Professional Documents
Culture Documents
Proc Sop
Proc Sop
0 PURPOSE
This guideline outlines the requirements for Non-Destructive Testing of structural and piping
welds to detect surface or subsurface discontinuities in materials, welds and fabricated parts or
components.
2.0 SCOPE
This guideline covers the personnel qualification, safety, equipment, examination, Inspection and
reporting of the following disciplines.
3. Radiographic Inspection.
4. Ultrasonic Inspection.
3.0 REFERENCE
1. Butt joints (B)a. Slots and butts of plates. bBoundary girders between themselves. c. Frame
girders to boundary girders. d. Frame girders and their flanges joints. e. Joints of
recess plates. f.Plate slots. g.Joints of frame girders and their flanges. h.Joint of
stanchion. i. Framing joints.
2. Lap joints (L):a. Slots and butts of plates. b. Slots of recess plates.
5.0 DEFINITIONS
6.0. RESPONSIBILITIES
The quality control department shall be responsible for ensuring that all NDT is performed
accurately, efficiently and expeditiously, in accordance with approved techniques.
The quality control department will be responsible for ensuring that all results of the NDT are
reviewed, interpreted and recorded in accordance with the applicable codes.
It is the responsibility of the production department to liaise with the quality control department
ensuring timely notice is given to allow testing to be performed which meets the obligations of this
procedure.
The QA/QC Manager will liaise with the client, advising of the day to day business of the
department, proposed activities and review of test results.
7.0. ORGANISATION
The quality control department will comprise of a QA/QC Manager and an appropriate number of
experienced inspectors. The QA/QC Manager will report directly to the Project QA Manager. The
department will ensure manning levels which adequately service the needs of the production
department in progressing fabrication efficiently. In turn the production department will take
account of the knowledge and experience available, in terms of valid advice for the avoidance of
quality control problems, when carrying out welding activities.
All personnel carrying out NDT shall be suitably trained and qualified to
SNT-TC-IA or equivalent recognized National Standard.
Only personnel qualified to ASNT level 11, 111 or equivalent National Standard shall carry out the
interpretation and evaluation of NDT results.
All personnel are required to undergo an eye examination for visual acuity and be able to read the
Jaeger chart.
This procedure describes the methods used for the magnetic particle inspection of welds and scarred
areas in ferro-magnetic materials.
Inspection shall only be performed at ambient temperatures unless otherwise approved by the Project
QA Manager and with the agreement of the Company.
Examination shall be done by the continuos method. The magnetizing current shall be on
while the examination medium is being applied and while the excess of the medium is being
removed.
a. Yoke technique
When using AC, the electromagnetic yokes shall have a lifting power of at least
4.5-Kg (10 lbs) and when DC or permanent electromagnetic yoke is used, the
lifting power shall be 18.1 Kg (40 lb) at maximum pole spacing where they will
be used. The lifting power of the Yoke shall be verified on a daily basis or
whenever damage or malfunction is suspected. Results shall be documented on
the Yoke Test Log see exhibit {1/1}
b. Prod Technique
Localized magnetization is achieved by flowing current through the parts via the
prods which resulted in circular magnetic field on the component around the
prods. Extreme care must be taken to maintain clean prod tips and ensure good
contact as to avoid localized heating and are strike on the components at the prod
tips. This technique is suitable for small and big components.
c. Coil/Cable Magnetization
d. Permanent Magnets
Permanent magnet should be used when power supply is not available or the
working environment does not permit not work. Type of permanent magnet to be
used shall be approved by Customer.
8.1.4. Lighting
Bright daylight conditions shall be considered adequate. In other conditions artificial lighting
shall be used, i.e. using a 100-watt tungsten bulb at a distance of approximately 300mm or by
using a 60-watt fluorescent tube at a distance of approx. 1m.
A magnetic particle field indicator is used to verify the adequacy or direction of the magnetic
field and shall position on the surface to examine.
See Figure Magnetic Particle Field Indicator. A suitable flux or field strength is indicated when
a clearly defined line of magnetic particles formed across the copper face of the indicator. The
magnetic particles are applied simultaneously with the magnetizing force. When the defined
line of the particles are not formed, or are not formed in the desired direction, the magnetizing
technique shall be changed or adjusted.
Copper plate
0.010” +/- 0.001” thick.
1/8”
Dry magnetic particle shall only be used when temperatures of test surface exceed 50. Re-
used of dry magnetic particles are not allowed.
Dry magnetic particles shall be applied in such a manner that a light uniform, dust-like
coating settles upon the surface of the test part while the part is being magnetized. The dry
particles can be applied by powder blowers or hand powders applicator.
Whenever a new batch of ink is required to be mixed, the concentration shall be verified as
follows.
iii. Allow to settle under gravity for, 30 minutes for water-based suspensions or 60 minutes for
petroleum distillate suspensions.
iv. The batch will be considered acceptable when the solid concentration is
from 0.1 to 0.4ml for Fluorescent particles and from 1.2 to 2.4ml for non-fluorescent
particles.
v. The above test shall be performed on a daily basic {if Aerosols are not used} and recorded
on the Magnetic ink test log.
Premixed paste form, powder form or pressurized can type of wet magnetic particles may be
used.
The mixing and concentration of wet magnetic particles shall follow the manufacturer’s
recommendation except those premixed and in pressurized can. See above.
PTSC/CORALL/042000/CPC3LQ99/NDT/SOP- QS4.10_3 Page 6 of 90
Before a new batch of water based ink is used the following Break test shall take place to
ensure proper wetting.
i. Prepare a coupon of material similar to that to be tested and apply a thin layer of contrast
lacquer.
iii. The ink should flow evenly over the surface. If the ink collects in globules on the surface
then it shall be rejected.
iv. These results shall also be logged on the Magnetic ink test log. .{ See Exhibit 1/2 }
In order to improve contrast a thin layer of a proprietary brand of rapid drying high opacity
white contrast lacquer is applied. The lacquer must adhere firmly to the test surface and not be
soluble in the detection medium.
