Grafički Rad 3 - Izrada Nanosne Skele

You might also like

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 2

III Izrada nanosne skele

3.1) Materijal:

-bunarska motka : 1.00 m1/ m1objekta * 500 din/ m1bm = 500 din/ m1objekta

-daska 48mm: 0.04 m3/m1objekta * (20000 din/ m3d) * = 800.00 din/ m1objekta

-ekseri: 0.10 kg/ m1objekta * 130 din/ kge = 13,00/ m1objekta

Σ=M= 1313.00 din/m1objekta

Radnici :

TIV : 0.05Nč/ m1objekta * 400din/ Nč = 20 din/ m1objekta

TIV: 0.05Nč/ m1objekta * 400 din/ Nč = 20 din/ m1objekta

Σ=R=40 din/ m 1objekta

Cijena izrade nanosne skele:


C = M+R (k+1)

C = 1313.00 din/m31:2:6 + 40 din/ m1objekta *(4+1) = 1513.00 din/ m1objekta

Transport materijala:

R II = 0.0989 Nč/ m 3gradje

0.0989 Nč/ m3gradje * 150din/ Nč = 14.835din/ m3gradje

14.835din/ m3gradje*0.04 m3gradje/ m1objekta = 0.59 din/ m1objekta

C = 0.59 din/ m1objekta * (4+1) = 2.95 din/ m1objekta

Ukupna cijena izrade I transporta:

C = = 1513.00 din/ m1objekta + 2.95 din/ m1objekta = 1515.95 din/ m1objekta


3.2.) Definisanje radne brigade

- TIV : 0.05Nč/ m1objekta

- TIV: 0.05Nč/ m1objekta

- R II : 0.0989 Nč/ m3gradje * 0.04 m3gradje/ m1objekta = 0.004 Nč/ m1objekta

Rekapitulacija:

TIV : ………………………………………………….0.1Nč/ m1objekta

R II : ………………………………………………….0.004 Nč/ m1objekta

Radna brigada:

Količina Norma Radnika


radnik Nč brigada dana
rada(m1) časa(m1) dana
1 2 3 4=1*3 5=4/n 6 7
147,519 TIV 0.1 14.75 2.11 1 3
R II 0.004 0.59 0.08 1
n-broj radnih sati u toku dana(7h)

3.3. Količina osnovnog materijala za 1 m1 objekta:

Bunarska motka:

1,0m1/ m1 objekta*147,519m1/ m1objekta=147,519 m1/m1 objekta

Daska 48mm:

0.04 m3/ m1 objekta * 147,519m1/ m1objekta=5.9 m3/m1 objekta

Ekseri:

0.10 kg/ m1 objekta * 147,519m1/ m1objekta=14,7519 kg/m1 objekta