Professional Documents
Culture Documents
Final 470
Final 470
Final 470
Procurement & Construction of 491 Villas and 3 Duplex Villas for Imam and Muazzin
REVIEWED BY:
9. LIST ATTACHMENT:
9.1 Attachment I - Temporary Facility Documents with Attachments.
9.2 Attachment II – Royal Commission Specifications & Requirements.
9.3 Attachment III – IFC Drawings.
9.4 Attachment IV - Technical BOQ.
END OF SCHEDULEB
Scope of Work
Temporary Facilities
Date of Issue: February 2015
REVIEWED BY:
Space Number
Offices 12
Achieve Room 1
Toilets 6
Meeting room 1
Prayer room 1
Pantry Area 1
Storage Area 2
Total Area 300 m2
Proposed layout of the space requirement is shown in ATTACHMENT 2.
The Scope sholl include provide mg 10 shaded proking in front of the facility
Scope of Work
Temporary Facilities
REVIEWED BY:
DIVISION 2- SITEWORK
Specification 0201 Survey work
0202 Earthwork - including Excavation, Filling and Grading
0203 Boundary Wall
0204 Pavement Sub-Base and Aggregate Base
0205 Underground Piping and Site Utility Pits
0206 Pre-construction Termite Control
0207 Interlock concrete paver block
0208 Curbs
0209 Landscape
DIVISION 3 - CONCRETE (Plain and Reinforced)
Specification 0301 Concrete Reinforcement
0302 Concrete Work (Cast in Place & Pre-cast)
DIVISION 4 - MASONRY
Specification 0401 Masonry Units
0402 Concrete Unit Masonry
DIVISION 5- METALS
Specification 0501 Steel Rectangular Hollow Sections and Small Sections
Structural Steel
DIVISION 6- WOOD AND ALUMINIUM
Specification 0601 Carpentry and Millwork
0602 Cabinet Work
DIVISION 7- THERMAL AND MOISTURE PROTECTION
Specification 0701 Waterproofing and Damp Proofing, Vapour Barrier for
Slabs
0702 Building Insulation
0703 Membrane Roofing
0704 Flashing and Sheet Metal
0705 Joint Sealants
0706 Bituminous Film Coatings
0707 Concrete Water proofing
DIVISION 8- DOORS AND WINDOWS
Specification 0801 Aluminum Doors and Frames
0802 Aluminum Windows
0803 Glazing and Mirrors
0804 Wood Doors
0805 Finish Hardware
0806 Steel Doors and Frames
0807 Garage Doors
DIVISION 9- FINISHES
Specification 0901 Solid Plaster Rendering Stucco Work
0902 Tiling
0903 Painting
0904 Gypsum Wallboard and Ceiling System
0905 Metal Stud and Ceiling Support Systems
0906 Marble and Granite Tiling
DIVISION 10- SPECIALTIES
Specification 1001 Sanitary Fixtures
1002 Bathroom Accessories
DIVISION 11- APPLIANCES
DIVISION 1:
GENERAL REQUIREMENTS:
0101 Summary of Work
0102 Quality Control
0103 Temporary Facilities
0104 Temporary Fences and Barricades
0105 Project Identification and Sign
0106 Close- out requirements
0107 Additional construction Requirements
c. The mobilization should commence Within 14 days after the NTP or letter of
acceptance or date of signing the contract is issued.
d. Within seven (7) calendar days of the date of commencement of the mobilization
period, the PC contractor shall submit for the approval fully dimensioned plans and
detail showing the proposed location and layout on the site of all necessary temporary
buildings including consuRant1owner office accommodations (located apart from PC
contractor’s offices), plant and materials stores, testing laboratory, messing facilities
etc. as such, plans shall also include (but not limited to) the following:
1. Temporary access routes to, from, and upon the site.
2. Temporary fencing, gates, parking and other security requirements.
3. Extent of covered or open areas designated for plant and materials storage
and/or for vehicle parking for PC contractors. Owner’s and consultant's
staff.
4. Refuse storage and collection points.
5. Means of providing fresh water supply, showing location of drinking water
storage tanks, tanker fill points, and lines of distribution about the Site.
6. Means of providing temporary fire protection facilities, showing location of
the firefighting water storage tanks, tanker fill points, pumping and fire hose
stations, and lines of distribution about the site.
7. Location and methods of sewage disposal and surface water drainage.
8. Location and source of temporary power generation, temporary switch
boards etc. for all temporary facilities, and as required providing lighting and
power for the execution of permanent works.
9. Telephone services.
10. Location of site name boards.
29.0 AS BUILT SUBMISSION:
1. Prior to transferring "As-Built" information from the record set of prints to the
originals of the approved drawings issued for construction and, in the case of PC
contracts, before the client! Royal Commission will loan the originals for this purpose,
the Contractor shall submit a sample drawing, prepared by each draftsman nominated
to do the transfers, to demonstrate its ability to comply with the specified quality
standards.
2. Following transfer of the "As-Built" information onto the originals of drawings issued
for construction. the Contractor shall submit them, together with all other related
Contractor's and Manufacturer's, etc. drawings and all other related documents, to the
client for review Each drawing and document shall be certified "As-Built" by the
Contractor's authorized signature in the space provided (see item 29.0 - 3 below). If,
as a result of review, the client finds the drawings or documents do not comply with
this specification they will be returned for Contractor's proper compliance and
resubmittal, Upon acceptance they will be signed as such by the client's/ Royal
Commission Project field Engineer, or his delegate, in the space provided (see item
29.0 -3 below) and the initial Acceptance, Partial Initial Acceptance of Beneficial
Occupancy (as applicable) process can proceed.
3. Each drawing and document shall be stamped, or otherwise noted, as
follows:
1. 13 DETAILED JTEMS:
A. Civil:
1. Earthwork:
a. General Excavation.
b. Backfill/compaction.
c. Trenching d. Materials Testing and Inspection.
2. Concrete:
a. Forms Material
b. Rebar Control &
c. Embedded Materials in place
d. Concrete Inspection
3. Structural and Miscellaneous Steel:
a. Receiving.
b. Pre-erection.
c. Erection complete d. Painting.
d. Painting.
4. Other Civil:
a. Pre-cast concrete.
b. Masonry.
c. Manholes.
5. Architectural:
a. Floor & wall finishes, Roofing and Cladding.
b. Roofs.
c. Doors, Windows, Louvers, Vents, Kitchen & Bath fittings, etc.
d. Rendering (Plastering).
B. Mechanical Piping (Exposed and Buried):
1. Pipes:
a. Materials.
b. Supports, Hangers.
c. Coatings.
d. Installation inspections.
e. Testing.
2. Valves.
3. Mechanical Equipment:
a. Storage and Maintenance.
b. Installation and Inspections.
c. Testing.
4. Welding.
5. Insulation.
C. Electrical:
1. Equipment:
a. Storage and Maintenance.
b. Installation and Inspection.
c. Testing.
2. Conduit.
3. Cable.
4. Connections.
5. Ducts.
1. 14 HOLD POINT INSPECTIONS:
A. "Hold Point" is defined as a part of the work that cannot proceed until it has
been inspected and certified by signature of the proper authority. Hold points can
be either Contractor "Hold Points", requiring the Contractor Q C. Manager's
signature or Owner "Hold Points" requiring a signature by a representative of the
Owner. The format of the "Hold Point" document shall include at what stage of
the work "Hold Point" is required, description of the work to be inspected,
appropriate pay item reference and shall be approved by the Owner.
1. 15 MATERIAL SUBMITTALS:
A. Submittals shall be made for all materials to be incorporated into the permanent
works as required by various sections of this Specification.
B. Within 30 days of the Notice to Proceed the Contractor shall submit a Material
Submittal Program to the Owner for review and approval. The Program shall be
completed and contain all the materials referred to above.
C. Wherever possible the Contractor shall submit a minimum of three (3)
alternative vendors for each category of material.
D. The Contractor shall allow a period of ten days for review of materials submittals
by the Owner/Owner's Representative.
E. Should the Contractor intend to propose the use of any alternative materials to
those specified in the Contract Documents, then the Contractor must provide a
detailed list of all such materials together with all relevant product data etc., and
a justification for this proposed substitution for the Owners approval.
F. All material submittals are to be supported technical literature which should
include as a minimum manufacturer's instruction, Q.A. certificates, etc.
G. Contractor to allow for material sample library on site of all submittals, including
technical literature.
H. Site condition Execute periodic cleaning to keep building, site, and adjacent
properties free of accumulations of waste materials, debris, rubbish, and
windblown debris resulting from construction operations, trucks not taking dirt
on the public roads, etc. and all to comply with local environmental laws.
I. Section on the shop drawings and approval process required.
===End of Section ===
0103 TEMPORARY FACILITIES
1. 1 GENERAL:
2.0 1 Description:
A. This section specifies Contractor's temporary services and, office and support facilities,
including utilities, construction and support facilities.
Provide facilities ready for use, maintain, expand and modify as needed. Remove
when no longer needed.
2.0 2 General Requirements:
A. Keep facilities clean and neat Operate in a safe and efficient manner. Take necessary
fire prevention measures.
Do not overload, or permit facilities to interfere with progress.
Do not allow hazardous, uncertainty conditions to develop or persist on site.
B. Inspection: Arrange for Client Representative to inspect and test each temporary
utility before use Obtain required approval and permits.
C. Cost or use changes for Contractor's temporary facilities are not chargeable to Client
and will not be accepted as a basis of claim for a change order.
2.0 3 Reference Standards:
A. IBC, International Building Code – 2003.
B. IPC, International Plumbing Code.
C. NFPA, National Fire Protection Association.
D. NEC, National Electric Code.
E. NEMA, National Electric Manufacturers Association.
F. NESC, National Electric Safety Code.
2.0 4 Submittals:
A. Submit reports of tests, inspections and similar procedures performed on temporary utilities.
Submit a schedule showing implementation and termination of each temporary utility within
15 days of commencement of the work.
2.0 2 Toilets:
A. Install self-contained toilet units, properly vented and fully enclosed. Toilets shall be in
accordance with the applicable reference as listed in Section 103 "Reference Standards".
3. Broadway vehicle.
4. New brand office.
Once the Contractor Provided Site Facilities are no longer required under this Contract,
and Client has so agreed in writing. Contractor shall remove all such Contractor Provided
Site Facilities and restore the land to as-found condition, unless Client and Contractor
have otherwise mutually agreed in writing.
C. Services:
E. Standard:
1. Contractor Provided Site Facilities shall be built and operated consistent with all Labor
and Workmen's Laws in the Kingdom of Saudi Arabia and applicable Royal Commission
RC standards.
2. Air conditioning with individual controls to maintain temperature between 70° and 75° F.
F. Contractor shall provide electrical power, 400/230V, 3 phase, 60 Hz as needed, continuous
communications facilities (phone, fax, and internet).
G. The contractor shall provide in an approval and as a self-contained compound, a company
consultants project office with 160 m2 of good quality air conditioned office, complete with
toilets, kitchen facility, telephone, tax, computer with printers A3, Wi-Fi internet, office
supplies, copy machine (A3) and complete furniture's.
1. Project manager offices with small meeting room with complete facilities, computer,
furniture, cabinet.... Etc.
2. Senior Civil Engineer (2) with complete facilities.
3. Meeting room for 10 persons with complete facilities.
4. Toilets (2).
5. Secretary section with complete facilities and attached with small room for
documentation store.
6. Guest sitting area.
7. Engineers hall for 10 persons with complete facilities.
8. Sample room for sample material (36m2).
9. Tea room.
10. The Contractor is to provide 1 no four-wheel drive Toyota Prada or equivalent to
SAUDI ARAMCO for site transportation for the project duration
A. The Contractor shall provide, supply, install and maintain service required for power,
lighting and communications.
B. Provide adequate artificial lighting for all areas of work when natural light is not adequate
for work and for areas accessible to the public.
C. Lighting and power of the Contractor Camp, accommodation and client offices shall
conform to the applicable Standards listed in Section 1.03 "Reference Standards" and all
Royal Commission /RC Standards under "P" index.
All non-electric utilities supply, installation, testing, flushing and disinfection shall be the
responsibility of the Contractor and shall be in accordance with the applicable references listed
in Section 1.03 "Reference Standards".
2.0 12 Equipments:
A. HVAC Equipment: Unless Owner authorizes use of permanent HVAC system, provide
vented, self-contained, liquid-propane-gas or fuel-oil heaters with individual space
thermostatic control.
1. Permanent HVAC System: If Owner authorizes use of permanent HVAC system
for temporary use during construction, provide filter with Minimum Efficiency
Ratina Value (MERV) of 8 at each return air grille in system and remove at end
of construction.
A. Prepare project identification signs as specified standard detail and install where indicated.
Prepare signs to provide directional information to construction personnel and visitors The
signs shall be erected in locations as directed by Client Representative,
1.0 4 Environmental Protection:
A. Operate temporary facilities and conduct construction by methods that comply with
environmental regulations to minimize the possibility that air and subsoil might be
contaminated or polluted.
A. Locate facilities where they will serve Project adequately and result in minimum
interference with performance of the Work. Relocate and modify facilities as required by
progress of the Work.
Part 1 – General:
1.0 1 Temporary Fences and Barricades:
A. Erect temporary fencing to prevent unauthorized personnel from entering construction
sites and Temporary Construction Facilities. Maintain the Fencing for the duration of
construction operations.
B. Erect fencing around the site perimeters.
C. Temporary fencing shall be as per the relevant authorities requirements and as approved
by the Client Representative.
- End of section -
1.0 5 PROJECT IDENTIFICATION AND SIGNS
PART 1 - GENERAL
1.0 1 Requirements:
A. Furnish, install and maintain project identification sign.
B. Provide temporary on-site informational signs to identify key elements of construction facilities.
C. Remove signs upon completion of construction.
D. Allow no other signs to be displayed.
1.0 2 Related Requirements:
A. Section 0103 - Temporary Construction Facilities
3.0 3 Maintenance:
A. Maintain signs and supports in a neat, clean condition; repair damages to structure,
framing or sign.
01 Requirements Included:
A. Close-out requirements include those general requirements in preparation for Initial
Acceptance, final payment and normal termination of the contract. Specific requirements for
individual units of work are specified in the technical sections of these specifications.
1. Record Drawings
2. As-Built Drawings
3. Record Specifications
4. Record Shop Drawing Information
5. Record Miscellaneous Submittals
6. Record Samples
C. The documents shall be organized in a logical order, bound or filed, ready for continued
use and reference.
D. Immediately prior to the time of Initial Acceptance, Client will meet with the Contractor
at the site, and will determine which of the record samples maintained by the Contractor
during the progress of the work are to be submitted. Any samples not required by Client
shall be properly disposed of by the Contractor.
A. Special cleaning for specific units of work shall be as specified in the various technical specifications.
B. Provide final cleaning of the work at the time indicated, consisting of cleaning each surface or unit
of work to the normal "clean" condition expected for a first-class building cleaning and
maintenance program comply with manufacturer's instructions for cleaning operations As a
minimum, the following are examples of the cleaning levels required.
1. Remove labels which are not required as permanent labels
2. Clear exposed hard-surfaced finishes, including metals, concrete, painted surfaces, special
coatings, and similar surfaces, to a dirt free condition, free of dust, stains, films and similar
noticeable distracting substances. Except as otherwise indicated, avoid the disturbances of
natural weathering of exterior surfaces Restore reflective surfaces to original condition.
3. Remove debris and surfaces dust from limited-access spaces including trenches, equipment
vaults and similar spaces.
4. Clean project site including landscape development areas of litter and foreign substances.
Sweep paved areas to a broom-clean condition; remove stains, petro chemical spills and
other foreign deposits. Rake grounds which are neither planted nor paved to a smooth,
even textured surface.
C. Except as otherwise indicated or requested by Client, remove temporary protective devices and
facilities which were installed during the course of the work to protect previously completed work
during the remainder of the construction period.
D. Comply with safety standards and governing regulations for cleaning operations. Do not burn
waste materials at the site, nor bury debris or excess materials on the property, nor discharge
volatile or other harmful or dangerous materials into drainage system. Remove waste materials from
the site and dispose of.
E. Green Housekeeping: Provide documentation that all cleaning products and janitorial paper
products meet requirements of relevant authorities in KSA.
Note: Property considered to be unclean, unserviceable and/or unfit for use will be rejected
by Client.
A. Utilize cleaning products that meet the requirements of Saudi or International Standards.
2.0 Constructability:
Constructability Requirements contractor shall implement and conduct constructability reviews during the
project. It is the Contractor's responsibility to assess and confirm all construction constructability aspects
PART 1 - GENERAL
1.0 1 Description:
A. Work in this Section includes, but is not limited to, furnishing survey crew, setting LL reference points
and bench marks, vertical and horizontal setting out of all building foundations, fences, grading, trench
work, utility installations, roadways, asphalt paving walkways and other works forming part of the
Contract.
B. Work is to be performed in accordance with the conditions as per standards.
1.0 5 Submittals:
A. Submit to Client Representative all data and grade sheets at least 48 hours prior to construction. Show
on the grade sheets the vertical and horizontal relationships between the stakes and the design reference
points shown on the Drawings
PART 2 – PRODUCTS:
2.0 1 Stakes
A. Construction Stakes: Construction stakes shall be 14 mm steel rebar. Wood or PVC stakes may be
used as directed by Client Representative.
B. Machine Control Stakes: Machine control stakes shall conform to manufacturer's specifications.
PART 3 – EXECUTION:
3.0 1 Surveying Work:
A. Contractor Survey Controls: From Client provided survey controls (refer to bench mark data shown on
the Drawings), Contractor shall establish additional survey controls with an accuracy as stipulated in
this Specification.
B. Survey Monuments: If the validity of any survey monument is threatened, place at least three (3)
reference or witness markers for each point likely to be disturbed. Submit survey notes listing the
relative positions of the reference markers to each other, and to the points they are referencing at least
48 hours prior to disturbing or threatening the validity of the monument.
C. Road Works:
1. General. Prior to the start of grading, and during the progress of the Work, set and maintain
sufficient stakes to show conformance with the Drawings. Locate all stakes in such a way that they
will not be disturbed by construction operations.
2. Stake Placement: Construction stakes shall be placed at the left and right of center lines, at
shoulders, edge of paving, grade breaks, beginning and ending of curves, angle points and
intersections of flow lines.
3. Stake Spacings :
D. Utility Work:
1. General: Prior to beginning trenching operations, and during the progress of the Work, set and
maintain sufficient stakes to show conformance with the Drawings. Locate all stakes in such a
way that they will not be disturbed by construction operations.
2. Stake placement Construction stakes are to be place at, but not limited to, the following
locations;
a. Utility Pipes: Stakes shall be placed at each wye or tee connection, cleanout and manholes
and at every 10 meter station.
E. Park Work: Prior to beginning of grading, and during the progress of the Work, set and maintain
sufficient stakes to show conformance with the Drawings. Locate all stakes in such a way that they will
not be damaged or disturbed by construction operations.
F. Contractor shall protect the stakes in areas where they are likely to be disturbed or displaced.
Preparation of sub-grade for isolated footings, grade beams, building slabs, walls, and pavements is included
as part of this work.
Excavation and backfill required in conjunction with underground mechanical and electrical utilities, and
buried mechanical and electrical appurtenances is included as work of this section
1.04 DEFINITION:
"Excavation" consists of removal of material encountered to sub-grade elevations indicated and subsequent
disposal of materials removed.
"Fill material consists of an approved soil material being placed upon the surface of an existing ground.
Codes and Standards: Perform excavation work in compliance with applicable requirements of governing
authorities having jurisdiction.
FIELD LABORATORY:
Contractor shall provide field laboratory with a skilled technician, including as a minimum the
following equipment:
- Equipment to execute the CBR (California Bearing Ratio) for roads on filling.
Employ, at Contractor's expense, testing laboratory to perform soil testing and inspection service for quality
control testing during earthwork operations
1. Structural fill - one every 75 cubic meters. (maximum involved structural fill: 10000m).
2. Backfill and sub-base- every 150 cubic meters. (maximum involved backfill and general fill:
20000m3).
3. Road base and sub-base-one every 75 cubic meters.
At least one set of these density tests must be performed on every lift of fill and further
placement shall not be allowed until the required density is achieved.
The number of tests shall be increased, if a visual inspection determines that the moisture
content is not uniform or if the compacting effort is variable and not considered sufficient to
obtain the specified density,
1.07 SUBMITTALS:
Test Reports - Excavation: Submit following reports directly to The Client Representative from the testing
services:
f. One optimum moisture-maximum density Curve for each type of soil encountered.
g. Report of actual unconfined compression strength and/or results of bearing test of each strata tested.
Site Information.
The contractor shall carry out, at his own expense, appropriate tests i.e plate bearing test or other
exploratory operations to determine the ground condition bearing the works capacity, water table depth etc.
prior to commencing the works.