The make, type and method of application of the paint shall be recorded on the Magnetic Ink
test log.{ See Exhibit 1/2 }
Wet magnetic particles may be applied by spraying or flowing over the areas to be inspected
during magnetization and the surface of the part shall not exceed 50C.
c. Fluorescent Particles
The examination is performed by using an ultraviolet light (Black Light). The examination
shall be performed as follows:
ii. The examiner shall be in the dark area for at least 5 minutes prior to performing the
examination to enable his eyes to adapt to dark viewing.
iii. Black light shall be allowed to warm up for a minimum of 5 minutes prior to use or
measurement of the intensity of the ultraviolet light emitted.
iv. Black light intensity shall be measured with a black light meter with a minimum of 800
uW/cm2 on the surface of the part being examined. The black light intensity shall be
measured at least once every 8 hours and whenever the workstation is changed.
Acceptance/Rejection criteria shall be in accordance with AWS D.1.1.2000 or ASME V111 Div .
1 whichever is applicable for the work under inspection.
Post cleaning and de-magnetization are required when residual magnetic fields will affect the
subsequent process to be carried out on the parts.
Nil.
8.1.11. Records.
This procedure provides the minimum standards required for dye penetrant inspection to detect the
surface breaking defects in parent materials and welds.
Dye Penetrant inspection of welds will be carried out in accordance with the following, structural
steel: AWS D1.1-2000, Section 6, Part D. Pipework: ASME V, Article 7.
8.2.2. Techniques
a. Water washable
b. Post-emulsifying
c. Solvent removable.
All surfaces within one (1) inch of area to be examined shall be clean, dry and free from
irregularities which could mask indications of unacceptable discontinuities. In general,
welded, cast, forged and rolled surfaces are considered satisfactory, unless surface
dressing is required to remove surface irregularities by grinding. Blasting surface before
Liquid Penetrant Inspection shall be prohibited.
8.2.4. Pre-Cleaning
Cleaning prior to Penetrant Testing shall be done with Solvent Pre-cleaner / Remover (e.g.
Magnaflux SKL – NF/ZC.7 or equivalent).
The temperature of the surface being tested shall be within 60F(16C to 125F (52C)
throughout the examination period.
Dye Penetrant (e.g. Magnaflux SKL-LO or equivalent) shall be applied by dipping, brushing
or spraying to the surface being examined. The entire area shall be maintained wet with Dye
Penetrant for a minimum of 10 minutes dwell time (or as per manufactures recommendation)
After prescribed holding time the excess penetrant shall be removed by using clean and
dry cloth. Repeat the operation until much traces of penetrant are removed. Lightly
PTSC/CORALL/042000/CPC3LQ99/NDT/SOP- QS4.10_3 Page 9 of 90
moisten a clean cloth with solvent and wipe the surface until all remaining traces of excess
penetrant are removed. Direct spraying of solvent following the application of the
penetrant and prior to developing is prohibited.
Drying of the surface after wipe-off excess penetrant shall be by normal evaporation.
a. Prior to application of suspension type wet developer to the surface, the developer
must be thoroughly agitated to ensure adequate dispersion of suspended particles.
b. As soon as the part is dry, apply developer (e.g.) Magnaflux SKL-NF or equivalent)
to the surface by spraying as manufacture’s recommendations.
c. Insufficient coating thickness may not draw the penetrant out of discontinuities,
conversely, excessive coating thickness may mask indications.
d. Final inspection should not be sooner than seven (7) minutes after the developer is
dry (i.e. solvent have evaporated). If bleed out does not alter the inspection results,
development period of over thirty (30) minutes is permitted.
e. Examine the item after the applicable development time to assure proper bleed out
of Penetrant from discontinuities onto the developed coating. It is a good practice to
observe the surface while applying the developer as an aid to evaluate indications.
a. Interpretation shall be made at intervals during the “bleed out” process {approx
20mins} so that the indication may be viewed before excessive diffusion occurs.
c. All indications shall be investigated to the extent that the examiner can evaluate
such indications in term of the Liquid Penetrant acceptance criteria.
b. Post clean shall be by solvent cleaning. Flooding and wiping until and signs of
penetrant and developers have been removed shall be required.
8.2.9. Lighting
When using penetrant inspection materials on austenitic stainless steels, titanium, or nickel-
based alloys, the need to restrict the chloride/fluorine ion content should be considered.
Under no circumstances use Developers with Penetrants from different manufactures. All
penetrants and developers from different manufactures shall be stored separately.
8.2.11. Records.
a. The QA/AC Manager shall be responsible for this procedure and shall be made available to
the respective personnel.
b. The CONTRACTOR’S Dye Penetrant Inspection Report shall contain, as a minimum, the
information as shown in (Exhibit 2): Example of Dye Penetrant Inspection Report.
Radiographic testing will be carried out in accordance with the following requirements. Welds on
structural steel: AWS D.1-2000, Section 6, Part E. Welds on pipework: ASME Section V. Article
2.
The following procedure describes the radiographic equipment techniques that will be used to
inspect the quality of welded structural joints. It also defines the method of interpretation and
evaluation of film images and to ensure that the results of the tests conform to the requirements of
the applicable standards and specifications.
a. Type of equipment and the methods of usage, storage and transportation of radioactive
and radiation emitting apparatus, including radiation dosage monitoring devices,
b. The radiation area must have temporary barriers and posted with proper/conspicuous
warning signs bearing the international radiation trefoil symbol (“ Radiation Area”
or “High Radiation Area” – Keep Out) both in English and Vietnamese. Barriers
and warning signs must be properly illuminated during non-daylight radiography
operation.
