SECTION 00080
INSTRUCTION TO BIDDERS ON ELECTRICAL WORKS
These Instructions to Bidders are hereby made part of the proposal and contract
documents and Bidders are advised to consider the same in the preparation for their bid.
1. TEMPORARY POWER:
1.1. The Bidder for General Constructions shall include in their bid cost the provision
of temporary power to be used during the construction of the entire building.
The General Contractor shall pay deposits and meter costs.
1.2. The General Contractor shall allow the Specialty Contractor of other trades,
directly hired by the Owner to connect to the General Contractor's temporary
connections. Cost of temporary power shall be billed by the General
Contractor to the Specialty Contractor.
1.3. In this connection, the General Contractor shall provide panel boxes where
the other contractors may tap for their specific use. For use of temporary
power, the sub-contractors who would require unusual power consumption
shall be in proportion to their respective contract amount.
2. The Electrical Contractor shall undertake the securing and payment of electrical
permits and other government fees.
3. Electrical Contractor shall remain responsible for the storage and safekeeping of
owner-supplied materials turned-over to them until final completion and turnover
of the project.
4. The General Contractor in his bid shall consider the cost of providing overall
security and storage facilities. However, individual contractor shall remain
responsible for the storage and safekeeping of owner-furnished materials turned-
over by the Owner until final completion and turn-over of the project.
5. The Bidders are required to submit unit costs of extras and credits in accordance
with the actual change and conditions.
6. Unit costs for extras and credits shall be subject to review and confirmation by the
Owner separate from the General Contractor which may be concluded by the
Owner with the Contractor unless said unit prices are duly confirmed herein.
8. Temporary water facilities shall be provided by the General Contractor and the
cost of water consumption for the entire project including use of parties in direct
contract with the Owner shall be considered by the General Contractor in his bid.
9. In general, all materials to be used shall be of first class quality the Contractor shall
be required within Thirty (30) days after signing of contract to submit samples of
materials that they intend to use for approval.
10. Bids shall be fixed and shall not be subject to escalation regardless of increase in
price of fuel, devaluation and other causes except due to an official increase in
minimum wage as indicated in the proposal.
11.1. Ten Percent (10%) of each monthly progress payment shall be retained by the
Owner until completion of electrical works; Fifty Percent (50%) of the total
amount retained shall be released to the Electrical Contractor upon
connection of permanent power by Meralco. Thereafter, the total retention
shall be equivalent to Five Percent (5%) of the total completed work.
13. MISCELLANEOUS
13.1. All roughing-ins of the auxiliary systems, i.e. Intercom, MATV system shall be by
the Electrical Contractor.
13.2. In general, all materials to be used shall be of first class quality. The Contractor
shall be required within Thirty (30) calendar days after signing of contract to
submit samples of materials that they intend to use for approval.
13.4. Preparation of "As-Built" plans with three (3) sets blue print, testing and
adjustments of the entire electrical system shall be included in the proposal.
1. SCOPE OF WORK:
Lump sum proposal for the supply of labor, materials, tools and equipment and
supervision for the complete electrical, roughing-ins excluding owner-supplied
items listed herein for A PROPOSED THREE-STOREY MIXED-USE BUILDING WITH
BASEMENT in accordance with specifications and other related contract
documents as Prepared by O’YEK DESIGNS.
1.1. Roughing-ins:
Work shall include supply of labor, materials, tools, equipment, supervision and
installation to complete the conduit runs from the Meralco terminal pole up to
and including all power, lighting, security, MATC, Intercom/Entry phone, Fire
Alarm System, Telephone, Air-conditioning and convenience outlets and other
auxiliary outlets including bus gutters, splice boxes, telephone cabinets and
wooden backboards.
Furnishing and installation of all wires and cables for lighting, power
convenience outlets, telephone communications and telephone house
cable.
1.6. Miscellaneous:
2.3. Telephone
2.5. CCTV
2.6. ________________________________________________________________
2.7. ________________________________________________________________
2.8. ________________________________________________________________
3. BID AMOUNT:
4. CONSTRUCTION PERIOD:
Completion and turn-over of contract works shall be within ____ calendar days
after signing of contract.
For failure to complete the total contract works at the specified ____ calendar
day contract period, the Electrical Contractor shall pay to the Owner an amount
equivalent to One Tenth of One Percent (0.1%) of the contract amount per
calendar day of delay as liquidated damages.
Bids shall be based on current labor wages. In the event of an official increase in
minimum wage or compulsory allowances during the construction period, the
contract price shall be adjusted accordingly.
If there shall be such an increase prior to start of work, the total increase in the
contract price for every One Pesos (P1.00) increase in minimum wage or
allowances shall be fixed amount as indicated below:
We (or I) make this proposal with full knowledge of the kind, quantity and quality
of the articles and services required and if the proposal is accepted, undersigned
agrees to enter into a formal agreement and start the work within Ten (10)
calendar days upon receipt of letter of award.
SUBMITTED BY :__________________________________________
FIRM :__________________________________________
ADDRESS :__________________________________________
___________________________________________
CONTACT :__________________________________________
DATE :____________________
APPROVED BY :__________________________________________
DATE :__________________________________________
END OF SECTION