Professional Documents
Culture Documents
Example of EVA
Example of EVA
Example of EVA
Cost control
Cost control is the practice of identifying and reducing business expenses to increase profits, and it starts
with the budgeting process. A business owner compares the company's actual financial results with the
budgeted expectations, and if actual costs are higher than planned, management has the information it needs
to take action.
Cost control may be broadly defined as the process of controlling the expenditure in a project at all stages
from its inception through its development. Cost control means controlling changes to project budget. Cost
control is equally important to all the firms regardless of size.
Cost control is mainly concerned with:
Influencing the factors which create changes to the cost baseline to ensure that changes are
beneficial.
Determining that the cost baseline has changed and
Managing the actual changes as and when they occur.
Earned Value Analysis(EVA)
Earned Value Analysis (EVA) is an industry standard method of measuring a project's progress at any given
point in time, forecasting its completion date and final cost, and analyzing variances in the schedule and
budget as the project proceeds. It compares the planned amount of work with what has actually been
completed, to determine if the cost, schedule, and work accomplished are progressing in accordance with the
plan. As work is completed, it is considered "earned".
EVA is a snapshot in time, which can be used as a management tool as an early warning system to detect
deficient or endangered progress. It ensures a clear definition of work prior to beginning that work. It
provides an objective measure of accomplishments, and an early and accurate picture of the contract status.
It can be as simple as tracking an elemental cost estimate breakdown as a design progresses from concept
through to 100% construction documents, or it can be calculated and tracked using a series of mathematical
formulae (see below). In either case, it provides a basis for course correction. It answers two key questions:
1. At the end of the project, is it likely that the cost will be less than, equal to or greater than the
original estimate?
2. Will the project likely be completed on time?
Durations Total
Activity Predecessor
(weeks) Cost
A 2 600
B A 3 1200
C B 3 1200
D B 2 400
E D 3 600
F D 4 1600
G E 5 2000
H G 4 1400
I E 3 600
J I 2 250
Field report at end of 2 weeks Field report at end of 5 weeks Field report at end of 7 weeks
Actual % Incurred Actual % Incurred Actual % Incurred
Activity Activity Activity
Complete Cost Complete Cost Complete Cost
A 100 600 A 100 600 A 100 600
B 0 0 B 100 1400 B 100 1400
C 0 0 C 33.33 500
D 50 200
E 0 0
Field report at end of 10 weeks Field report at end of 13 weeks Field report at end of 18 weeks
Actual % Incurred Actual % Incurred Actual % Incurred
Activity Activity Activity
Complete Cost Complete Cost Complete Cost
A 100 600 A 100 600 A 100 600
B 100 1400 B 100 1400 B 100 1400
C 100 1300 C 100 1300 C 100 1300
D 100 350 D 100 350 D 100 350
E 80 400 E 100 400 E 100 400
F 50 600 F 100 1300 F 100 1300
G 0 0 G 65 1460 G 100 2240
H 0 0 H 90 1100
I 100 650 I 100 650
J 0 0 J 100 250
Solution:
The Bar diagram of estimated duration of activities from A to J is shown below.
Chart Title
Time (Weeks)
0 2 4 6 8 10 12 14 16 18 20
4
Activity
10
Actual cost of worked performed (ACWP), Budget cost of Worked Performed (BCWP) and Budget Cost of
Worked Schedule (BCWS) at the end of 2,5,7,10,13, and 19 weeks are calculated as below.
Activit BCW Activit BCW Activit
ACWP BCWP ACWP BCWS ACWP BCWP BCWS
y S y P y
At the end of 2 weeks At the end of 5 weeks At the end of 7 weeks
A 600 600 600 A 600 600 600 A 600 600 600
Total 600 600 600 B 1400 1200 1200 B 1400 1200 1200
Total 2000 1800 1800 C 500 400 800
D 200 200 400
Total 2700 2400 3000
The plot of Cumulative Weeks vs Cumulative Amount for ACWP, BCWP, BCWS are given below.
10000
8000
Cumulative Amount
6000
4000
2000
0
0 2 4 6 8 10 12 14 16 18 20
Cumulative Weeks
ACWP BCWS BCWP