1.09 Existing Utilities: Verify location of existing underground utilities in areas of work. Where utilities
are to remain in place, provide adequate means of support and protection during earthwork operations.
1.010 Should uncharted, or incorrectly charted, piping or other utilities be encountered during excavation,
consult utility owner immediately for directions. Cooperate with Owner and utility companies in keeping
respective services and facilities in operation. Repair damaged utilities to satisfaction of utility owner.
1.011 Do not interrupt existing utilities serving facilities occupied and used by Owner or others, during
occupied hours, except when permitted in writing by The Client Representative and then only after
acceptable temporary services have been provided.
A. Provide minimum of 48 hours notice to the Client Representative, and receive written notice to proceed
before interrupting any utility.
1.012 Use of Explosives: The use of explosives is not permitted.
1.013 Protection of Persons and Property: Barricade open excavations occurring as part of this work and
post with warning lights.
1.014 Operate warning lights as recommended by authorities having jurisdiction.
1.015 Protect structures, utilities, sidewalks, pavements, and other facilities from damage caused by
settlement, lateral movement, undermining, washout and other hazards created by earthwork operations.
0201 EARTHWORK
PART II – PRODUCTS:
2.01 SOIL MATERIALS:
Definitions.
Satisfactory backfill materials below structural members are those classified as A-1-a materials as per
ASTM D-3282.
2.02 Unsatisfactory soil materials are defined as those complying with ASTM, D2487 soil Classification
groups GC, SC, ML, MH, CL, CH, OL, OH and PT.
2.03 Sub-base Material Naturally or artificially graded mixture of natural or crushed gravel, Crushed
stone, crushed slag, natural or crushed sand.
2.04 Backfill and Fill Materials: Satisfactory soil materials free of clay, rock or gravel larger than 100mm
in any dimension, debris, waste materials, vegetable and other deleterious matter.
TABLE 2.04A: SIEVE GRADATION LIMITS FOR SAND BACKFILL:
0201 EARTHWORK
Methods:
a. The Contractor shall receive prior approval from the RC/Client and utilizes methods for placement and
compaction of fill that have been based on the Contractor's proposal.
b. Whether or not specifically indicated in the Contractors description of the approved methods, the
Contractor shall place and compact fill in an orderly manner using equipment maintained in first class
operating condition Prior to compacting, ruts in the surface of any layer shall be filled and leveled.
c. Each layer of backfill material shall be so placed as to maintain adequate drainage and to prevent
accumulation of water.
d. Structure backfill shall be placed in uniform layers and shall be brought up uniformly on all sides of the
structure being backfilled. Within 1.5 m of the sides of a structure, backfill shall be placed in layers not
to exceed 150 mm in un-compacted thickness.
e. Each layer shall be spread uniformly, wetted or dried as required, and rolled with an approved tamping
or power roller Compacting equipment or methods that transmit excessive pressure to the structure
shall not be used.
f. At all times while compacting. vibratory rollers shall be operated within the manufacturer
recommended frequency range for the type of material being compacted and at the optimum operating
frequency.
g. Compaction of unclassified structure backfill by ponding or jetting is not permitted unless recommended
by its Contractor and specifically approved in advance by the Royal Commission
3.0 1 EXCAVATION:
Excavation is Unclassified, and includes excavation to sub-grade elevations indicated regardless of character
of materials and obstructions encountered.
3.0 2 Unauthorized excavation consists of removal of materials beyond indicated sub-grade elevations of
dimensions without specific direction of the Client Representative. Unauthorized excavation, as well as remedial
work directed by the Client Representative, shall be at Contractor's expense.
3.0 3 Under footings, foundation bases, or retaining walls, fill unauthorized excavation by extending indicated
bottom elevation of footing or base to excavation bottom, without altering required top elevation. Lean concrete
fill may be used to bring elevations to proper position, when acceptable to the Client Representative.
3.0 4 Elsewhere, backfill and compact unauthorized excavations as specified for authorized excavations of same
classification unless otherwise directed by The Client Representative.
3.0 5 Additional Excavation: When excavation has reached required sub-grade elevations, notify The Client
Representative who will make an inspection of conditions.
3.0 6 If unsuitable bearing materials are encountered at required sub-grade elevations, carry excavations deeper
and replace excavated materials as directed by The Client Representative.
3.0 7 Stability of Excavations: Slope sides of excavations to comply with local codes and ordinances having
jurisdiction, Shore and brace where sloping is not possible because of space restrictions or stability of material
excavated.
3.0 8 Maintain sides and slopes of excavations in safe condition until completion of backfilling.
3.0 9 Shoning and Bracing: Provide materials for shoring and bracing, such as sheet piling, up rights, stringers and
cross-braces, in good serviceable condition.
3.0 10 Establish requirements for trench shoring and bracing to comply with local codes and authorities having
jurisdiction.
3.0 11 Maintain shoring and bracing in excavations regardless of time period excavations will be open. Carry down
sharing and bracing as excavation progresses.
3.0 12 Dewatering: Prevent surface water and sub-surface or ground water from flowing into excavations and from
flooding project site and surrounding area.
3.0 13 Do not allow water to accumulate in excavations. Remove water to prevent softening of foundation bottoms,
undercutting footings, and soil changes detrimental to stability of subgrades and foundations. Provide and
maintain pumps, well points, sumps, suction and discharge lines, and other dewatering system components
necessary to convey water away from excavations.
3.0 14 Material Storage: Stockpile satisfactory excavated materials where directed, until required for backfill or fill.
Place, grade and shape stockpiles for proper drainage
3.0 15 Locate and retain soil materials and waste materials as herein specified.
3.0 16 Dispose of excess soil materials and waste materials as herein specified.
3.0 17 Excavation for Structures: Conform to elevations and dimensions shown within a tolerance of plus or minus
20mm and extending a sufficient distance from footings and foundations to permit placing and removal of
concrete formwork, installation of services, other construction, and for inspection.
3.0 18 in excavating for footings and foundations, take care not to disturb bottom of excavation Excavate by hand
to final grade just before concrete reinforcement is placed. Trim bottoms to required lines and grades to leave
solid base to receive other work.
3.0 19 Excavation for Pavements' Cut Surface under pavements to comply with cross-sections, elevations and
grades as shown.
3.0 20 Excavation for Trenches Dig trenches to the uniform width required for particular item to be installed,
sufficiently wide to provide ample working room. Provide 150mm to 225mm clearance on both sides of pipe or
conduit.
3.0 21 Excavate trenches to depth indicated or required. Carry depth of trenches for piping to establish indicated
flow lines and invert elevations. Beyond building perimeter, keep bottoms of trenches sufficiently below finish
grade.
3.0 22 For pipes or conduit 125mm or less in nominal size and for flat-bottomed multiple-duct conduit units, do
not excavate beyond indicated depths, Hand excavate bottom cut to accurate elevations and support pipe or
conduit on undisturbed soil.
3.0 23 For pipes or conduit 150mm or larger in nominal size and other mechanical/electrical work Indicated to
receive sub-base, excavate to sub-base depth indicated, or, if not otherwise indicated, to 150mm below the bottom
of work to be supported .
3.0 24 Except as otherwise indicated, excavate for exterior water bearing piping (water and drainage) so top of
piping is not less than 0.6m below finished grade.
3.0 25 Grade bottoms of trenches as indicated, notching under pipe bells to provide solid bearing for entire body of
pipe.
3.0 26 Backfill trenches with concrete where trench excavations pass within 450mm of columns or wall footings
and which are carried below bottom of such footings, or which pass under wall footings. Place concrete to level of
bottom of adjacent footing.
3.0 27 Do not backfill trenches until tests and inspections have been made and backfilling authorized by The
Client Representative. Use care in backfilling or avoid damage or displacement of pipe systems.
3.0 28 For piping or conduit less that 750mm below surface of roadways, provide 100mm thick concrete base slab
support. After installation and testing of piping or conduit, provide minimum 100mm thick encasement (sides
and top) of concrete prior to backfilling or placement of roadway sub-base.
3.0 29 COMPACTION:
General Control soil compaction during construction providing minimum percentage of density specified for
each area classification indicated below.
3.0 30 Percentage of Maximum Density Requirements: Compact soil to not less than the following percentages of
maximum density for soils which exhibit a well-defined moisture density relationship (cohesive soils) determined
in accordance with ASTM D 1557; and not less than the following percentages of relative density, determined in
accordance with ASTM D 2049, for soils which will not exhibit a well-defined moisture-density relationship
(Cohesionless soils).
A. Structures, raft foundation, Building Slabs and Steps, Pavements: Compact top 300mm of sub-grade and
each layer of backfill or fill material at 90% maximum density for cohesive material or 95% relative
density for cohesion less material
Compact top 150mm of sub-grade and each layer of backfill or fill material at 85% maximum density
for cohesive soils and 90% relative density for cohesion less soils.
C. Walkways:
Compact top 150mm of sub-grade and each layer of backfill or fill material at 90% maximum density
for cohesive material or 95% relative density for cohesion less material.
3.0 31 Moisture Control: Where sub-grade or layer of soil material must be moisture conditioned before
compaction, uniformly apply water to surface of sub-grade, or layer of soil material, to prevent free water
appearing on surface during or subsequent to compaction operations.
Remove and replace, or scarify and air dry, soil material that is too wet to permit compaction to specified density.
3.0 32 BACKFILL AND FILL:
General: Place acceptable soil material in layers to required sub-grade elevations, for each area classification listed
below.
A. In excavations, use satisfactory excavated or borrow material.
C. Under walks and pavements, use sub-base material, or satisfactory excavated or borrow material, or
combination of both.
E. Under piping and conduit, use sub-base material where sub-base is indicated under piping or conduit;
shape to fit bottom of cylinder.
3.0 33 Backfill excavations as promptly as work permits, but not until completion of the following:
A. Acceptance of construction below finish grade including, where applicable, damp- proofing, water-
proofing, and perimeter insulation.
B. Inspection, testing, approval, and recording locations of underground utilities.
C. Removal of concrete formwork.
D. Removal of shoring and bracing, and backfilling of voids with satisfactory materials.Cut off temporary
sheet piling driven below bottom of structures and remove in manner to prevent settlement of the
structure or utilities, or leave in place if required.
E. Removal of trash and debris.
F. Permanent or temporary horizontal bracing is in place on horizontally supported walls.
3.0 34 Ground Surface Preparation: Remove vegetation, debris, unsatisfactory soil materials, obstructions, and
deleterious materials from ground surface prior to placement of fills. When existing ground surface has a density
less than that specified under "Compaction" for particular area classification, break up ground surface, pulverize,
moisture-condition to optimum moisture content, and compact to require depth and percentage of maximum
density
3.0 35 Placement and Compaction Place backfill and fill materials in layers not more than 200mm in loose depth
for material compacted by heavy compaction equipment, and not more that 100mm in loose depth for material
compacted by hand-operated tampers
3.0 36 Before compaction, moisten or aerate each layer as necessary to provide optimum moisture content.
Compact each layer to required percentage of maximum dry density or relative dry density for each area
classification. Do not place backfill or fill material on surfaces that are muddy.
3.0 37 Place backfill and fill materials evenly adjacent to structures, piping or conduit to required elevations. Take
care to prevent wedging action of backfill against structures or displacement of piping or conduit by carrying
material uniformly around structure, piping or conduit to approximately same elevation in each lift.
3.0 38 GRADING:
General: Uniformly grade areas within limits of grading under this section, including adjacent transition areas.
Smooth finished surface within specified tolerances, compact with uniform levels or slopes between points where
elevations are indicated, or between such points and existing grades.
3.0 39 Grading outside Building Lines: Grade areas adjacent to building lines to drain away from structures and to
prevent ponding.
3.0 40 Finish surfaces free from irregular surface changes, and as follows:
A. Lawn or Unpaved Areas: Finish areas to receive top soil to within not more that 25mm above or below
required sub-grade elevations.
B. Walks: Shape surface of areas under walks to line, grade and cross-section, with finish surface not more
that 25mm above or below required sub-grade elevation.
C. Pavements: Shape surface of areas under pavement to line, grade and cross section, with finish surface
not more that 10mm above or below required sub-grade elevation.
3.0 41 Grading Surface of Fill under building Slabs: Grade smooth and even, free of voids, compacted as specified,
and to require elevation. Provide final grades within a tolerance of 10mm when tested with a 3m straight edge.
3.0 42 Compaction: After grading, compact sub-grade surfaces to the depth and indicated percentage of maximum
or relative density for area classification.
3.0 43 PAVEMENT SUB-BASE COURSE:
General: Sub-base course consists of placing sub-base material, in layers of specified thickness, over sub-grade
surface to support a pavement base course
3.0 44 Grade Control: During construction, maintain lines and grades including crown and cross-slope of sub-base
course.
3.0 45 Shoulders' Place shoulders along edges of sub-base course to prevent lateral movement. Construct shoulders
of acceptable soil materials, placed in such quantity to compact to thickness of each sub-base course layer.
Compact and roll at least a 300mm) width of shoulder simultaneously with compacting and rolling of each layer
of sub-base course.
3.0 46 Placing: Place sub-base course material on prepared sub-grade in layers of uniform thickness, conforming to
indicate cross-section and thickness. Maintain optimum moisture content for compacting sub-base material
during placement operations.
3.0 47 When compacted sub-base course is shown to be 150mm thick or less, place material in a single layer.
When shown to be more that 150mm thick, place material in equal layers, except no single layer more than
150mm or less than 75mm in thickness when compacted.
General: Sub-base course consists of placement of sub-base material in layers of indicated thickness, over sub-
grade surface to support concrete building slabs.
3.0 49 Placing: Place sub-base material on prepared sub-grade in layers of uniform thickness conforming to
indicated cross-section and thickness. Maintain optimum moisture content for compacting material during
placement operations.
3.0 50 When a compacted sub-base course is shown to be 150mm thick or less place material in a single layer.
When shown to be more than 150mm thick, place material in equal layers, except no single layer more than
150mm or less than 75mm in thickness when compacted.
Quality Control Testing during Construction: Allow testing services to inspect and approve sub-grades and fill
layers before further construction work is performed.
3.0 52 Perform Field density tests in accordance with ASTM D 1556 (sand cone method) or ASTM D 2167
(rubber balloon method), as applicable.
A. Footing Sub-grade: For each strata of soil on which footings will be placed, conduct at least one test to verify
required design bearing capacities. Subsequent verfication and approval of each footing sub-grade may be
based on a visual comparison of each sub-grade with related tested strata, when acceptable to The Client
Representative.
B. Paved Areas and Building Slab sub-grade: Make at least one field density test of subgrade for each 2008q.m
of paved area or building slab, but in no case less than 3 tests. In each compacted fill layer, make one field
density test for every 2008q.m of over-laying building slab or paved area, but in no case less than 3 tests.
C. Foundation Wall Backfilt: "Take at least 2 field density tests, at locations and elevations as directed.
If in opinion of The Client Representative, based on testing service reports and inspection, sub-grade or fills
which have been placed are below specified density, provide additional compaction and testing at no
additional expense
3.0 53 MAINTENANCE:
Protection of Graded Areas: Protect newly graded areas from traffic and corrosion Keep free of trash and debris.
Repair and re-establish grades in settled, eroded, and rutted areas to specified tolerances.
3.0 54 Reconditioning Compacted Areas: Where completed compacted areas are disturbed by subsequent
construction operations or adverse weather, scarify surface, re-shape and compact to required density prior to
further construction.
3.0 55 Settling: Where settling is measurable or observable at excavated areas during general project warranty
period, remove surface (pavement, lawn or other finish), add backfill material, compact, and replace surface
treatment. Restore appearance, quality, and condition of surface or finish to match adjacent work, and eliminate
evidence of restoration to greatest extent possible.
3.0 56 DISPOSAL OF EXCESS AND WASTE MATERIALS:
Remove excess excavated material, trash, debris and waste materials and dispose of it off Owner's as approved by
the Client representative.
3. See Section 0501 - Steel rectangular hollow sections and small sections structural steel.
4. See Section 0701 - Waterproofing and damp proofing vapour barrier for slabs.
The codes and standards which are generally appli cable to the Work of the Section are listed hereinafter.
A. AASHTO American Association of State Highway and Transportation Officials.
T-193 The California Bearing ratio (as modified by ASTM D 1983).
B. ASTM American Society For Testing & Materials
C. 131 Resistance to Abrasion of Small size Coarse Aggregate by Use of the Los Angeles Machine. Test for,
C-136 Sieve or Screen Analysis of Fine and Coarse Aggregates.
D-422 Particle-Size Analysis of Soils.
0-423 Liquid Limit of Soils, Test for,
D-424 Plastic Limit and Plasticity Index of Soils, Test for,
D-1140 Amount of Material in Soils finer than the No. 200 (75 micron) Sieve, Test for,
D-1557 Moisture-Density Relations of Soils Using 10 lb. (4.5kg) Rammer and 18 inch (457 mm) Drop.
Test for
D-1883 Bearing Ratio of Laboratory-Compacted Soils, Test for,
D-2217 Wet Preparation of Soil Samples for Particle-Size Analysis and Determination of Soil constants.
D-2844 Resistance R-Value and Expansion Pressure of Compacted Soils, Test for,
D-2922 Density of Soil and Soil-Aggregate in Place by Site Radiology (Shallow Depth) Tests for.
1.04 QUALITY CONTROL:
A. The Contractor shall be responsible for the quality of all work and material to be used in the Work and
shall propose a prograrn for inspection and testing, such as to achieve the specified quality, in
accordance with Section 0102, "QUALITY CONTROL".
The Contractor shall have all necessary tests performed and submit its findings in a report form to the
Client Representative for review and approval prior to the transportation of materials to the site.
B. The Contractor shall perform all specified testing on the existing subgrade and on the subbase and
roadbase materials placed under this Contract. The test results for each type of material and the
Contractors recommendations shall be submitted in a report form to the Client Representative for
review.
Approval by the Client Representative of each report will be required prior to proceeding with the
construction of a subsequent material.
0203 RAVEMENT SUB- BASE AND AGGREGATE BASE
PART II - MATERIALS:
A. General:
All goods and products covered by these specifications shall be procured, when available from an in-
Kingdom manufacturer. Procurement of all goods and products manufactured out-of-Kingdom must be
approved by the Client Representative.
B. Gradation Requirements:
Subbase material shall be tested in accordance with ASTM D 422 and D- 2217 and grading shall be
within the limits as shown in Table 2.01B.
The Contractor shall demonstrate compliance with this Subsection before the material to site.
TABLE 2.01B - SUBBASE GRADING LIMITATIONS:
Parameter Limit
ASTM Ref. Frequency of
Testing
2.02 ROADBASE:
A. Roadbase shall be a mixture of crushed gravel and sand with natural sand and filler suitable binding
quality blended such that it can be readily compacted at optimum moistu conditions to form a firm and
stable pavement course.
B. Gradation Requirements:
Road base material when tested in accordance with ASTM D-2217 and ASTM C-136, she be within the
limits shown in Table 2.02B.
Additionally, not less than 10% shall be retained between each pair of successive sie sizes as specified in
Table2.02C, excluding the largest pair. The Contractor is permitted reduce the percentage larger than
37.5mm to zero if level control or segregation problematic and as approved by the Client
Representative. The Contractor sh demonstrate compliance with this subsection before delivery of the
material to site.
TABLE 2.02B - ROADBASE GRADING LIMITATIONS:
%Passing by Weight
Selve Size
Mix Design Plant Mix Tolerance
63 mm 100 Nil
37.5 mm 90-100 +6%
19mm 50-80 +8%
9.5mm 40-70 +8%
4.75mm 30-60 +7%
600micron 10-25 +5%
75micron 3-10 +3%
C. Classification and Performance Requirements shall be in accordance with Table 2.03C.Soaked CBR
testing is an alternative for use only with Client Representative written approval.
Parameter Limit
ASTM Ref. Frequency of
Testing
25 Max
Liquid Limit D-4318 Daily
2.01 MATERIALS:
General:
A. All goods and products covered by these specifications shall be procured from an in Kingdom
manufacturer when available (manufacturer: NEPRO or approval equal).
B. All pipes shall be of pressure class and diameters as shown on the drawings and all cables and
conduits shall be of size shown on the drawings
PPR Type 3, Sch. 80, Din 8062 & ISO 161/1 Class 5.
2.03 Sanitary Sewer plpe and Fittings:
Polyvinyl Chloride (PVC) SASO-14 & 15, Sch. 40, Din 8062 & ISO 161/1, with elastomeric ring joints.
2.04 Gate valves shall conform to ANSI / AWWA C500, solid wedge disc, non-rising stem, for
underground service, pressure rated to 14kgim. end connection shall be compatible with the pipe joints
selected.
2.05 Valve boxes shall be precast or cat in-situ concrete with cast iron cover and frame.
2.06 Manhole covers shall be Gray Iron confirming to ASTM A48M, Class 25B.
2.07 Underground Electrical Conduits:
A. These conduits should be uPVC schedule 40 and sizes as shown in the electrical drawings. On the
path of cable markers are to be places for identification.
