PROJECT SCHEDULE

ENGINEERING

ID Task Name Duration Start Finish Predecess

02 Mar '20 23 Mar '20 13 Apr '20 04 May '20 25 May '20 15 Jun '20 06 Jul '20
22 01 09 17 25 02 10 18 26 04 12 20 28 05 13 21 29 07
1 ENGINEERING PROJECT 90 days Mon 02/03/20 Fri 03/07/20
2 DRY POWDER SILO 12 days Mon 02/03/20 Tue 17/03/20
3 General Arrangement 8 days Mon 02/03/20 Wed 11/03/20
4 1st Submission 2 days Mon 02/03/20 Tue 03/03/20
5 Client Comment 2 days Wed 04/03/20 Thu 05/03/20 4
6 2nd Submission 1 day Fri 06/03/20 Fri 06/03/20 5
7 Client Approval 3 days Mon 09/03/20 Wed 11/03/20 6
8 Shell Course & Support Detail 7 days Wed 04/03/20 Thu 12/03/20
9 1st Submission 1 day Wed 04/03/20 Wed 04/03/20 4
10 Client Comment 2 days Thu 05/03/20 Fri 06/03/20 9
11 2nd Submission 1 day Mon 09/03/20 Mon 09/03/20 10
12 Client Approval 3 days Tue 10/03/20 Thu 12/03/20 11
13 Nozzle Details 7 days Thu 05/03/20 Fri 13/03/20
14 1st Submission 1 day Thu 05/03/20 Thu 05/03/20 9
15 Client Comment 2 days Fri 06/03/20 Mon 09/03/20 14
16 2nd Submission 1 day Tue 10/03/20 Tue 10/03/20 15
17 Client Approval 3 days Wed 11/03/20 Fri 13/03/20 16
18 Manhole Details 7 days Fri 06/03/20 Mon 16/03/20
19 1st Submission 1 day Fri 06/03/20 Fri 06/03/20 14
20 Client Comment 2 days Mon 09/03/20 Tue 10/03/20 19
21 2nd Submission 1 day Wed 11/03/20 Wed 11/03/20 20
22 Client Approval 3 days Thu 12/03/20 Mon 16/03/20 21
23 Name Plate Details 7 days Mon 09/03/20 Tue 17/03/20
24 1st Submission 1 day Mon 09/03/20 Mon 09/03/20 19
25 Client Comment 2 days Tue 10/03/20 Wed 11/03/20 24
26 2nd Submission 1 day Thu 12/03/20 Thu 12/03/20 25
27 Client Approval 3 days Fri 13/03/20 Tue 17/03/20 26
28 PTU EFFLUENT TANK 12 days Mon 02/03/20 Tue 17/03/20
29 General Arrangement 8 days Mon 02/03/20 Wed 11/03/20
30 1st Submission 2 days Mon 02/03/20 Tue 03/03/20
31 Client Comment 2 days Wed 04/03/20 Thu 05/03/20 30
32 2nd Submission 1 day Fri 06/03/20 Fri 06/03/20 31
33 Client Approval 3 days Mon 09/03/20 Wed 11/03/20 32
34 Shell Course & Support Detail 7 days Wed 04/03/20 Thu 12/03/20
35 1st Submission 1 day Wed 04/03/20 Wed 04/03/20 30
36 Client Comment 2 days Thu 05/03/20 Fri 06/03/20 35
37 2nd Submission 1 day Mon 09/03/20 Mon 09/03/20 36
38 Client Approval 3 days Tue 10/03/20 Thu 12/03/20 37
39 Nozzle Details 7 days Thu 05/03/20 Fri 13/03/20
40 1st Submission 1 day Thu 05/03/20 Thu 05/03/20 35
41 Client Comment 2 days Fri 06/03/20 Mon 09/03/20 40
42 2nd Submission 1 day Tue 10/03/20 Tue 10/03/20 41
43 Client Approval 3 days Wed 11/03/20 Fri 13/03/20 42
44 Manhole Details 7 days Fri 06/03/20 Mon 16/03/20
45 1st Submission 1 day Fri 06/03/20 Fri 06/03/20 40
46 Client Comment 2 days Mon 09/03/20 Tue 10/03/20 45
47 2nd Submission 1 day Wed 11/03/20 Wed 11/03/20 46
48 Client Approval 3 days Thu 12/03/20 Mon 16/03/20 47
49 Name Plate Details 7 days Mon 09/03/20 Tue 17/03/20
50 1st Submission 1 day Mon 09/03/20 Mon 09/03/20 45
51 Client Comment 2 days Tue 10/03/20 Wed 11/03/20 50
52 2nd Submission 1 day Thu 12/03/20 Thu 12/03/20 51
53 Client Approval 3 days Fri 13/03/20 Tue 17/03/20 52
54 OXIDATIONS TANK 12 days Mon 02/03/20 Tue 17/03/20
55 General Arrangement 8 days Mon 02/03/20 Wed 11/03/20
56 1st Submission 2 days Mon 02/03/20 Tue 03/03/20
57 Client Comment 2 days Wed 04/03/20 Thu 05/03/20 56
58 2nd Submission 1 day Fri 06/03/20 Fri 06/03/20 57
59 Client Approval 3 days Mon 09/03/20 Wed 11/03/20 58
60 Shell Course & Support Detail 7 days Wed 04/03/20 Thu 12/03/20
61 1st Submission 1 day Wed 04/03/20 Wed 04/03/20 56
62 Client Comment 2 days Thu 05/03/20 Fri 06/03/20 61
63 2nd Submission 1 day Mon 09/03/20 Mon 09/03/20 62
64 Client Approval 3 days Tue 10/03/20 Thu 12/03/20 63
65 Nozzle Details 7 days Thu 05/03/20 Fri 13/03/20
66 1st Submission 1 day Thu 05/03/20 Thu 05/03/20 61
67 Client Comment 2 days Fri 06/03/20 Mon 09/03/20 66
68 2nd Submission 1 day Tue 10/03/20 Tue 10/03/20 67
69 Client Approval 3 days Wed 11/03/20 Fri 13/03/20 68
70 Manhole Details 7 days Fri 06/03/20 Mon 16/03/20
71 1st Submission 1 day Fri 06/03/20 Fri 06/03/20 66
72 Client Comment 2 days Mon 09/03/20 Tue 10/03/20 71
73 2nd Submission 1 day Wed 11/03/20 Wed 11/03/20 72
74 Client Approval 3 days Thu 12/03/20 Mon 16/03/20 73
75 Name Plate Details 7 days Mon 09/03/20 Tue 17/03/20
76 1st Submission 1 day Mon 09/03/20 Mon 09/03/20 71
77 Client Comment 2 days Tue 10/03/20 Wed 11/03/20 76
78 2nd Submission 1 day Thu 12/03/20 Thu 12/03/20 77
79 Client Approval 3 days Fri 13/03/20 Tue 17/03/20 78
80 FUEL GAS DRUM 12 days Mon 02/03/20 Tue 17/03/20
81 General Arrangement 8 days Mon 02/03/20 Wed 11/03/20
82 1st Submission 2 days Mon 02/03/20 Tue 03/03/20
83 Client Comment 2 days Wed 04/03/20 Thu 05/03/20 82
84 2nd Submission 1 day Fri 06/03/20 Fri 06/03/20 83
85 Client Approval 3 days Mon 09/03/20 Wed 11/03/20 84
86 Shell Course & Support Detail 7 days Wed 04/03/20 Thu 12/03/20
87 1st Submission 1 day Wed 04/03/20 Wed 04/03/20 82
88 Client Comment 2 days Thu 05/03/20 Fri 06/03/20 87
89 2nd Submission 1 day Mon 09/03/20 Mon 09/03/20 88