Additionally, the vicinity immediately outside the radiation area must be manned
to ward –off potential intruders.
d. Contractor shall develop, for approval, radiation safety emergency Procedure{ See
Appendix 5 } to be implemented in the event of accidental/ emergency radiation
exposure situation. The procedure shall include, as a minimum, recovery
procedures for radioactive sources, emergency notification procedure and 24 –
hour emergency contact person (Radiation Protection Supervisor).
b. Radiographers shall have the necessary equipment, tools and consumables to perform
the radiographic inspection including applicable codes and standards.
a. Radiation source should be X-ray or Gamma ray. Radioisotopes such as Ir. 192 and
Co 60 may be used as radiation source.
b. All Gamma ray sources shall be of the remote wind-out type. The source strength for
Iridium 192 shall be between 12 and 25 curies.
c. In the event that the source strength is greater than 25 curies due to the material
thickness, the activity shall be agreed upon between Customer and the Contractor
provided the Contractor ensures all
Radiographic safety precautions are carried out during the test.
f. X-ray machines should be rated at least 170 KV-3MA for internal single 360
exposure and a minimum of 200 KV-3MA for external exposure. The electrical
focal spot size should not exceed 5mm.
a. A double coated industrial film having low-speed, very fine grain, very high
contrast (ASTM FILM TYPE 1) or medium speed, fine grain, high contrast (ASTM
TYPE 2) suitable for use with lead or fluorometallic intensifying screens shall be
used.
b. All unexposed films shall be stored in a clean dry store where they will not be
subjected to chemical vaporous, funnies, radiation, light, excessive heat, humidity
and undue pressure.
c. Films shall be checked for fog density and shall be between {and including}2.0 to
3.0 H&D on the weld.
d. For radiography of Cu-Ni and SS welds, Type 1 films shall be used regardless of
thickness.
a. Lead intensifying screens of 0.125mm thickness (front and back) shall be used.
c. Screens shall be periodically checked and cleaned. Screens with dents and scratches
shall be replaced.
8.3.6. Cassettes
a. Cassettes must be sturdy, light proof and designed for loading and unloading of film
with minimum possibility of damage to film or lead screens. Cassettes support
devices must not produce images on film or create excessive pressure that could
result in film defects.
a. To check for radiation backscatter, a ½” lead symbol ‘B’ of thickness 1/8” should be
attached to the back of the film cassette. If the ‘ B’ image appears on the radiograph,
radiation backscatter is considered excessive and thus, unacceptable. Whenever
backscattering is evident, a lead sheet or additional layer of intensifying screens
should be placed at the back of the film cassette during exposure to shield the film
from radiation backscatter.
Ug: Ft/D
Where:
F = Source Size
a. Each radiograph must be properly identified for permanent correlation between the
part being radiographed and the film.
i. Contract
ii. Component
v. Date of radiograph
c. The minimum separation between identification markers and weld edges shall be
6mm minimum.
a. Type
DIN 54 109 (1962),ISO or equivalent wire type shall be used. The IQI material shall
be radiographically similar material to the object to be radiographed.
b. Placement of IQI.
i. Wire type IQI shall be placed on the source side with the thinnest wire
outward (but within) the end of the diagnostic film length.
ii. IQI shall be placed across or perpendicular to the weld axis. The IQI
identification markings must not obscure the area of interest.
iii. Where placement of IQI at source side is impractical, the IQI may be
placed on the film identification to signify film side penetrameter
placement.
c. Number of IQI
i. At least two (2) IQI shall be placed at each end of the diagnostic film
length. For diagnostic film less than 10”, one (1) IQI may be used.
PTSC/CORALL/042000/CPC3LQ99/NDT/SOP- QS4.10_3 Page 15 of 90
ii. For double wall double image technique, one (1) IQI placed on the source
side shall be used.
iii. For radiographs made in a single exposure (panoramic), at least three (3)
IQI equally spaced around for circumference of the weld shall be used
8.3.11. Sensitivity
iii. Sensitivity
c. If the evaluated test film does not meet the required criteria, the Contractor shall
perform another qualification test until acceptable radiograph(s) is produced.
8.3.15. Density
a. The density on the area of interest shall be 2.0 minimum and 3.0 maximum for
radiograph both by X or gamma ray.
b. The densities measured within the diagnostic film length of the are of interest shall
not vary by more than 30%.
a. Preparation
Exposed films shall be unloaded for processing under a suitable darkroom with
filtered illumination. Processing chemicals should be free from contaminants that
will interfere with proper processing. Temperature of processing chemicals should
be 20-25C or as per manufacturer’s recommendation. Chemicals shall be stirred
to remove bubbles and to equalize the temperature across the processing tank. The
minimum separation of film holders or hangers should be 12.7mm minimum
b. Developing
Set the timer and immerse films into the developer tank with constant agitation for
15 seconds. Developing time shall be in accordance to the film manufacturer’s
recommendation. Normal developing time is 5 to 8 minutes at 20 C
c. Stop Bath/Rinse
After development is completed, the film shall be neutralized by an acid stop bath
or rinsed with vigorous agitation in clean running water to stop the activity of
developer
Fixing shall be done for at least twice the clearing time but not more than 15
minutes in fresh fixer. Agitate the hangers vertically for about 10 seconds and
again at the end of the first minute to ensure rapid and uniform fixation
e. Fixer Neutralizing
The hypo eliminator or fixer neutralizer is used to reduce the time and amount of
water necessary for adequate washing.
f. Washing
g. Wetting Agent
h. Drying
Films shall be dried using a suitable film drier with thermostat switch and cut-off
timer. Dying temperature must not exceed 55C. Manual drying in still air at
ambient temperature with air circulated by a fan may be used. Care should be
taken that films do not touch one another during drying.
All radiographs shall be free from mechanical, chemical or other blemishes to the
extent that they will not mask or be confused with the image of any discontinuity
in the are of interest. Such blemishes include:
a. Fogging
The acceptance criteria shall be in accordance with ANSI/ASME B31.3 (for piping)
and AWSD1.1( for structural).
a. All sheet films shall be inserted in the paper sleeves and packed into their original
boxes after interpretation
b. All roll films (Rollpac) shall be rolled up properly and packed into suitable boxes
after interpretation.
c. Upon project completion, the film boxes shall be packed into fireproof container for
transportation and storage to location as maybe directed by Customer.
d. Suitable markings shall be provided on the boxes and cartons for easy retrieval
including proper documentation as required by Customer.
a. Prior to any radiography work, a permit shall be obtained from the Contractor’s safety
department.
b. The beacon light shall be functioning throughout the radiography work to warm
people from entering the are.
