SHREE BALAJI TEST HOUSE PVT. LTD.

DAILY PROGRESS REPORT OF GORAKHPUR LINK EXPRESSWAY PROJECT

Date of Reporting : 20.01.2020

Day Wise Total


Chainage Total BH
Date Machine No. Structure BH No. Running Running Northing Estaing Remarks
No. Depth
Depth Depth

20.11.2019 1 MNB 6+235 8 - - 40 mtr. 2951030.2648 727239.2248 Completed

21.11.2019 1 MNB 6+235 7 - - 20 mtr. 2950922.2131 727120.5563 Completed

24.11.2019 2 MNB 6+235 4 - - 40 mtr. 2951058.2361 727191.4909 Completed

24.11.2019 1 MNB 6+235 3 - - 40 mtr. 2951055.9425 727220.446 Completed

25.11.2019 2 MNB 6+235 1 - - 20 mtr. 2951159.8910 727280.402 Completed

25.11.2019 1 MNB 6+235 2 - - 20 mtr. 2951120.8250 727230.1464 Completed

27.11.2019 2 MNB 6+235 10 - - 40 mtr. 2950991.6142 727212.7423 Completed

27.11.2019 1 MNB 6+235 5 - - 40 mtr. 2951016.9442 727194.2178 Completed

29-11-19 1 MNB 6+235 9 - - 40 mtr. 2951010.8164 727226.1702 Completed

29-11-19 2 MNB 6+235 6 - - 20 mtr. 2950998.1684 727149.0372 Completed

1.12.2019 2 MNB 2+058 2 - - 20 mtr. 2955121.2342 728132.7995 Completed

1.12.2019 1 MNB 2+058 3 - - 40 mtr. 2955067.654 728161.0777 Completed

30.11.2019 1 MNB 2+058 1 - - 20 mtr. 2955187.4969 728154.9384 Completed

2.12.2019 2 MNB 2+058 5 - - 36 mtr. 2955038.6704 728162.5624 Completed

2.12.2019 1 MNB 2+058 8 - - 40 mtr. 2955063.4008 728191.0845 Completed

3.12.2019 1 MNB 2+058 6 - - 20 mtr. 2954988.7359 728165.1204 Completed

3.12.2019 2 MNB 2+058 10 - - 40 mtr. 2955034.4388 728192.5682 Completed

8.12.2019 1 MNB 2+058 7 _ _ 20 mtr. 2954922.4929 728142.9444 Completed

5.12.2019 2 MNB 2+058 13 _ _ 40 mtr. 2955046.5909 728106.8342 Completed


Prepared by Checked by Approved by

SHREE BALAJI TEST HOUSE PVT. LTD.


DAILY PROGRESS REPORT OF GORAKHPUR LINK EXPRESSWAY PROJECT

Date of Reporting : 20.01.2020

Day Wise Total


Chainage Total BH
Date Machine No. Structure BH No. Running Running Northing Estaing Remarks
No. Depth
Depth Depth

8.12.2019 1 FLYOVER 0 4 _ _ 20 mtr. 2957109.649 728030.938 Completed

8.12.2019 2 FLYOVER 30 5 _ _ 20 mtr. 2957080.992 728057.94 Completed

8.12.2019 1 FLYOVER 150 7 _ _ 20 mtr. 2956961.150 728064.079 Completed

9.12.2019 2 FLYOVER 80 6 _ _ 40 mtr. 2957029.753 728035.031 Completed

10.12.2019 1 MNB 17+477 2 _ _ 20 mtr. 2951120.8250 727230.1464 Completed

10.12.2019 2 MNB 17+477 3 _ _ 40 mtr. 2951055.9425 727220.4460 Completed

11.12.2019 1 MNB 17+477 1 _ _ 20 mtr. 2951159.8910 727280.4020 Completed

11.12.2019 2 MNB 17+477 4 _ _ 40 mtr. 2951058.2361 727191.4909 Completed

13.12.2019 1 MNB 17+477 5 _ _ 20 mtr. 2951016.9442 727194.2178 Completed

13.12.2019 2 MNB 17+477 6 _ _ 20 mtr. 2950998.1684 727149.0372 Completed

16.12.2019 1 MNB 17+477 7 _ _ 40 mtr. 2942502.4502 720363.5154 Completed

16.12.2019 2 MNB 17+477 8 _ _ 40 mtr. 2942477.7070 720358.6740 Completed

16.12.2019 1 FLYOVER 27+680 6 _ _ 20 mtr. 2932896.941 719715.5380 Completed

17.12.2019 2 LVUP 17+290 2 _ _ 20 mtr. 2942719.1556 720455.2215 Completed

17.12.2019 1 FLYOVER 27+630 5 _ _ 40 mtr. 2932920.352 719766.550 Completed

18.12.2019 2 LVUP 17+290 1 _ _ 20 mtr. 2942664.7108 720442.1155 Completed

18.12.2019 1 LVUP 17+290 3 _ _ 20 mtr. 2942610.1225 720429.6209 Completed

18.12.2019 _ FLYOVER 27+450 1 _ _ 20 mtr. 2933061.560 719878.176 Completed

19.12.2019 1 VUP 10+210 1 _ _ 20 mtr. 2947987.0562 724701.7304 Completed


19.12.2019 2 VUP 10+210 2 _ _ 20 mtr. 2948039.5735 724734.6839 Completed

Prepared by Checked by Approved by

SHREE BALAJI TEST HOUSE PVT. LTD.