90 Client Approval 3 days Tue 10/03/20 Thu 12/03/20 89
91 Nozzle Details 7 days Thu 05/03/20 Fri 13/03/20
92 1st Submission 1 day Thu 05/03/20 Thu 05/03/20 87
93 Client Comment 2 days Fri 06/03/20 Mon 09/03/20 92
94 2nd Submission 1 day Tue 10/03/20 Tue 10/03/20 93
95 Client Approval 3 days Wed 11/03/20 Fri 13/03/20 94
96 Internal Details 7 days Fri 06/03/20 Mon 16/03/20
97 1st Submission 1 day Fri 06/03/20 Fri 06/03/20 92
98 Client Comment 2 days Mon 09/03/20 Tue 10/03/20 97
99 2nd Submission 1 day Wed 11/03/20 Wed 11/03/20 98
100 Client Approval 3 days Thu 12/03/20 Mon 16/03/20 99
101 Name Plate Details 7 days Mon 09/03/20 Tue 17/03/20
102 1st Submission 1 day Mon 09/03/20 Mon 09/03/20 97
103 Client Comment 2 days Tue 10/03/20 Wed 11/03/20 102
104 2nd Submission 1 day Thu 12/03/20 Thu 12/03/20 103
105 Client Approval 3 days Fri 13/03/20 Tue 17/03/20 104
106 LCO FLUSHING OIL DRUM 13 days Wed 18/03/20 Fri 03/04/20
107 General Arrangement 8 days Wed 18/03/20 Fri 27/03/20
108 1st Submission 2 days Wed 18/03/20 Thu 19/03/20 2
109 Client Comment 2 days Fri 20/03/20 Mon 23/03/20 108
110 2nd Submission 1 day Tue 24/03/20 Tue 24/03/20 109
111 Client Approval 3 days Wed 25/03/20 Fri 27/03/20 110
112 Shell Course & Support Detail 7 days Fri 20/03/20 Mon 30/03/20
113 1st Submission 1 day Fri 20/03/20 Fri 20/03/20 108
114 Client Comment 2 days Mon 23/03/20 Tue 24/03/20 113
115 2nd Submission 1 day Wed 25/03/20 Wed 25/03/20 114
116 Client Approval 3 days Thu 26/03/20 Mon 30/03/20 115
117 Nozzle Details 7 days Mon 23/03/20 Tue 31/03/20
118 1st Submission 1 day Mon 23/03/20 Mon 23/03/20 113
119 Client Comment 2 days Tue 24/03/20 Wed 25/03/20 118
120 2nd Submission 1 day Thu 26/03/20 Thu 26/03/20 119
121 Client Approval 3 days Fri 27/03/20 Tue 31/03/20 120
122 Manhole Details 7 days Tue 24/03/20 Wed 01/04/20
123 1st Submission 1 day Tue 24/03/20 Tue 24/03/20 118
124 Client Comment 2 days Wed 25/03/20 Thu 26/03/20 123
125 2nd Submission 1 day Fri 27/03/20 Fri 27/03/20 124
126 Client Approval 3 days Mon 30/03/20 Wed 01/04/20 125
127 Internal Details 7 days Wed 25/03/20 Thu 02/04/20
128 1st Submission 1 day Wed 25/03/20 Wed 25/03/20 123
129 Client Comment 2 days Thu 26/03/20 Fri 27/03/20 128
130 2nd Submission 1 day Mon 30/03/20 Mon 30/03/20 129
131 Client Approval 3 days Tue 31/03/20 Thu 02/04/20 130
132 Name Plate Details 7 days Thu 26/03/20 Fri 03/04/20
133 1st Submission 1 day Thu 26/03/20 Thu 26/03/20 128
134 Client Comment 2 days Fri 27/03/20 Mon 30/03/20 133
135 2nd Submission 1 day Tue 31/03/20 Tue 31/03/20 134
136 Client Approval 3 days Wed 01/04/20 Fri 03/04/20 135
137 HCO FLUSHING OIL DRUM 14 days Wed 18/03/20 Mon 06/04/20
138 General Arrangement 8 days Wed 18/03/20 Fri 27/03/20
139 1st Submission 2 days Wed 18/03/20 Thu 19/03/20 28
140 Client Comment 2 days Fri 20/03/20 Mon 23/03/20 139
141 2nd Submission 1 day Tue 24/03/20 Tue 24/03/20 140
142 Client Approval 3 days Wed 25/03/20 Fri 27/03/20 141
143 Shell Course & Support Detail 7 days Fri 20/03/20 Mon 30/03/20
144 1st Submission 1 day Fri 20/03/20 Fri 20/03/20 139
145 Client Comment 2 days Mon 23/03/20 Tue 24/03/20 144
146 2nd Submission 1 day Wed 25/03/20 Wed 25/03/20 145
147 Client Approval 3 days Thu 26/03/20 Mon 30/03/20 146
148 Nozzle Details 7 days Mon 23/03/20 Tue 31/03/20
149 1st Submission 1 day Mon 23/03/20 Mon 23/03/20 144
150 Client Comment 2 days Tue 24/03/20 Wed 25/03/20 149
151 2nd Submission 1 day Thu 26/03/20 Thu 26/03/20 150
152 Client Approval 3 days Fri 27/03/20 Tue 31/03/20 151
153 Manhole Details 7 days Tue 24/03/20 Wed 01/04/20
154 1st Submission 1 day Tue 24/03/20 Tue 24/03/20 149
155 Client Comment 2 days Wed 25/03/20 Thu 26/03/20 154
156 2nd Submission 1 day Fri 27/03/20 Fri 27/03/20 155
157 Client Approval 3 days Mon 30/03/20 Wed 01/04/20 156
158 Internal Details 7 days Wed 25/03/20 Thu 02/04/20
159 1st Submission 1 day Wed 25/03/20 Wed 25/03/20 154
160 Client Comment 2 days Thu 26/03/20 Fri 27/03/20 159
161 2nd Submission 1 day Mon 30/03/20 Mon 30/03/20 160
162 Client Approval 3 days Tue 31/03/20 Thu 02/04/20 161
163 Insulation Support Details 7 days Thu 26/03/20 Fri 03/04/20
164 1st Submission 1 day Thu 26/03/20 Thu 26/03/20 159
165 Client Comment 2 days Fri 27/03/20 Mon 30/03/20 164
166 2nd Submission 1 day Tue 31/03/20 Tue 31/03/20 165
167 Client Approval 3 days Wed 01/04/20 Fri 03/04/20 166
168 Name Plate Details 7 days Fri 27/03/20 Mon 06/04/20
169 1st Submission 1 day Fri 27/03/20 Fri 27/03/20 164
170 Client Comment 2 days Mon 30/03/20 Tue 31/03/20 169
171 2nd Submission 1 day Wed 01/04/20 Wed 01/04/20 170
172 Client Approval 3 days Thu 02/04/20 Mon 06/04/20 171
173 BACK FLUSH OIL DRAW‐OFF DRUM 14 days Wed 18/03/20 Mon 06/04/20
174 General Arrangement 8 days Wed 18/03/20 Fri 27/03/20
175 1st Submission 2 days Wed 18/03/20 Thu 19/03/20 54
176 Client Comment 2 days Fri 20/03/20 Mon 23/03/20 175
177 2nd Submission 1 day Tue 24/03/20 Tue 24/03/20 176
178 Client Approval 3 days Wed 25/03/20 Fri 27/03/20 177