8.3.21. Records
a. All reports shall be prepared and completed by the interpreter and submitted together
with the radiographs for PTSC/Corall’s review within 24 hours after completion of
radiography.
b. All reports and films shall be compiled, filed and maintained in safe location or
temporary storage to avoid damages.
c. The Contractor shall submit radiographic records and reports in accordance with the
following:
ii. A summary of all items to be radiographed and the results of inspection shall be
furnished to PTSC/Corall on a daily basis.
iv. All processed radiographs shall be packaged and delivered to the Customer not later
than one month from the date of acceptance of the work by Customer.
Source side
Acceptable
Film Side
Unacceptable
Flat Component or Longitudinal Seam Curved Components with radiation Source to Film
{ See sketch E for Alternative} Distance Less than Radius of Component
Source Side
Acceptable
Film Side
I Source Side
Film Side Unacceptable
Acceptable
Unaccept
able
X M X Curved Components with Radiation Source to
Film Distance Greater than Radius of Curvature
Curved {Components
D} with
Radiation Source At
Source Side Marker Alternative.
Flat Component or Longitudinal Seam. Centre Curvature
X= { I/D}{M/2}
X: - Additional Required Coverage , in
BeyondPTSC/CORALL/042000/CPC3LQ99/NDT/SOP-
Film Side Location Marker. QS4.10_3 Page 20 of 90
I:- Component Thickness.
M:-Film side Location Marker Interval.
D:-Source to Component Distance..
8.4. Ultrasonic Testing { UT }
This procedure is used to define the ultrasonic techniques used to detect flaws in welded joints, to
evaluate the screen indications of these flaws and to ensure the welded joints conform to the
requirements of the contract specifications, and that the results of the examinations are correctly
documented.
Ultrasonic testing will be carried out in accordance with the following requirements. Welds on
structural steel: AWS D.1-2000, Section 6, Part F. Welds on pipework: ASME Section V. Article 5.
8.4.1. Equipment
a. Ultrasonic Set
iii. Sweep Linearity: The system shall provide a horizontal sweep with
linearity within 1% of the full screen or CRT grid overlay range.
b. Ultrasonic Probe:
i. Straight Beam
At least one longitudinal or compressional wave transducer, 1/2 to 1 in.
(12.5mm to 25mm) in diameter of a nominal frequency of 2 through 2.25
megahertz.
d. Couplant
Ultrasonic testing units and probes shall be checked for the performance periodically. The
units shall be standardized and calibrated for functions as follows:
Angle
probe
i. Procedure
ii. Tolerance
C
iii. Frequency
E
of
D
Checking
This will depend on the rate of probe wear due to usage and to the
roughness of the testing surface. When a probe is in continuous use, daily
check or at leas every four hours is required.
F G
B A
H
i. Procedure
c. Marked the difference between the probe index and the block
engraved reference lines on the probe.]
ii. Tolerance
This will depend on the rate of probe wear due to usage and to the
roughness of the testing surface. When a probe is in continuous use, check
shall be carried out every four hours or daily before production test and the
new angle shall be used for all evaluations.
C
100 mm
25Bmm
c. For range less than 25 mm, place the probe at B. For range greater
than25 mm, place the probe at A or C.
ii. Tolerance
Check shall be carried out at least once per week if the unit is used daily or
prior to production testing.
Perspex
91 m 100 m
100 mm
50 mm
i. Procedure
PTSC/CORALL/042000/CPC3LQ99/NDT/SOP- QS4.10_3 Page 26 of 90
a. To determine the linearity of calibrated gain control
2 Adjust the gain to set this signal to 80% of full screen height
and note the value of the calibrated control (dB). Adjust the
calibrated control to increase the gain by 2(dB). The signal
should increase to full screen height (100%). Restore the
gain to its original value and then reduce it by 6 dB. The
signal should fall to 40% of full screen height. Reduce the
gain by a further 12 dB. The signal should fall to 10% of full
screen height. Reduce the gain by 6dB. The signal should
fall to 5 % of full screen height.
ii. Tolerance
This is to check the ability of probe unit combined to discriminate between signals
from separate reflectors lying at only slightly different in ranges or near to surface
11w V1-BLOCK
91 mm 85 mm
A 0 Deg Probe
100 mm
B
E
D
IOW BEAM PROFILE BLOCK
i. Procedure
a. Compressional (0) Probe
ii. Tolerance
H/2 H/2
The resolution check of probe–unit combined shall be carried out for new
probe, when beam index/angle has changed or at least once a month
2 2 2 4 4 6 4 6 6
A
A B
B
E
D
C
F A – Hole Index
B – Probe Index.
C – Centre Line of Beam.
D – Trailing Edge of Beam.
A E – Leading Edge of Beam.
B F – Probe Movement.
i. Procedure
E a. The response from the 1.5 mm side drilled hole will be maximized
C D at the 12.5 mm depth and the amplitude will be adjusted to 100 %
screen height.
b. The distance between the hole index and the beam index will be
measured and recorded
c. The probe will moved forward (the amplitude will decrease) until
the response drops to 10% of the screen height.
d. The distance between the hole index and the beam index will be
measured and recorded.
f. The distance between the hole index and the beam index will be
measured and recorded.
h. This procedure will be repeated utilizing the responses from the two
further reflectors at varying depths (as a minimum requirement) to
provide an accurate beam profile chart.
i. Draw a straight line through the centre line points and extend the
line to the search unit. This indicates the beam centre line point on
the search unit. The beam angle maybe read with a protractor as the
angle between the beam centreline and a perpendicular line to the
examination surface such as the search unit front line projection.
ii. The procedure will be repeated for each of the remaining probes.
300 mm
200 mm
perspex
100 mm 91mm
100 mm
100 mm 50 mm
75 mm
25 mm
50 mm
5 mm
IIW VI and V2 blocks or other suitable blocks can be used for calibration.
1 VI-Block
Set up multiple signal at 100mm intervals by reflections
between the quadrant and notches on the faces of the block.
2 V2-Block
Set up repeated signal at 25mm, 100mm, 175mm, etc., when
probe is directed on the 25mm quadrant and 50mm, 125mm,
200mm, etc., when probe is directed on the 50mm quadrant.
c. Maximizing of signals
1. VI-Block
2. V2-Block
e. at finish of testing
DAC curve is the primary reference curve for equipment sensitivity setting in
ultrasonic testing which compensate for the loss of sound energy from traversing in
material being tested due to beam spread and attenuation. The construction of the
reference block is as per ASME V Article 5. See Figure II: Basis Calibration
Block.
a. Position the probe for maximum response from the hole which
gives the highest amplitude.
e. Position the probe for maximum amplitude from the third hole
indication and mark on the peak on the screen.
g. Connect the screen marks for the side-drilled hole to provide the
DAC curve.