B. All Saudi Electricity Company - Eastern operating area (SEC-EOA) direct interface work, shall be
done with SEC - EOA prior approval and in strict accordance with SEC-EOA standards.
C. Low voltage power cables shall be installed in underground conduits as specified in the drawings.
D. The minimum burial depths to the top of electrical conduits shall be as specified in articles 300 and
310 of NEC.
E. Upon completion of installation and prior to final acceptance, each component of every system shall
be tested to the satisfaction of the customer and/ or his representative.
F. The contractor shall provide all test instruments, equipment and accessories necessary for
demonstration and putting the equipment into operation before commissioning. All testing
equipment shall be calibrated by approved authorities.
G. Special care shall be taken during field testing including the safety of personnel and test apparatus,
wiresi cables and their accessories from injuries and damages.
A. Water pipe shall be installed to the design lines and grades and in accordance with the
manufacturer's recommendations.
B. Water lines shall not cross below sanitary sewer lines. Vertical clearances shall be minimum
600mm. All water line joints shall be at least 1.0m away from the Sewer line and water pipe shall be
cut as necessary to provide this clearance. Water lines shall not parallel sanitary sewers with less
than 3m horizontal spacing. All pipe ends shall be capped and protected until ready for final
connections The pipe separation to be follow as per Royal commission plumbing code standards or
approval equal.
C. PPR Type 3 water pipe shall be installed in accordance with ASTM D2774 and applicable portions
of ASTM D2321.
D. Concrete thrust blocks shall be placed at all changes of alignment and shall be as per detail
drawing.
E. The water system shall include isolating and air relief valves as required.
B. Horizontal Separation:
1. A minimum horizontal separation of 3 m shall be maintained between potable water supply lines
and sewer lines, except when bottom of water pipe is at least 500 mm above the top of the sewer
pipe, in which case a 2 m minimum horizontal spacing will be permitted.
2. Water lines under the building shall be at least 300 mm (12 in.) above the top of the drainage or
waste water line or appurtenance and be placed on a solid shelf excavated at one side of the trench.
Underground pipes shall be designed to provide a minimum of 1.2 m earth cover over the pipes where this
cover cannot be achieved; pipes shall be encased in concrete.
3.05 Testing:
A. Water Pipe:
All piping systems shall be field tested hydrostatically at 10 Bars pressure for leakage in the presence of the
authorizing inspector before backfilling is done all to the client approval.
B. Sewage Pipe: The Sewer pipe shall be tested in sections as approved. Pipe below ground water level shall
be tested by measuring infiltration. Pipe above ground water level shall be tested by measuring leakage
The section to be tested shall be filled with water up to the maximum head available as controlled by
manhole or cleanout, but not less than 3 meters. Leakage shall be measured by the amount of water
required to keep the test section full under the specified head for twenty four hours, after a presoak
period of 4 hours.
3.06 DISINFECTION:
When the entire water system, including valves, fittings and allied work has been installed and tested, it shall
be disinfected by the procedures of AWWA C651. After final flushing and before the system is placed in
service, water samples shall be collected from the system at approved sources and tested for bacteriological
quality in accordance with Section 9 of AWWA C651. If the initial samples fail to meet the requirements,
disinfection of the system shall be repeated until satisfactory samples are obtained.
3.07 IDENTIFICATION:
All manholes, valve boxes, pits etc, shall have approved identification markings.
For all underground utilities approved plastic identification tapes should be laid at a depth of 300mm below
finished grade elevation during backfilling.
=== End of Section ===
0205 PRE-CONSTRUCTION TERMITE CONTOROL
PARTI – GENERAL:
1.0 3 SUBMITTALS:
A. Submit for review and approval to Client the following items before procurement:
1. All manufacturer's test reports as well as certificate of compliance to the specification, reference
codes and standards.
2. Sample of materials.
3. Complete catalog data for all Termiticides and equipment required.
4. Shop drawings as required for effective placement of treatment on all horizontal & vertical areas.
The use of the product prevents and controls termite infestations in and around structures and
constructions.
To meet the criteria, procedure and execution has been given for permethrin Dragent FT. for any other
termiticide, proper execution procedure per manufacturer's recommendations should be got approved before
execution.
Effective pre-construction subterranean termite control is achieved by the establishment of vertical and/or
horizontal insecticidal barriers using 0 5%, 1.0% emulsion of Dragnet FT. to meet lermite proofing
requirements follow the procedures in the latest edition of the Housing and Urban Development Minimum
Property Standards (refer to U.S.D.A home and Garden Bulletin No 64).
Horizontal Barriers: create a horizontal barrier wherever treated soil will be covered, such as footing
trenches, slab floors, carports, and the soil beneath stairs and crawlspaces.
To produce a horizontal insecticide barrier, apply the emulsion at the rate of 1 gallon per 10 square feet to
fill soil. If fill is washed gravel or other coarse material, apply at 1.5 gallons of emulsion per 10 square feet, so
that the emulsion will reach the soil beneath the fill.
Applications shall be made by a low pressure spray (less than 50p.s.i.) using a coarse spray nozzle. If slab
will not be poured the same day as treatment, cover treated soil with a water-proof barrier such as
polyethylene sheeting. This is not necessary if foundation walls have been installed around the treated soil.
Vertical Barriers: vertical barriers should be established in areas such as around the base of foundations,
plumbing, utility entrances, back filled soil against foundation walls and other critical areas.
To produce a vertical barrier in soil, apply the emulsion at a rate of 4 gallons of emulsion per 10 linear feet
per foot of depth. Distribute the treatment as evenly as possible
a. When rodding or trenching. It is important that emulsion reaches the top of the footing, Rod Holes
should be spaced to provide a continuous insecticidal barrier.
b. Care should be taken to avoid soil wash-out around the footing.
c. Trenches need not be wider than 6 inches. Emulsion should be mixed with the soil as it is being
replaced in the trench.
d. For a monolithic slab, an inside vertical barrier may not be required Hollow block voids may be
treated at a rate of 2 gallons of emulsion per 10 linear feet, so that the emulsion will reach the top
of the footing.
Apply manufacturer's required cleaning methods, as specified and approved under Section 1.03, submittals.
3.03 TESTING:
Required tests shall be done as specified and approved under Section 1.03, submittals.
===End of Section ===
0206 INTERLOCK CONCRETE PAVER BLOCK
PARTI – GENERAL:
A. The work includes ground preparation which require cutting or filling and compaction to the lines and
grades shown on the drawings and approval by the Client Representative. Placing of pavers shall be on
mortar setting bed over reinforced concrete slab on compacted ground.
1.0 4 SUBMITTALS:
A. Submit under provisions specified in the Client Contract Documents.
B. Shop Drawings Indicate layout of interlock concrete paver block, dimensions of paved areas, elevations,
and effected adjacent construction.
C. Product Data: Provide characteristics of paver unit, dimensions, and special shapes.
D. Samples Submit two samples of each paver size, illustrating style, size, color range and Surface texture of
units being provided for Client approval prior to ordering product.
E. Manufacturer's Installation Instructions :Indicate substrate requirements and .installation methods.
PART 2 – PRODUCTS:
2.01 PAVER MATERIALS:
A. Interlock Concrete Paver block. Pavers with shape and color subject to the approval of Client
representative.
B. Recycled Content of Products: Provide products with an average recycled content so postconsumer
recycled content plus on-half of preconsumer recycled content in not less than 30 percent.
C. Regional Materials: Provide materials that are extracted, processed and manufactured within 500
miles/800km from the project site.
2.02 BEDDING:
A. Mortar setting bed type specified in section 0400.
B. Reinforced concrete cast-in-place type as specified in section 0301.
PART 3 – EXECUTION:
3.01 EXAMINATION:
A. Verify substrate conditions under provisions of Section 0201-Earthwork.
B. Verify that substrate is level, smooth, capable of supporting pavers and mortar and concrete bedding
imposed loads, and ready to receive work of this Section.
C. Verify gradients and final elevations including substrate base are correct
3.02 INSTALLATION:
A. The sub grade or select fill shall be shaped to lines, grades and sections and compacted to not less than
95% of the maximum dry density as per ASTM D-1557.
B. After the sugared or select fill preparation had been completed, with all the curbs and forms already set
to the lines and elevations as shown on the drawings and has been approved by the Client
Representative, the area is now ready to receive the cast-in-place reinforced concrete slab bedding.
C. Interlock /Mosaic tile pavers shall be laid on a 2.0 cm thick (minimum) mortar setting bed above
reinforced concrete slab. The pavers finish surface levels shall be as specified on the drawings
A. This Section covers the furnishing and installation of curbs at the locations and to the lines, grades,
details and dimensions as shown on the Contract Drawings and approval by Client Representative.
B. The Contractor shall provide all material, labor, tools, equipment and other incidentals as required to
complete the work in accordance with the Contract Requirements.
1.0 2 REFERENCES:
A. The referred codes and standards are intended to provide an acceptable level of quality for materials,
products and workmanship. In case of conflict between these standards and the text of this Specification,
the Specification text shall govern.
B. The latest revision of the referred codes and standards shall be used wherever applicable. In case of
conflict, the Contractor shall propose equipment, materials and processes conforming to one group of
codes and standards.
C. The codes and standards generally applicable to the work.
D. MOT - Ministry of Transportation, Kingdom of Saudi Arabia.
1.0 3 SUBMITTALS:
A. Submit under provisions specified in the Client Contract Documents.
B. Shop Drawings Indicate dimensions of curbs, elevations, and effected adjacent construction.
C. Product Data: Provide characteristics of curbs unit, dimensions, and special shapes.
D. Samples: Submit two samples of each curb size, illustrating style, size, And color range, for Client
approval prior to ordering product.
E. Manufacturer's Installation Instructions. Indicate substrate requirements and installation methods
The Granular Base shall be the same material as the aggregate base course of the asphalt road pavement
extended 100 mm at the concrete base of the curb as shown on details.
PART 3 – EXECUTION:
3.05 EXAMINATION AND PREPARATION:
A. Verity base conditions under provisions of the Client Contract Documents.
B. Verity base had been completed, inspected, tested and accepted.
C. Verify gradients and elevations of base are correct as per approved drawings.
D. Notify Client Representative, a minimum of 24 hours prior to commence concreting operation.
3.02 CURB CONCRETE PLACEMENT AND FINISHING:
A. Formed Curb:
Concrete shall be placed to the section required in a single lift. Consolidation shall be achieved by using
approved mechanical vibrators.
B. Concrete Finishing:
Exposed surfaces shall be floated and finished with a smooth wood float until true to grade and section
and uniform in texture. Floated surfaces shall then be brushed with a fine-hair brush with longitudinal
strokes The top of the curb shall be rounded with an edging tool to a radius of 13 mm (V2 inch)
Immediately after removing the front curb form, the face of the curb shall be rubbed with a wood or
concrete rubbing block and water until blemishes, form marks, and tool marks have been removed. The
front curb surface, while still wet, shall be brushed in the same manner as the curb top.
C. Joint Finishing:
Curb edges at formed joints shall be finished as indicated.
D. Surface and Thickness Tolerances:
Finished surfaces shall not vary more than 6.4 mm from the testing edge of a 3.05 m straight edge.
The Contractor shall perform the inspection and tests described and meet specified the requirements for
inspection details and frequency of testing.
PARTI – GENERAL:
1.0 1 DESCRIPTION:
A. The Contractor shall submit details of the preparation of landscaped areas with furnish all labor,
materials, tools and equipment necessary to complete and maintain the work as indicated on the
Drawings.
B. Work to be performed and supervised at all times by qualified personnel.
PART 2 – PRODUCTS:
2.0 1 SOIL MATERIALS:
A. Sand for soil mixes shall be obtained from approved borrow sources. It shall conform to the
following physical and chemical characteristics.
1. Physical Characteristic:
Material passing a No. 10 sieve : 100%
Material passing a No. 35 sieve : 90 - 100%
Material passing a No. 140 sieve: 0-10%
Material passing a No. 270 sieve: 0-3%
2. Chemical Characteristics:
Salinity (ECe x 10) : less than 2
SAR (Sodium Absorption Ration) : less than 1
Boron (saturation extract):less than 0.5 ppm
Рн : less than 8.5
B. Soil organic amendment shall be sphagnum moss with the following chemical and physical
characteristics:
1. Physical Characteristics:
2. Chemical Characteristics:
Organic Matter :95 - 98% weight
pH :35 - 4.5
Total Nitrogen :0.9 -2.0% weight (dry)
Ash :1-3% by weight
Exchange capacity : 100 - 150 mval/100g
organic matter (dry)
C. The Contractor shall provide fertilizers as indicated below for soil mixes:
1. Soil Mixes:
A. For outside use.
1. Single superphosphate, Ca(H2PO2)-HO with guaranteed analysis of 20% P205 (0-20-
0) granular form.
2. Potassium nitrite, KNO with guaranteed analysis of 13% Nitrogen and 44% K20. (13-
0 44), powder form.
3. Soil sulphur, S, 99% sulphur content with 100% passing a 16 mesh screen and 50%
passing a 100 mesh screen.
4. Dolomite, CaCO3MgCO3, with 100% calcium carbonate equivalency Kasiser AG-65
or approved equal
B. For indoor use.
1. 25% sand, 25% peat moss, 25% potting sail 25% vermiculite.
2. Tree and Shrub Pits.
Slow release fertilizer tablets weighing 21 grams each, shall be provided. tightly
compressed, long lasting (two years continuous), and with guaranteed analysis of (20-
10-5) plus Fe, Mn, Zn in chelated form.
3. The Contractor shall furnish a certificate of compliance stating that materials
delivered meet the Specification.
C. Soil Amendments.
1. Expanded horticultural vermiculite shall be grade No. 3 and shali meet the following
requirements:
a. Color-Brown
i. Water retention % by weight-530 00.
ii. Bulk density - 80.1 to 1442 kg/m3.
iii. Particle size range - 0.1 to 2.4mm air porosity % -24 to 44.
iv. Caution exchange capacity (me/100g)-approx 75.
b. Extractable concentrations of Nutrients from vermiculite in (ppm).
P Soluble Salts Mmhos/cm NO3 NH4 P K Ca Mg Fe 6 0.03 0 0 0.10 3.99 0.65
0.71 0.27
2. Provide other amendments as required by the soil test analysis.
D. Depth of Soil.
The depth of soil will be as follows: Lawn & Ground cover =30 cm.
Shrubs & Succulent =80cm.
Trees = 120-150cm.
Date Palm = 200-250cm.
2.0 2 INSPECTION:
A. The Client representative has the right to reject unsatisfactory or defective material at any time
during the progress of the work.
2.0 3 PREPARATION OF SOIL MIXES:
A. The soil mixes shall be in the quantities or proportions as indicated below according to the
procedures outlined and amended as necessary by any required soil analysis
1. Soil Mix-A (Date palmi Trees/Shrubs/Ground Cover! succulent Vines) Ingredients:
Sand - 80% by volume
Sphagnum Moss - 10% by volume
Vermiculite - 10% by volume
Single super phosphate - 1 kg/m3
Soil sulphur - 1 kg/m3
2. Soil Mix-B (Pots/Planters) Ingredients:
Sand - 25% by volume
Sphagnum Moss - 50% by volume
Vermiculite - 25% by volume
Single super phosphate - 05 kg/m3
Potassium Nitrate - 0.3 kg/m3
Dolomite - 03 Kgim3
3. Soil-Mix-C(Date Palm Trees/Shrubs/Ground Cover/ Succulent Vines/Planters)
Red Dune Sand (Khurais) -69% by volume.
Imported Organic Soil -35% by volume
Wadis Soil -5% by volume.
Single superphosphate - 1 kg kg/m3
Soil sulphur - 1 kg/m3.
B. In the event that the soil mixes are above a pH of 7.5 the sand portion of the mix shall be amended
with suitable additives (soil, sulphur, sulphuric acid, etc.) to bring the resultant soil mixes into the
specified range of 6.5 to 7.5. Such additives shall be added to the sand prior to addition of the
organic amendment or fertilizer. After adding such additives the sand shall be kept moist for a
minimum of 30 days and then leached with landscape irrigation water to bring the salinity, SAR,
PH and Boron of the resultant mix within the ranges indicated above.
C. Three trial lots of 1m' each for both mixes shall be prepared by the Contractor prior to the start of
full soil mixing operations. Samples of these trials shall be submitted for analysis as described. The
analysis shall include specific recommendations for changes in the soil mix formulations. The
Contractor shall submit such analysis and recommendations and shall make adjustments to the Soil
mix as directed by the Client representative after approval the Contractor may begin the full soilt
mixing operations.
PART 3 – EXECUTION:
1.0 1 DESCRIPTION:
This section, governs for furnishing, fabrication and placing of all reinforcing steel bars, welded wire fabrics,
including chairs, ties, splicing devices, and other reinforcing accessories required to complete all types of
concrete work for the projects.
1.0 2 RELATED DOCUMENTS:
Section 0302 - Concrete Work
1.0 4 SUBMITTALS:
The Contractor shall submit samples and manufacturer's certificates of the compliance, for
Owner/Consultant approval.
Note: Prior to start of work, the contractor shall prepare and submit bar bending schedule, all in accordance with the
relevant cod for approval of the Consultant.
Wall Panels: 20 mm exposed to weather nor earth. 20 mm not exposed to weather nor earth.
Other: 40 mm exposed to weather nor earth. 40 mm not exposed to weather nor earth.
D. Future Extension:
Exposed reinforcement and inserts which are intended for bonding with future extensions
shall be protected from corrosion by embedding it into grouted cells of concrete masonry
or into lean concrete (20 N/mm') as shown on the drawings where applicable.
=== End of Section ===
0302 CONCRETE WORK
PARTI – GENERAL
1.0 1 DESCRIPTION:
A. General:
This section covers furnish and install of concrete work (cast-in-situ and pre-cast) where applicable:
B. Related Works Specified Elsewhere:
1. Section 0102 - Quality Control.
2. Section 0301 - Concrete Reinforcement.
3. Section 0701 - Waterproofing and Damp Proofing, Vapour Barrier for Slabs.
1.0 2 QUALITY ASSURANCE:
1. Codes and Standards:
Comply with the provision of following codes, specifications and standards except as otherwise specified.
a. ACI 117 "Standard Specification for Tolerances for Concrete Construction and Material.
b. ASTM C172" Standard Practice for Sampling Freshly Mixed Concrete C).
c. ACI 301 "Specification for Structural Concrete for Buildings".
d. ACI 315 "Manual of Standard Practice for detailing Reinforced Concrete Structures.
e. ACI 318 "Building Code Requirements for Reinforced Concrete".
f. ACI 347 "Recommended Practice for Concrete Formwork”.
g. ACI 305 "Recommended Practice for Hot Weather Concreting".
h. PCI (Pre-cast & Pre-stressed Concrete) Institute, 4th Edition – 92.
i. PCI Journal & PCI Committee Reports.
j. ASTM C173M" Standard Test Method for Air Content of Freshly Mixed Concrete by the
volumetric Method.
2. Workmanship:
a. The Contractor is responsible for correction of concrete work which does not conform to the
specified requirements including strength, tolerances and finishes. Correct deficient concrete as per
Consultant approved repair procedures.
b. Maintain procedures and conditions for quality control which are equivalent to plant production
for precast panels.
3. Tolerances:
1. Erection tolerances/variations:
a. Variations from plumb: 6 mm in any 6096 mm run or storey height: 13 mm total in any 12192
mm or longer run.
b. Variations from level or elevation 6 mm in any 6096 mm run, 13 mm in any 12192 mm run.
c. Variations from theoretical position in plan: plus or minus 6 mm maximum at any locations.
d. Offsets in alignment of adjacent members at any joint: 1.5 mm in any 3048 mm run, 6 mm
maximum.
2. Allowable Casting Tolerance as per PCI Design Handbook:
LOCATOIN TOLERANCE PRECAST ELMENT KEY
Length + 12 mm 6.7.8.9.03
+ 19mm 3.5 1=Double Tee
+ 25 mm 1.2.4.11.12 2=Sing Tee
Width + 6 mm 1.2.3.5.6.8.9.12 3=Bldg.beam rect& Ledger
+ 9mm 4 4=l-beam
+ 9mm 11.13 5= Box Beam
Depth + 6mm-3 mm 10 6= Column
+ 6mm 1.2.3.5.6.7.8.9.12 7=Hollow Core Slab
+ 12mm-6 mm 4 =8 Ribbed wall panel
+ 9mm 11 9= insulated wall panel
+ 12mm 13 10=Archit wall panel
Flange of + 6mm-3 mm 1.2.8.10.12 11=Pile
thickness
+ 6mm 3.4.13 12= Joist
Web thickness + 3mm 1.8.10.12 13= step unit
+ 6mm 2.3
+ 9 mm-6 4
Mm
+ 9 mm 5
Position of + 6mm 1.2.3.4.5.6.8.9.11.12
tendons
+ 3 mm 10
Camber, variation + 6mm per3 m 1.2.12
from design
+ 19 mm max
+ 3mmper3m
+ 25 mm max 4
+ 19 mm max 3
+ 12 m max 5
Camber,Differntia + 6 mm per 3m 1.2.5
l
+ 19 mm max 1.2.3.12
+ 16 mm 4
Beaning plates, +3 1.2.3.4.12
Tipping,
Flushness
4. Concrete Testing Services:
a. Contractor shall employ at his own expense independent testing laboratory for mix design and
testing requirements and the timely submission of results to the Consultant for review.
b. Materials and installed work may require testing and re-testing, as directed by the Consultant,
at any time during the progress of the work. Tests to be done at the Contractor's expense,
including re-testing of rejected materials and installed work.
