Professional Documents
Culture Documents
! - 1996 (реальн исп) - Heberlein, G. E. -Report on enclosure internal arcing tests
! - 1996 (реальн исп) - Heberlein, G. E. -Report on enclosure internal arcing tests
I
I
I
I
I
I
Report on Enclosure I
I
I
I
I
I
I
I
I
he improvement of electrical equipment is Maintenance had just completed overhauling an I
an ongoing process including investigative old size 3, two-speed, 460 V MCC starter unit. As I
research. This is a report on research work the contactor was closed to start up the cooling I
concerning factors regarding high-energy arcing tower fan, a loud “rattling” was heard from inside I
faults, the tests conducted on containment of these the starter compartment. The electrician, who was I
faults, and standards addressing arcing fault test I
dressed in flame-retardant clothing, reached for the I
requirements. This report is focused on low-voltage,
starter disconnect as two other electricians in the I
600 V class Motor Control Centers (MCCs),but the
issues presented should not be limited to only this area, dressed in street clothes, ran for cover. As the I
electrician opened the disconnect there was a loud I
type of electrical equipment. Also, the scope of this
I
work is restricted to a high-energy arcing fault explosion. The MCC starter unit door was blown
I
occurring in a latched or closed compartment dur- open and the electrician was engulfed in flaming hot
I
ing “normal” operating conditions and does not gases. Fortunately, his protective clothing and face I
include arcing faults occurring in compartments shield prevented serious injury, and his co-workers I
when the compartment door is open. were able to get behind other equipment and also I
In one major chemical company over a five-year escaped injury. Although difficult to reconstruct, I
period there were approximately 75 incidents in I
the findings of the investigation were that the rat-
I
which an arcing fault occurred. An incident was tling noise was actually caused by the contactor I
defined as an event that did, or had the potential to, armature, which was missing its shaded pole piece. I
result in personal injury and/or major equipment Subsequently, the electrician actually opened the I
damage. Roughly 75% of these occurred in 600 V switch under motor accelerating current and the I
class motor control equipment. Of these incidents, I
older switch was unable to contain the current in
I
43 occurred with persons present, and 23 burn the arc chute, resulting in a phase-to-ground fault I
injuries resulted. Several of these injuries resulted and ultimately a phase-to-phase fault in the vertical I
due to the misconception that an MCC with doors bus structure. I
and covers properly fastened would protect the In a second incident the operator was performing I
individual under all arcing fault conditions. These I
a routine switching operation to energize a size 2
I
findings have resulted in expanding their personal MCC starter unit. An explosion initiated in the I
protective equipment usage to many “routine” op- starter unit, causing the unit door to blow open. The I
erations such as switching. The following are actual operator, although wearing protective clothing, did I
incidents and are typical of many that occur annu- receive second-degree burns on his upper arm, I
ally throughout industry. I
where there was a gap between his clothing and
I
glove. Investigation revealed that a metal lever that I
This article appeared in its originalform at the 1994 was part of the switch operator had come loose and I
Petroleum and Chemical Industry Conference in Vancou- fallen into the line side fuse clips, causing a line-to- I
ver, B.C. Heberlein, an IEEE Senior Member, and ground arcing fault. I
I
Higgins, an IEEE Member, are with Allen-Bradley The arcing fault phenomenon has been well
I
Company of Milwaukee, Wis. Epperly, an IEEE Senior known particularly for medium- and high-voltage I
Member, is with E.I. du Pont de Nemours C. Co. of equipment. Ralph Lee and others began raising I
Wilmington, Del. awareness of this hazard in low-voltage equipment I
-
I generated by these high currents is proportional to
I enclosure t o contain a high-energy 2
the square of the peak current (Ip ) and is therefore
I
I
urcing fault. maximized in a bolted fault. Certainly, the bolted
I
fault tests are essential to qualify equipment to
I withstand short circuit stresses. However, the
I bolted fault withstand test is not a measure of the
I in the early to mid-1980s 11, 2). Lee’s IEEE paper capabhty of an enclosure to contain a high-energy
I
“The Other Electrical Hazard: Electric Arc Blast arcing fault Enclosure containment is relative to
I
I Burn” was one of the first attempts t o quantify this the amount of thermal energy transferred over a
I hazard [lf.This signaled industry to begin estab- short period of time This rapid transfer of thermal
I lishing standards and practices that address the energy superheats the surrounding air, causing
I hazards presented by the high temperatures and rapid expansion, which in turn causes high pressure.
