Professional Documents
Culture Documents
p89 PDF
p89 PDF
33 KV 11 KV
I. INTRODUCTION
400 V 400 V
Distribution reforms have been implemented by many
electricity supply utilities to improve their performance and LT feeder LT feeder
achieve economic self sustenance. In this regard, one aspect
Metering point
which still bothers the distribution companies is the distribution
system losses which are found to be very high in the range of Fig 1: Schematic diagram of Distribution feeder
18-62%[1] compared to the existing levels in developed
countries. Hence loss reduction is seen as one of the primary II. PROCEDURE FOR TOTAL LOSS ESTIMATION
means of achieving commercial performance improvement of
distribution companies. The need for reducing excessive The total energy loss in a distribution feeder is in general
distribution losses, in the Indian power sector is now being defined as the difference between the energy input and energy
recognized as one of the key requirements for restoring supplied (billed). The following expressions are true:
financial viability of the distribution companies.
Total energy loss = Loss in HT feeder + Loss in LT feeder,
The distribution system losses have two components, kWh
namely, technical and commercial, together called “total Where,
distribution loss”. Technical loss [2] is amenable to reasoning
and fairly accurate estimation. Hence could be controlled with Loss in HT feeder = Energy input to HT feeder - (energy sent
some financial investment, the returns on which could be out on LT feeders + billed energy of HT
predicted. Contrary to this, commercial loss is mainly governed consumers), kWh
by non-technical issues like theft, lack of metering and non and,
timely replacement of faulty meters which make its
quantification difficult. Loss in LT feeder = Energy input to LT feeder – billed energy
of LT consumers, kWh
P.Chandhra Sekhar is with Central Power Research Institute, 9480619140,
pcs@cpri.in
R.S. Shiva Kumara Aradhya is with Central Power Research Institute,
From the above, it is evident that the total loss estimation
9448282334, aradya@cpri.in requires accurate measurement of energy input to the HT (11
M.M.Babu Narayanan is with Central Power Research Institute, 9448282321, kV) and associated LT (440 V) feeders, feeder wise
babu @cpri.in
450
Fifteenth National Power Systems Conference (NPSC), IIT Bombay, December 2008
consumption of energy by HT and LT consumers, all distribution companies as per their schedule is also formulated
recorded simultaneously for the same period of time. The to suit different class of consumers.
estimated losses will be dependable only if all the energy
meters are in good working condition. In reality, certain A. Estimation of energy supplied to the LT feeders with non-
percentage of meters at LT feeder and LT consumer may be functional DTR energy meters
non-functional [3] due to some reason or the other. While there
is no standard procedure followed by distribution companies to 1. For a HT feeder under consideration, from the energy
account for the unread energy input to the LT feeders, for HT recorded by the healthy DTR meters, the average
and LT consumers’ average consumption based on the previous energy sent out per KVA rating of the transformers
few month’s consumption is considered for billing. The same per hour are calculated separately for different ratings
data is also considered for loss estimation. As exact meter of the transformers in the feeder.
reading date and time is not generally recorded by distribution
companies, the conventional method does not account for the 2. The estimates for the energy sent out by transformers
non-simultaneous reading of the energy meters and assumes having non-functional energy meters are obtained
that the data is gathered for the same duration and hence by multiplying the transformer KVA rating by
suitable for loss estimation. respective average consumption per hour.
Field experience of the authors in gathering the energy There are some cases where individual LT consumption
and consumer consumption data shows that in most cases, could not be read using spot billing machine due to various
appreciable percentage of meters, mainly at the sending end of reasons for the period considered for loss estimation. In such
the LT feeders located at the secondary of the Distribution cases, the average LT consumption per KVA rating of a
Transformers (DTR) and consumer meters would be faulty at distribution transformer is calculated by considering the data of
any given point of time. In addition, though arrangements are successfully down loaded DT meters and their LT
available to record the HT and LT feeder inputs simultaneously, consumption, wherever both are available. The LT
by use of Load Survey type of electronic energy meters, the consumption corresponding to a transformer where some
individual HT and LT consumer consumption supplied by these consumer meters could not be read is calculated by multiplying
feeders are collected by different agencies at their own the average LT consumption per KVA with the KVA rating of
schedule, often convenient for billing. Adding to the the transformer under consideration.