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 1
PROJECT SCHEDULE
ENGINEERING

ID Task Name Duration Start Finish Predecess

02 Mar '20 23 Mar '20 13 Apr '20 04 May '20 25 May '20 15 Jun '20 06 Jul '20
22 01 09 17 25 02 10 18 26 04 12 20 28 05 13 21 29 07
179 Shell Course & Support Detail 7 days Fri 20/03/20 Mon 30/03/20
180 1st Submission 1 day Fri 20/03/20 Fri 20/03/20 175
181 Client Comment 2 days Mon 23/03/20 Tue 24/03/20 180
182 2nd Submission 1 day Wed 25/03/20 Wed 25/03/20 181
183 Client Approval 3 days Thu 26/03/20 Mon 30/03/20 182
184 Nozzle Details 7 days Mon 23/03/20 Tue 31/03/20
185 1st Submission 1 day Mon 23/03/20 Mon 23/03/20 180
186 Client Comment 2 days Tue 24/03/20 Wed 25/03/20 185
187 2nd Submission 1 day Thu 26/03/20 Thu 26/03/20 186
188 Client Approval 3 days Fri 27/03/20 Tue 31/03/20 187
189 Manhole Details 7 days Tue 24/03/20 Wed 01/04/20
190 1st Submission 1 day Tue 24/03/20 Tue 24/03/20 185
191 Client Comment 2 days Wed 25/03/20 Thu 26/03/20 190
192 2nd Submission 1 day Fri 27/03/20 Fri 27/03/20 191
193 Client Approval 3 days Mon 30/03/20 Wed 01/04/20 192
194 Internal Details 7 days Wed 25/03/20 Thu 02/04/20
195 1st Submission 1 day Wed 25/03/20 Wed 25/03/20 190
196 Client Comment 2 days Thu 26/03/20 Fri 27/03/20 195
197 2nd Submission 1 day Mon 30/03/20 Mon 30/03/20 196
198 Client Approval 3 days Tue 31/03/20 Thu 02/04/20 197
199 Insulation Support Details 7 days Thu 26/03/20 Fri 03/04/20
200 1st Submission 1 day Thu 26/03/20 Thu 26/03/20 195
201 Client Comment 2 days Fri 27/03/20 Mon 30/03/20 200
202 2nd Submission 1 day Tue 31/03/20 Tue 31/03/20 201
203 Client Approval 3 days Wed 01/04/20 Fri 03/04/20 202
204 Name Plate Details 7 days Fri 27/03/20 Mon 06/04/20
205 1st Submission 1 day Fri 27/03/20 Fri 27/03/20 200
206 Client Comment 2 days Mon 30/03/20 Tue 31/03/20 205
207 2nd Submission 1 day Wed 01/04/20 Wed 01/04/20 206
208 Client Approval 3 days Thu 02/04/20 Mon 06/04/20 207
209 BACK FLUSH OIL RECEIVER 14 days Wed 18/03/20 Mon 06/04/20
210 General Arrangement 8 days Wed 18/03/20 Fri 27/03/20
211 1st Submission 2 days Wed 18/03/20 Thu 19/03/20 80
212 Client Comment 2 days Fri 20/03/20 Mon 23/03/20 211
213 2nd Submission 1 day Tue 24/03/20 Tue 24/03/20 212
214 Client Approval 3 days Wed 25/03/20 Fri 27/03/20 213
215 Shell Course & Support Detail 7 days Fri 20/03/20 Mon 30/03/20
216 1st Submission 1 day Fri 20/03/20 Fri 20/03/20 211
217 Client Comment 2 days Mon 23/03/20 Tue 24/03/20 216
218 2nd Submission 1 day Wed 25/03/20 Wed 25/03/20 217
219 Client Approval 3 days Thu 26/03/20 Mon 30/03/20 218
220 Nozzle Details 7 days Mon 23/03/20 Tue 31/03/20
221 1st Submission 1 day Mon 23/03/20 Mon 23/03/20 216
222 Client Comment 2 days Tue 24/03/20 Wed 25/03/20 221
223 2nd Submission 1 day Thu 26/03/20 Thu 26/03/20 222
224 Client Approval 3 days Fri 27/03/20 Tue 31/03/20 223
225 Manhole Details 7 days Tue 24/03/20 Wed 01/04/20
226 1st Submission 1 day Tue 24/03/20 Tue 24/03/20 221
227 Client Comment 2 days Wed 25/03/20 Thu 26/03/20 226
228 2nd Submission 1 day Fri 27/03/20 Fri 27/03/20 227
229 Client Approval 3 days Mon 30/03/20 Wed 01/04/20 228
230 Internal Details 7 days Wed 25/03/20 Thu 02/04/20
231 1st Submission 1 day Wed 25/03/20 Wed 25/03/20 226
232 Client Comment 2 days Thu 26/03/20 Fri 27/03/20 231
233 2nd Submission 1 day Mon 30/03/20 Mon 30/03/20 232
234 Client Approval 3 days Tue 31/03/20 Thu 02/04/20 233
235 Insulation Support Details 7 days Thu 26/03/20 Fri 03/04/20
236 1st Submission 1 day Thu 26/03/20 Thu 26/03/20 231
237 Client Comment 2 days Fri 27/03/20 Mon 30/03/20 236
238 2nd Submission 1 day Tue 31/03/20 Tue 31/03/20 237
239 Client Approval 3 days Wed 01/04/20 Fri 03/04/20 238
240 Name Plate Details 7 days Fri 27/03/20 Mon 06/04/20
241 1st Submission 1 day Fri 27/03/20 Fri 27/03/20 236
242 Client Comment 2 days Mon 30/03/20 Tue 31/03/20 241
243 2nd Submission 1 day Wed 01/04/20 Wed 01/04/20 242
244 Client Approval 3 days Thu 02/04/20 Mon 06/04/20 243
245 SLURRY DRAW‐OFF DRUM 14 days Mon 06/04/20 Thu 23/04/20
246 General Arrangement 8 days Mon 06/04/20 Wed 15/04/20
247 1st Submission 2 days Mon 06/04/20 Tue 07/04/20 106
248 Client Comment 2 days Wed 08/04/20 Thu 09/04/20 247
249 2nd Submission 1 day Fri 10/04/20 Fri 10/04/20 248
250 Client Approval 3 days Mon 13/04/20 Wed 15/04/20 249
251 Shell Course & Support Detail 7 days Wed 08/04/20 Thu 16/04/20
252 1st Submission 1 day Wed 08/04/20 Wed 08/04/20 247
253 Client Comment 2 days Thu 09/04/20 Fri 10/04/20 252
254 2nd Submission 1 day Mon 13/04/20 Mon 13/04/20 253
255 Client Approval 3 days Tue 14/04/20 Thu 16/04/20 254
256 Nozzle Details 7 days Thu 09/04/20 Fri 17/04/20
257 1st Submission 1 day Thu 09/04/20 Thu 09/04/20 252
258 Client Comment 2 days Fri 10/04/20 Mon 13/04/20 257
259 2nd Submission 1 day Tue 14/04/20 Tue 14/04/20 258
260 Client Approval 3 days Wed 15/04/20 Fri 17/04/20 259
261 Manhole Details 4 days Fri 10/04/20 Wed 15/04/20
262 1st Submission 1 day Fri 10/04/20 Fri 10/04/20 257
263 Client Comment 2 days Mon 13/04/20 Tue 14/04/20 262
264 2nd Submission 1 day Wed 15/04/20 Wed 15/04/20 263
265 Client Approval 3 days Mon 13/04/20 Wed 15/04/20 249