1.0 3 SUBMITTALS:
1. Product Data:
Submit a copy of manufacturer's/suppliers specifications with application and installation
instructions for proprietary materials and items, including reinforcement and forming accessories,
admixtures, patching compounds, Mix design Data, water stops if required, joint systems, methods
statement and any others requested by the Consultant
2. Laboratory Test Reports:
Submit one copy of laboratory test reports for cast in-situ & pre-cast concrete materials and mix
design test as specified.
3. Method statement and site testing procedures:
The Contractor shall submit to the client the method statement and site
Testing procedures anf get approval before commencing work.
Proportion and design mixes to result in concrete slump at the point of placement as follows:
1. Ramps and sloping surfaces: 100 mm (+/-25mm).
2. Reinforced foundation systems: 100mm (+/-25mm).
3. All other concrete including pre-cast concrete: Not less than 25 mm and not more than 102 mm.
3.02 FORMS:
Note: Contractor shall obtain approval of the methods and material proposed for form works for various type of
forms: a) Temporary, b) Permanent, c) Rough and d) fine form works.
A. Design, erect, support, brace and maintain formwork to support vertical and lateral loads that might be
applied until such loads can be supported by the concrete structure.
B. Design formwork to be readily removable without impact, shock or damage to cast-in place concrete
surface and adjacent member.
C. Chamfer exposed corners and edges using wood, metal, PVC or rubber chamfer strips fabricated to
produce uniform smooth lines and tight edge joints.
D. Provide openings in concrete formwork to accommodate work of other sections (plumbing, mechanical
and electrical work) using sleeve pipes etc.
3.04 JOINTS:
A. Construction Joints Locate and install construction joints as required, so as not to impair the strength
and appearance of the structure.
1. Provide key ways at least 38 mm depth in all construction joints in walls, slabs and between
walls and footings.
2. Place construction joints perpendicular to the main reinforcement except as indicated
otherwise, continue all reinforcement across construction joints.
Water Stops: If required, provide water stops in construction joints as shown on drawings.
Install water stops to form a continuous diaphram in each joint.
Set and build into the work anchorage devices and other embedded items required for other work that is
attached to, or supported by, cast-in-place, or pre-cast concrete, use setting drawings, diagrams, instructions
and directions provided by supplier of the items to be attached thereto.
Any defective work discovered after form removal to be repaired and replaced immediately at Contractor's
expense.
The Contractor shall at all times incorporate methods that will minimise the cause of requiring future
concrete repairs due to construction.
Main causes are surface air voids, sand streaking, peeling and blistering.
Prepackaged cementations repair shall be mixed and used as per manufacturer's recommendations. Fins shall
be neatly removed from exposed surface.
3. Fine Aggregates: 2 1 to 3 times the sum of volume of cement and lime materials.
4
4. Coarse Aggregates: 1 to 2 times the sum of volume of cement and lime materials.
3. The sum of volumes of fine and coarse aggregates shall not exceed 4. times the sum of
volumes of cement and lime materials.
4. Cement Setting Bed:
a. Combine 1 part of portland cement with 2 parts of damp setting bed sand. Use water to
dampen sand (if required), but water shall not be added to the mix.
5. Grout for Masonry Bond Beams and Lintels
a. Portland cement, fine aggregate, coarse aggregate, and water are proportioned to
provide a 28-day compressive strength of 14 MPa, and in conformance with
ASTM C109.
6. Air-entraining agents or other admixtures shall not be added to grout materials,
except when approved by to the Royal Commission.
7. Calcium chloride is not permitted in grout mix.
Note: Grout: Include ancillary itens Damp proof, wall ties, joint filers, fire resistance requirement, sealant and
anchors, etc.
C 1 : Construction tolerances:
The Contractor shall erect masonry within the following tolerances from the specified dimensions:
1. Dimension of Elements:
a. Variation from Plumb.
b. True to a Line.
c. Alignment of Columns and walls(bottom versus top.
2. Location of Elements:
a. Indicated in Plan.
b. Indicated in Elevation.
a. In cross section or elevation: - 6 mm, + 13 mm.
3. Elements:
a. Variation from Level.
1. Bed joints: 16 mm in 3 m, + 13 mm max.
2. Top Surface of Bearing walls: + 6 mm in 3 m, +13 mm max.
+ 6 mm in 3 m; + 9 mm in 6 m;
+13 mm max
+6 mm in 3 m: 9 mm in 6 m;
+ 13 mm max
+13 mm for bearing walls
+19 mm for non-bearing walls
+ 13 mm in 6 m; 119 mm max.
+ 6mm in storey height; 19 mm max
D. Masonry Reinforcement:
1. Horizontal and vertical reinforcement in walls shall be placed as indicated on drawings.
2. All cells at corners, edges or at intersecting walls, and all cells adjacent openings shall contain
reinforcing.
3. Reinforcement shall be continuous except at thermal control joints. Laps to be provided as
necessary. See Section 0301 "Concrete Reinforcement" Clause 3.01A2. All reinforcement shall be in
place prior to grouting.
4. The minimum cover over reinforcement of mortar, masonry and grout, treated as a homogeneous
material shall be as required by Section 0301 "Concrete Reinforcement" Clause 3.01C8.
Note: External joinery or metal works bedded against block works / concrete are to be painted with approved silicon
sealant or as appropriate local specification.
0501 Steel Rectangular Hollow Sections and Small Sections Structural Steel.
0601 STEEL RECTANGULAR HOLLOW SECTIONS AND SMALL SECTION STRUCTURAL
STEEL:
PARTI – GENERAL:
1.0 1 DESCRIPTION:
Work Included:
Supply and Install all ornamental stair and balcony rails, supports etc. as shown on the drawings and as
specified herein.
1.0 3 SUBMITTALS:
A. Samples and workshop drawings showing elevation and details of fixing. Junctions etc for approval by
the owner.
1.0 4 PRODUCT HANDLING:
A. Protection: Use all means necessary to protect the materials of this Section before, during and after
installation and to protect the work and materials of all other trades.
B. Replacements: in the event of damage, immediately make all repairs and replacements necessary to the
approval of the Client and at no additional cost to the Client.
C. Storage: If the manufactured steel items are stored prior to erection, store in straight and horizontal
position, avoiding any contact with the ground. Protect carefully from weather and from excessive
exposure.
0501 STEEL RECTANGULAR HOLLOW SECTIONS AND SMALL SECTION
STRUCTURAL
STEEL:
PART II – PRODUCTS:
2.01 STEEL FABRICATION:
A. Ali steel used in manufacture shall be free from blemish and heavy rust prior to fabrication and
painting.
B. Where shown or indicated all steel assemblies shall be galvanized by hot dip process after all
fabrication and welding has been completed. Take care to avoid distortion and accurately straighten
members where necessary before delivery to job-site. All bolts and other fastenings shall be galvanized
by hot dipping and threads shall be specially cut to avoid binding.
All other materials, not specifically described but required for a complete and prope installation of the work
of this Section, shall be selected by the Contractor subject to and in accordance with accepted engineering
practice and the approval of the Architect.
3.01 INSTALLATION:
A. Inspection: Examine the areas and conditions under which work of this Section will be installed.
Incorrect conditions detrimental to the proper and timely completion of the Work. Do not proceed until
unsatisfactory conditions have been corrected.
B. Erection:
1. Erect and install the work of this Section in accordance with the Drawings and all pertinent codes
and regulations.
2. Do not permit temporary construction loads which cause members stresses beyond design limits.
=== End of Section ===
DIVISION 6:
WOOD AND ALUMINIUM:
0601 Carpentry and Millwork.
0602 Cabinet Work.
1.02 SUBMITTALS:
A. Submit samples and shop drawings of carpentry and millwork materials used for the proposed work.
B. Submit for approval full schedule of all wood specified intended for inclusion in the proposed work
including grades and wood preservative and treatment, their location and finish.
Obtain warranty from the manufacturer for a period of one year for free replacement of defective
components
1.03 SUBMITTALS:
A. The Contractor shall submit samples of materials, fittings, hardware and shop drawings indicating
elevations, details, construction, finishes and hardware.
B. Product data: submit manufacturer's installation instructions for hardware and other materials used in
the fabrication of casework.
C. Shop drawings submit shop drawings for casework, showing location of each item, dimensioned plans
and elevations, large scale details, anchors and other components. Indicate compliance with specified
requirements for materials and workmanship.
D. Samples: submit fully finished samples of the following items required in the casework. Samples will be
reviewed for appearance and finish.
1. Submit samples of each element that will be incorported in the cabinet work.
2. A mock-up sample for kitchen cabinet and vanity laundry/cabinet.
0701 WATER PROOFING & DAMP PROOFING VAPOUR BARRIER FOR SLAB
PART I – GENERAL:
1.01 DESCRIPTION:
General:
This section covers the furnishing and application of bituminous damp proofing for all concrete surfaces and
film sheeting damp proofing and floor water proofing in wet areas, as specified herein and as shown on the
drawings The Contractor shall furnish all labour, materials, tools and equipment required to complete the
work.
0701 WATER PROOFING AND DAMP PROOFING VAPOUR BARRIER FOR SLAB
PART II – PRODUCT:
2.01 GENERAL:
1. Procurement of all goods and products covered by these specifications must be approved by the
Owner/Consultant.
2. The cold application of bituminous coating to be used for general damp proofing and protective
purposes to the vertical surfaces of perimeter foundations.
3. Damp proofing shall be scheduled so that curing will be accomplished prior to backfilling and so that
backfilling will be accomplished as soon as possible after curing.
4. Primary coat and bitumen materials shall be applied when the ambient temperature is above 5°C.
2.02 MATERIAL PRODUCT:
1. Bituminous Coating: Non-flammable, non-toxic asphalt emulsion, Chemically treated for maximum
adhesion and shall be water and salt resistant type. One of the following product/manufacturer or
equivalent shall be acceptable.
A. BLACK "PU" CMCI products or equivalent approved for wet areas such as toilet &
bathrooms, kitchen, wash areas, laundry, pantry, etc.
B. SK-60, Fosam products or approved equivalent for foundation and structures in
contact to ground.
The mineral Filled asphalt emulsion shall be applied by brush, spray or dipping or
mopping and diluted with proper clean potable water as per manufacturer's
recommendation.
2. Film Sheet Damp Proofing Shall be polyethylene sheeting "Moistop" or approved equal and be not
less than 250 micron high impact strength rating.
3. Floor Waterproofing in Wet Areas: The cold applied one component liquid waterproofing shall be
applied for wet areas such as bathrooms, toilet, kitchen, wash areas, laundry. main and family
entrance porch, etc.
0701 WATER PROOFING AND DAMP PROOFING VAPOUR BARRIER FOR SLAB
PART III – EXECUTION:
Concrete surfaces to receive damp proofing shall be cleaned of foreign matter and loose particles and shall
be surface dry at the time damp proofing is applied. Surfaces to receive asphalt or fibrous asphalt damp
proofing shall be given a priming coat of asphalt primer. Priming coat shall be applied when the ambient
temperature is above 5°C and at the rate of approximately 0.4 liter per m2, fully covering the entire surface
to be damp proofed.
3.02 INSTALLATION:
Cold Application Method: Surfaces to be damp proofed shall be given zero coat with primer and first coat
with 2 coats black P.U. waterproof. Each coat shall be applied uniformly using not less than 0.5 litres of
asphalt per m2 for each coat. The first coat shall be applied by brush to provide full bond with the primed
surface, and the second coat may be brushed or sprayed over a thoroughly dry first coat The finished surface
shall be uniform thickness and impervious to moisture. Porous spots shall be recoated.
The above procedure shall be followed unless manufacturer recommendation specified
Apply bituminous material to the all wall perimeter up to the height of floor finish
3.03 FILM SHEETING:
Film sheeting damp proofing shall be laid out in accordance with the installation instruction of the
manufacturer. Lap joints minimum 300 mm and seal. Care shall be taken not to disturb or damage the
membrane while concrete reinforcing.
Overlap the sheet edges with minimum of 300 mm to be taped with reinforced tape as specified
Ensure no projections exist above ground which may damage the membrane.
Ensure continuity of covering at junction of horizontal/inclined and vertical membranes, by bonding with an
approved bonding compound or sealing tape, in particular at the corners of footings the primary
polyethylene sheet shall be cut to follow the excavated profile. Continuity of membrane may be ensured by
covering with smaller pieces of polyethylene sheeting and bonding with sealing tape.
Form collars around pipes and projections and seal with sealing tape.
Lay sheets loose on base, lap edge 150 mm and seal with adhesive tape.
Turn up sheets at edges of slab and seal against foundation or slab edge using sealing tape as indicated on
the drawings, ensure surfaces are dry and dust-free at time of applying sealing tape.
Protect sheets and prevent puncturing before or during laying of subsequent covering.
Repair any damage to the membrane with adhesive tape. Ensure a completely puncture free membrane just
prior to concreting.
Ensure that permanent covering is laid as soon as possible after laying sheets.
3.04 WET AREA WATER PROOFING:
Remove all dirt, dust, laitance, oil, grease and loose materials prior to application. Voids and cracks must
also be filled with latex cement mortar The polyurethane membrane shall be applied by brush, squeeze or
airless spray to a minimum thickness of 1 mm and allowed to dry overnight.
Testing Recommendations: Upon completion of waterproofing application the insulated area shall be tested
by pooling water at least of 50 mm depth kept for 48 hours. Owner/Consultant will inspect the ceiling under
slab surface for any leakage and further work can proceed only after clearance from Owner/Consultant.
==== End of Section =====
0702 BUILDING INSULATION
PART I – GENERAL:
1.01 DESCRIPTION:
A. Work Included:
The section covers the furnishing and installation of building insulation for walls and roofs as
shown on drawings.
B. Related Work Specified elsewhere:
PART II - PRODUCTS:
2.0 1 MATERIALS:
General:
All goods and products shall be as detailed on drawings and from reputable manufacturer approved by
Client. The Client will select the design in the workshop drawings. (manufacturer: AI Bawardi or approval
equal).
2.0 2 WOOD DOORS:
A. Mahogany semi-solid timber panel and solid wood frame with architraves for doors. At the locations
indicated on the drawings.
B. Flush door (60%) and solid wood frame with architraves for doors, at the locations indicated on the
drawings.
C. All wooden doors for toilets and bathrooms shall be laminated with Formica sheets all the entire
intenor surface (Inner side) of the door.
D. Completed doors shall be sound, rigid and free from defects and warp. All edges shall be aligned and
smooth Doors shall be a minimum thickness of 44 mm.
E. The width of the lipping shall equal the thickness of the door and the lipping itself shall not be less
than 10 mm thick. Lipping's shall be glued to the core. Where edges are required to be rebated the
lipping shall be a minimum of 30 mm thick and the rebate shall be formed in the lipping.
F. Joints shall be close fitting, hardwood dowelled or mortised framed and of strength to maintain the
structural properties of members connected, All adjoining faces and edges shall be flush and smooth.
G. Edges shall be rectangular and solid except that the leading edge shall be beveled from front to back.
Rebated edges shall be at least 13 mm deep.
H. Adhesives: all adhesives shall be waterproof, melamine fortified urea type.
I. Door frames shall be of quality grade wood of same species and as detailed on the drawings, Refer to
Section 0601.
J. All locks shall be as specified in Section 0805 - Finish Hardware.
3.01 Contractor shall verily that door frames are of the type required for proper installation of doors in their
respective locations.
3.02 Doors shall be installed in strict conformance with the door manufacturer's written Instructions.
3.03 Do not install doors in frames which would hinder the operation of the doors.
3.04 Install all finish hardware as recommended by the hardware manufacturer.
=== End of Section ===
0805 FINISH HARDWARE
PART I- GENERAL:
1.0 1 DESCRIPTIDN:
A. Work Included:
This section covers the installation of all finish hardware's such as door locksets, door stops,
cabinet handle and door hardware.
B. Related Works Specified Elsewhere:
3.01 Co-ordinate with other relevant sections as required to ensure proper and adequate provision in door for
installation of the finish hardware in the required location.
3.02 Prior to installation, inspect location of all hardware and verify that all necessary provisions have been
made. Do not proceed with installation in areas of discrepancies until they have been resolved.
3.03 Install all finish hardware with matching screws in the quantities and location shown on the drawings
and in full accordance with the manufacturer's recommendations install hardware firmly in place for
long life under the anticipated usage.
3.04 Install each item in compliance with the manufacturer's instructions and recommendations. Whenever
cutting and fitting is required to install hardware onto or into surfaces which are later to be painted or
finished in another way, co-ordinate of removal, storage and reinstallation or application of surface
protection with finishing work elsewhere.
3.05 Set units plumb and true to line and location. Adjust and reinforce the attachment substrate as necessary
for proper Installation and operation. Separate aluminum and other corridible metal surfaces from
sources of corrosion or electrolytic action at points of contact with other materials Drill and countersink
units which are factory prepared for anchorage fasteners Space fasteners and anchors in accordance
With manufacturer's instructions or as directed.
3.06 Locks and Latches:
A. Unless otherwise indicated or specified, provide latches that comply with ANSI 156.2.
B. Strikes: provide manufacture’s standard wrought box strike for each latch, with curved lip
extended to protect frame, finish to match hardware set.
C. Lock Throw, provide 16 mm minimum throw of latch on pairs of doors.
3.07 Lock Cylinders and Keying:
A. Standard system: the Contractor shall submit to Owner/Consultant and approval a keying
system for the buildings The keying system shall be designed in order to provide the utmost
convenience, safety and security of SAUDI ARAMCO in use of the premises.
B. Metal: construct lock cylinder parts from brass/bronze, stainless steel or nickel silver.
C. Key Material, provide keys of nickel silver.
D. Key Quantity: furnish 3 keys for each locks.
E. Provide each cylinder with series 1000: Escutcheon rose knob and outside in chrome plated
metal.
=== End Section ===
0806 STEEL DOORS AND FRAMES
PART I – GENERAL:
1.01 DESCRIPTION:
Extent of standard steel external doors and frames is shown and scheduled on drawings, for main
entrance, family entrance, kitchen service and roof deck access doors.
(Note: Aluminum door for roof central heater room).
1.02 QUALITY ASSURANCE:
o Provide doors and frames complying with Steel Door Institute “Recommended Specifications:
Standard Steel Doors and Frames” (SDI-100) and as herein specified.
o Manufacturer: Provide standard steel doors and frames by a local manufacturer approved by
the Client Representative and specialising in production of this type of work.
1.03 SUBMITTALS:
o Product Data: Submit manufacturer's specifications for fabrication and installation, including
data substantiating that products comply with requirements.
o Shop Drawings: Submit for fabrication and installation of steel construction, location and
installation requirements of finish hardware and reinforcements. and details of joints and
connections, Show anchorage and accessory items.
o Provide schedule of doors and frames using same reference details and openings as those on
contract drawings.
o Samples: Full range of colour samples for Owner/Consultant selection; 2 samples, 6" square
min. of each colour and texture selected for factory finished doors and frames.
1.04 DELIVERY, STORAGE AND HANDLING:
o Deliver doors cartoned or crated to provide protection during transit and job storage.
o Inspect doors upon delivery for damage, Minor damages may be repaired provided finished
items are equal in all respects to new work and acceptable to Owner/Consultant; otherwise,
remove and replace damaged items as directed.
o Store doors and frames at building site under cover. Place units on wood sills at least 4” high,
or otherwise store on floors in manner that will prevent rust or damage, Avoid use of non-
vented plastic or canvas shelters which could create humidity chamber. If cardboard wrapper
on door becomes wet, remove carton immediately. Provide ¼” spacers between stacked doors
to promote air circulation.
3.01 INSPECTION:
The Contractor must examine substrate and conditions under which steel doors and frames are to be
installed and must notify the Owner/Consultant In writing of any conditions detrimental to proper and
timely completion of work, Do not proceed with work until unsatisfactory conditions have been
corrected.
3.02 INSTALLATION:
A. General, Install steel doors, frames, and accessories in accordance with final shop drawings and
manufacturer's data, and as here in specified.