10 -
8-
6- DAC
4-
2 6
Sensitivity
a. The 45 angle shear wave reflects well from a corner reflector.
However, mode conversion and redirection of reflection occurs to
part of the beam when a 60 angle beam shear wave hits the same
reflector. This problem also exists to a lesser degree throughout the
50 to 70 angle beam shear wave range. This correction is required
in order to be equally critical for such an imperfection regardless of
the examination beam angle.
b. Position the probe for maximum amplitude from the square notch
on the opposite surface. Mark ‘X’ at the peak of the indication on
the screen.
PTSC/CORALL/042000/CPC3LQ99/NDT/SOP- QS4.10_3 Page 34 of 90
c. The opposite surface square notch may give an indication 2 to 1
above DAC at 45 and ½ DAC at 60. Therefore the indication
from the square notch must be considered when evaluating
reflectors at the opposite surface.
2 4 6 8 10 2 4 6 8 10
Reflectors
moved into beam
b. Check of DAC curve shall be carried out at the beginning and end
of testing or every four hours. If any deviation as stated in (iii a) is
experienced, component tested earlier shall be re-examined with the
corrected DAC.
iv. Deviation
I. Transfer Correction
There is a difference in instrument sensitivity between the reference block and test
component due to test surface roughness, contact area, component temperature and
acoustical attenuation characteristic. A correction in instrument sensitivity is
required to compensate for these differences and is describe below:
Screen display
(Transmitter) Receiver Receiver
Fixed (position 1) (position 2)
75%
50%
25%
1 skip 1 2 3 4
2 skip
i. Use two angle beam probes of the same type. One acting as transmitter and
the other as receiver.
ii. Placed the probes in-tandem on the reference block at one skip distance and
maximize the signal to 75%. Note down the gain (dB).
iii. Mark on the screen or on a graphical paper the peak of the maximized
signal.
iv. Reposition the probes to achieve peak signal at two-skip distance. Repeat
step (iii.) and joint the two points to obtain line R.
v. On the surface of test component, carry out step (ii) and at the same dB
gain. Increase or decrease the signal where the peak is on line R and note
down the gain (dB) difference.
b. The choice of angle probes for scanning different material thickness are as follows:
However, the probe which give the best response should be used which is
dependent of weld and welding parameters.
a. Longitudinal Discontinuities
ii. Scanning Movement B. Scanning distance b shall be such that the section
of weld being tested is covered.
ii. Scanning pattern E is to be used when the weld reinforcement is not ground
flush. Scanning angle e=15max.
Note :The scanning pattern is to be such that the full weld section is covered.
a. A critical root scan at stand-off distance of ½ skip from near root penetration face
shall be carried out on all full penetration constant configuration joints. Probe of
70 nominal angle is recommended for critical root scanning for all thickness. Take
note for tubular, 70 beam may not reach the bore and other appropriate angles
shall be used.
d. The cross-section of defect shall be sized with maximum amplitude technique and
the length of defects shall be determined by 6Db (1:2) drop technique.
The height, shape and orientation of the flaw will be determine using the –20 dB
drop system.
e. Reporting of defective areas shall be referred to a datum and the defective area are
physically marked adjacent to the defective weld.
g. A spherical discontinuity is one in which its length is three times its width or less
and may be round or irregular.
h. When two or more linear or planar discontinuities are not separated by at least the
length of the longer discontinuity up to the standard sensitivity level, the
continuities shall be considered a single linear or planar discontinuity.
No ultrasonic testing on mild steel (Y.S. less than 40 ksi) should be carried out less than 24
hours after welding has been completed. /for higher strength steel the time delay should be
minimum of 48 hours.
a. Customer has the right to verify the joint conducted by the Contractor’s UT Operator.
8.4.9. Records
a. All rejectable and acceptable discontinuities having more than half (6 dB) the amplitude at
standard sensitivity level shall be reported in the Ultrasonic Examination Report.
b. Areas for which complete inspection was not practicable shall also be noted along with the
justification.
c. All root discontinuities whose amplitudes exceed the disregard level shall be reported accept
or reject by the Ultrasonic Operator indicating the depth, length and width or height.
d. Each rejectable discontinuity shall be indicated on the weld by marking directly over the
discontinuity for its entire length. The depth from the test surface shall be noted on base
metal.
e. Welds found unacceptable shall be repaired and retested by the same ultrasonic testing
technique with results tabulated on additional report forms with R1 or R2 prefixed in the
same report number.
f. The Contractor’s Ultrasonic Testing Report shall contain, as a minimum, the information as
shown in (Exhibit 4) : Example of Ultrasonic Report).
WELD AXIS
Pattern D
E E
A
A PATTERN E
C
B
MOVEMENT
PTSC/CORALL/042000/CPC3LQ99/NDT/SOP-
A QS4.10_3 C Page 39 of 90
MOVEMENT C
Movement B
BASIC CALIBRATION BLOCK
3 T min
T/2
T/4
T/2
2” 3T/4
T/2
T/2
6”min
GENERAL NOTES:
a) Holes shall be drilled and reamed a minimum of 1 – ½” deep essentially parallel to the examination
surface.
Page
Exhibit 1 Magnetic Particle Inspection Report. 42
Surface Preparation:
EQUIPMENT
Model: S. No:
Method of inspection
Dry Wet Visible Fluorescent
Ink Manufacturer and Contrast Manufacturer
Batch No: and Batch No:
Residual Continuous True-Continuous
AC DC Half- Wave
Prods Yoke Cable Wrap Other________
Direction for Field Circular Longitudinal
POST EXAMINATION
Demagnetizing Technique (if required):
Cleaning (if required): Marking Method:
We, the undersigned, certify that the statements in this record are correct and that the welds were
prepared and tested in accordance with the requirements of the American Welding Society ANSI/AWS
D1.1, (____________) structural welding Code-Steel, year
Fluorescent Black
Surface Preparation:
EQUIPMENT
Manufacturer. Penetrant Batch No:
Developer Batch No:
Cleaner Batch No:
Method of inspection
Visible Fluorescent
Exhibit 3
RADIOGRAPHIC EXAMINATION REPORT No.