266 Internal Details 7 days Mon 13/04/20 Tue 21/04/20
267 1st Submission 1 day Mon 13/04/20 Mon 13/04/20 262
268 Client Comment 2 days Tue 14/04/20 Wed 15/04/20 267
269 2nd Submission 1 day Thu 16/04/20 Thu 16/04/20 268
270 Client Approval 3 days Fri 17/04/20 Tue 21/04/20 269
271 Insulation Support Details 7 days Tue 14/04/20 Wed 22/04/20
272 1st Submission 1 day Tue 14/04/20 Tue 14/04/20 267
273 Client Comment 2 days Wed 15/04/20 Thu 16/04/20 272
274 2nd Submission 1 day Fri 17/04/20 Fri 17/04/20 273
275 Client Approval 3 days Mon 20/04/20 Wed 22/04/20 274
276 Name Plate Details 7 days Wed 15/04/20 Thu 23/04/20
277 1st Submission 1 day Wed 15/04/20 Wed 15/04/20 272
278 Client Comment 2 days Thu 16/04/20 Fri 17/04/20 277
279 2nd Submission 1 day Mon 20/04/20 Mon 20/04/20 278
280 Client Approval 3 days Tue 21/04/20 Thu 23/04/20 279
281 INTERSTAGE DRUM 13 days Tue 07/04/20 Thu 23/04/20
282 General Arrangement 8 days Tue 07/04/20 Thu 16/04/20
283 1st Submission 2 days Tue 07/04/20 Wed 08/04/20 137
284 Client Comment 2 days Thu 09/04/20 Fri 10/04/20 283
285 2nd Submission 1 day Mon 13/04/20 Mon 13/04/20 284
286 Client Approval 3 days Tue 14/04/20 Thu 16/04/20 285
287 Shell Course & Support Detail 7 days Thu 09/04/20 Fri 17/04/20
288 1st Submission 1 day Thu 09/04/20 Thu 09/04/20 283
289 Client Comment 2 days Fri 10/04/20 Mon 13/04/20 288
290 2nd Submission 1 day Tue 14/04/20 Tue 14/04/20 289
291 Client Approval 3 days Wed 15/04/20 Fri 17/04/20 290
292 Nozzle Details 7 days Fri 10/04/20 Mon 20/04/20
293 1st Submission 1 day Fri 10/04/20 Fri 10/04/20 288
294 Client Comment 2 days Mon 13/04/20 Tue 14/04/20 293
295 2nd Submission 1 day Wed 15/04/20 Wed 15/04/20 294
296 Client Approval 3 days Thu 16/04/20 Mon 20/04/20 295
297 Manhole Details 7 days Mon 13/04/20 Tue 21/04/20
298 1st Submission 1 day Mon 13/04/20 Mon 13/04/20 293
299 Client Comment 2 days Tue 14/04/20 Wed 15/04/20 298
300 2nd Submission 1 day Thu 16/04/20 Thu 16/04/20 299
301 Client Approval 3 days Fri 17/04/20 Tue 21/04/20 300
302 Internal Details 7 days Tue 14/04/20 Wed 22/04/20
303 1st Submission 1 day Tue 14/04/20 Tue 14/04/20 298
304 Client Comment 2 days Wed 15/04/20 Thu 16/04/20 303
305 2nd Submission 1 day Fri 17/04/20 Fri 17/04/20 304
306 Client Approval 3 days Mon 20/04/20 Wed 22/04/20 305
307 Name Plate Details 7 days Wed 15/04/20 Thu 23/04/20
308 1st Submission 1 day Wed 15/04/20 Wed 15/04/20 303
309 Client Comment 2 days Thu 16/04/20 Fri 17/04/20 308
310 2nd Submission 1 day Mon 20/04/20 Mon 20/04/20 309
311 Client Approval 3 days Tue 21/04/20 Thu 23/04/20 310
312 PRIMARY ABSORBER REFLUX DRUM 13 days Tue 07/04/20 Thu 23/04/20
313 General Arrangement 8 days Tue 07/04/20 Thu 16/04/20
314 1st Submission 2 days Tue 07/04/20 Wed 08/04/20 173
315 Client Comment 2 days Thu 09/04/20 Fri 10/04/20 314
316 2nd Submission 1 day Mon 13/04/20 Mon 13/04/20 315
317 Client Approval 3 days Tue 14/04/20 Thu 16/04/20 316
318 Shell Course & Support Detail 7 days Thu 09/04/20 Fri 17/04/20
319 1st Submission 1 day Thu 09/04/20 Thu 09/04/20 314
320 Client Comment 2 days Fri 10/04/20 Mon 13/04/20 319
321 2nd Submission 1 day Tue 14/04/20 Tue 14/04/20 320
322 Client Approval 3 days Wed 15/04/20 Fri 17/04/20 321
323 Nozzle Details 7 days Fri 10/04/20 Mon 20/04/20
324 1st Submission 1 day Fri 10/04/20 Fri 10/04/20 319
325 Client Comment 2 days Mon 13/04/20 Tue 14/04/20 324
326 2nd Submission 1 day Wed 15/04/20 Wed 15/04/20 325
327 Client Approval 3 days Thu 16/04/20 Mon 20/04/20 326
328 Manhole Details 7 days Mon 13/04/20 Tue 21/04/20
329 1st Submission 1 day Mon 13/04/20 Mon 13/04/20 324
330 Client Comment 2 days Tue 14/04/20 Wed 15/04/20 329
331 2nd Submission 1 day Thu 16/04/20 Thu 16/04/20 330
332 Client Approval 3 days Fri 17/04/20 Tue 21/04/20 331
333 Internal Details 7 days Tue 14/04/20 Wed 22/04/20
334 1st Submission 1 day Tue 14/04/20 Tue 14/04/20 329
335 Client Comment 2 days Wed 15/04/20 Thu 16/04/20 334
336 2nd Submission 1 day Fri 17/04/20 Fri 17/04/20 335
337 Client Approval 3 days Mon 20/04/20 Wed 22/04/20 336
338 Name Plate Details 7 days Wed 15/04/20 Thu 23/04/20
339 1st Submission 1 day Wed 15/04/20 Wed 15/04/20 334
340 Client Comment 2 days Thu 16/04/20 Fri 17/04/20 339
341 2nd Submission 1 day Mon 20/04/20 Mon 20/04/20 340
342 Client Approval 3 days Tue 21/04/20 Thu 23/04/20 341
343 DEBUTANIZER REFLUX DRUM 14 days Tue 07/04/20 Fri 24/04/20
344 General Arrangement 8 days Tue 07/04/20 Thu 16/04/20
345 1st Submission 2 days Tue 07/04/20 Wed 08/04/20 209
346 Client Comment 2 days Thu 09/04/20 Fri 10/04/20 345
347 2nd Submission 1 day Mon 13/04/20 Mon 13/04/20 346
348 Client Approval 3 days Tue 14/04/20 Thu 16/04/20 347
349 Shell Course & Support Detail 7 days Thu 09/04/20 Fri 17/04/20
350 1st Submission 1 day Thu 09/04/20 Thu 09/04/20 345
351 Client Comment 2 days Fri 10/04/20 Mon 13/04/20 350
352 2nd Submission 1 day Tue 14/04/20 Tue 14/04/20 351
353 Client Approval 3 days Wed 15/04/20 Fri 17/04/20 352
354 Nozzle Details 7 days Fri 10/04/20 Mon 20/04/20
355 1st Submission 1 day Fri 10/04/20 Fri 10/04/20 350
356 Client Comment 2 days Mon 13/04/20 Tue 14/04/20 355