B. Placing Frames' Comply with provisions of SDI-105 "Recommended Erection Instructions For Steel
Frames", unless otherwise indicated.
In masonry construction, locate 3 wall anchors per jamb at hinge and strike levels.
C. Door Installation: Fit steel doors accurately in frames, within clearances specified in SDI-100.
D. Adjust and Clean: Prime cost touch up immediately after erection, sand smooth any rusted or
damaged areas of prime coat and apply touch-up of compatible air-drying primer.
Protection Removal: Immediately prior to final inspection, remove protective plastic wrappings
from prefinished doors.
Final Adjustments Check and readjust operating finish hardware Items, leaving steel doors and
frames undamaged and in complete and proper operating condition.
1.02 SUBMITTALS:
All technical brochures, colour samples and shop drawings.
2.01 MATERIALS:
A. The sectional garage door to be supplied by a local manufacturer approved by the Client Representative
(Manufacturer: AI dress or approval equal).
B. The door is to be remote controlled with manual operation in case of power failure The motor shall
have a built-in auto reverse safety feature.
C. The door shall be factory painted to colour selected by Client Representative.
D. The motor must be American manufacturer with ¾ hours capacity or equally approved.
3.01 The Contractor shall ensure that the door opening conforms to the dimensions shown on the drawings.
3.02 The door, frame motors etc. shall be fixed in strict accordance with the manufacturer's Instructions.
=== End of Section ===
DIVISION 9:
FINISHES:
1.01 DESCRIPTION:
A. Work included:
This section covers the finishing and installation of all internal and external cement plaster, metal
lath and accessories, to complete the work as indicated on the drawings.
B. Related work specified elsewhere:
2.01 GENERAL:
A. All goods and products shall be the product of a manufacturer regularly engaged in the manufacture of all
plastering constituents and accessories including metal lath.
2.02 MATERIALS:
A. Metal Lath:
1. Where detailed and where required to ensure high standards, galvanized steel sellf-furring lath
weighting 1.5 Kg/m2 for exterior stucco. Staggered Identifications spaced 88mm part horizontally
and 50mm apart vertically hold the body of the lath not less than 6mm away from the wall.
B. Wire Ties:
Soft annealed galvanized steel wire, not less than 1.5mm (16 gauge) for tying metal lath to anchor.
C. Plaster Accessories:
1. Corner Beads' Galvanized steel short flange, spring fit angle weighing 75 Kg/300 linear meter.
2. Casing Beads' Galvanized steel of weight 110 Kgl1000 linear meter.
3. Expansion control Joints' Galvanized steel bellows types with expansion flanges weighing 140
Kg/300 m2.
D. Cement Plaster:
1. Cement As per Portland Cement Section 0303.
2. Aggregate: Aggregate shall be clean, hard, durable, sharp particles completely free from all
deleterious salts.
3. Lime: Lime shall be hydrated finished lime; Lime shall not be used for exterior plaster.
4. Water shall be potable, clean and free from deleterious amounts of oils, salts, alkali, organic matter
and other harmful materials.
5. Mix Proportions shall be one (1) part cement, four (4) parts sand and one half (1/2) part hydrated
lime.
Note: Allow different thickness of the plaster for decorative panels as shown the drawing.
3.01 Ensure that all required and necessary insulation has been installed to building surfaces, pipe and other
items.
3.02 Install plaster accessories to plaster bases of substrates with galvanized fasteners.
3.03 Plaster for exterior surfaces shall consist of three-coat work 19mm thickness finished with a fine wood
float.
3.04 Plaster for interior surfaces of masonry walls to be plastered shall be not less than two coats for
thicknesses up to 12mm thickness and three coat work for thicknesses above 12mm and up to 15mm
thickness, Top coat shall be best quality Gypsum and fine sharp sand plaster mixed to manufacturers
recommendations.
3.05 Each coat of cement plaster shall be kept continuously moist for a minimum of 48 hours after
application and shall be protected from direct sunlight for not less than 7 days.
3.06 On surfaces where plaster is to be applied over two differing materials (e.g. concrete block and poured-
in-place concrete and around door, window and arched openings) a strip of metal lath shall be located at
the abutting edge to prevent future plaster cracking. The overlap on each side shall be at least 100mm.
3.07 All plastering shall be done when the temperature is between 13 Degree Centigrade and 35 Degree
Centigrade. No plastering shall be done when the temperature is above 35 Degree Centigrade.
3.08 Finished doors, window frames, all aluminum and other surfaces which do not receive a plaster finish
shall be protected during plaster application.
3.09 3mm thick finishing Coat of gypsum to be applied to all plasterboard surfaces to walls.
3.010 Plaster for interior surface to underside of concrete floor and roof slabs to be three coats to
thickness 15mm finished smooth to received texture coating finish (see Section 0903).
1.01 DESCRIPTION:
A. General:
This section covers the provision and installation of all floor and wall tiling as shown on the drawings
and specified herein.
B. Related works specified elsewhere:
0902 TILING
PART II -PRODUCTS
2.01 MATERIALS:
A. All materials shall be new and the best "Grade One" of their respective kinds and shall be manufactured
by Saudi Ceramics, RAK or approved equal.
1. Bathrooms & toilets, kitchen, dirty kitchen & store, laundary room, maid's room, water heater and
store room:
a. 300 x 300 x 8 mm, 300 x 600 x 8 mm, 200 x 200 x 8 mm or 400 x400 x 8 mm un-glazed
(non-slip) ceramic tiles for floor.
b. 300 x 600 x 6 mm, 200 x 200 x 6 mm or 600 x 600 x 6 mm ceramic tiles for wall (For
bathroom, toilet and wash areas).
c. 300 x 100 mm high ceramic tile skirting.
d. Colour and decorative design for ceramic tiles to be selected by Owner.
2. Ground floor, first floor and roof deck floor area (Except above mentioned areas).
a. 400 x 400 x 8 mm or 800 x 800 x 8 mm unglazed ceramic tiles for floor.
b. 400 x 100 mm high ceramic tile skirting.
c. Colour and decorative design for ceramic tiles to be selected by Owner.
3. Staircase and landing:
a. 30mm thick marble for stair landing.
b. 30mm thick marble for steps with three cut grooves behind 6mm radius rounded edges and
20mm thick marble riser.
c. 20 mm thick x 100mm high marble skirting.
d. Marble material from grade A or B (refer to section 0906).
4. Roof Deck and Upper Roof Deck area:
a. 250 x 250 x25mm Terrazo tiles for roof deck floor.
b. Gravel ballast finish for upper roof deck floor.
5. Main/Family/Service entrance area:
a. 400 x 400 x 20 mm marble tile (Cecilian /gemco/ omani or other equal marble tiles).
b. 100 mm marble skirting.
c. Granite material from grade A or B (refer to section 0908).
B. Bedding screed shall be 1:3 cement, sand mixed with latex.
C. Cement based adhesive use "Iaticrete" 4237 or similar approved.
D. Grout for wall and floor tiles shall be of matching colour according 10approved samples submitted by
Contractor, Grout shall be pre-mixed as Balfloor/Balwall or equal approved The Contractor to submit
manufacturer's full technical data for approval of the Owner/Consultant.
E. Approved material to be used for installation of wall and floor tiles shall be mixed and used strictly in
accordance with the manufacturer's written recommendations.
2.02 EXTRA STOCK:
Upon completion of this section. deliver to Owner an extra stock of one carton of not less than 25 pieces of
each colour and type of tile used in the building, including all trims and accessories.
0902 TILING
PART III-EXECUTION:
2.01 INSPECTION:
Examine the areas to be done under this section and ensure that all preceding and preparatory work of
other sections IS complete and satisfactory, Correct conditions detrimental to proper and timely
completion of the work, Do not proceed until satisfactory conditions have been achieved.
2.02 INSTALLATION:
Note: Allow for minimal cutting ot tiles on the location of the floor tiling around drains and wall tiling
around sockets, etc.
A. Floors:
Proceed with laying in strict accordance with the manufacturer’s recommendations and quoted
standard all as approved by the Owner/Consultant. Lay bedding screed to entire area with 10 mm
Foam Polystyrene full depth perimeter breaker strip, carefully maintaining levels and falls where
necessary and where indicated to fall drains. Before bedding has set while still plastic dust with neat
cement, spray fine mist of latex fixative and lay tiles to line, tamping them to form a firm bond true
to levels and falls as indicated avoiding all Voids under tiles Maintain joints and insert temporary
spacer in full depth of expansion and control joints, Any hollowness, hair cracks, chips will not be
accepted and shall be immediately replaced A water flow test is to be carried out prior to grouting
of tiles.
B. Walls:
Wall tiling shall generally be by the adhesive method Set out to allow for sanitary fixtures and
bathroom accessories. Spread adhesive on surface to be tiled with notched trowel of type
recommended by the manufacturer for the surface and type of tile. Cover surface uniformly without
bare spots. Apply adhesive only in areas which can be covered with tile before the adhesive "films"
over. Remove any adhesive that films over and refloat with fresh adhesive. Fastening heads for
Gypsum Linings shall be covered directly with adhesive and tile with no finishing compound Refer
Section 0905.
C. Grout wall and floor tiles without joint voids or skips, with neat grout (colour to be approved), of
creamy consistency, rub well-in and polish off Clean off grout to depth of shoulder of cushion edge.
Rake-out perimeter joints subsequently to receive sealant of matching colour.
D. Movement joints shall be sealed and caulked using silicone at top and bottom of walls, at fillings, at
doors and window frames, and polysulphide for floor, strictly according to the Manufacturer’s
written recommendation and to Section 0705 Use backing breaker strip or foam polyethylene
backing rod to sealed joints.
E. On completion keep tiles moist for 72 hours. Clean off tiles if necessary on unglazed tiles only
using 1:10 dilution of Muriatic Acid at least 10 days after grouting but only under written approval
of the Owner/Consultant. Neutralize, polish and leave clean for final inspection.
F. Avoid usage of tiles less than half tile width.
G. All floors are 10be water tested for level and water tightness.
H. Selling of Ceramic Floor Tile:
Floor tile shall be set generally as for wail tile and in accordance with ANSI A108.2, Use Portland
cement mortar setting for floors on substrates, Use commercial grout for grouting wall and floor
tiles. Colour pigment shall be mineral oxide unaffected by lime, cement or weathering.
Tile shall be pressed and beaten into position to obtain full contact with mortar bed with no Voids
in the mortar.
If tile is rib-backed, a layer of mortar shall be troweled on the back of each tile prior to placing on
the mortar bed.
Paper and glue shall be removed within one hour after tile is set and all tiles that are out of line or
level shall then be adjusted.
Colour of the tile shall be determined by the Owner or his representative.
=== End of Section ===
0903 PAINTING
PART I – GENERAL:
1.0 1 DESCRIPTION:
A. Work included:
Paint and finish all exterior and interior exposed surfaces listed on the Painting Schedule in Part 3 of
this Section, in accordance with the types of finish shown on the Finish Schedules in the Drawings and
as specified herein.
B. Related works described elsewhere:
Priming or priming and finishing of certain surfaces are specified to be factory performed or installer
performed under pertinent other sections.
C. Work not included:
1. Do not include painting which is specified under other sections.
2. Unless otherwise indicated, painting is not required on surfaces in concealed areas and inaccessible
areas such as furred spaces, pipe spaces, and duct shafts, Inside of service rooms and cupboards will
be finished.
3. Metal surfaces of Powder Coated aluminium, stainless steel. chromium plate, copper, bronze, and
similar finished materials will not require painting under this Section except as may be specified
herein.
4. Do not paint any moving surfaces of parts of operating units, mechanical or electrical parts such as
valve operators, linkages, sink ages. sensing devices, and motor shafts, unless otherwise indicated.
5. Do not paint over any required labels or equipment identification, performance rating, name, or
nomenclature plates.
D. Definitions:
The term "paint", as used herein, means all coating systems materials including primers, emulsions,
rubber finish, epoxy, enamels, sealers, fillers, and other applied materials whether used as prime,
intermediate, or finish coats.
1.0 2 QUALITY ASSURANCE:
A. Standards: Comply with standards specified in this Section.
B. Qualifications of Manufacturer' Products used in the work of this section shall be produced by
manufacturers regularly engaged in manufacture of similar Items and with a history of successful
production acceptable to the Client.
C. Qualification of Workmen:
1. Provide at least one person who shall be present at all times during execution of the work of this
Section, who shall be thoroughly familiar with the specified requirements and the materials and
methods needed for their execution, and who shall direct all work performed under this Section.
2. Provide adequate numbers of workmen skilled in the necessary crafts and properly informed of the
methods and materials to be used.
3. In acceptance or rejection of the work of this Section, the Client will make no allowance for lack of
skill on the part of workmen.
D. Paint Coordination:
1. Provide finish coats which are compatible with the prime coots used.
2. Review other Sections of these Specifications as required, verifying the prime coats to be used and
ensuring compatibility of the total coating system for the various substrata.
3. Upon request, furnish information on the characteristics of the specific finish materials to ensure
that compatible prime coats are used.
4. Provide barrier coats over non-compatible primers, or remove the primer and reprime as required.
5. Notify the Client in writing of anticipated problems in using the specified coating systems over
prime-coating supplied under other Sections.
1.0 3 SUBMITTALS:
A. General:
Comply with provisions of Section 1
B. Manufacturers' Data:
Within 30 calendar days after award of the Contract, submit:
1. Complete materials list of all items proposed to be furnished and installed under this Section.
2. Manufactures' specifications and other data required to demonstrate compliance with the
specified requirements.
3. For information only submit three copies of the manufacturers' specifications, including paint
label analysis and application instructions for each materials specified. Indicate by transmittal
that a copy of each manufacturer's instructions has been distributed to the applicator.
Upon receipt of review comments, make all revisions and corrections, and resubmit if so
required.
C. Samples:
1. Following the selection of colours and finish by the Client, as described In Paragraph 2.10, below,
submit samples for the Client's review.
a. Provide three samples of each colour and each finish for each material on which the finish is
specified to be applied. These samples also become a guide for establishing acceptability of
surface textures.
b. Except as otherwise directed by the Client samples shall be approximately 20cm x 25cm.
c. If so directed by the Client, submit samples during progress of the work of this Section in the
form of actual application of the approved materials on actual surfaces to be painted.
2. Revise and resubmit each sample as requested until the required finish, colour, and texture are
achieved Such samples when approved, shall constitute standards for colour and finish for
acceptance or rejection of completed work.
1.0 4 PRODUCT HANDLING:
A. Delivery of Materials:
Deliver all materials to the job site in original, new and unopened containers bearing the
Manufacturer’s name and label showing the following information:
1. Name of title of material.
2. Fed. spec, number, if applicable.
3. Manufacturer's stock number.
4. Manufacturer's name.
5. Contents by volume for major constituents.
6. Thinning instructions.
7. Application instructions.
8. Date of Manufacture/Shelf Life.
B. Storage of Materials:
Provide proper storage to prevent damage to; and deterioration of, paint materials.
C. Protection:
Use all means necessary to protect the materials of this Section before, during, and after installation and
to protect the work and materials of all other trades.
D. Replacement:
In the event of damage, immediately make all repairs and replacements necessary to the approval of the
Client and at no additional cost to the Client.
1.0 5 JOB CONDITIONS:
A. Surface Temperatures:
Do not apply solvent-thinned paints when the temperature of surfaces to be painted and the
surrounding air temperatures are below 7 Degree Centigrade or above 35 Degree Centigrade, unless
otherwise permitted by the manufacturer's printed instructions as approved by the Owner.
B. Weather Conditions:
Do not apply paint In Dust Storms, rain, fog, or mist, or when the relative humidity exceeds 65%. or to
damp or wet surfaces; unless otherwise permitted by the manufacturer's printed instructions as approved
by the Client. Application may be continued during inclement weather within the temperature limits
specified by the paint manufacturer during application and drying periods.
0903 PAINTING
PART II- PRODUCTS:
A. Design is based on use for texture coatings and paint products manufactured by JOTUN PAINTS
LTD, Equal products of other manufacturers approved in advance by the Client, may be substituted
in accordance with the provisions of Section on Substitutions.
B. General:
Provide the best quality grade of the various types of coatings as regularly manufactured by paint
materials manufacturer's approved by the Client. Materials not displaying the manufacturer's
identification as a standard best-grade product will not be acceptable.
C. Durability:
Provide paints of durable and washable quality. Do not use paint materials which will not
withstand normal washing as required to remove pencil marks. ink, ordinary Soil, and similar
material without showing discolouration, loss of gloss, staining, or other damage.
D. Colours and Glosses: Clear varnish finishes:
1. The Client will select colours to be used in the various types of paint and will be the sole judge
of acceptability of the various glosses obtained from materials proposed to be used by the
Contractor.
2. Colour Schedules: The Client will prepare a Colour schedule with samples for the guidance of
the painter and reserves the right to select, allocate, and vary colours on different surfaces
throughout buildings, subject to the following limitations.
3. Exterior Work: A maximum of 5 different dark tones shall be allowed with variations for trim,
doors, miscellaneous woods, and metal work. Use only light and alkali proof pigments.
4. Interior Work: A maximum of 8 different pigmented colours will be used with variations for
trim and wall surfaces, Ceilings shall be white Wood trim shall be finished where directed in
clear e.g.,. polyurethane varnish.
5. Darktones: Approximately 15% of all in tenor colours will be deep darktones but will be
subject to Client's specific instruction.
E. Undercoats and Thinners: Provide undercoat paint produced by the same manufacturer as the
finish coat. Use only the thinners recommended by the paint manufacturer. And use only to the
recommended limits. Insofar as practicable, use undercoat, finish coal, and thinner material as parts
of unified systems of paint finish.
F. Standards' Provide paint materials which meet or exceed the Paint Industry standards.
2.02 APPLICATION EQUIPMENT:
A. General:
For application of the approved paint, use only such equipment as recommended tor application of
the particular paint by the manufacturer of the particular paint, and as approved by the Client.
B. Compatibility:
Prior to actual use of application equipment, use all means necessary to verify that the proposed
equipment is actually compatible With the material to be applied and that the integrity of the finish
will not be jeopardized by use of the proposed application equipment.
2.03 OTHER MATERIALS:
All other materials, not specifically described but required for a complete and proper Installation of the
work of this Section, shall be new, first-quality of their respective kinds, and as selected by the
contractor subject to the approval of the Client.
0904 PAINTING
PART III-EXECUTION:
3.01 SURFACE:
A. Inspection: Prior to Installation of the work of this Section, carefully inspect the installed work of
all other trades and verify that all such work is complete to the point where this Installation may
properly commence. Verify that painting may be completed in strict accordance with the original
design and with the manufacturer's recommendations as approved by the Client. Ensure that high
levels of lighting are provided to allow at any time detailed inspection 0/ surfaces and proper
conditions for application.
B. Discrepancies: Do not proceed in areas of discrepancy until all such discrepancies have been /fully
resolved.
3.02 MATERIALS PREPARATION:
A. General:
1. Mix and prepare painting materials In strict accordance with the manufacturer's
recommendations as approved by the Client.
2. Store materials not in actual use in tightly covered containers.
3. Maintain containers used in storage, mixing, and application of paint In a clean condition, free
from foreign materials and residue.
B. Stirring: Stir all materials before application to produce a mixture of uniform density, and as
required during the application of materials Do not stir into the material any film which may form
on the surface. Remove the film and, if necessary, strain the material before using.
3.03 SURFACE PREPARATION:
A. General:
1. Perform all preparation and cleaning procedures in strict accordance with the paint
manufacturer's recommendations as approved by the Clients.
2. Remove all removable items which are in place and are not scheduled to receive paint finish, or
provide surface-applied protection prior to surface preparation and painting operations.
3. Following completion of painting in each space or area, reinstall the removed items by using
workmen skilled in the necessary trades.
4. Clean each surface to be painted until they are completely free from dirt, dust, laitance, oil,
grease and loose materials prior to applying paint or surface treatment
5. Remove oil and grease with clean clothes and cleaning solvents of low toxicity and a flash
point in excess of 38 Degree Centigrade, prior to start of mechanical cleaning.
6. Schedule the cleaning and painting so that dust & other contaminants from the cleaning
process will not fall into wet newly painted surfaces.
B. Preparation of Wood Surfaces:
1. Clean all wood surfaces until they are free from dirt, oil ,and all other foreign substance.
2. Smooth all finished wood surfaces exposed to view, using the proper sandpaper Where so
required, use varying degrees of coarseness In sandpaper to produce a uniformly smooth and
unmarred wood surface.
3. Unless specifically approved by the Client, do not proceed with painting of wood surfaces until
the moisture content of the wood is 12% or less as measured by dry-weight process or a
moisture-meter approved by the Client.
C. Preparation of Metal Surfaces:
1. Thoroughly clean all surfaces until they are completely free from dirt, oil, and grease.
2. On galvanized surfaces, use solvent for the Initial cleaning and then treat the surface
thoroughly with phosphoric acid, etc., remove all etching solution before proceeding.
