METHOD STATEMENT
OF
PIPE BRIDGE LAUNCHING
(SG SEBATANG)
Contractor:
H.K.K & SALEM CONSTRUCTION SDN BHD
96000,SIBU,SARAWAK.
TEL : 084-333123/339089
FAX : 084-333621
TABLE OF CONTENTS
1.0 INTRODUCTION
2.0 REFERENCE
3.0 MACHINERIES & MATERIAL RESOURCES
4.0 METHOD OF CONSTRUCTION
5.0 SAFETY, HEALTH & ENVIRONMENT COMPLIANCE
6.0 APPENDICES
1.0 INTRODUCTION
The project of Construction and Completion of Proposed 800mm ND MSCL Pipeline from
Nyabau Water Treatment Plant to Kidurong Industrial Estate, Bintulu Division, Sarawak
is implemented by Jabatan Bekalan Air Luar Bandar (JBALB). The site of proposed works
is along Jalan Bukit Nyabau and Jalan Kidurong where the total pipe route is around
9.71km following by road side within road reserve from Nyabau Treatment Plant. Pipe
route A along Jalan Bukit Nyabau is about 3.5km and Pipe route B along Jalan Kidurong
is about 6.21km.
The document describes the typical construction method with its governing vectors to
enable the work to be executed smoothly and efficiently. The details of the documents may
be refined, enriched and further improvised based on the actual site scenario and
requirements. This document comprises the following:
1. Setting Out
Prior to any commencement of any physical works, a professional land surveyor shall
be appointed to carry out demarcation works and establish temporary bench marks on
site, upon obtaining all the necessary survey data. A joint survey to check existing
ground levels shall be carried out under the inspection of resident engineer.
As for pipe bridge, the piling point for each pipe support shall be pegged and jointly
reviewed and confirmed by resident engineer.
2. Preparation on Site
When any material is disposed outside the site, the disposal material shall be graded to
a neat appearance and shall not obstruct natural drainage or cause damage to road
highways or property. All precautions shall be taken to prevent any erosion of the soil
on the affected areas.
All unsuitable material and surplus suitable material shall be run to spoil in tips
approved by the engineer.
All necessary machineries, materials and resources shall be mobilized to site
accordingly.
Temporary bridges, barriers, traffic signals, lighting, reflective warning signs and
watchmen shall be provided to ensure the safety and convenience to public users.
3. Sequence of Construction
The following details describe the method of construction for concrete pipe support
and pipe bridge launching:
Length = 32m
NOTES
1. All non-essential personnel should keep out of the working area during assembly, operation and
disassembly of the crane.
2. Safety factor of the crane load is 1.49
5.0 SAFETY HEALTH AND ENVIRONMENT COMPLIANCE
Workers & Operators
Operator with valid driving license with certificate of competency.
Alcohol and drug were strictly prohibited from project area.
Usage of PPE are mandatory to be used at all time when entering work site based on
activity involved.
Sub-Contractors
Conduct Safety Toolbox meeting.
Equipment
Ensure equipment in proper working condition and well maintained.
Equipped with fire extinguisher.
Daily equipment checks before commencement of work.
Only authorized specialists are allowed to repair, maintain, clean and execute
modification on the machines.
Safety Precautions
1. Pilot Trenching
Activity Hazard Safety Precaution
Pilot trenching 1. Underground 1. Excavation activities for pilot trenching must always
for Piling Works cable supervised by supervisor
2. Slowly excavate and don’t excavate too deep at once
3. If any underground cable being accidentally
excavated, immediately stop and go far from the area.
4. Supervisor must immediately inform HSE personnel
for further action.
5. Inform SEB and ask for their supervision during pilot
trenching
2. Piling Works and Reinforced Concrete Works
Piling work 1.Sharp object 1. Wear suitable PPE i.e. safety boots, safety
helmet hand glove
2. Falling
object/Sling 2. Not related personal must not go near to piling
parted work area.
3. Unguarded 3. Don’t used damaged wire sling
machineries, tool
and equipment 4. Do not remove machinery safety guard.
4. Swing and hit 5. To do inspection/audit on machinery and
5. Oil leakage equipment weekly/monthly.
5. Lifting work
6. Welding work
Plastic Barrier
45T Crane
Pipe Bridge
30m
Temporary Road Closed
Signage
ge
30m
Caution Signage