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 2
PROJECT SCHEDULE
ENGINEERING

ID Task Name Duration Start Finish Predecess

02 Mar '20 23 Mar '20 13 Apr '20 04 May '20 25 May '20 15 Jun '20 06 Jul '20
22 01 09 17 25 02 10 18 26 04 12 20 28 05 13 21 29 07
357 2nd Submission 1 day Wed 15/04/20 Wed 15/04/20 356
358 Client Approval 3 days Thu 16/04/20 Mon 20/04/20 357
359 Manhole Details 7 days Mon 13/04/20 Tue 21/04/20
360 1st Submission 1 day Mon 13/04/20 Mon 13/04/20 355
361 Client Comment 2 days Tue 14/04/20 Wed 15/04/20 360
362 2nd Submission 1 day Thu 16/04/20 Thu 16/04/20 361
363 Client Approval 3 days Fri 17/04/20 Tue 21/04/20 362
364 Internal Details 7 days Tue 14/04/20 Wed 22/04/20
365 1st Submission 1 day Tue 14/04/20 Tue 14/04/20 360
366 Client Comment 2 days Wed 15/04/20 Thu 16/04/20 365
367 2nd Submission 1 day Fri 17/04/20 Fri 17/04/20 366
368 Client Approval 3 days Mon 20/04/20 Wed 22/04/20 367
369 Insulation Support Details 7 days Wed 15/04/20 Thu 23/04/20
370 1st Submission 1 day Wed 15/04/20 Wed 15/04/20 365
371 Client Comment 2 days Thu 16/04/20 Fri 17/04/20 370
372 2nd Submission 1 day Mon 20/04/20 Mon 20/04/20 371
373 Client Approval 3 days Tue 21/04/20 Thu 23/04/20 372
374 Name Plate Details 7 days Thu 16/04/20 Fri 24/04/20
375 1st Submission 1 day Thu 16/04/20 Thu 16/04/20 370
376 Client Comment 2 days Fri 17/04/20 Mon 20/04/20 375
377 2nd Submission 1 day Tue 21/04/20 Tue 21/04/20 376
378 Client Approval 3 days Wed 22/04/20 Fri 24/04/20 377
379 LPG AMINE SETTLER 13 days Fri 24/04/20 Tue 12/05/20
380 General Arrangement 8 days Fri 24/04/20 Tue 05/05/20
381 1st Submission 2 days Fri 24/04/20 Mon 27/04/20 245
382 Client Comment 2 days Tue 28/04/20 Wed 29/04/20 381
383 2nd Submission 1 day Thu 30/04/20 Thu 30/04/20 382
384 Client Approval 3 days Fri 01/05/20 Tue 05/05/20 383
385 Shell Course & Support Detail 7 days Tue 28/04/20 Wed 06/05/20
386 1st Submission 1 day Tue 28/04/20 Tue 28/04/20 381
387 Client Comment 2 days Wed 29/04/20 Thu 30/04/20 386
388 2nd Submission 1 day Fri 01/05/20 Fri 01/05/20 387
389 Client Approval 3 days Mon 04/05/20 Wed 06/05/20 388
390 Nozzle Details 7 days Wed 29/04/20 Thu 07/05/20
391 1st Submission 1 day Wed 29/04/20 Wed 29/04/20 386
392 Client Comment 2 days Thu 30/04/20 Fri 01/05/20 391
393 2nd Submission 1 day Mon 04/05/20 Mon 04/05/20 392
394 Client Approval 3 days Tue 05/05/20 Thu 07/05/20 393
395 Manhole Details 7 days Thu 30/04/20 Fri 08/05/20
396 1st Submission 1 day Thu 30/04/20 Thu 30/04/20 391
397 Client Comment 2 days Fri 01/05/20 Mon 04/05/20 396
398 2nd Submission 1 day Tue 05/05/20 Tue 05/05/20 397
399 Client Approval 3 days Wed 06/05/20 Fri 08/05/20 398
400 Internal Details 7 days Fri 01/05/20 Mon 11/05/20
401 1st Submission 1 day Fri 01/05/20 Fri 01/05/20 396
402 Client Comment 2 days Mon 04/05/20 Tue 05/05/20 401
403 2nd Submission 1 day Wed 06/05/20 Wed 06/05/20 402
404 Client Approval 3 days Thu 07/05/20 Mon 11/05/20 403
405 Name Plate Details 7 days Mon 04/05/20 Tue 12/05/20
406 1st Submission 1 day Mon 04/05/20 Mon 04/05/20 401
407 Client Comment 2 days Tue 05/05/20 Wed 06/05/20 406
408 2nd Submission 1 day Thu 07/05/20 Thu 07/05/20 407
409 Client Approval 3 days Fri 08/05/20 Tue 12/05/20 408
410 FEED MP STEAM HEATER CONDENSATE  13 days Fri 24/04/20 Tue 12/05/20
POTS
411 General Arrangement 8 days Fri 24/04/20 Tue 05/05/20
412 1st Submission 2 days Fri 24/04/20 Mon 27/04/20 281
413 Client Comment 2 days Tue 28/04/20 Wed 29/04/20 412
414 2nd Submission 1 day Thu 30/04/20 Thu 30/04/20 413
415 Client Approval 3 days Fri 01/05/20 Tue 05/05/20 414
416 Shell Course & Support Detail 7 days Tue 28/04/20 Wed 06/05/20
417 1st Submission 1 day Tue 28/04/20 Tue 28/04/20 412
418 Client Comment 2 days Wed 29/04/20 Thu 30/04/20 417
419 2nd Submission 1 day Fri 01/05/20 Fri 01/05/20 418
420 Client Approval 3 days Mon 04/05/20 Wed 06/05/20 419
421 Nozzle Details 7 days Wed 29/04/20 Thu 07/05/20
422 1st Submission 1 day Wed 29/04/20 Wed 29/04/20 417
423 Client Comment 2 days Thu 30/04/20 Fri 01/05/20 422
424 2nd Submission 1 day Mon 04/05/20 Mon 04/05/20 423
425 Client Approval 3 days Tue 05/05/20 Thu 07/05/20 424
426 Manhole Details 7 days Thu 30/04/20 Fri 08/05/20
427 1st Submission 1 day Thu 30/04/20 Thu 30/04/20 422
428 Client Comment 2 days Fri 01/05/20 Mon 04/05/20 427
429 2nd Submission 1 day Tue 05/05/20 Tue 05/05/20 428
430 Client Approval 3 days Wed 06/05/20 Fri 08/05/20 429
431 Insulation Support Details 7 days Fri 01/05/20 Mon 11/05/20
432 1st Submission 1 day Fri 01/05/20 Fri 01/05/20 427
433 Client Comment 2 days Mon 04/05/20 Tue 05/05/20 432
434 2nd Submission 1 day Wed 06/05/20 Wed 06/05/20 433
435 Client Approval 3 days Thu 07/05/20 Mon 11/05/20 434
436 Name Plate Details 7 days Mon 04/05/20 Tue 12/05/20
437 1st Submission 1 day Mon 04/05/20 Mon 04/05/20 432
438 Client Comment 2 days Tue 05/05/20 Wed 06/05/20 437
439 2nd Submission 1 day Thu 07/05/20 Thu 07/05/20 438
440 Client Approval 3 days Fri 08/05/20 Tue 12/05/20 439
441 BLOWDOWN COLLECTOR 14 days Fri 24/04/20 Wed 13/05/20
442 General Arrangement 8 days Fri 24/04/20 Tue 05/05/20
443 1st Submission 2 days Fri 24/04/20 Mon 27/04/20 312
444 Client Comment 2 days Tue 28/04/20 Wed 29/04/20 443
445 2nd Submission 1 day Thu 30/04/20 Thu 30/04/20 444
446 Client Approval 3 days Fri 01/05/20 Tue 05/05/20 445
447 Shell Course & Support Detail 7 days Tue 28/04/20 Wed 06/05/20
448 1st Submission 1 day Tue 28/04/20 Tue 28/04/20 443
449 Client Comment 2 days Wed 29/04/20 Thu 30/04/20 448
450 2nd Submission 1 day Fri 01/05/20 Fri 01/05/20 449
451 Client Approval 3 days Mon 04/05/20 Wed 06/05/20 450
452 Nozzle Details 7 days Wed 29/04/20 Thu 07/05/20
453 1st Submission 1 day Wed 29/04/20 Wed 29/04/20 448
454 Client Comment 2 days Thu 30/04/20 Fri 01/05/20 453
455 2nd Submission 1 day Mon 04/05/20 Mon 04/05/20 454
456 Client Approval 3 days Tue 05/05/20 Thu 07/05/20 455
457 Manhole Details 7 days Thu 30/04/20 Fri 08/05/20
458 1st Submission 1 day Thu 30/04/20 Thu 30/04/20 453
459 Client Comment 2 days Fri 01/05/20 Mon 04/05/20 458
460 2nd Submission 1 day Tue 05/05/20 Tue 05/05/20 459
461 Client Approval 3 days Wed 06/05/20 Fri 08/05/20 460
462 Internal Details 7 days Fri 01/05/20 Mon 11/05/20
463 1st Submission 1 day Fri 01/05/20 Fri 01/05/20 458
464 Client Comment 2 days Mon 04/05/20 Tue 05/05/20 463
465 2nd Submission 1 day Wed 06/05/20 Wed 06/05/20 464
466 Client Approval 3 days Thu 07/05/20 Mon 11/05/20 465
467 Insulation Support Details 7 days Mon 04/05/20 Tue 12/05/20
468 1st Submission 1 day Mon 04/05/20 Mon 04/05/20 463
469 Client Comment 2 days Tue 05/05/20 Wed 06/05/20 468
470 2nd Submission 1 day Thu 07/05/20 Thu 07/05/20 469
471 Client Approval 3 days Fri 08/05/20 Tue 12/05/20 470
472 Name Plate Details 7 days Tue 05/05/20 Wed 13/05/20
473 1st Submission 1 day Tue 05/05/20 Tue 05/05/20 468
474 Client Comment 2 days Wed 06/05/20 Thu 07/05/20 473
475 2nd Submission 1 day Fri 08/05/20 Fri 08/05/20 474
476 Client Approval 3 days Mon 11/05/20 Wed 13/05/20 475
477 MP CONDENSATE COLLECTOR 14 days Mon 27/04/20 Thu 14/05/20
478 General Arrangement 8 days Mon 27/04/20 Wed 06/05/20
479 1st Submission 2 days Mon 27/04/20 Tue 28/04/20 343
480 Client Comment 2 days Wed 29/04/20 Thu 30/04/20 479
481 2nd Submission 1 day Fri 01/05/20 Fri 01/05/20 480
482 Client Approval 3 days Mon 04/05/20 Wed 06/05/20 481
483 Shell Course & Support Detail 7 days Wed 29/04/20 Thu 07/05/20
484 1st Submission 1 day Wed 29/04/20 Wed 29/04/20 479
485 Client Comment 2 days Thu 30/04/20 Fri 01/05/20 484
486 2nd Submission 1 day Mon 04/05/20 Mon 04/05/20 485
487 Client Approval 3 days Tue 05/05/20 Thu 07/05/20 486
488 Nozzle Details 7 days Thu 30/04/20 Fri 08/05/20
489 1st Submission 1 day Thu 30/04/20 Thu 30/04/20 484
490 Client Comment 2 days Fri 01/05/20 Mon 04/05/20 489
491 2nd Submission 1 day Tue 05/05/20 Tue 05/05/20 490
492 Client Approval 3 days Wed 06/05/20 Fri 08/05/20 491
493 Manhole Details 7 days Fri 01/05/20 Mon 11/05/20
494 1st Submission 1 day Fri 01/05/20 Fri 01/05/20 489
495 Client Comment 2 days Mon 04/05/20 Tue 05/05/20 494
496 2nd Submission 1 day Wed 06/05/20 Wed 06/05/20 495
497 Client Approval 3 days Thu 07/05/20 Mon 11/05/20 496
498 Internal Details 7 days Mon 04/05/20 Tue 12/05/20
499 1st Submission 1 day Mon 04/05/20 Mon 04/05/20 494
500 Client Comment 2 days Tue 05/05/20 Wed 06/05/20 499
501 2nd Submission 1 day Thu 07/05/20 Thu 07/05/20 500
502 Client Approval 3 days Fri 08/05/20 Tue 12/05/20 501
503 Insulation Support Details 7 days Tue 05/05/20 Wed 13/05/20
504 1st Submission 1 day Tue 05/05/20 Tue 05/05/20 499
505 Client Comment 2 days Wed 06/05/20 Thu 07/05/20 504
506 2nd Submission 1 day Fri 08/05/20 Fri 08/05/20 505
507 Client Approval 3 days Mon 11/05/20 Wed 13/05/20 506
508 Name Plate Details 7 days Wed 06/05/20 Thu 14/05/20
509 1st Submission 1 day Wed 06/05/20 Wed 06/05/20 504
510 Client Comment 2 days Thu 07/05/20 Fri 08/05/20 509
511 2nd Submission 1 day Mon 11/05/20 Mon 11/05/20 510
512 Client Approval 3 days Tue 12/05/20 Thu 14/05/20 511
513 LP CONDENSATE COLLECTOR 12 days Wed 13/05/20 Thu 28/05/20
514 General Arrangement 8 days Wed 13/05/20 Fri 22/05/20
515 1st Submission 2 days Wed 13/05/20 Thu 14/05/20 379
516 Client Comment 2 days Fri 15/05/20 Mon 18/05/20 515
517 2nd Submission 1 day Tue 19/05/20 Tue 19/05/20 516
518 Client Approval 3 days Wed 20/05/20 Fri 22/05/20 517
519 Shell Course & Support Detail 7 days Fri 15/05/20 Mon 25/05/20
520 1st Submission 1 day Fri 15/05/20 Fri 15/05/20 515
521 Client Comment 2 days Mon 18/05/20 Tue 19/05/20 520
522 2nd Submission 1 day Wed 20/05/20 Wed 20/05/20 521
523 Client Approval 3 days Thu 21/05/20 Mon 25/05/20 522
524 Nozzle Details 7 days Mon 18/05/20 Tue 26/05/20
525 1st Submission 1 day Mon 18/05/20 Mon 18/05/20 520
526 Client Comment 2 days Tue 19/05/20 Wed 20/05/20 525
527 2nd Submission 1 day Thu 21/05/20 Thu 21/05/20 526
528 Client Approval 3 days Fri 22/05/20 Tue 26/05/20 527
529 Manhole Details 7 days Tue 19/05/20 Wed 27/05/20
530 1st Submission 1 day Tue 19/05/20 Tue 19/05/20 525
531 Client Comment 2 days Wed 20/05/20 Thu 21/05/20 530
532 2nd Submission 1 day Fri 22/05/20 Fri 22/05/20 531
533 Client Approval 3 days Mon 25/05/20 Wed 27/05/20 532