3. Allow to dry thoroughly before application of paint.
3.04 PAINT APPLICATION:
Note: Application is as per manufacturer's recommendation and specification.
A. General:
1. Touch-up all shop-applied prime coats which have been damaged and touch-up all bare areas
prior to start of finish coats applications.
2. Slightly vary the shade of succeeding coats, Do not apply additional coats until the completed
coat has been Inspected and approved, only the inspected and approved coats of paint will be
considered in determining the number of coats applied.
3. Sand and dust between enamel coats to remove all defects visible to the unaided eye from
distance of five feet.
4. On all screw- fix removable panels and all hinged panels, paint the back sides to match the
exposed sides.
B. Drying:
1. Allow sufficient drying time between coats, Modify the period as recommended by the material
manufacturer to suit adverse weather conditions.
2. Oil-base oleo-resinous solvent-type paints shall be considered dry for re-coating when the paint
feels firm does not deform or feel sticky under moderate pressure of the thumb, and the
application of another coat of paint does not cause lifting or loss of adhesion of the undercoat.
C. Brush Application: Brush-out and work all brush coals onto the surfaces in an even film.
Cloudness, spoiling, holidays, laps, brush marks, runs, sags, ropiness, and other surface
imperfections will not be acceptable.
D. Spray Application:
1. Confine spray application to metal framework and similar surfaces where hand brush work
would be inferior.
2. Wherever spray application is used, apply each coat to provide the equivalent hiding of
brush-applied coats, Do not double back with spray equipment for the purpose of building
up film thickness of two coats in one pass.
E. Completed work shall match the approved sample for colour, texture, and coverage Remove,
refinish, or re-paint all work not in compliance with specified requirements.
3.05 PAINTING SCHEDULE:
A. General:
Painting required under this Section is called for on the drawings, Paint types or equal are
defined below.
B. Exterior Metal:
C. Interior Finish:
1. On wall surfaces all areas:
3. On Gypsum Board:
4. On metal, use:
b. Second Coat: Uotun Heavytex (hopper gun pressed) or equal approved by client
c. Third Coat: Uotun Heavytex (hopprt gun pressed) or equal approved by client
1.0 1 DESCRIPTION:
A. Work included:
Provide all gypsum drywall and accessories, complete, in place, as shown on the drawings, specified
herein, and needed for a complete and proper Installation.
B. Related Works Specified Elsewhere:
1.0 1 DESCRIPTION:
A. Work Included:
The work in this section covers all metal framing members for non-structural walls, wall furring
and ceiling support systems as outlined and defined on the drawings.
B. Related work specified elsewhere:
3.01 CONDITIONS:
A. Prior to installation coordinate with others as necessary and determine the requirements of other
work sections to the need for location of framing and provision for additional fixings, members and
anchor points not shown but required for the completion of the finished work of other sections,
Failure to determine such requirements will not absolve the contractor to provide such provisions in
the finish work, under this Section.
B. Prior to installation of the work of this section, carefully Inspect the Installed work of all other
trades and verify that all such work is complete to the point where this installation may properly
commence. Verify that Metal Stud and Furring may be Installed in strict accordance with all
pertinent codes and regulations, the manufactures' recommendations as approved by the Client,
and the original design.
C. Discrepancies:
Do not Install Metal Stud or Furring until all unsatisfactory conditions have been corrected.
3.02 INSTALLATION:
A. General:
Accurately set out all member before commencing installation, making due allowance for the work
of other Sections. Ensure all members are erected true to line and plumb with all additional
members at corners and Intersection to receive linings and fittings. Ensure set out allows
subsequent linings to button centre lines of members.
B. Stud Work:
Generally set out bottom and top track channels to line and studs at 600mm centers and as
necessary. Bridging shall be set out accurately to horizontal lines at not more than 800mm centers
vertically and as required. Secure bottom tracks with masonry anchors, end and edge studs and top
tracks with screws at not more than 300mm centers Use fastenings appropriate to the location.
C. Ceiling Support System:
Generally set out ceiling sections (runners) and intermediate channels, locate and fix hangers with
anchors, fix ceiling sections and channels to hangers and level to provide horizontal fixing for
plasterboard. Fix perimeter channel to all wall junctions.
D. Coat all surfaces of metal studs in contact with concrete or masonry with suitable damp- proofing
compound.
E. Tolerances:
Align all partition and wall assemblies to a tolerance of one in 200 horizontally and one in 500
vertically.
F. Co-ordination:
1. Space the members as required for compliance with all pertinent regulations, to give proper
support for the covering materials, and as indicated on the drawings.
2. Carefully coordinate all requirements for backing and other support of items to be mounted on
the finished covering.
3. Carefully coordinate all requirements for pipe and other items designed to be housed within
the partitions and wall and ceiling systems.
=== End of Section ===
0906 MARBLE TILING
PART I – GENERAL:
1.0 1 DESCRIPTION:
A. General:
This section covers the provision of installation of marble thresholds, treads and risers to stairs,
main and family entrance as shown on the drawings and specified herein.
1.0 2 QUALITY ASSURANCE:
A. Manufacturer:
The products used in the work of this section shall be produced by manufacturers regularly
engaged in the manufacture of these products and with a history of production and quality
acceptable to the Client.
The quality colour and design shall be established by samples supplied by the contractor and
approved In writing by the Client and it shall be no less quality than the material specified in Part
II- PROOUCTS of this section.
B. Installer:
Use adequate numbers of skilled workmen who are thoroughly trained and experienced in the
necessary crafts and who are completely familiar with the specified requirements and methods
needed for proper performance of the work in this section.
1.0 3 SUBMITTALS:
Within 30 days of contract award, submit complete samples of the complete range of colours and
pattems of marbles from the range at least one manufacturer. Not less than two different colour- ways
shall be submitted.
1.0 4 STANDARDS:
The standards required to be met in this section shall be those as defined, and set out in ASTM CS03
and for soundness, with M.I.A. requirements.
2.01 MATERIALS:
A. General:
All materials shall be new and the best grade of their respective kinds and shall be manufactured by
Cecilian / Omani / Gemco or approved equal.
B. 30mm thick marble for treads and landing 20mm thick for risers to stair with three cut grooves
behind the 6mm radius rounded edge for each step with 20mm thick x 100mm high skirting. Shall
be marble from grade (A) material of approval color and design.
C. 30mm thick marble threshold at exterior door and toilet doors.
D. 400 x 400 x 20mm thick marble for main, family and service entrance area, shall be made from
grade (A) material of approval color and design.
E. Bedding screed shall be 1:3 cement, sand mixed with latex.
F. Cement based adhesive use "Laticrete" 4237 or similar approved.
G. Grout shall be pre-mixed as Baifloor / Balwall or equivalent.
3.01 INSPECTION:
Examine the areas to be done under work of this section and ensure that all preceding and preparatory
work of other sections are complete and satisfactory. Correct conditions detrimental to proper and
timely completion of the work. Do not proceed until satisfactory conditions have been achieved.
3.02 INSTALLATION:
A. Thresholds:
Thresholds fixing shall generally be by the adhesive method. Spread adhesive on surface to be tiled
with notched trowel of type recommended by the manufacturer for the surface. Cover surface
uniformly without bare spots Apply adhesive 1only in areas which can be covered the adhesive
"films" over. Remove any adhesive that films over and refloat with fresh adhesive.
B. Treads and rises to stair shall bedded in white cement and sand mix and laid to the correct level
and alignment so as to adhesive equal sizes and threads through the stairway.
C. Marble tiles to main entrance shall bedded in cement and sand mix and laid to the correct level.
===End of Section ===
DIVISION 10:
SPECIALTIES:
1001 Sanitary Fixtures.
1002 Bathroom Accessories.
1.0 1 DESCRIPTION:
A. Work included:
This section covers the supply and installation of all sanitary fixtures including all carriers, supports,
anchors and accessories, in the location and quantities shown on the drawings and as required.
B. Related work specified elsewhere:
1. Section 1501 - Plumbing Systems.
2. Section 1002 - Bathroom Accessories.
1.0 2 QUALITY ASSURANCE:
A. ANSI- American National Standards Institute.
A112.19.2 Vitreous China Sanitary Fixtures.
B. 8SI- British Standards Institution.
3402 Quality of Vitreous China Sanitary Appliances.
1.0 3 SUBMITTALS:
A. Submit copies of manufacturer's catalogues containing technical specifications for fixtures proposed
to the Owner/ Consultant for approval.
B. Shop drawings showing the location of fixtures, the method of installation and fittings / accessories.
2.01 GENERAL:
A. All fixtures shall be SAUDI CERAMIC, RAK or equal approved and furnished by a manufacturer
or supplier regularly engaged in the manufacture or supply Of sanitary fixtures.
B. All fixtures shall be of make and model selected from a high quality available range. See specific
drawings for details of fixtures, equipment and fillings required to be used in conjunction.
1. Western Water Closet:
a. W.C. bowl.
Cistern tank.
Flush system.
b. Seat cover.
c. Complete fixing accessories.
2. Bath Tub:
a. Acrylic bath tub from local manufacturer with bath panel and sliding DUSCHOLUX
enclosure.
b. Set of pop-up waste, overflow & p-trap.
c. Telephone shower, GROHE original.
3. Shower Tray:
a. Acrylic shower fray from local manufacturer.
b. Waste strainer.
c. Telephone shower. GROHE original.
4. Perennial Spray:
a. GROHE original, c/w vacuum breaker, CPL angle stop valve, hose, hand spray &
hook.
5. Pedestal Lavatory:
a. Pedestal wash basin, white vitreous china lavatory with pedestal & centre hole for
faucet.
b. 1 ¼ trap for lavatory.
c. Single lever mixer, GROHE original.
6. Vanity Basin:
a. MAROMIX or similar approved artificial granite counter top with half rounded edges
and 100mm high splash-back, complete with built-in wash basin.
b. 1 ¼ trap for lavatory.
c. Single lever mixer, GROHE original.
7. Kitchen double bowl stainless steel Sink (Single bowl for dirty kitchen):
a. 20 mm thick artificial granite resin work counter lop with half rounded edges and
100mm high splash-back, complete with built-in double bowl stainless steel Sink.
b. Double p-trap assembly (PVC).
c. Sink disposer, KENMORE (USA).
d. Basket strainer.
e. Single lever mixer, GROHE original.
8. Laundry / Utility Sink (if applicable):
a. Artificial granite counter top with stainless steel sink.
b. With 3 holes faucet drilling.
c. Single lever mixer, GROHE original.
1.01 DESCRIPTION:
A. General:
This section covers the provision and installation of all bathroom accessories, as shown on the
drawings specified herein.
B. Related works specified elsewhere:
1. Section 1001 - Sanitary Fixtures.
2. Section 0803 – Glazing.
3. Section 0902 - Tile Work.
1.02 QUALITY ASSURANCE:
A. Qualification of Manufacturer:
Products used in the work of this section shall be produced by manufacturer's regularly engaged in
the manufacture of similar products and with a history of successful production acceptable and
approved by the Owner/Consultant.
B. Qualification of Installer:
Use adequate numbers of skilled workmen who are thoroughly trained and experienced in the
necessary crafts and who are completely familiar with the specified requirements and methods
needed for proper performance of the work of this section.
1.03 SUBMITIALS:
A. Product Data:
The following material/document should be submitted for review and approval of the
Owner/Consultant prior to start procurement process.
1. Manufacturer's recommended installation procedures.
2. Manufacturer's specifications.
B. Samples:
1. Accompanying the above submittals, submit samples of each toilet/bathroom accessory
proposed to be furnished and installed under this section.
2. Samples will be returned to the Contractor at the site of the work and may be incorporated
into the finished work, provided they are identified and their locations noted.
3.01 INSPECTION:
Examine the areas and conditions under which work of this section will be installed. Correct conditions
detrimental to proper and timely completion of the work Do not proceed until unsatisfactory conditions
have been corrected.
3.02 CO-QRDINATION:
Throughout construction of substrate surfaces, use all means necessary to ensure proper and adequate
provision for concealed support devices and for finished openings to receive the work of this section.
3.03 INSTALLATION:
Install in strict accordance with the manufacturer's recommendations as approved by the
Owner/Consultant, anchonng all components firmly into position for long Iile under hard
use.
===End of Section ===
DIVISION 11:
APPLIANCES:
1101 Schedule of Kitchen and Other Appliances.
1.0 1 DESCRIPTION:
General:
This section covers the supply and installation of kitchen and other appliances, namely electric water
heaters, washer, dryer, refrigerator/freezer, food disposer, cooking range, extract hood.
2.01 GENERAL:
A. All appliances to be new, of the latest model and delivered to the site in the manufacturer's packing
labeled clearly to indicate date of manufacture.
B. Colours of trim to be selected from the manufacturer's standard range of colours and trim.
C. All colours and trim for the appliances to be matching in each dwelling.
2.02 PRODUCTSHANDLING:
A. Protection: Use all means necessary to protect the materials before, dunng and after installation
and to protect the work and materials of all other trades.
B. Replacement: In the event of damage, immediately make all repairs and/or replacement
necessary, to the satisfaction and at no additional cost to the Owner/Consultant.
2.03 DESCRIPTIONOFAPPLIANCES:
1. Electric water heater for Drivers Room, 50 liters capacity by Ariston or approval equal, (as per
drawing details).
2. Centralized electric water heater, 300 liters capacity by A.O. Smith or approval equal, (as per
drawing details).
3. Kenmore 30" slide in type, self-cleaning, coil elements electric range.
4. KDK range hood - 72 watts, 700mm wide, 150cfm, 230V/1P/60Hz.
5. Kenmore disposer - heavy duty ¾ HP.
6. Kenmore 25 cu. fl. Refrigerator.
7. Kenmore washer - 16.0 kg capacity.
8. Kenmoredryer-160kg capacity.
=== End of Section ===
DIVISION 15:
MECHANICAL:
1501 Plumbing system.
1502 Description of HVAC system.
1503 Fire protection system.
1.0 1 DESCRIPTION:
A. Work included:
This section covers the furnishing and Installation of all plumbing systems in the location and
quantities shown on the drawings.
B. Related work specified elsewhere:
1. Section 1001 – Sanitary Fixtures and Accessories.
2. Section 0204 - Underground Piping & Utilities pits.
1.0 2 QUALITY STANDARDS:
A. Comply with all requirements of the National Plumbing Code (NPC), Saudi Arabian Codes and
Standards, and International Plumbing Code (IPC)..
B. ASTM D2665-78 Specification for Polyvinyl Chloride (PVC) Plastic Drain, Waste, Vent Pipe and
Fittings.
C. ASTM B88, Types K and L (ASTM 888M, Type A and B), water tube annealed temper or type M
hard temper.
ASME A40.8-55 National Plumbing Code. Minimum Requirement for Plumbing.
D. ASTM - American Society for Testing & Materials.
D1785 - PVC Plastic Pipes sch 40,80,120.
D1784 - Compounds for PVC and CPVC.
D2466 - PVC Plastic Pipe Fittings (Schedule 40).
D2464, D2467 - PVC Sch. 40, 80, 120 - PVC sch, 40 Socket Type, PVC Sch.80.
ASME B16 18, Cast copper alloy fittings.
ASME B16 22 wrought copper, solder joint fittings.
ANSI/ASME B16.26, Cast copper alloy fittings for flanged copper tubes.
ANSI/ASME B16.29, Wrought copper and wrought copper alloy solder joint drainage fittings.
E. American Water Works Association (AWVVA).
B300 Series Standards – Disinfection.
F. Saudi Arabian Standards:
SAS 11- Electric Water Heaters.
SASO 14' Unplasticized poly vinyl chloride (u PVC) for potable water.
SASO 15: Methods of testing of Unplasticized poly vinyl chloride (u PVC) pipes for potable water.
G. The plumbing system shall be tested in accordance With the material standard plumbing code
procedure.
1.0 3 HEALTH AND SAFETY CONSIDERATIONS:
All works undertaken in relation to this specifications are to be completed in full accordance with the
respective health and safety requirements established by the following:
King don of Saudi Arabia's legislation, Regulation, Standards and Codes.
1.0 4 SUBMITTALS:
A. Submit product data, manufacturer's certificate and certificate of compliance to Specification,
QA/QC certificates reference codes and standards on each item of equipment for all materials
specified, for the Owner/Consultant review and approval prior to procurement.
B. Submit descriptive literature for fixtures and equipment specified herein.
C. Submit written procedure for solvent welding of plastic piping joints.
D. Submit written procedure for copper piping brazing methods.
E. Operation and Maintenance Manuals for appliances and fixtures.
F. Sample of the different sizes of pipes, fittings, hangers to cover all the waste and venting system.
G. Submit shop drawings showing all Internal and external water supply system in isometric with all
associated fittings and specialties and enlarge layouts and sections of wet areas.
H. Prior of testing the plumbing and water system the Contractor should submit for review and
approval of Owner/Consultant the manual of testing procedure for the different request tests under
this Section.
B. Electrical loading for water heaters shall be as shown and indicated on the drawing. Brand is to be
A. 0. Smith, Ariston or Kenmore for 300 liter and 50 Liter capacity water waters and approved by
the Owner/Consultant.
C. Water heaters shall be provided With two stage heating elements one at top and one at the bottom
of vessel container.
D. The water heater interior surface will be glass lined and the sides and top of the tank outside shall
be covered with thick lining of Insulator to retard heat loss. Each unit will be furnished with
magnesium anode rods rigidly supported, and will be furnished with combination temperature and
pressure relief valve.
E. Voltage and combined wattage of the heating elements shall be as required to satisfy the loading.
Wiring shall be so arranged that, when required by thermostats, both heating elements will operate
simultaneously.
F. Heaters shall be furnished with adjustable mounting supports.
G. Water heaters shall be provided with circulating pump including thermostat automatic 110-170° F
{44°C-77°C) temperature range and required thermo-sensors, pressure vessel for expansion and
back flow preventer.
Pump shall be bronze fitted. Install line size butterfly, ball, or gate valve and strainer on pump
suction, Install line size spring loaded check valve and butterfly, ball, or gate valve on discharge.
H. Backflow preventers :
Bronze body, stainless steel and brass trim.
Relief ports and test cocks.
Tight seating check valve assemblies.
If the valves are flanged, flange bolts and rubber gaskets shall be provided for attachment of valves
to each end of backflow preventer.
Means to service backflow preventer while installed in pipe, shall be provided.
Suitable melting flanges, unions, or nipples shall be provided as necessary for installation of back
flow preventer.
The dimensions, connection Sizes, capacity, and pressure drop at design capacity.
2.06 HANGERS AND SUPPORTS:
Type hangers 10 mm diameter galvanized steel hanger rods space on 1,5 meter on centers for pipe
13mm diameter or less, 1.8 meter on centre for pipes up to 25 mm diameter. Inserts shall be provided in
the concrete floor slabs for supporting the piping.
2.07 SLEEVES:
a. Pipe sleeves shall be installed and properly secured in place at all points where pipe
pass, through masonry or concrete panels, except unframed floors on earth.
b. Pipe sleeves (except sleeves through footing) shall be of sufficient diameter to provide
approximately 6 mm clearance around the pipe or insulation.
c. Pipe sleeves in floors/walls shall be PVC pipe, Sch. 40. Sleeves In floor shall extend
not less than 25 mm and not more than 50 mm above and the space around the pipe
shall be packed with plastic material and made watertight.
d. Pipe sleeves in footings shall be PVC and shall be not less than 100 mm larger In
diameter than the pipe to be installed.
e. Flashing sleeves shall be installed where pipes pass through water proofing
membrane, floor slabs and walls. The sleeves shall be provided with an internal
flashing flange or clamping device to which a flashing shield be of sixteen ounce, soft
sheet copper, shall extend not less than 200 mm from the sleeves and flashing flanges
and shield be thoroughly mopped to the membrane.
f. The space between the pipe and sleeves shall be made weather tight by inserting a
picked oakum gasket and filling the remaining space with weather proof sealant.
2.08 SANITARY SOIL, WASTE AND VENT PIPE AND FITTINGS:
a. All soil, waste and vent pipe lines shall be polyvinyl chloride (PVC) Sch. 40 and size
of pipes and fittings shall be according to International Plumbing Code.
b. All joints shall be air and water tight. For joining PVC pipes, use PVC cement.
c. Floor Drains:
I. Floor drains shall comply with ANSI A112 21.1.
II. The contractor shall provide all gaskets and accessories required to install floor
drains In PVC drain pipe.
III. Open hub drains for Indirect or equipment waste shall be as indicated on the
Contract Drawings.
IV. Floor drains serving water heater areas shall be of deep seal type or shall be
discharged to the indirect waste funnel (IWF).
V. Floor drains shall be supplied With.
Body material: Gray iron.
Seepage Flange: Required.
Clamping Device: Required.
Outlet: Bottom.