complexity is the fact that it is not the practice of distribution
companies to collect and record the individual consumer C. Estimation of energy Consumed by un metered
consumption feeder wise. It is also observed that the set date Agricultural pump sets
and time in the HT and LT feeder meters are non-synchronized
either due to not taking care while commissioning or not setting LT Agricultural feeder consists of mix of agriculture and
it correctly after replacing the drained batteries providing power rural domestic consumers. Energy supply is restricted to a few
supply to the memory unit. Hence correlation between the hours per day to suit agricultural consumers. Some of the
energy input and consumption in a particular feeder for a fixed distribution companies do not provide energy meters to
duration of time is not possible. Obviously the losses estimated agricultural pump sets as the energy is to be supplied free as per
using this data would be erroneous. the policies of the government. Hence the consumption is to be
derived from one time measurement of the load current and
IV. THE NOVEL PROCEDURE average time for which the energy is supplied.
As none of the constraints mentioned in the previous Collection of field information showed that power supply
section could be readily overcome, in order to bring some is restricted to an average duration of 5½ hours/day to
acceptability to the estimated losses, procedures have been agricultural pump sets. An average power factor of 0.85 for the
formulated for reasonable estimation of (a) energy supplied to pump sets is found to be a reasonably good assumption.
the LT feeders with non-functional DTR energy meters, (b)
total energy consumed by consumers on LT feeder where some Therefore,
consumer meters could not be read and (c) energy consumed by
agricultural pump sets which are not metered. Consumption of an agricultural Pump set
Procedure for indirect time synchronization between HT = ¥3 VLIL CosɎ * Nh*Nm , Wh / month
feeder input, LT feeder input , HT consumer consumption data
and LT consumer consumption data for the data collected by Where,
451
Fifteenth National Power Systems Conference (NPSC), IIT Bombay, December 2008
VL= line voltage c. The total DTR consumption (LT feeder input) is calculated
IL = line current by adding Normalized Distribution transformer
CosɎ = power factor consumption and projected normalized Distribution
Nh = No. of hours of power supply per day transformer consumption.
Nm = Period considered for loss calculation, days
Total DTR Consumption =
D. Procedure for Indirect time synchronization of feeder inputs
and consumer data Normalized consumptio n Pr ojectedNor malizedDTR consumptio n
Feeder loss estimation requires time synchronized energy 2 .Time Synchronization at Consumer level
data for HT feeder input, LT feeder energy input and HT and
LT consumer consumption. This aspect will be presented in The procedure varies based on the category of the consumers in
detail while discussing field data collection for this work. the feeder. The following procedures are proposed for each category
b. Industrial feeders
Re cordedFeederInputEnergyxAverageDuration
LT consumption reading, date and time are noted down
Actualrecordedduration(hrs )
manually for individual LT consumers in the case of Industrial
feeder and procedures similar to that described in section D are
b. Projected Normalized Energy of Non-functional
followed.
Energy (DTR) Meters is calculated as
c. Agricultural feeders
EstimatedE nergyasper D u AverageDur ationinHrs
There is no requirement for specific procedure in the case
of agriculture consumers as the time considered for estimating
the consumption in section C it self is average time. However,
452
Fifteenth National Power Systems Conference (NPSC), IIT Bombay, December 2008
agriculture feeder also has domestic (rural) consumers whose Feeder Date of meter reading Dura- Energy
consumption is normalized using procedure in section D. First Second tion input to
(Hours) the feeder
(kWh)
d. HT Consumers Urban 3-7-06 7-8-06 840 1650835
Indus- 19-8-06 21-9-06 840 789288
The HT consumer billing data collected from Private agencies trial
Agric- 7-7-06 12-8-06 864 642054
with the permission of concerned utility officials .The data is ultural
normalized using procedure in section D.