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 3
PROJECT SCHEDULE
ENGINEERING

ID Task Name Duration Start Finish Predecess

02 Mar '20 23 Mar '20 13 Apr '20 04 May '20 25 May '20 15 Jun '20 06 Jul '20
22 01 09 17 25 02 10 18 26 04 12 20 28 05 13 21 29 07
534 Name Plate Details 7 days Wed 20/05/20 Thu 28/05/20
535 1st Submission 1 day Wed 20/05/20 Wed 20/05/20 530
536 Client Comment 2 days Thu 21/05/20 Fri 22/05/20 535
537 2nd Submission 1 day Mon 25/05/20 Mon 25/05/20 536
538 Client Approval 3 days Tue 26/05/20 Thu 28/05/20 537
539 LIGHT HYDROCARBON SUMP DRUM I 14 days Wed 13/05/20 Mon 01/06/20
540 General Arrangement 8 days Wed 13/05/20 Fri 22/05/20
541 1st Submission 2 days Wed 13/05/20 Thu 14/05/20 410
542 Client Comment 2 days Fri 15/05/20 Mon 18/05/20 541
543 2nd Submission 1 day Tue 19/05/20 Tue 19/05/20 542
544 Client Approval 3 days Wed 20/05/20 Fri 22/05/20 543
545 Shell Course & Support Detail 7 days Fri 15/05/20 Mon 25/05/20
546 1st Submission 1 day Fri 15/05/20 Fri 15/05/20 541
547 Client Comment 2 days Mon 18/05/20 Tue 19/05/20 546
548 2nd Submission 1 day Wed 20/05/20 Wed 20/05/20 547
549 Client Approval 3 days Thu 21/05/20 Mon 25/05/20 548
550 Nozzle Details 7 days Mon 18/05/20 Tue 26/05/20
551 1st Submission 1 day Mon 18/05/20 Mon 18/05/20 546
552 Client Comment 2 days Tue 19/05/20 Wed 20/05/20 551
553 2nd Submission 1 day Thu 21/05/20 Thu 21/05/20 552
554 Client Approval 3 days Fri 22/05/20 Tue 26/05/20 553
555 Manhole Details 7 days Tue 19/05/20 Wed 27/05/20
556 1st Submission 1 day Tue 19/05/20 Tue 19/05/20 551
557 Client Comment 2 days Wed 20/05/20 Thu 21/05/20 556
558 2nd Submission 1 day Fri 22/05/20 Fri 22/05/20 557
559 Client Approval 3 days Mon 25/05/20 Wed 27/05/20 558
560 Internal Details 7 days Wed 20/05/20 Thu 28/05/20
561 1st Submission 1 day Wed 20/05/20 Wed 20/05/20 556
562 Client Comment 2 days Thu 21/05/20 Fri 22/05/20 561
563 2nd Submission 1 day Mon 25/05/20 Mon 25/05/20 562
564 Client Approval 3 days Tue 26/05/20 Thu 28/05/20 563
565 Insulation Support Details 7 days Thu 21/05/20 Fri 29/05/20
566 1st Submission 1 day Thu 21/05/20 Thu 21/05/20 561
567 Client Comment 2 days Fri 22/05/20 Mon 25/05/20 566
568 2nd Submission 1 day Tue 26/05/20 Tue 26/05/20 567
569 Client Approval 3 days Wed 27/05/20 Fri 29/05/20 568
570 Name Plate Details 7 days Fri 22/05/20 Mon 01/06/20
571 1st Submission 1 day Fri 22/05/20 Fri 22/05/20 566
572 Client Comment 2 days Mon 25/05/20 Tue 26/05/20 571
573 2nd Submission 1 day Wed 27/05/20 Wed 27/05/20 572
574 Client Approval 3 days Thu 28/05/20 Mon 01/06/20 573
575 AMINE SUMP DRUM 12 days Thu 14/05/20 Fri 29/05/20
576 General Arrangement 8 days Thu 14/05/20 Mon 25/05/20
577 1st Submission 2 days Thu 14/05/20 Fri 15/05/20 441
578 Client Comment 2 days Mon 18/05/20 Tue 19/05/20 577
579 2nd Submission 1 day Wed 20/05/20 Wed 20/05/20 578
580 Client Approval 3 days Thu 21/05/20 Mon 25/05/20 579
581 Shell Course & Support Detail 7 days Mon 18/05/20 Tue 26/05/20
582 1st Submission 1 day Mon 18/05/20 Mon 18/05/20 577
583 Client Comment 2 days Tue 19/05/20 Wed 20/05/20 582
584 2nd Submission 1 day Thu 21/05/20 Thu 21/05/20 583
585 Client Approval 3 days Fri 22/05/20 Tue 26/05/20 584
586 Nozzle Details 7 days Tue 19/05/20 Wed 27/05/20
587 1st Submission 1 day Tue 19/05/20 Tue 19/05/20 582
588 Client Comment 2 days Wed 20/05/20 Thu 21/05/20 587
589 2nd Submission 1 day Fri 22/05/20 Fri 22/05/20 588
590 Client Approval 3 days Mon 25/05/20 Wed 27/05/20 589
591 Manhole Details 7 days Wed 20/05/20 Thu 28/05/20
592 1st Submission 1 day Wed 20/05/20 Wed 20/05/20 587
593 Client Comment 2 days Thu 21/05/20 Fri 22/05/20 592
594 2nd Submission 1 day Mon 25/05/20 Mon 25/05/20 593
595 Client Approval 3 days Tue 26/05/20 Thu 28/05/20 594
596 Name Plate Details 7 days Thu 21/05/20 Fri 29/05/20
597 1st Submission 1 day Thu 21/05/20 Thu 21/05/20 592
598 Client Comment 2 days Fri 22/05/20 Mon 25/05/20 597
599 2nd Submission 1 day Tue 26/05/20 Tue 26/05/20 598
600 Client Approval 3 days Wed 27/05/20 Fri 29/05/20 599
601 STRIPPER LP CONDENSATE POTS 13 days Fri 15/05/20 Tue 02/06/20
602 General Arrangement 8 days Fri 15/05/20 Tue 26/05/20
603 1st Submission 2 days Fri 15/05/20 Mon 18/05/20 477
604 Client Comment 2 days Tue 19/05/20 Wed 20/05/20 603
605 2nd Submission 1 day Thu 21/05/20 Thu 21/05/20 604
606 Client Approval 3 days Fri 22/05/20 Tue 26/05/20 605
607 Shell Course & Support Detail 7 days Tue 19/05/20 Wed 27/05/20
608 1st Submission 1 day Tue 19/05/20 Tue 19/05/20 603
609 Client Comment 2 days Wed 20/05/20 Thu 21/05/20 608
610 2nd Submission 1 day Fri 22/05/20 Fri 22/05/20 609
611 Client Approval 3 days Mon 25/05/20 Wed 27/05/20 610
612 Nozzle Details 7 days Wed 20/05/20 Thu 28/05/20
613 1st Submission 1 day Wed 20/05/20 Wed 20/05/20 608
614 Client Comment 2 days Thu 21/05/20 Fri 22/05/20 613
615 2nd Submission 1 day Mon 25/05/20 Mon 25/05/20 614
616 Client Approval 3 days Tue 26/05/20 Thu 28/05/20 615
617 Manhole Details 7 days Thu 21/05/20 Fri 29/05/20
618 1st Submission 1 day Thu 21/05/20 Thu 21/05/20 613
619 Client Comment 2 days Fri 22/05/20 Mon 25/05/20 618
620 2nd Submission 1 day Tue 26/05/20 Tue 26/05/20 619
