PAKTECHPOINT
E&I CONSTRUCTION FOLLOW:
Home
INSTRUMENTATION & CONTROL
Instrumentation
Surge arrestor
Ad RTEK Corporation Open
requirement specifications.
4. Cable tray installation shall be self supporting type with a wide flange (48mm or Marine Hardware manufacturer
72mm or 100mm) in accordance with cable cross section. Ad Sail Rigging Get Quote
SPONSORED SEARCHES
6. Cable trays shall be fixed onto standard steel shapes, welded to steel structures Meet Your Mature Ladies
or fixed on to concrete structures with self-drilling dowels. Distance between Ad DateMyAge.com Sign Up
fixing points and cable tray support spacing shall be a maximum of three meter for
ladder type tray and two meter maximum for perforated tray so as to avoid strain
on cable trays.
7. Cable tray installation shall be designed to carry a load of 100kg/m. All cable
trays shall be perforated or ladder type to avoid the retention of water and to allow
fastening of the cables.
8. Cable trays shall be provided with covers where there is high risk of mechanical
damage during normal operation or maintenance periods. Cover fabrication shall
be the same as that of cable trays themselves and shall be fixed on cable trays with
proper clips recommended by cable tray Manufacturer/Vendor and comply with
project required specification.
Kontraktor Baja Surabaya
Ad Bisesa Contractor Buka
CATEGORIES
CIVIL ENGG.
CONTROL SYSTEM
9. The number of single or multi-conductor cables rated 11kV, 6.6kV, 1kV or less E&I CONSTRUCTION
in cable trays shall include an allowance of 20% extra space for future expansion.
E&I QA QC
10. Separate racking/trays shall be installed for the following electrical systems,
generally arranged top to bottom manner. ELECTRICAL
The cable tray system shall be installed in accordance with the project Measurement & Instrumentation
specification, manufacturer’s instruction and the referenced standard installations
details. MECHANICAL
Locate the area where cable tray shall be installed as per the Issued For
PAINTING
Construction (IFC) drawings.
Q/As CIVIL
Q/As Instrumentation
STRUCTURAL
TELECOM RF
Uncategorized
Prepare the required tools and materials to be used for the installation of the cable VIDEOES
tray. Inspect tools for proper working condition.
WORK PERMIT SYSTEM
Install cable tray supports for the stability of the cable tray.
Ensure sufficient space provided and maintained for cable tray to permit adequate
RECENT COMMENTS
access for installing & maintaining the cable.
Reymart Manablug on Level Transmitters
Ensure that cable trays are exposed and accessible for installation.
Selection and Types of Level Transmitters
Cable tray sections, fittings and connected raceways shall be bonded using bolted SYNCHRONOUS MOTOR ELECTRICAL DESIGN -
mechanical connectors or bonding jumpers. PAKTECHPOINT on Three phase connections Star
and Delta Connections
Lifting Hardware Manufacturer NEC Medium Voltage Switchgear Design
Requirement - PAKTECHPOINT on ELECTRICAL
Ad More than 200 kinds of products to meet customers'
TESTING PERFORMING IN SWITCHGEAR –
demands.More than 100 industry patent.
Ad GENERAL
Sail Rigging
Induction Motors Design Requirements below
150 kW in Plants - PAKTECHPOINT on Electrical
Get Quote
Field Test Procedures as per Standard IEEE, ANSI,
NEMA, UL, and IEC
Check all braces and supports are adequate to handle weight of the tray & SYNCHRONOUS MOTOR ELECTRICAL DESIGN
cables in accordance with the detailed drawings.
Inspect the installed supports to ensure that it is levelled and aligned vertically
and the whole assembly is rigid.
Check the expansion joints or connectors are properly installed.
Check of cable tray installation if it does not conflict with other services or
equipment.
Where supports are bolted to structural steel, ensure that all bolts, nuts, etc.
are correctly installed & securely fixed.
Hold down clamps shall be installed properly and are anchored on required
locations.
Ensure no sharp edges & burr that would cut or damage the cables.
All metallic cable tray systems shall be bonded at every 25m of length. Coupler
plates or bonding jumpers shall be used with every section and across each tray
joint to give electrical continuity.
Earth bonding jumpers are checked for proper connection and bonded to main
grounding grid.
SPONSORED SEARCHES
cable tray manufacturing machine cable tray fixing method to pipe rack
paktechpoint.com
Surge monitor E&I MS Archives Meet Ideal Single Ladies JOB SAFETY ANALYSIS
JSA FOR INSTALLATION
OF CABLE TRAY
Ad RTEK Corporation paktechpoint.com Ad DateMyAge.com paktechpoint.com
wire and cable production Transformer Technologies Electrical conduit E&I Construction
- High quality electric - Substation Equipment Installation Aboveground Archives
cable & Undergroud Techniques
Ad hzyjcable.com Ad transformertechnologies.com paktechpoint.com paktechpoint.com
Share to Friends
E&I QC Inspector Interview Procedure for Dress-up of Vessels PROCEDURE FOR INSTRUMENT
Questions Pipe Supports Installation BRANCH CABLE TRAY
In "E&I QA QC" In "MECHANICAL" INSTALLATION
In "E&I CONSTRUCTION"
Tags: E&I MS
3 RESPONSES
Comments 3 Pingbacks 0
Could anyone advise me regarding the deadline for Switalskis Solicitors Training Contract
Application? Season’s Greetings and Best Wishes to you and your family
Loading...
Reply
You should participate in a contest for probably the greatest blogs on the web. I’ll suggest this
website!
Loading...
Reply
Hi. I have checked your paktechpoint.com and i see you’ve got some duplicate content so probably it
is the
reason that you don’t rank high in google. But you can fix this issue
fast. There is a tool that creates articles like human, just search in google: mi olo’s tools
Loading...
Reply
LEAVE A REPLY
Comment
Name * Email *
Website
Post Comment
SUBSCRIBE YOUTUBE CHANNEL
Home
INSTRUMENTATION & CONTROL
Instrumentation
Sensor & Transducer
Calibration
FOUNDATION™ Fieldbus
COMPRESSOR CONTROL SYSTEM
VIBRATION
DCS
CONTROL SYSTEM
Formulas(I&C)
control valve
E&I MS
PLC
ELECTRICAL & POWER
Electrical standard
Electrical Engineering
E&I MS
E&I Construction
PLUMBING
HVAC
TELECOM RF
GSM RF Optimization
3G/WCDMA RF Optimization
LTE RF Optimization
CIVIL ENGG
E&I QA QC
MECHANICAL
ARAMCO WPR
International Standards & Codes
Cathodic Protection
PAKTECHPOINT © 2020. All Rights Reserved.
Powered by - Designed with the Hueman theme