF
Here confirmation will done w.r.t the material and planned order will be mentioned.