621 Client Approval 3 days Wed 27/05/20 Fri 29/05/20 620
622 Insulation Support Details 7 days Fri 22/05/20 Mon 01/06/20
623 1st Submission 1 day Fri 22/05/20 Fri 22/05/20 618
624 Client Comment 2 days Mon 25/05/20 Tue 26/05/20 623
625 2nd Submission 1 day Wed 27/05/20 Wed 27/05/20 624
626 Client Approval 3 days Thu 28/05/20 Mon 01/06/20 625
627 Name Plate Details 7 days Mon 25/05/20 Tue 02/06/20
628 1st Submission 1 day Mon 25/05/20 Mon 25/05/20 623
629 Client Comment 2 days Tue 26/05/20 Wed 27/05/20 628
630 2nd Submission 1 day Thu 28/05/20 Thu 28/05/20 629
631 Client Approval 3 days Fri 29/05/20 Tue 02/06/20 630
632 FUEL GAS K.O. DRUM 13 days Fri 29/05/20 Tue 16/06/20
633 General Arrangement 8 days Fri 29/05/20 Tue 09/06/20
634 1st Submission 2 days Fri 29/05/20 Mon 01/06/20 513
635 Client Comment 2 days Tue 02/06/20 Wed 03/06/20 634
636 2nd Submission 1 day Thu 04/06/20 Thu 04/06/20 635
637 Client Approval 3 days Fri 05/06/20 Tue 09/06/20 636
638 Shell Course & Support Detail 7 days Tue 02/06/20 Wed 10/06/20
639 1st Submission 1 day Tue 02/06/20 Tue 02/06/20 634
640 Client Comment 2 days Wed 03/06/20 Thu 04/06/20 639
641 2nd Submission 1 day Fri 05/06/20 Fri 05/06/20 640
642 Client Approval 3 days Mon 08/06/20 Wed 10/06/20 641
643 Nozzle Details 7 days Wed 03/06/20 Thu 11/06/20
644 1st Submission 1 day Wed 03/06/20 Wed 03/06/20 639
645 Client Comment 2 days Thu 04/06/20 Fri 05/06/20 644
646 2nd Submission 1 day Mon 08/06/20 Mon 08/06/20 645
647 Client Approval 3 days Tue 09/06/20 Thu 11/06/20 646
648 Manhole Details 7 days Thu 04/06/20 Fri 12/06/20
649 1st Submission 1 day Thu 04/06/20 Thu 04/06/20 644
650 Client Comment 2 days Fri 05/06/20 Mon 08/06/20 649
651 2nd Submission 1 day Tue 09/06/20 Tue 09/06/20 650
652 Client Approval 3 days Wed 10/06/20 Fri 12/06/20 651
653 Internal Details 7 days Fri 05/06/20 Mon 15/06/20
654 1st Submission 1 day Fri 05/06/20 Fri 05/06/20 649
655 Client Comment 2 days Mon 08/06/20 Tue 09/06/20 654
656 2nd Submission 1 day Wed 10/06/20 Wed 10/06/20 655
657 Client Approval 3 days Thu 11/06/20 Mon 15/06/20 656
658 Name Plate Details 7 days Mon 08/06/20 Tue 16/06/20
659 1st Submission 1 day Mon 08/06/20 Mon 08/06/20 654
660 Client Comment 2 days Tue 09/06/20 Wed 10/06/20 659
661 2nd Submission 1 day Thu 11/06/20 Thu 11/06/20 660
662 Client Approval 3 days Fri 12/06/20 Tue 16/06/20 661
663 HEAVY HYDROCARBON SUMP DRUM I 13 days Tue 02/06/20 Thu 18/06/20
664 General Arrangement 8 days Tue 02/06/20 Thu 11/06/20
665 1st Submission 2 days Tue 02/06/20 Wed 03/06/20 539
666 Client Comment 2 days Thu 04/06/20 Fri 05/06/20 665
667 2nd Submission 1 day Mon 08/06/20 Mon 08/06/20 666
668 Client Approval 3 days Tue 09/06/20 Thu 11/06/20 667
669 Shell Course & Support Detail 7 days Thu 04/06/20 Fri 12/06/20
670 1st Submission 1 day Thu 04/06/20 Thu 04/06/20 665
671 Client Comment 2 days Fri 05/06/20 Mon 08/06/20 670
672 2nd Submission 1 day Tue 09/06/20 Tue 09/06/20 671
673 Client Approval 3 days Wed 10/06/20 Fri 12/06/20 672
674 Nozzle Details 7 days Fri 05/06/20 Mon 15/06/20
675 1st Submission 1 day Fri 05/06/20 Fri 05/06/20 670
676 Client Comment 2 days Mon 08/06/20 Tue 09/06/20 675
677 2nd Submission 1 day Wed 10/06/20 Wed 10/06/20 676
678 Client Approval 3 days Thu 11/06/20 Mon 15/06/20 677
679 Manhole Details 7 days Mon 08/06/20 Tue 16/06/20
680 1st Submission 1 day Mon 08/06/20 Mon 08/06/20 675
681 Client Comment 2 days Tue 09/06/20 Wed 10/06/20 680
682 2nd Submission 1 day Thu 11/06/20 Thu 11/06/20 681
683 Client Approval 3 days Fri 12/06/20 Tue 16/06/20 682
684 Insulation Support Details 7 days Tue 09/06/20 Wed 17/06/20
685 1st Submission 1 day Tue 09/06/20 Tue 09/06/20 680
686 Client Comment 2 days Wed 10/06/20 Thu 11/06/20 685
687 2nd Submission 1 day Fri 12/06/20 Fri 12/06/20 686
688 Client Approval 3 days Mon 15/06/20 Wed 17/06/20 687
689 Name Plate Details 7 days Wed 10/06/20 Thu 18/06/20
690 1st Submission 1 day Wed 10/06/20 Wed 10/06/20 685
691 Client Comment 2 days Thu 11/06/20 Fri 12/06/20 690
692 2nd Submission 1 day Mon 15/06/20 Mon 15/06/20 691
693 Client Approval 3 days Tue 16/06/20 Thu 18/06/20 692
694 SOUR HYDROCARBON SUMP DRUM 12 days Mon 01/06/20 Tue 16/06/20
695 General Arrangement 8 days Mon 01/06/20 Wed 10/06/20
696 1st Submission 2 days Mon 01/06/20 Tue 02/06/20 575
697 Client Comment 2 days Wed 03/06/20 Thu 04/06/20 696
698 2nd Submission 1 day Fri 05/06/20 Fri 05/06/20 697
699 Client Approval 3 days Mon 08/06/20 Wed 10/06/20 698
700 Shell Course & Support Detail 7 days Wed 03/06/20 Thu 11/06/20
701 1st Submission 1 day Wed 03/06/20 Wed 03/06/20 696
702 Client Comment 2 days Thu 04/06/20 Fri 05/06/20 701
703 2nd Submission 1 day Mon 08/06/20 Mon 08/06/20 702
704 Client Approval 3 days Tue 09/06/20 Thu 11/06/20 703
705 Nozzle Details 7 days Thu 04/06/20 Fri 12/06/20
706 1st Submission 1 day Thu 04/06/20 Thu 04/06/20 701
707 Client Comment 2 days Fri 05/06/20 Mon 08/06/20 706
708 2nd Submission 1 day Tue 09/06/20 Tue 09/06/20 707
709 Client Approval 3 days Wed 10/06/20 Fri 12/06/20 708
710 Manhole Details 7 days Fri 05/06/20 Mon 15/06/20
711 1st Submission 1 day Fri 05/06/20 Fri 05/06/20 706