Top or strainer material. Nickel bronze.
Top of body and strainer finish: Satin Nikaloy.
Top shape, Round.
Top loading Classification: Light duty
Inlet fitting: Gray iron, with threaded inlet and threaded or spigot outlet.
Trap Material: Cast iron.
Trap pattern: Deep-seal P-trap.
Trap features: Trap seal primer valve drain connection.
Bottom inside caulk connection suitable for PVC pipe connection.
Flashing clamp and waterproofing membrane.
Leveling adjustment.
Floor drain / cover Top
I. 150 mm diameter, polished bronze, for rest rooms, toilets,
laboratory rooms and first aid areas.
II. 220 mm diameter, cast iron equipment rooms.
VI. Floor cleanouts:
Floor cleanouts shall be supplied with:
I. Cast iron body with adjustable housing.
I. Inside caulk connection suitable for PVC or other drain pipe
connection.
II. Closure: Brass plug with straight threads and gaskets.
III. Adjustable housing material: Cast Iron with threads.
IV. Frame and cover material and finish: Nickel- bronze, copper or
stainless steel to suite room finish.
V. Frame and cover shape Round.
VI. Ferrule with plug.
VII. Round polished brass top, secured.
d. Floor drain to be cast brass or aluminum-bronze body with integral trap and
adjustable nickel-alloy polished strainer, side outlet, diameter of strainer 100 mm,
chrome finish.
e. Cleanout to be floor cleanout spigot or hub connection with internal gasket and cast
nickel. Allow polished covers where inside and cast brass where located outside.
f. Drain pipe slope shall not be less than 2%.
g. Fittings to match pipe and where possible to be from same manufacturer.
2.09 ROOF DRAIN (RAINWATER) SYSTEM:
Roof dome type cast iron drain and painted cast iron body with splash pad system, as per detail shown
in architectural drawing.
1.0 1 DESCRIPTION:
This section covers the furnishing, testing, shipment, installation, and placing in satisfactory service of
the air conditioning equipment as specified herein and as shown on the Drawings.
1.0 2 QUALITY ASSURANCE:
Specification and standard referenced in this specification (including addenda, amendments and errata
listed) shall form part of this specification to the extent indicated by reference thereto In case of
difference between reference specifications or standards and this specification, this specification shall
govern.
AHRI Air-conditioning, Heating, and Refrigeration Institute.
ASHRAE American Society of Heating. Refrigerating and Air conditioning Engineers.
SMACNA Sheet Metal and Air-conditioning Contractors National Association Inc.
ASME American Society of Mechanical Engineers.
UL Underwriters laboratories Inc.
ASTM American Society of Testing and Materials
ANSI American National Standard Institute.
NEC National Electric Code.
NFC National Fire Code.
NFPA National Fire Protection Association.
All regulations and standards shall be of the latest issue unless governing authorities require on earlier
issue.
Units will be rated In accordance with the latest edition of ANSI /AHRI Standard 210/240: 2008.
Units will be certified for capacity, efficiency, and listed in the latest ARI directory.
Unit construction will comply with latest edition of ANSI/ASHRAE and with NEC.
Units will be constructed in accordance with UL standards and will carry the UL label of approval.
Units will have a c-UL approval.
Unit cabinets will be capable of withstanding Federal Test Method Standard No. 141 (Method 6061)
500-hr salt spray test.
Air-cooled condenser coils will be leak tested at 150 psig and pressure tested at 300 psig.
1.0 3 SUBMITIALS:
A. Shop Drawings and Samples:
1. Contractor shall submit shop drawing, engineering data and samples of materials for approval
by the Owner/Consultant.
2. Shop drawings shall include schedule of all materials, detail drawings of the Installation,
assembly construction, methods of attachment, size of components and positions as well as
relations with other trades e.g. electrical, plumbing etc.
3. Contractor shall install according to approved shop drawing and shall be only approved
equipment and materials.
4. All materials and equipment shall be brand new.
B. As-built Drawings, Operation and Maintenance Manual, Instructions:
1. The Contractor shall record all changes arising during the execution of the work so that as-
built drawings can be prepared accordingly. These drawings shall detail all relevant data
concerning makes, types, number, code numbers, capcities, quantities.
2. After the approval by Owner/Consultant, the Contractor shall submit two (2) sets of prints
and one (1) set of soft copies of drawings in a compact disc.
3. Contractor shall supply three (3) copies of complete maintenance and operation instructions
manual of each piece of equipment, for the approval of the Owner/Consultant. These
instruction shall not consist of manufacturer's advertising literature or catalogues, but shall be
genuine and clearly written instructions that will guide In the proper operations of the
equipment.
4. The Contractor shall supply the as-built drawings and the operating and maintenance
instructions as soon as possible, but not later than (8) weeks after practical completion of the
works.
5. Included with the Instructions manual shall be a maintenance schedule for the pnncipal Items
of equipment furnished under this contract and complete diagrams of all installations.
1.0 4 PRODUCT DELIVERY, STORAGE AND HANDLING:
A. All materials required for the Installation of the villa including window air conditioning units, DX
Mini split units and ventilation system shall be delivered in time to avoid any delay In progress of
the work.
B. Materials shall be delivered to the site in their original wrappings or boxes with unbroken seals
bearing the name of the manufacturer and the brand.
C. The Contractor shall consult the Owner/Consultant and shall arrange with him for the allocation
of sheds and storage areas on site for the Contractor's materials and equipment. The Contractor
shall not store materials in areas other than those set aside for the purpose.
D. All materials shall be stored so as to protect them from damage or deterioration before fixing.
Materials stored in the open shall be suitably covered to protect against rain, excessive heat or
sunshine.
The installation of conduits and cables, distribution panels and temporary lightings on site needed
by the Contractor is on his account and shall be made only in concern with the building contractor.
E. Damaged or defective materials shall be replaced at no cost to the Owner.
F. Handle materials and equipment carefully to prevent damage.
1.0 5 REQUIREMENTS:
A. Materials and equipment furnished under this specifications shall be of standard products of
manufacturers regularly engaged in the production of such materials or equipment and shall be the
manufacturer's latest standard design that complies to the requirements of this specifications.
B. Materials or products specified by name of manufacturers, brand or trade name or catalog reference
shall be the basis of final agreed price, and furnished under the contract. Where two or more
materials or products are named, the choice of these shall be optional with the Contractor Should
the Contractor wish to use materials or products other than those specified, he shall so state prior
to commitment of contract, naming the proposed substitutions and indicating what difference if
any, will be made in the based price, including changes it cost of all work affected thereby.
C. Contractor shall procure all equipment and materials specified In the drawings or In this
specifications and shall install the window air conditioning units and mini split units until
completion and according to conditions, graphic or verbal descriptions that appear In the drawings
or in this specifications. All electrical equipment must be designed specifically for 60 Hertz electrical
supply.
2.01 GENERAL:
All equipment brand shall be the product of LG or approval equal and delivered to the work site In
perfect condition.
2.02 CONTRACTOR FURNISHED MATERIALS:
Mini DX Split Air Conditioning Units:
A. General:
The unit shall be complete, consisting of evaporator units(indoor unit) and remote air cooled
condensing unit (outdoor unit).
Indoor unit shall be either horizontal or vertical draw-through construction and shall either be
free air blow or ducted type as required.
The separate assemblies shall be designed to be used together and ratings are based on
matched assemblies.
The outdoor control panel in NEMA class 4 enclosure shall be designed for easy connection
with terminal blocks clearly identified for easy termination of power and control wiring with
the indoor unit.
The outdoor unit shall be assembled on a heavy - gauge Integral steel base. designed for
outdoor installation, complete with weather proof control panel.
B. Direct expansion split type air conditioner includes support hangers, control fillers, refrigerant,
refrigerant piping and insulation, electrical wiring connection, condensate drain lines, anchor,
thermostats and vibration isolator.
Condenser Fans - Condenser fan will be direct-drive propeller type, discharging air upward or
horizontally.
Condenser fan motors will be totally enclosed, 1-phase type with class B insulation and
permanently lubricated bearings. Shafts will be corrosion resistant Fan blades will be statically
and dynamically balanced. Condenser fan openings will be equipped with PVC- coated steel
wire safety guards.
Compressor - Compressor will be hermetically sealed The compressor type shall be air cooled
reciprocating / rotary and it shall be mounted on rubber vibration isolators.
Condenser Coil - Condenser coil will be air cooled. Coil will be constructed of aluminum fins
mechanically bonded to copper lubes which are then cleaned, dehydrated, and sealed.
Evaporators Fans - Evaporator fans shall confirm to AMCA 210 and shall be forward curved
type or backward inclined centrifugal type specially designed and suitable for the operating
pressure. Fan motors shall confirm to NEMA MG2. Motar starters shall confirm to NEMA ICS
1. Motors shall be totally enclosed type. Motar starters shall be magnetic across- the line type
with weather-resistant enclosure.
Direct expansion coils - Direct expansion coils shall be fin-and-tube type constructed of
seamless copper tubes of minimum thickness equal to 0.63 mm and the aluminum fins of
minimum thickness equal to 0.19 mm, mechanically banded or soldered to copper tubes.
Casing and tube support sheets shall not be higher than 1.52 mm (16 gauge) galvanized steel,
farmed to provide structural strength. When required, multiple tube supports shall be provided
to prevent the tube sag Each coil shall be tested at the factory under water at not less than 2070
kap air pressure and shall be suitable for 1380 kpa working pressure. Coils shall be mounted
for counter flow service. Coils shall confirm to ARI 410.
Refrigeration Components - Refrigeration circuit components will include liquid line shutoff
valve with sweat connections, suction line shutoff valves with sweat connections, system charge
of refrigerant R22, and compressor oil.
Controls:
Complete packaged control system shall be provided as required for the safe and proper
operation of each unit including high and low pressure cutout witches and "fan-auto-on"
switches on the thermostat. All other controls Including motor starters and safety controls shall
be mounted inside the enclosure and all wiring thereof shall be factory wired.
Condenser controls:
a. Head pressure control shall be provided to ensure condensing temperature for proper
system operation at all ambient temperatures down to 0°C.
Air Volume Control:
b. Solid state variable speed fan motor controller may be provided In lieu of volume
dampers to control air-flow over coil, Control shall be set for a minimum of 35°C
saturated refrigerant condensing temperature.
Condenser Start-Up Control:
a. Condenser with start-up control package which permits start-up of compressor
regardless of low ambient temperatures shall be provided. Package shall temporarily
bypass system low pressure-state to permit start-up whenever minimum ambient
temperature is below design evaporator coil suction temperature.
Refrigerant Circuits:
a. Entire refrigerant circuit shall be dehydrated, purged and charged with refrigerant and
oil at factory, charges shall be the full amount required for operation.
2.03 PACKAGED ROOFTOP AIR CONDITIONING UNITS:
A. General:
1. Roof type air conditioners shall be designed, constructed, assembled, rated and tested in
accordance with ARI 210/240 and 340/360 and ANSI. Unit shall have capacities to meet
the design conditions specified or indicated.
B. Description:
1. Factory assembled and tested; designed for exterior installation; consisting of compressor,
indoor and outside refrigerant coils, Indoor fan and outside coil fan, refrigeration and
temperature controls, filters and dampers.
C. Performance Rating:
1. Cooling capacity of unit shall meet both the sensible heat requirements and total heat
requirements indicated. In selecting unit size, true allowance shall be made for "sensible
to total heat ratio" to satisfy required sensible cooling capacity.
2. Submittals shall include catalog selection data which accounts for sensible to total heat
ratio, entering air-conditions at evaporator and condenser entering air conditions.
3. Energy Efficiency Ratio (EER) should not be less than 10.
D. Casing:
1. Galvanized-steel conforming to ASTM A53M, construction with enamel paint finish,
removable panels or access doors with neoprene gaskets for inspection and access to
internal parts, minimum 12.5 mm (½ in.) thick thermal insulation, knockouts for
electrical and piping connections, exterior condensate drain connection and lifting lugs.
E. Indoor Fan:
1. Forward curved, centrifugal, belt driven with fixed or adjustable motor sheaves, grease-
lubricated ball bearings and motor.
F. Return/Exhaust-Fan:
1. Forward curved, airfoil or airfoil plug, centrifugal, belt driven with adjustable or fixed
motor sheaves, grease-lubricated ball bearings and motor. Mount fan and motor assembly
on base with rubber in shear isolators. Mount fan and motor assembly on base with spring
isolators having 50 mm (2 In.) deflection.
G. Outside Coil Fan:
1. Propeller type, directly driven by permanently lubricated motor.
H. Refrigerant Coils:
1. Aluminum-plate fin and seamless copper tube in steel casing with equalizing type vertical
distributor. Provide phenolic epoxy corrosion- protection coating to both coils.
I. Compressor:
1. Hermetic or semi-hermetic compressors with integral vibration isolators, Internal over-
current and over-temperature protection, internal pressure relief and crankcase heater.
J. Refrigeration System:
1. Compressor.
2. Outside call and fan.
3. Indoor coil and fan.
4. Four-way reversing valve and suction line accumulator.
5. Check Valves.
6. Expansion valve with replaceable thermostatic element.
7. Refrigerant dryer.
8. High-pressure switch.
9. Low-pressure switch.
10. Thermostat for coil freeze-up protection during low-ambient temperature operation or loss
of air.
11. Independent Refrigeration circuits.
12. Brass service valves installed in discharge and liquid lines.
13. Charge of refrigerant.
14. Hot-Gas Bypass:
a. Factory-installed valve.
15. Timed Off Control:
a. Automatic-reset control shuts compressor off after 5 minutes.
K. Filters:
1. 50 mm (2 in.) thick, fiberglass, pleated or throwaway filters in filter rack.
L. Heat Exchanger:
1. Aluminized steel or stainless steel construction for natural or propane-gas-fired burners
with the following controls:
a. Redundant dual gas valve with manual shutoff.
b. Direct-spark pilot ignition.
c. Electronic flame sensor.
d. Induced-draft blower.
e. Flame rollout switch.
M. Outside-Air Damper:
1. Linked damper blades, for 0 to 25 or 0 to 100% outside air, with manual slide and fully
modulating, spring-return damper motor and hood.
N. Economizer:
1. Return and outside air dampers with neoprene seals, outside- air fitter and hood.
a. Damper Motor:
1. Fully modulating spring return with adjustable minimum position.
b. Control:
1. Electronic-control system uses outside-air temperature, mixed-air and outside-air
temperature, outside-air enthalpy, mixed-air temperature and selects between
outside-air and return-air enthalpy to adjust mixing dampers.
c. Relief Damper:
1. Gravity actuated with bird screen and hood.
O. Power Connection:
1. Provide for single connection of power to unit with unit-mounted disconnect switch
accessible from outside unit and control-circuit transformer with built-in circuit breaker.
P. Unit Controls:
1. Solid-state control board and components contain at least the following features:
a. Indoor fan on/off delay.
b. Default control to ensure proper operation after power interruption.
c. Service relay output.
d. Unit diagnostics and diagnostic code storage.
e. Field-adjustable control parameters.
f. Defrost control.
g. Dehumidification control with dehumidistat.
h. Economizer control.
i. Gas valve delay between first- and second-stage firing.
j. Indoor-air quality control with carbon dioxide sensor.
k. Low-ambient control, allowing operation down to -17,78°C (O°F).
l. Minimum run time.
m. Night setback mode.
n. Return-air temperature limit.
o. Smoke alarm with smoke detector installed in supply air.
p. Low-refrigerant pressure control.
q. Digital display of outside temperature, supply-air temperature, return-air
temperature, economizer damper position, indoor-air quality and control
parameters.
Q. DDC:
1. Install stand-alone control module providing link between unit controls and DDC
temperature control system Control module shall be compatible with temperature-control
systems as specified in SECTION 15910.
R. Electromechanical Thermostat:
1. Staged healing and cooling on sub-base with manual system switch, on-heat-auto-cool and
fan switch auto-on.
a. Night setback operation with single-stage healing control with 7-day or 24-hour
lime clock with battery backup.
b. Fan-proving switch to lock out unit if fan falls.
c. Dirty-filter switch.
S. Thermostat:
1. Programmable, electronic; with heating setback and cooling setup with 7- day
programming; and the following:
a. Touch sensitive keyboard.
b. Automatic switching.
c. °c (°F) readout.
d. LED indicators.
e. Hour/day programming.
f. Manual override capability.
g. Time and operational mode readout.
h. Status indicator.
i. Battery backup.
j. Sub-base with manual system switch (on-heal-auto-cool) and fan switch (aula-
on).
k. Fan-proving switch 10lock out unit if fan fails.
l. Dirty-filter switch.
T. Optional Accessories:
1. Cold-Weather Kit:
a. Electric heater maintains temperature in gas burner compartment.
2. Service Outlets:
a. Two, 115 V, ground-fault, circuit-interrupter type.
3. PVC or copper condensate drain trap.
4. Dirty-filter switch.
5. Coil guards of painted, galvanized-steel wire, Hail guards of steel, painted to match casing.
6. Step-down or flush diffuser with aluminum grilles, insulated diffuser box with flanges and
interior transition.
7. Power exhaust fan.
8. Vertical vent extension.
U. Roof Curb:
1. Steel with corrosion-protection coating, gasketing and factory-installed wood nailer;
minimum height of 350 or 600 mm (14 or 24 in.).
V. Horizontal Discharge Roof Curb:
1. Steel with corrosion-protection coating, insulation, gasketing and factory-installed wood
nailer and configured to convert from down flow to horizontal airflow: minimum height of
650, 750, 925 or 1025 mm (26, 30, 37 or 41 in.),
W. Isolation Curb:
1. Rigid upper and lower steel structure with vibration isolation springs having 50 mm (2 in.)
static deflection and vertical and horizontal restraints; with elastomeric waterproof
membrane.
2.04 VENTILATION FANS:
1. Refer to the equipment schedule for ratings, capacities, and motor voltage requirements
Brand is to be Green heck, KDK, XPELAIR or approval equal for exhaust fans on kitchen
and fan type shall be belt drive centrifugal inline.
2. Toilet fans shall be wall mounted propeller fan, Provide solenoid operated outdoor louver
shutter for all wall mounted fans and louver color shall match With the wall color The
brand shall be KDK, XPELAIR or equal approved.
3. Fans shall be licensed to bear the "Air Moving and Conditioning Association, Inc."
Certified ratings seal. Ratings shall be not less than the values indicated, and shall be based
on 21 Degree Centigrade standard air.
4. Construction shall be in accordance with the AMCA classes of construction.
5. Fan wheels shall be statistically and dynamically balanced.
6. Furnish all accessories indicated.
7. Fan shall be direct drive motor designed for continuous operation with flexible aluminium
duct wall connection.
2.05 PIPE VALVES AND FITTINGS:
1. Furnish and Install all piping fittings, and specials shown, noted on the drawings, specified, or
required for the complete and operable mechanical installation.
2. Pipe shall be type and class and joined as described below:
a. Condensate Drainage:
1. Condensate drainage pipe shall be PVC schedule 40.
2. Provide a deep seal P-trap at each air fan coil unit.
b. Refrigerant Pipe:
Type "L" hard drawn copper joined by wrought copper sweat fillings made up with
95-5 solder and a suitable flux.
3. Valves: Fumish and install valves shown, noted or required for piping systems.
1.01 DESCRIPTION:
A. Scope of Work Included:
This Section covers the supply, installation, testing and putting into operation of all mentioned electrical
installation as specified herein, complete and in perfect working order, notwithstanding any item or
system component not mentioned in the drawings / specifications but necessary for system operation
shall be provided by the contractor The Contractor shall be responsible for locating exact position of the
equipment, upon the written approval of the Owner/Consultant prior to installation. Wherever details
are lacking, working drawings shall be submitted by the Contractor to owner/ consultant for approval.
Workmanship shall be of the best accepted standard practice for such installation.
1.02 QUALITY ASSURANCE:
A. Applicable Codes and Standards:
1. Saudi Arabian Standards Organisation – SASO.
2. STC (Saudi Telecom Company) Ministry of Communications, KSA.
3. Ministry of Industry and Electricity,KSA.
4. BICSI (Building Industry Consulting Service International).
5. Saudi Electricity Company (SEC).
6. Saudi Building Code.
7. National Electnc Code US – 2011.
8. Ministry of Communication, KSA.
B. All electrical work shall be carried out in accordance With the latest issue of National Electric Code,
regulations for the Electrical equipment of build published by IEEE, where not in contradiction with the
local power supply authority requirements.
All equipment and materials specified under this section must be manufactured in strict compliance
with approved specifications Acceptance test shall conform to the requirements of approved codes and
standards. All materials to be used shall be subject to the approval of the Owner/Consultant before
being ordered or Installed. Samples shall be submitted along with the technical material submittal for all
systems' components. The Contractor however shall make sure that the different materials of each
system fit together and form a homogeneous installation irrespective of the Owner/Consultant prior
approval.