I ’
Accompanying this gas expansion may be pressure
pressures developed in an arcing fault. Although
I
I there have been subsequent papers addressing this shock waves and gas ionization, which can create
I hazard, the subject, like many facing engineering, secondary faults due to the highly conductive ions.
I is complex and difficult to define. Finding solutions This thermal energy is proportional to the square of
I to the problem, and furthermore cost-effective so- the rms current (Irm:) multiplied by the arc resis-
I tance, while the pressure developed is proportional
lutions, is recognized to be a substantial technical
I
challenge. One common solution today is that to the rate of transfer, change in temperature per
I
I many companies are now requiring electricians and unit of time (dT/dt), of air heating created by this
I operators to wear personal protective equipment thermal energy
I (PPE), e.g., flash suits, flame-retardant clothing, It should be noted, as developed by Lee, that the
I maximum fault energy transfer occurs when the
hard hats with face shields, leather gloves, etc.
I
Although the PPE probably represents the best mpedance across the arc equals the impedance of
I
I “solution” to date, it can introduce other potential the distribution system El). There is a continuum
I safety issues, such as restricted visibility, loss of
I dexterity, and heat exhaustion for personnel.
I The purpose of this article is to share our test
I
I
results with others and to raise awareness so that Bolted L. A’CW
I work can continue in the area of arc containment,
E’ectromagnetic Thermal Energy
I i.e., guidance for standards, manufacturers, and Energy
I
I
users. The tests are focused on low-voltage MCCs, +II) :1 I2t)
(1
I
I
I
I
I
I
I
In addition to the IEC
I
test requirements, a pres- I
s u r e t r a n s d u c e r was I
mounted in the side wall of I
the MCC unit to monitor I
I
pressures encountered in
I
the MCC unit as a result of I
the high-energy arcing I
faults. The particular unit I
under test had an experi- I
mental latching system on I
I
its door, with the exception
I
of Tests 9 and 10, which I
utilized the standard latch- I
ing system. I
The experimental latch I
I
under test shown in Fig. 4
I
was specifically designed I
with two main features to I
enhance the capability of I
the unit door to withstand I
I
the forces developed by the
I
high-energy arcing fault: I
1. The latching pin is a I
quarter-turn “bayonet” I
type that fits into a station- I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
into the vertical bus and did not self-extinguish
I
until approximately 46.7 ms (2.8 cycles). The peak The dutu obtuined did, in generul, I
pressure, 4.62 psi, developed in approximately 1.7
substantiate the basicpremises I
ms (0.1 cycles). I
For the final test, Test 10, the vertical bus concerning the expected relative forces I
I
isolation was removed to determine the likelihood encountered in a high-energy I
of an arc which was initiated in a size 1 unit to urczng fuult. I
propagate to the exposed bus work. Standard I
latches were used on all unit doors. In this test the I
black cotton flame indicators were not used. I
Test Summary I
Test 10: 67.8 kA rms sym available open circuit,
The results of these tests should provide a higher I
486 V, 16.7% PF, without fuse protection. I
degree of confidence. Tests 1 through 9 indicated
The total three-phase 12t on this test was 177.4 I
that the high-energy arcing fault was contained in
x 106 A2s. The voltage was maintained for 6 cycles I
the unit compartment. However, under no circum- I
or 100 ms; however, the fault current propagated
stances should one assume that these tests in any I
into tt e vertical bus and did not self-extinguish. The
way guarantee that under all conceivable circum- I
peak pressure, 9.0 psi, developed in approximately I
stances a fault would be contained. The violence of
2.5 ITS (0.15 cycles). Some additional pressure I
these faults, condition of the equipment, capabili-