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 4
PROJECT SCHEDULE
ENGINEERING

ID Task Name Duration Start Finish Predecess

02 Mar '20 23 Mar '20 13 Apr '20 04 May '20 25 May '20 15 Jun '20 06 Jul '20
22 01 09 17 25 02 10 18 26 04 12 20 28 05 13 21 29 07
712 Client Comment 2 days Mon 08/06/20 Tue 09/06/20 711
713 2nd Submission 1 day Wed 10/06/20 Wed 10/06/20 712
714 Client Approval 3 days Thu 11/06/20 Mon 15/06/20 713
715 Name Plate Details 7 days Mon 08/06/20 Tue 16/06/20
716 1st Submission 1 day Mon 08/06/20 Mon 08/06/20 711
717 Client Comment 2 days Tue 09/06/20 Wed 10/06/20 716
718 2nd Submission 1 day Thu 11/06/20 Thu 11/06/20 717
719 Client Approval 3 days Fri 12/06/20 Tue 16/06/20 718
720 LIGHT HYDROCARBON SUMP DRUM II 12 days Wed 03/06/20 Thu 18/06/20
721 General Arrangement 8 days Wed 03/06/20 Fri 12/06/20
722 1st Submission 2 days Wed 03/06/20 Thu 04/06/20 601
723 Client Comment 2 days Fri 05/06/20 Mon 08/06/20 722
724 2nd Submission 1 day Tue 09/06/20 Tue 09/06/20 723
725 Client Approval 3 days Wed 10/06/20 Fri 12/06/20 724
726 Shell Course & Support Detail 7 days Fri 05/06/20 Mon 15/06/20
727 1st Submission 1 day Fri 05/06/20 Fri 05/06/20 722
728 Client Comment 2 days Mon 08/06/20 Tue 09/06/20 727
729 2nd Submission 1 day Wed 10/06/20 Wed 10/06/20 728
730 Client Approval 3 days Thu 11/06/20 Mon 15/06/20 729
731 Nozzle Details 7 days Mon 08/06/20 Tue 16/06/20
732 1st Submission 1 day Mon 08/06/20 Mon 08/06/20 727
733 Client Comment 2 days Tue 09/06/20 Wed 10/06/20 732
734 2nd Submission 1 day Thu 11/06/20 Thu 11/06/20 733
735 Client Approval 3 days Fri 12/06/20 Tue 16/06/20 734
736 Manhole Details 7 days Tue 09/06/20 Wed 17/06/20
737 1st Submission 1 day Tue 09/06/20 Tue 09/06/20 732
738 Client Comment 2 days Wed 10/06/20 Thu 11/06/20 737
739 2nd Submission 1 day Fri 12/06/20 Fri 12/06/20 738
740 Client Approval 3 days Mon 15/06/20 Wed 17/06/20 739
741 Name Plate Details 7 days Wed 10/06/20 Thu 18/06/20
742 1st Submission 1 day Wed 10/06/20 Wed 10/06/20 737
743 Client Comment 2 days Thu 11/06/20 Fri 12/06/20 742
744 2nd Submission 1 day Mon 15/06/20 Mon 15/06/20 743
745 Client Approval 3 days Tue 16/06/20 Thu 18/06/20 744
746 HEAVY HYDROCARBON SUMP DRUM II 13 days Wed 17/06/20 Fri 03/07/20
747 General Arrangement 8 days Wed 17/06/20 Fri 26/06/20
748 1st Submission 2 days Wed 17/06/20 Thu 18/06/20 632
749 Client Comment 2 days Fri 19/06/20 Mon 22/06/20 748
750 2nd Submission 1 day Tue 23/06/20 Tue 23/06/20 749
751 Client Approval 3 days Wed 24/06/20 Fri 26/06/20 750
752 Shell Course & Support Detail 7 days Fri 19/06/20 Mon 29/06/20
753 1st Submission 1 day Fri 19/06/20 Fri 19/06/20 748
754 Client Comment 2 days Mon 22/06/20 Tue 23/06/20 753
755 2nd Submission 1 day Wed 24/06/20 Wed 24/06/20 754
756 Client Approval 3 days Thu 25/06/20 Mon 29/06/20 755
757 Nozzle Details 7 days Mon 22/06/20 Tue 30/06/20
758 1st Submission 1 day Mon 22/06/20 Mon 22/06/20 753
759 Client Comment 2 days Tue 23/06/20 Wed 24/06/20 758
760 2nd Submission 1 day Thu 25/06/20 Thu 25/06/20 759
761 Client Approval 3 days Fri 26/06/20 Tue 30/06/20 760
762 Manhole Details 7 days Tue 23/06/20 Wed 01/07/20
763 1st Submission 1 day Tue 23/06/20 Tue 23/06/20 758
764 Client Comment 2 days Wed 24/06/20 Thu 25/06/20 763
765 2nd Submission 1 day Fri 26/06/20 Fri 26/06/20 764
766 Client Approval 3 days Mon 29/06/20 Wed 01/07/20 765
767 Internal Details 7 days Wed 24/06/20 Thu 02/07/20
768 1st Submission 1 day Wed 24/06/20 Wed 24/06/20 763
769 Client Comment 2 days Thu 25/06/20 Fri 26/06/20 768
770 2nd Submission 1 day Mon 29/06/20 Mon 29/06/20 769
771 Client Approval 3 days Tue 30/06/20 Thu 02/07/20 770
772 Name Plate Details 7 days Thu 25/06/20 Fri 03/07/20
773 1st Submission 1 day Thu 25/06/20 Thu 25/06/20 768
774 Client Comment 2 days Fri 26/06/20 Mon 29/06/20 773
775 2nd Submission 1 day Tue 30/06/20 Tue 30/06/20 774
776 Client Approval 3 days Wed 01/07/20 Fri 03/07/20 775

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 5
PROJECT SCHEDULE
ENGINEERING

6 Jul '20 27 Jul '20 17 Aug '20 07 Sep '20 28 Sep '20 19 Oct '20 09 Nov '20 30 Nov '20 21 Dec '20 11 Jan '2
07 15 23 31 08 16 24 01 09 17 25 03 11 19 27 04 12 20 28 06 14 22 30 07

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 6
PROJECT SCHEDULE
ENGINEERING

6 Jul '20 27 Jul '20 17 Aug '20 07 Sep '20 28 Sep '20 19 Oct '20 09 Nov '20 30 Nov '20 21 Dec '20 11 Jan '2
07 15 23 31 08 16 24 01 09 17 25 03 11 19 27 04 12 20 28 06 14 22 30 07

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 7
PROJECT SCHEDULE
ENGINEERING

6 Jul '20 27 Jul '20 17 Aug '20 07 Sep '20 28 Sep '20 19 Oct '20 09 Nov '20 30 Nov '20 21 Dec '20 11 Jan '2
07 15 23 31 08 16 24 01 09 17 25 03 11 19 27 04 12 20 28 06 14 22 30 07

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 8
PROJECT SCHEDULE
ENGINEERING

6 Jul '20 27 Jul '20 17 Aug '20 07 Sep '20 28 Sep '20 19 Oct '20 09 Nov '20 30 Nov '20 21 Dec '20 11 Jan '2
07 15 23 31 08 16 24 01 09 17 25 03 11 19 27 04 12 20 28 06 14 22 30 07

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 9
PROJECT SCHEDULE
ENGINEERING

6 Jul '20 27 Jul '20 17 Aug '20 07 Sep '20 28 Sep '20 19 Oct '20 09 Nov '20 30 Nov '20 21 Dec '20 11 Jan '2
07 15 23 31 08 16 24 01 09 17 25 03 11 19 27 04 12 20 28 06 14 22 30 07

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 10