REQUEST No.
:
:
REPORT DATE :
PROJECT : WELDER QUALIFICATION TEST SHEET OF
CLIENT : PROCEDURE No. :
CODE :
WELDING :
PROCESS
MATERIAL : TYPE OF JOINT : THICKNESS : DWG No. :
X-RAY GAMMA RAY
EQUIPMENT
TYPE : kV MA TYPE :
TEST VOLTAGE : kV MA SOURCE SIZE :
FOCAL SPOT SIZE : mm x mm EXPOSURE TIME :
EXPOSURE TIME : FFD : ACTIVITY :
FILM : KODAK AA 400 IQI : ASTM 1B 03 WIRE TYPE
FILM SIDE : 10x40CM LOCATION SOURCE SIDE FILM SIDE
TECHNIQUE
RESULTS
REPORT No. :
ULTRASONIC EXAMINATION DATE TEST. :
EXHIBIT 4
REPORT REQUEST No.:
ITEM :
PROJECT : PAGE 1 OF
CLIENT : PROCEDURE No. :
CODE : WELDING PROCESS :
EQUIP.(MODEL & S/N) : PANAMETRIC EPOCH III CALIBRATION BLOCK (MODEL & S/N) : IIW V1, V2
COUPLANT Grease CMC OIL SURFACE CONDITION As Ground As Welded
TECHNIQUE Contact Immerse Straight Beam Angle Beam
Type Angle Frequency Size
MB4F 00 4MHZ 10
TRANSDUCER
MWB70-4 700 4MHZ 8x9
0
MWB60-4 60 4MHZ 8x9
DWG No. : Material : Carbon Steel Thickness :
EXAMINATION RESULT
Decibels (dB) Discontinuity Judgement
Angular Distance
Attenuation Level
Indication Rating
Reference Level
Indication Level
Indication Number
Distance (mm)
Length (mm)
Position
Accetable
Remarks
Reject
(sound path)
From Y
From X
a b c d
APPENDIX 1
WELD
a. Remove slag weld spatters and other debris from weld surface.
c. Place the magnetic York across the weld with poles spacing approximately 6”.
d. Apply the magnetic ink between the poles and magnetized the weld while the ink is
flowing away from the surface, visually inspect for indication.
e. Reposition the magnetic Yoke so that the magnetic field is perpendicular t that of step (iv)
above. Repeat step (ii) and (iv) above.
g. If indication still appear after grinding approved repair procedure shall be followed.
i. During a subsequent magnetization an overlap of at least one inch over the previous step is
necessary to ensure complete coverage.
MAGNETIC
SOURCE : Electro magnetic Yoke Magnaflux’s model Y-6
MAGNETIC
PARTICLES : Magnaflux’s Red (No.8A) or Black dry powder
FLUX
INDICATOR
FLUX
Electric INDICATOR
Cable
WELD
PLATE PLATE
Inspection Sequence:
a. Remove slag, weld spatters and other debris from weld surface.
c. Apply dry powder onto the magnetize surface with plastic powder container or blower so
that the powder reach the surface as fluffy dust. Remove excess powder by blowing.
d. Visually inspect for magnetic indication. Steps (iii) and (iv) above to be carried out while
the magnetizing current is ‘ON’.
h. During a subsequent magnetization an overlap of at least one inch over the previous step is
necessary to ensure complete coverage.
A A’ A A’
Yoke
WELD
Gouged
Area
A’
A A’ A
Flux
PTSC/CORALL/042000/CPC3LQ99/NDT/SOP-
indicator QS4.10_3 Page 52 of 90
a. Remove slag, weld spatters and other debris from weld surface.
c. Place the magnetic Yoke across the weld with poles spacing approximately 6”.
d. Apply the magnetic ink between the poles and magnetize the weld while the ink is
flowing away from the surface, visually inspection for indication.
e. Reposition the magnetic York so that the magnetic field is perpendicular to that of step
(iv) above, i.e. at A-A and A’ –A’.
g. Indications can be removed by light grinding. If indication still appear after grinding,
approved repair procedure are shall be followed.
i. During a subsequent magnetization an overlap of at least one inch over the previous
step is necessary to ensure complete coverage.
LEAD
A A’ A A’
Yoke
WELD
Gouged
Area
A’
A A’ A
Flux
indicator
Inspection Sequence
a. Remove slag, weld spatters and other debris from weld surface.
b. Place the magnetic Yoke across the weld with poles spacing approximately 6”.
c. Apply dry powder onto the magnetize surface with plastic powder container blower so
that the powder reach the surface as fluffy dust. Remove excess powder by blowing.
d. Visually inspect for magnetic indication. Steps (iii) and (iv) above to be carried while
the magnetizing current is ‘ON’
PTSC/CORALL/042000/CPC3LQ99/NDT/SOP- QS4.10_3 Page 54 of 90
e. Reposition the magnetic Yoke so that the magnetic field is perpendicular to that of step
(iv) above i.e. at A’-A’.
g. Indications can be removed by light grinding. If indication still appear after grinding,
approved repair procedure shall be followed.
i. During a subsequent magnetization an overlap of at least one inch over the previous
step is necessary to ensure complete coverage.
WELD
A’ A
Flux
Indicator Overlapping of prods on subsequent magnetization
PTSC/CORALL/042000/CPC3LQ99/NDT/SOP- QS4.10_3 Page 55 of 90
required
Inspection Sequence
a. Remove slag, weld spatters and other debris from weld surface.
c. Press firmly the electrodes across test surface and energize the prods.
d. Apply wet magnetic ink between the prods and inspect for indication while excess ink
is flowing away.
e. Switch off current supply and reposition the prods alternately at A-A or A’-A’ as
shown above. Repeat step (iv) each time.
f. Irrelevant indication shall be removed, visually examine the surface and re-MPI.
g. Indications can be removed by light grinding. If indication still appear after grinding,
approved repair procedure shall be followed.
i. During a subsequent magnetization, an overlap of at least one inch over the previous
step is necessary to ensure complete coverage.