surges of lesser magnitude were recorded, which I
ties of the power systems, and other variables all I
probably indicate restriking of the arc as it pro-
provide a high degree of unpredictability, and PPE I
gressed into the bus structure. Due to the pressure,
should be utilized in areas where high-energy arcing I
none of the standard latches in the MCC section I
faults can occur. Table 2 is a summary of actual
were 2 ble to hold the unit doors closed. I
measured pressures and resultant total force devel- I
All tests, Tests 1 through 10, were initiated as a 2
oped on the unit doors with total I t developed. I
single phase fault between A and B phase, but the
The data obtained did, in general, substantiate I
fault c uickly developed into a three-phase high-en-
the basic premises concerning the expected relative I
ergy arcing fault. I
forces encountered in a high-energy arcing fault. As
In the tests where the black cotton flame indi- I
can be seen in Table 2 the measured pressures I
cators were used, Tests 1 through 9, there were no
converted to total force on unit doors indicates I
indications of burning or scorching on any of the
shock wave pressures with resultant forces ranging I
black cotton indicators. I
from approximately 600 pounds to more than
In rests 1 through 9, the doors that were fitted I
1,500 pounds on a 1 space factor door (approxi-
with the experimental latch did not open. Interest- I
mately 14 in x 13 in) to more than 7,200 pounds I
ingly, on several tests, the top door on the vertical
on a full vertical section door (approximately 20 in I
sectio 1, two space factors away from the unit being
x 78 in). In summary, the data reinforced the I
tested, opened. This door was fitted with the stand- I
following basic premises:
ard latches. It should be noted that no hot gases I
w The pressures developed in identical tests tend
were observed escaping from this upper door. 2 I
to track the expended I t. I
The adjacent units or wireways showed little or w For these high-energy arcing faults, the more I
no internal sooting and no indication of any dam- current-limiting the upstream fuse, the less I
age. S:orch marking was observed on external sur- pressure developed under identical test condi- I
faces immediately adjacent to the faulted unit, tions. I
particilarly on the latch and hinge sides. The dam- H The larger the enclosure, the less psi pressure I
developed, but total pressure on the enclosure I
age in the faulted unit was extensive. Wires feeding
door increases significantly. I
the unit under test were vaporized. The doors were I
bulge'l and the hinge sides were bent and sprung. Unprotected bus work when exposed to the
I
All hi iges remained intact. The experimental door ionized fault gases will tend to allow the fault I
to propagate into a highly damaging traveling I
latches and the holders were, in some cases, slightly
arcing fault. An important additional obser- I
bent.
vation can be drawn from the pressure data is I
It .vas particularly noticeable on the high-speed the unpredictable nature of the magnitude of I
video: that the spring loaded latches allowed the the faults and the resultant pressures devel- I
door t o open slightly at the instant of fault to relieve oped. Uncontrollable and unpredictable vari- I
some ?ressure. The gases escaping during this pres- ables such as arc characteristics, initiation I
I
sure Ielief appeared to flow along the face of the conditions, propagation characteristics,
I
adjacmt section and to cool rapidly. dT/dt, etc., make it virtually impossible to I
I
I We invice readers to submit copic sugges- John PI. Kassrbaum, Editor-in-Chief
I
tions, m d rlie associated author(s), for future l E E E lndwrty App/icatzG??rMqil‘“zi?ze
I
I feacure articles. Please reply either by using the 2503 Pleasant Way, West Drirc
I Reader Service Card ot by sending your sugges- Indianapolis, I S 46280
I (ions dittccly to: Fax: 3 17-844-9678
I , E-mail: j.i:asscbauni~~iee.or~
I
I
I