Table 2: Details of energy input to HT feeders
V. DISTRIBUTION FEEDERS CONSIDERED FOR THE
LOSS ESTIMATION
The Table 3 and Table 4 shows details of measurement dates
Three typical 11 kV feeders are chosen representing the and energy input to feeders.
three common types of consumers, namely, urban, industrial
and agricultural. The details of these feeders are given in Table
1. HT Date of meter reading Average
Feeder First Second Duration
(Hours)
Type Lengt Distribution transformers and Urban 3rd July 2007 3rd Aug to 19th 16days
of h DTR meters in the feeder to 19th July Aug 07
feeder of Total Working % of 2007
11 kV meters meters Working Indus- 6th Sep07 13th Oct 07 1 day
feeder (No.) (No.) meters trial
(km) Agric- Rural 4July 07 to 14 days
Urban 5.39 51 39 76.47 ultural Consumer 17July 07
Agricultural 10th to 11th Aug 2 days
Indus- 7.10 24 20 83.33
consumer 07
trial
Agric- 15.2 55 21 38.18
ultural
Table 3: Details of dates of measurements of energy input
to LT feeders
Table 1: Details of distribution feeders chosen
HT Total energy input to LT feeders for the duration
for the study Feeder given in Table 3
(kWh)
It could be observed from the feeder data that the Measured for Estimated for Total
agricultural feeder is the longest and is evident that being rural LT feeders with LT feeders with
working meters faulty meters
feeder, may have received less attention in provide metering. Urban 746867 129074 875941
Indus- 770729.9 NA 770729.9
VI. COLLECTION OF ENERGY INPUT AND trial
CONSUMPTION INFORMATION Agric- 132331.9 480146.6 612478.5
ultural
453
Fifteenth National Power Systems Conference (NPSC), IIT Bombay, December 2008
A. Result from Conventional Method In this case, as observed from the results, the % loss in urban
feeder is considerably lower compared with the loss estimated
The % losses at HT level, LT level and total losses are shown in with conventional method.
Table 5 for the three classes of feeder considered.
C. Comparison of Results from the Two Methods
URBAN FEEDER
The various percentage losses estimated with data received
Sr.No Category of Loss % Loss
loss (kwh) from utility is compared with that obtained with normalized
1 HT Level 102272.48 6.2% data with proper date and time in Table 7.
2 LT Level 197849.2 18.425%
3 Total losses 300121.63 25.52% The results clearly indicate that the loss estimated
INDUSTRIAL FEEDER without normalization of data is in general higher.
Sr.No Category of Loss % Loss
loss (kwh) URBAN FEEDER
1 HT Level 18558.1 ( 2.35%) Sr. Voltage Difference Difference
2 LT Level 7392.9 ( 14.02%) No. Level in in % Loss
3 Total losses 25951 (16.37%) loss (kwh)
RURAL/AGRICULTURE FEEDER 1 HT Level 53221.905 (3.14%)
Sr.No Category of Loss % Loss 2 LT Level 107662.25 (10.045%)
loss (kwh) 3 Total losses 160883.745 (13.15%)
1 HT Level 37415.59 ( 5.76) INDUSTRIAL FEEDER
2 LT Level 71099.20 (11.61) Sr. Voltage Difference Difference
3 Total losses 108514.79 (16.70) No. Level In Loss in % Loss
Table 5: Results from Conventional Method (kwh)
454
Fifteenth National Power Systems Conference (NPSC), IIT Bombay, December 2008
IX . CONCLUSIONS
X. ACKNOWLEDGEMENT
1. Estimation of HT & LT losses for urban, industrial and
rural feeder was attempted by collecting field data on The authors wish to thank management of CPRI for
consumption & supply. granting permission to publish this paper .The authors are also
thankful to Smt.J.Sri Devi, E.O.IV and S.Shyamsundar, EO IV of
Power System Division of CPRI for their help during the field work
2. Loss estimation was carried out with data received from and the authors also thank Prof.Atmanand for his valuable inputs in
field as followed by utilities. the dissertation .
455