MAGNETIC
SOURCE : Magnaflux model P-910 portable test unit.
MAGNETIC :
PARTICLES. Magnaflux’s Red{ No.8A} or dry
powder.
Prods A A’
WELD
A’ A
Flux
Indicator Overlapping of prods on subsequent magnetization required
Inspection Sequence.
a. Remove slag, weld spatters and other debris from weld surface.
b. Press firmly the electrodes across test surface and energize the prods.
c. Apply the magnetic powder with rubber blower in between the prods and inspect for
indications. Excess powder to be blown away.
d. Switch off current supply and reposition the prods alternately at A-A and A’-A’ as
shown above. Repeat step {iv}each time.
e. Irrelevant indications shall be removed. Visually examine the surface and re-MPI.
f. Indications can be removed by light grinding. If indications are still present after
grinding, approved repair procedures shall be followed.
MAGNETIC
SOURCE . Magnaflux electro magnetic Yoke.
MAGNETIC
PARTICLES. Ardox’s 800/3 Black Magnetic ink or equivalent..
CODE/
SPECIFICATIONS. Acceptance Criteria as per AWS D1.1 and
ASME V111.
Gouged A A’
Weld
Yoke
WELD
Gouged
Area
Overlapping of prods on subsequent magnetization required
Flux
A A’
indicator
a. Remove slag, weld spatters and other debris from gouged area..
c. Place magnetic Yoke across the gouged area with poles spacing approximately 6”.
d. Apply wet magnetic ink between the poles and magnetize the weld while the ink is flowing
away from the surface, visually inspect for indications.
e. Reposition the Yoke at A-A and A’-A’ as shown above. Repeat step {iv} above.
f. If indications are observed, determine whether the indications are caused by discontinuity or
false/irrelevant indications. Removing the indication, visually examining the surface and re-
MPI can do this.
g. Indications can be removed by light grinding. If indications still appear after grinding,
approved repair procedures shall be followed.
i. During a subsequent magnetization, an overlap of at least one inch over the previous step is
necessary to ensure complete coverage.
MAGNETIC
PARTICLES Magnaflux’s Red{ No.8A} or dry powder.
CODE/
SPECIFICATIONS Acceptance Criteria as per AWS D1.1 and
ASME V111.
Gouged A A’
Weld
Yoke
WELD
Gouged
Area
A
Flux
indicator
A’
Inspection Sequence.
a. Remove slag, weld spatters and other debris from gouged area.
b. Place magnetic Yoke across the gouged area with poles spacing approximately 6”.
c. Apply the magnetic powder with rubber blower in between the prods and inspect for
indications. Excess powder to be blown away.
d. Visually inspect for magnetic indications. Step {iii} and {iv} above to be carried out while
the magnetizing current is on.
e. Reposition the magnetic yoke aas shown at A-A and A’-A’ above. Repeat steps{iii} and { iv}
above.
f. Indications can be removed by light grinding. If indications are still present after grinding,
approved repair procedures shall be followed.
h. During a subsequent magnetization, an overlap of at least one inch over the previous step is
necessary to ensure complete coverage.
5.8. Evaluation
i. Discontinuities on the surface are indicated by retention of the magnetic particles. Areas of
false indications due to surface irregularities shall be re-tested after removing the
irregularities. Broad areas of particle accumulations which might mask indications from
discontinuities shall be cleaned and re-tested.
APPENDIX 2
The radiation passes through only on (1) wall of the weld (material) which viewed
for acceptance on the radiograph. The resultant image is directly captured in the
film. Where accessible, a single panoramic single –wall exposure (the source to
object are equi-distant at all points) can be used for large diameter pipes or tanks.
Radiation passes through two walls and the weld (material) in both walls are
viewed for acceptance on the same radiograph. It is recommended to pipe weld up
to 2.5 inches or less in nominal outside diameter. At least two films must be taken
at 90 to each other.
APPENDIX 3
b. Apply thin layer of couplant on the test point and place the probe over the
couplant. Press the probe lightly and evenly onto the test surface.
d. Record down the reading with sketch. For lamination check, at least two
signals which indicates the wall thickness should be seen.
Thickness
1 ½ Skip
0o
b. Root Scan.
c. With appropriate angle probes, scan the whole volume of the welds
h. All defective areas shall be marked, with cross section of defective weld
marked adjacent to defective area.
11.3 Component :Butt Welds – Scanning from both sides and faces of the weldments
and parent metal.
a. 0 Probe –scan until 2 skips distance from weld centre line from both side
of welds.
c. With appropriate angle probes, scan the whole volume of the weld.
h. All defective areas shall be marked, with cross section of defective weld
adjacent to defective area.
0o
If accesible
FACE A
¾ skip
Inspection Sequence:
b. Root Scan-as per Section 5.7.1. Then scan the whole volume of weld with
other appropriate angle probes.
0o
‘A’
0o
If accesible
f. All defective areas shall be marked, with cross section of defective weld
marked adjacent to defective area.
11.6 Component:T and K- Joint – Scanning from external surface of stub only.
Chord member
Inaccessible
1 ¼ skip
Inspection Sequence:
a. 0 Probe – Scan until one slip distance from edge of weld on face A. If accessible, scan
from face B for lamella tearing and lack of fusion.
b. Roof Scan as per Section 5.7.1. Then scan the whole volume of weld with other
appropriate probes.
e. Due to the curvature of the stub, small diameter probes shall be used. All indication, high
or low amplitude, within testing range shall be carefully evaluated.
g. All defective areas shall be marked, with cross section of defective weld marked
adjacent to defective area.
1 ½ Skip
If accessible
0 Deg
Plates
45 Deg only
b. Root Scan – as per Section 5.7.1. then scan the whole volume of weld with other
appropriate angle probes.
e. Due to the curvature of the stub, small diameter probes shall be used. All indication, high
or low amplitude, with testing range shall be carefully evaluated.
g. All defective areas shall be marked, with cross section of defective weld marketed adjacent
to defective area.