DAILY PROGRESS REPORT OF GORAKHPUR LINK EXPRESSWAY PROJECT

Date of Reporting : 20.01.2020

Day Wise Total


Chainage Total BH
Date Machine No. Structure BH No. Running Running Northing Estaing Remarks
No. Depth
Depth Depth

19.12.2019 3 FLYOVER 27+570 3 _ _ 40 mtr. 2932967.421 719803.758 Completed

20.12.2019 1 VUP 10+210 3 _ _ 20 mtr. 2947934.5390 724668.7769 Completed

20.12.2019 2 VUP 9+218 3 _ _ 20 mtr. 2948774.7306 725207.2967 Completed

20.12.2019 3 FLYOVER 27+520 2 _ _ 20 mtr. 2933022.459 719814.761 Completed

20.12.2019 4 FLYOVER 27+600 4 _ _ 40 mtr. 2932959.700 719765.150 Completed

21.12.2019 1 VUP 9+218 1 _ _ 20 mtr. 2948821.5295 725238.0516 Completed

21.12.2019 2 VUP 9+218 2 _ _ 20 mtr. 2948868.3284 725268.8065 Completed

21.12.2019 3 FLYOVER 27+750 7 _ _ 20 mtr. 2932826.214 719692.132 Completed

23.12.2019 1 LVUP 8+792 2 _ _ 20 mtr. 2949224.3343 725502.7634 Completed

23.12.2019 2 LVUP 8+792 3 _ _ 20 mtr. 2949130.7365 725441.2536 Completed

23.12.2019 3 PUP 4+045 A1 _ _ 20 mtr. 2953185.6436 727589.5628 Completed

23.12.2019 4 PUP 2+753 A1 _ _ 20 mtr. 2954372.9947 728062.8200 Completed

24.12.2019 1 LVUP 8+792 1 _ _ 20 mtr. 2949177.5354 725472.0085 Completed

24.12.2019 2 LVUP 1+650 2 _ _ 20 mtr. 2955518.3882 728125.2211 Completed

24.12.2019 3 LVUP 1+650 3 _ _ 20 mtr. 2955406.5349 728130.9510 Completed

25.12.2019 1 PUP 8+245 A1 _ _ 20 mtr. 2949632.6725 725775.3050 Completed


26.12.2019 1 FLYOVER -150 1 _ _ 20 mtr. 2957260.757 728048.731 Completed

27.12.2019 2 PUP 0+500 A1 _ _ 20 mtr. 2956610.9556 728069.2518 Completed

Prepared by Checked by Approved by

SHREE BALAJI TEST HOUSE PVT. LTD.


DAILY PROGRESS REPORT OF GORAKHPUR LINK EXPRESSWAY PROJECT

Date of Reporting : 20.01.2020

Day Wise Total


Chainage Total BH
Date Machine No. Structure BH No. Running Running Northing Estaing Remarks
No. Depth
Depth Depth

28.12.2019 3 FLYOVER -80 2 _ _ 40 mtr. 2957189.544 728026.846 Completed

10.01.2020 1 VUP 22+715 3 _ _ 20 mtr. 2937251.1871 720399.1066 Completed

12.01.2020 2 VUP 22+715 1 _ _ 20 mtr. 2937307.2014 720372.5286 Completed

13.01.2020 1 VUP 22+715 2 _ _ 20 mtr. 2937364.0139 720347.7024 Completed

14.01.2020 2 PUP 24+010 2 _ _ 20 mtr. 720984.9680 2936227.5961 Completed

15.01.2020 1 PUP 24+010 1 _ _ 20 mtr. 721008.9109 2936179.7527 Completed

16.01.2020 1 LVUP 24+625 1 _ _ 20 mtr. 721121.0552 2935581.8880 Completed


Work not done due to
17.01.2020 _ _ _ _ _ _ _ _ _ heavy rain

18.01.2020 1 LVUP 24+625 2 _ _ 20 mtr. 721123.7122 2935637.8249 Completed

19.01.2020 2 LVUP 24+625 3 _ _ 20 mtr. 721115.7881 2935526.1363 Completed

Note: 1. Total Sixty Six (66 nos.) Bore Holes are completed.
2. Site work is being stopped by the farmer ( water lodged ) and due to land issue problem from date 28.12.2019 to 8.01.2020

Prepared by Checked by Approved by