Any work which is not In accordance with the local authority regulations or upto the satisfaction of the
Owner/Consultant shall be removed and repaired at the Contractor’s own expense. All materials
supplied must be standard factory finished or painted to the requirements of the Owner/Consultant.
1.03 SUBMITTALS:
A. Complete technical submittals of materials and equipment proposed for incorporation in the work
including the following:
1. List shall include manufacturer's name and material or equipment identification such as styles,
types or catalog numbers for complete identification purposes, country of origin.
2. Include complete set of catalogs (original) covering these submittals.
3. Compliance statement shall indicate compliance with appropriate standard as specified and must be
part of technical submittal.
B. Shop drawings shall be submitted for equipment not readily identifiable by information named above
and will be submitted for, but not limited to abinets, panel boards, supports etc.
C. Installation and testing / commissioning method statements.
D. As built drawings in soft and hard copies.
E. Submit samples of each type of material intended for the proposed work.
2.01 GENERAL:
All goods and products covered by this specification shall be from manufacturers and suppliers regularly
engaged in the manufacture or supply of electrical materials and accessories.
2.02 MATERIALS:
A. WIRE, CABLE AND CONNECTORS:
1. Provide electrical wires, cables and connectors, which conform to the relevant specification,
made of manufacture's standard materials, designed and constructed as recommended by
manufacturer and as required for the installation. (Manufacture: Riyadh cables or approved
equal).
2. Provide colour coding for single conductor as follows ( as per Saudi Building Code Table 51-2):
ØA ØB ØC Neutral
230 Volts and Brown Brown Black Grey Blue
Insulated equipment ground green and yellow,
3. Building wire shall not be less than 4,0 mm 2 for power and 4.0 mm2 for lighting tinned copper
annealed class B standard, 600 Volts, Shall be PVC insulated wires with 70° C.
4. Main and sub-main cables shall be multiple stranded, tinned, copper for sized as indicated in
drawing; rated 90°C for XLPE (cross linked polyethylene) 600V/1000V or approved equal and
these shall be constructed and tested according to IEC 60227 and BS-6004.
Thermostat cable shall be 2.5 mm2 tinned copper, 7 conductors, 600 Volt, vinyl jackets, IPCEA
color coded.
B. RACEWAY SYSTEM:
1. Non-metallic Conduit: Conduit shall be rigid PVC, schedule 40, moisture resistant, flame
retardant, resistant to impact and crushing. (Manufacture. NEPRO, FABCO, SAPPCO or
approved equal).
2. Electrical Metallic Tubing (EMT):
1. Electrical metallic tubing shall be manufactured in accordance with ANSI C80.3.
2. Electrical metallic tubing larger than Trade Size 2 shall not be used.
3. It shall generally be used for routing lI1e cables for branch circuits, control circuits and
signal circuits, except for the following conditions and locations:
a. Locations where there are a possibility of crushing and damaging during
installation or utilization.
b. Damp and wet locations or conditions.
c. Corrosive locations or conditions.
d. Hazardous classified areas.
3. Flexible Steel Conduit: Conduit shall be flexible steel, zinc coated, thread less, liquid-tight and
moisture-proof, conforming to ANSI C33 92, safety standard for flexible metal conduit Fittings
shall be as recommended by the conduit manufacturer, thread less hinged clamp type,
galvanized or cadmium plated malleable cast iron. Conduits and fittings used in wet areas shall
be extruded with Black or Grey Thermoplastic cover.
4. Conduit Supports: Conduit hangers and supports shall be galvanized cast malleable iron or
structural steel, with galvanized nuts and bolts. Supports shall be as recommended by the
conduit manufacturers.
5. Electrical Accessories: Electrical accessories, including switches, junction boxes, pull boxes and
socket outlets, shall be in accordance to relevant IEC/ SASO standards.
C. WIREWAYS, CABINETS & BOXES:
Materials:
a. Cabinets: Provide cabinets constructed of code-gauge steel minimum 2 mm thick,
for surface or flush mounting as Indicated on the drawings. Unless scheduled
otherwise on the drawings, use NEMA Type 3R galvanized cabinets in outdoor
location, and use primed and grey bake-on enameled NEMA 1 cabinets in dry, indoor
areas.
b. Boxes: 1. This is applicable for back boxes for switches & socket outlets, tap, Junction
and pull boxes.
2. Boxes shall be suitable for use in ambient temperature up to at least 55 degree Celsius. In
all other respects they should conform to IEC 60670.
3. Terminations In junction, switch and outlet boxes shall be of screwed type.
4. Provide switch, outlet, tap, junction and pull boxes with screw-fastened cover. Where
required, provide weatherproof boxes, NEMA Type 3R enclosures, with gasketted covers
and flanges designed to prevent entrance of rain water. Junction and pull boxes shall be
cadmium or zinc coated sheet metal for indoor application.
5. Where required watertight boxes, provide watertight boxes constructed of galvanized cast
metal with gasket, bolt-on covers, with tapped holes in bosses or hubs for conduit
entrances With integrally cast mounting lugs.
c. Wire ways: Provide wire ways assemblies of the sizes and configurations indicated.
D. PANELBOARDS:
1. General: The Contractor shall furnish and Install at locations as shown on the drawings
approved panel boards of a type indicated and specified herein. Panel boards shall comply with
the applicable sections of NEC and NEMA and shall be as manufactured by General Electric,
Westinghouse Electric Corporation, Legrand, Siemens, ABB or equivalent approved.
2. Dead front safe type, panel boards conforming to NEMA and SASO Standards are to be
provided. The copper bus size, the number of branch circuits, their amp rating and number of
poles for each panel board is noted on the drawings. Panel boards should have solder less lugs,
or connectors, in the correct number and sizes for conductors, on Incoming side and on the
load side of each branch circuit, and on ground and neutral bars.
Provide an insulated neutral bus and a bonded equipment ground bus, mounted at the
opposite end of the structure from the mains, and having numbered screw or lug terminals for
connection of wires.
3. Interiors: Interiors shall be completely factory assembled with Screw or Bolt-on Main
Breakers / Isolators and DIN rail mounted Branch Circuit Breakers. They shall be designed
such that switching and protective devices can be replaced without disturbing adjacent units
and without removing the main bus connectors.
4. Bus bars:
Main bus bars shall be plated copper, sized in accordance with standards to limit temperature
rise on any current carrying part to a maximum of 50°C above an ambient of 40°C maximum.
(A ground bus shall be included in all panels.).
Unless otherwise noted, full size insulated neutral bar taps for panels with single pole branches
shall be arranged for sequence phasing of the branch circuit devices. Neutral busbar shall have
a suitable lug for each outgoing feeder requiring a neutral connection.
5. Circuit breaker:
a. Branch and main circuit breakers shall be bolt-on type and shall have frame sizes, trip
settings, and number of poles as indicated on the drawings.
b. All circuit breakers shall have their trip rating clearly marked and visible. Branch and
main MCGBs rated 400 Volts shall have an interrupting rating of not less than 25 KA
rms symmetrical/or as shown In the drawings, at rated voltage and shall be calibrated
at 50°C.
c. MCCBs should conform to IEC 60947 - 2. They should be provided with thermo
magnetic trip releases as per ratings indicated In the drawing. Thermal releases
adjustable from 0.7 to 1 of nominal current and fixed magnetic trip at 10 time's of
nominal current.
d. MGB are to be provided with thermal release and Instantaneous magnetic release type
C. they should have an Interrupting capacity of not less than 14 KA. MGBs should be
as per lEC 60898 -1.
e. Manufacturers: Provide breakers manufactured by one of the following (breakers
selected should be compatible with panel board selected): General Electnc, Legrand,
Schneider Electric, Siemens, ABB, Westinghouse, Mitsubishi Electric.
6. Enclosures: Ready to use panel board cabinets shall be constructed of sheet steel minimum 2
mm thick and shall be of suitable size to provide adequate space around the perimeter for risers
and outgoing circuits. The enclosures should be fitted with DIN rails, plates, and face plates.
Outgoing MCCB or MCBs are to be fitted in a row.
A directory frame with transparent cover shall be furnished and installed on the inside of the
door of each panel board.
All cabinets shall be lockable and supplied with master keys.
Enclosure degree of protection should be NEMA 1 - indoor type.
A directory card with clear plastic cover shall be supplied mounted on the inside of each door.
Directory should be Arabic and English. Provide an engraved nameplate for each panel section.
At least four interior mounting studs with adjustable nuts shall be provided.
Enclosures shall be provided with removable blank ends.
E. WIRING ACCESSORIES:
1. Includes all receptacles, switches, wall plates, flexible cable outlets & spur units. Equipment
should be Legrand, General Electric, ABS, Siemens, Pass & Seymour or equivalent make.
2. Switches:
a. Switches shall be flush mounted with the operating handle in upward position when
in the "ON" position.
b. Switches used on lighting branch circuit shall be quick make, quick break, with silver
alloy Contact, rocker, operated with quick operating mechanism rated at 16 amperes,
250 volts AC or higher capacity as required by the circuit controlled in accordance
with the drawing.
c. Switches shall be single, duplex, triplex, two way flush mounted type as indicated on
the drawings.
d. Plates:
i. Plates shall be of rectangular shape to the approval of the Owner/Consultant.
ii. Fixing screws shall be chromium plated and polished. Screw head shall be
finished to suit plate.
iii. Plates shall be designed to match associated devices. Plates for multigang switches
shall be provided as required/ indicated in the drawings.
iv. Plates for all electrical devices on walls shall be impact resistant plastic, and of the
same pattern and color throughout.
3. Receptacle outlets:
Provide single or duplex type receptacles, 13 amperes, 250 Volts, with metal plaster ears, side
wiring, as per BS1363: Part 2. Outlets can be switched or without switch, as indicated in the
drawing.
4. Special purposes power receptacle outlets:
These shall be single, rated 13 A, 45 A, 50 A, 250 Volts, polarized, 3 or 4 wires grounding type,
flush mounted, as per BS 1363: Part 2, as shown in the drawing.
5. Range Receptacles:
Range receptacles shall be single, 50 amperes, 250 volts polarized, 3 wire grounding type, flush
mounted.
6. Flexible cable outlets:
Flexible cable outlets shall be conforming to BS 5733 fitted with clamp and outlet membrane as
required in the drawing.
7. Weatherproof switches and receptacles:
Weatherproof Switches shall consist of acceptable flush mounting switches as specified herein
NEMA type 4 gusseted through a shaft in the matching cast metal boxes. Switch enclosures
shall be type MC or MCC, made by Crouse hinds Co, Syracuse, N.Y or equivalent. Gusseted
and weatherproof cover including corrosion
resistant fasteners shall be provided Weatherproof receptacles shall be standard single flush
receptacles as specified herein gusseted cast metal NEMA type enclosures, with gusseted cover
screw.
F. SAFETY/DISCONNECT SWITCHES:
1. General: Provide safety and disconnect switch with rating and sized as shown on the drawings.
2. Enclosures: Provide NEMA I, for indoor enclosures and NEMA 3R/4 for outdoor enclosures
for switches.
G. MOTORS AND MOTOR STARTING EQUIPMENT:
1. Motor Operating Characteristics:
Motors shall be rated for 60 HZ operation at the following voltages:
230 V single phase may by used for Kitchen equipment, pumps and major appliances.
Motors shall have a horsepower rating based on continuous operation at full load, 50°C
maximum ambient, and 1.0 service factor without exceeding the requirements of NEMA.
2. Magnetic Starters:
Magnetic starters shall be weather proof with 50 degree Celsius operating
temperature, as specified in NEMA ICS, Industrial Controls and Systems, and shall
be fitted with ambient compensated thermal overload relays, sized for nameplate
amperes and service factors. Overload relays for starters shall have normally closed
contracts that are manually reset with the compartment door closed.
Starters for single-phase motors shall be manual type with two pole-toggle units for
across-the-line-starting, and fitted with one overload element. Starters shall be
surface or flush mounted.
The control voltage for all starters and for all control circuits shall be 230 V unless
otherwise specified.
3. Controls:
Unless otherwise indicated or required by the driven equipment, all starters shall be
provided with heavy duly start-stop push buttons, one red pilot light, one green
pilot light and one reset pushbutton. Push buttons shall be a one unit momentary
contact "START” or "STOP" with normally open and normally closed contacts as
required by the wiring diagrams and with lockout attachments. All devices, such as
push buttons, selector switches and pilot lights shall be the heavy-duly-type.
All starter pushbuttons shall be labeled in Arabic and English, stating which
machine they control, and the functions of the various buttons. Words such as
START and STOP shall be used.
4. Enclosures:
Individually mounted starters shall be totally enclosed in a metallic enclosure of the
required NEMA lype4. It shall not be possible to open the enclosure door with the
starter energized.
5. Motor Features:
a. Insulation:
The motor windings shall be epoxy-coated or otherwise suitably treated so that
the insulation is moisture-resistant and non-hydroscopic. Motor windings shall
have class B insulation as specified in NEMA MG-1 for specified operating
conditions, Class F insulation may be used when approved.
b. Enclosures:
Motor enclosures shall be severe duly, totally-enclosed fan-cooled (TEFC) or
totally-enclosed non-ventilated (TENV), whichever is standard for the rating. It
should be as per standard of pump manufacturer but should be suitable for
installation in underground pump room.
6. Finish:
Motors shall be painted as specified In the manufacturer's standard specifications
for hot and humid conditions. The color shall be grey.
7. Identification:
All motors shall have a stainless steel nameplate giving a complete motor
description as specified in NEMA MG1, including AFBMA bearing replacement
numbers. The direction of rotation, in reference to the phase sequence terminal
marking, when viewing the motor from opposite the drive end, shall be shown.
H. GROUNDING:
1. Low voltage distribution system shall be provided with a separate green and yellow insulated
grounding conductors for each single or three-phase feeder. The required grounding
conductors shall be Installed in common conduit with the related phase and/of neutral
conductors Single phase branch circuits required for 230 Volts lighting, receptacle and motors
shall consist of phase neutral and ground conductors installed in common conduit.
2. The electrical system ground and equipment ground shall be connected to the common ground
base. All equipment metal frames shall be adequately connected to the ground bus. Ground
rods of copper-clad 16 mm diameter, 3.0 m long shall be installed as shown in the drawings.
High electrical conductivity with soft-drawn bare-stranded copper wire ground cable should be
used to form the ground grids. PVC insulated copper conductors shall be for final connections
of formed ground grids to structures, equipment etc.
3. All grounding medium shall be bonded together This shall include electric, telephone and TV
antenna system ground and other underground metallic piping, where they enter into the
building The common ground connections shall be made by using main size conductors and
connectors. Grounding system shall be as shown on the drawings.
4. If a total ground resistance of 5 ohms or less is not obtained with tile ground rod, a longer rods
or additional rods shall be installed until a combined ground resistance of 5 ohms or less is
obtained.
I. OTHER RELATED WORK:
A. The Contractor shall furnish all materials, labor, equipment and perform all operations
necessary for the installation of hand holes and manholes.
a. Provide excavation, shoring, bracing, backfilling, grading etc in accordance
with the applicable portions of the specification. Concrete shall be 25 N/mm 2
concrete and shall not be constructed until final conduit grading has been
determined, including any field changes required by underground
interferences. Shop drawings shall be submitted for all hand holes and
manholes.
b. Cable racks are to be heavy duty type with adjustable arms, and free moving
porcelain saddle Insulators. Pulling in irons shall be provided opposite each
duct entrance and as detailed.
B. Metering Equipment:
a. Contractor shall coordinate with SEC for power supply and metering arrangements,
Owner will be responsible for all the required fees.
b. Kilowatt hour meter opening at boundary wall shall be provided as required and
approved by SEC.
1.0 1 DESCRIPTION:
A. To supply, install, connect and test lighting fixtures:
The work includes the provision of labor, material, equipment, transportation and services required to
completely furnish, install, connect, test and commission to operate In proper order all lighting fixtures
as shown on the drawings and herein specified and as required.
B. Related work specified elsewhere:
Section 1601- Electrical Work.
1.0 2 QUALITY ASSURANCE:
A. Lighting fixture shall be of type and manufacturers as as specified In the “schedule of lighting Fixtures”,
except products of similar type and features of approved equal manufacturers are acceptable.
1. The fittings have to be of good quality and the housing thereof must be made of lacquered
metal or as per specified product details. The fittings must comprise rotor lamp sockets and a
ground terminal has to be provided.
2. All fixtures and lamps shall be new components of the same type, Size, rating, functional
characteristics and make should be interchangeable.
1.0 3 APPLICABLE CODES AND STANDARDS:
The following codes and standards are intended to provide an acceptable level of quality for materials and
products. The Contractor may propose alternative codes and standards provided they are of equal or better
quality than the referenced codes and standard and are submitted for review and approval.
SAUDI ARABIAN STANDARDS ORGANISATION:
Heavy duty stainless steel latches. catches, release mechanism, hinges, rivets.
screws, bolts, studs. nuts, additional washers and springs with the following
requirements
Latches and catches Captive type
Operating hardware Self-retaining type
2.09 FINISH:
Baked Enamel:
Non-specular finish consisting of six-stage hot cleaning wash, phosphate coat, prime coat and finish coat of
sprayed white or other color acrylic enamel, baked at 177°C (350°F) for a minimum of 30 minutes, with the
following additional requirements:
Undercutting of enamel film from scored line after exposing to 10 per cent salt spray for 1.500 hours, per
ASTM 3117 1.6 mm (1/16 inch) maximum.
Baked white enamel after 100 hours exposure to fadeometer: 86 percent, minimum reflectance factors, no
appreciable visual colour change.
Porcelain Enamel:
Opaque fused vitreous surface flush with 88 percent average reflectance factor.
Alzak coating 14 stage process for permanently sealed specular or semi specular finish, as shown in
accordance with patented electrolytic process.
Anodic Coating:
milligrams per mm2 hot water seal overall, tested in accordance with the following requirements:
Undercutting of anodic film from scored line after exposing to 10% salt spray for 1,500 hours, per ASTM
BII7:1.6 mm (1/16 Inch) maximum.
Factory Painting:
Consisting of through chemical cleaning wash, phosphate coat, coat of trust inhibiting primer and finish coat
of sprayed Federal Colour No, 20040 Paint.
Field Painting:
Not permitted without Client approval.
3.01 GENERAL:
Except as may be described in Part II and Part III of this Section refer to the applicable provisions of
Section 1601.
3.02 INSTALLATION:
Furnish, assemble, install and wire up complete, all lighting fixtures Fixtures shall be complete with
lamps, lamp holders and all necessary accessories. All fixtures shall be wired in accordance with
temperature limitations.
Fixtures shall be rigidly mounted by approved means. Pendant-hung fixtures shall be equipped with
approved ball type aligners.
Provide adequate protection for fixtures during construction. At completion of work, all fixtures clean
and free from foreign materials.
Before starting the manufacture of any fixtures under this Section, the Contractor shall submit complete
technical of each fixture specified The Contractor shall submit a complete sample of all of the fixtures
specified.
The Contractor shall note that proper framing of the ceiling shall be provided for all recessed fixtures.
All fixtures recessed in plaster ceilings shall be provided with plaster boxes. The ceiling installation, air
diffusers etc must be in line and present a neat and orderly appearance. Recessed fixtures shall be
removable from below to allow access to an outlet in the ceiling.
Furnish and set all inserts, anchors, studs and hangers for the support of lighting fixtures and respective
equipment and make all necessary adjustments required thereto Where fixtures are surface mounted,
neat holes shall be cut in the hung ceilings as required for the fixture supports. All supports, hangers,
channels, bolts etc shall be galvanized. Two supports shall be provided for each fluorescent fixture, one
at each end of the fixture.
=== End of Section ===
1. OVERVIEW:
This project, B1-28-10012, provides for the Home Ownership Lot Development, Phase I, at Al- Mutrafiah, Jubail
Industrial City in the Eastern Province of the Kingdom of Saudi Arabia.
This Contract will accommodate 491 house units, in total, with varying lot sizes for sectors F1-1, F1-2 and F1-3
and the construction of three (3) Duplex type houses for the Imam & Muazzin to be built on three (3) lots to be
selected by Saudi Aramco, in addition to three (3) Local day mosques.
2. DESCRIPTION OF THE AREA:
The site is located in the Mutrafiah District of the Jubail Industnal City residential area.
Sketch No 1. Site Location Map.
Sketch No. 2 Master plan and Location of Mosques.
Mutraflah District is a new development within the Jubail Industrial City residential area SAUDI ARAMCO has
been granted a total of 491 villas.
The infrastructure (Initial Development) to the Saudi Aramco is completed by another Contractor. The final
development shall be completed once the houses are constructed.
3. SCOPE OF WORE:
3. 1 GENERAL:
3.1. 1 Construct the Three (3) Dally Mosques as per the IFC drawings and in accordance with
Royal commission requirements.
3.1. 2 Description of the Mosques.