¼ Skip
Chord Member
a. 0 Probe – Scan on the lifting lug and the chord member. See above sketch.
b. Root Scan – as per Section 5.7.1. Then scan the whole volume of weld with other
appropriate angle probes.
e. All defective areas shall be marked with cross section of defective weld marked adjacent
to defective area.
f. All defective areas shall be marked, with cross section of defective weld marked
adjacent to defective area.
1 Skip
0o
Or similar
½ Skip
1 skip
Inspection Sequence :
(If accessible)
a. 0 Probe – Scan until 2 slip distance on surface of stub.
f. All defect areas shall be marked, with cross section of defective weld marked adjacent to
defective area.
1¼
g. All scanning limitation 0
shall be reported. 0 Skip
Inspection Sequence:
a. 0 Probe – Scan until 1-1/2 skip distance ( far from 70 probe) from toe of weld and
other accessible area as indicated in the sketch.
b. Root Scan as per Section 5.7.1. then scan the whole volume of weld with other
appropriate angle probes.
f. All defective area shall be marked with cross section of defective weld marked adjacent
to defective area.
All welds which are examined by ultrasonic testing shall be judged in accordance with ASW D1.1 Par
10.17.14.1 Class R or ASME V111.
12.1. Introduction.
12.1.1. Purpose
12.2. Administration
12.3.1 General
12.4. Equipment
12.4.1. General
12.4.2. Storage and Security
12.4.3. Accident and Malfunction
12.4.4. Safety Equipment
12.5.1. General
12.5.2. Storage
12.5.3. Working Enclosure and Suitable Marked Areas
12.5.4. Warning signals
12.5.5. Dose Rate Measurement
12.5.6. General Precautions
12.6.1. General
12.6.2. Categories of Consignment
12.7.1. General
12.7.2. Emergencies with X-Ray Equipment
12.7.3. Emergencies with Radioactive Sources
Appendices
1.Warning Notice to all Persons
2.QA/QC AND SAFETY MANAGER Notice of Appointment
12.1.1. Purpose
12.2. ADMINISTRATION
Every person working with radiation or radioactive materials shall not expose himself or others to
radiation to a grater extend than is absolutely necessary for the purposes of the work. In addition, the
worker should be responsible for the following:
PTSC/CORALL/042000/CPC3LQ99/NDT/SOP- QS4.10_3 Page 77 of 90
Using those personal monitoring devices issued to him and recurring them at the end of the
prescribed period. He should also take every precaution to ensure that personal dosimeter devices
are exposed only to those ionizing radiation are incident on his body during the normal course of
his work.
Informing the QA/QC and Safety Manager in advance of any proposed work with radioactive
apparatus, together with methods and safety precautions to be used.
Reporting immediately to the QA/QC and Safety Manager any instance of known or suspected
unsafe practice or other hazardous situation or contingency.
Becoming familiar with the main chemical and physical properties and biological effects or the
radiation or radioactive materials he is using.
Reducing to a minimum the radiation hazards in the work.
Knowing what to do in case of an accident.
Wear personal safety equipment during the performing of NDT activities.
All other persons likely to encounter ionizing radiation as a result of the work.
OPERATOR COMPETENCE
EQUIPMENT
12.4.1 General
Warning Signs
Warning sigh will be posted where a potential radiation
hazard exists. This will be at all time including the
workstation where radiography is being performed. Warning
signs will be sufficiently large to be clearly visible. Warning
signs will be appropriately worded and carry the
internationally recognized ‘trefoil” symbol.
METHOD OF WORK
PTSC/CORALL/042000/CPC3LQ99/NDT/SOP- QS4.10_3 Page 81 of 90
12.5.1 General
Pre-Exposure Warning
12.6.1 General
12.7.1 General
The P/C Has the Primary responsibility for dealing with any
radiation emergency that arises. In the event of unexpected
difficulties this could entail requesting outside assistance
particularly where prompt action necessary and such
assistance is quickly available.
General
The most likely type of emergency with X-ray Equipment is exposure of persons to X-ray as a
result of either the apparatus being energized unintentionally or to persons getting past the
warning barriers unnoticed.
Switch off the equipment and do not restart until the QA/AC
AND SAFETY MANAGER grants approval.
General
Identify all persons who may have been within the restricted area and report them to the
QA/ QC AND SAFETY MANAGER.
Before entering the restricted are the QA/ QC AND SAFETY MANAGER will plan a
course of action and gather together tools, shielding material etc.
Inform the Project manager of what has happened and what action is proposed.
If possible the QA/ QC AND SAFETY MANAGER and his assistants will replace the
source within its container within its shielded position.
The QA/ QC AND SAFETY MANAGER will notify PTSC/CORALL who will provide
assistance as required.
Where it appears likely that persons have received excessive exposure, the relevant Authorities
will be noticed, medical examinations arranged,and film badges processed etc. Without
delay.
Where the sources has not been returned to its container in a fully safe condition then the QA/
QC AND SAFETY MANAGER will make a further planned attempt and if necessary
obtain another container. Once this has arrived then the source will be placed in it and
removed from the worksite for disposal in an approved manner.
Injured Persons
When accident involving possible damage to a source container and injury to personnel.
The first consideration is the rescue of injured or trapped persons. This wills precedence
over all other action. The QA/ QC AND SAFETY MANAGER and Project manager are
responsible for insuring all those involved and until measurements have been made it must
be assumed that the source is fully exposed.
Sources and container are designed to withstand quite severe fire conditions but should be
removed from the area if this can be done. If this is not possible then the QA/ QC AND
SAFETY MANAGER and Project manager must advise the fire fighters of the presence of
radioactive source.
Missing Source
A full search, cross checking shipping manifest etc. Will be conducted and the QA/ QC AND
SAFETY MANAGER advised of the outcome
If the source is not located the QA/ QC AND SAFETY MANAGER will advise the necessary
Authorities immediately.
Any person requiring information or clarification regarding the use of ionizing radiation must
consult the QA/ QC AND SAFETY MANAGER and all incidents involving ionizing radiation
must be reported him.
ASSIGNMENT
are appointed QA/ QC Manager and Safety Manager { RPS}respectively in accordance with
requirements.
Signed Name
Position Project QA Manager
Date 4th May 2000