Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

Fifteenth National Power Systems Conference (NPSC), IIT Bombay, December 2008

A Novel Method for Estimation of HT and LT


Feeder Losses in Distribution System
P. Chandra Sekar, R.S. Shivakumara Aradhya and M.M.Babu Narayanan

Abstract: Losses in distribution system play a major role in


the economic viability of power system operation. Efforts toMa Many distribution companies are adopting the approach of
estimate distribution losses by suitable metering are very limited “100% metering and Total Energy Audit” to curb the
in our country. Practical experience in one of the distribution commercial loss. While load flow analysis is universally used
companies show that reliability of load survey type energy meters
for technical loss estimation, the commercial loss is obtained by
used to record energy input to HT and LT distribution feeders is
poor and the scenario may not be much different in many other subtracting technical loss from the total loss. However, the
distribution companies. Effort is made in this paper to estimate estimation of total loss pose the same difficulty attributed to the
the total energy loss in three types of distribution feeders, namely, estimation of commercial loss mentioned above. Hence, there is
urban, industrial and rural with data as collected by utilities to a need for formulating and standardizing the procedure for total
highlight the need for deriving common time duration (data time loss estimation, which in turn facilitates estimation of
synchronization) for the collected data at different schedules by commercial loss with reasonable accuracy. The new procedure
different agencies to be used for loss estimation. shall take into account all major constraints experienced in
collection of the necessary field data for total loss estimation. A
Simple method is proposed to estimate the energy input to
schematic of a typical distribution is shown in fig 1.
HT and LT feeders where the meters are not functional. With the
estimated energies and time synchronization of data, the estimated
LT
total HT and LT losses are found to be much different and appear
LT feeder feeder
reasonable.
400 V
400 V
It is also found that the new method is effective only if the
number of defective meters is limited within a certain range. HT feeder

33 KV 11 KV
I. INTRODUCTION
400 V 400 V
Distribution reforms have been implemented by many
electricity supply utilities to improve their performance and LT feeder LT feeder
achieve economic self sustenance. In this regard, one aspect
Metering point
which still bothers the distribution companies is the distribution
system losses which are found to be very high in the range of Fig 1: Schematic diagram of Distribution feeder
18-62%[1] compared to the existing levels in developed
countries. Hence loss reduction is seen as one of the primary II. PROCEDURE FOR TOTAL LOSS ESTIMATION
means of achieving commercial performance improvement of
distribution companies. The need for reducing excessive The total energy loss in a distribution feeder is in general
distribution losses, in the Indian power sector is now being defined as the difference between the energy input and energy
recognized as one of the key requirements for restoring supplied (billed). The following expressions are true:
financial viability of the distribution companies.
Total energy loss = Loss in HT feeder + Loss in LT feeder,
The distribution system losses have two components, kWh
namely, technical and commercial, together called “total Where,
distribution loss”. Technical loss [2] is amenable to reasoning
and fairly accurate estimation. Hence could be controlled with Loss in HT feeder = Energy input to HT feeder - (energy sent
some financial investment, the returns on which could be out on LT feeders + billed energy of HT
predicted. Contrary to this, commercial loss is mainly governed consumers), kWh
by non-technical issues like theft, lack of metering and non and,
timely replacement of faulty meters which make its
quantification difficult. Loss in LT feeder = Energy input to LT feeder – billed energy
of LT consumers, kWh
P.Chandhra Sekhar is with Central Power Research Institute, 9480619140,
pcs@cpri.in
R.S. Shiva Kumara Aradhya is with Central Power Research Institute,
From the above, it is evident that the total loss estimation
9448282334, aradya@cpri.in requires accurate measurement of energy input to the HT (11
M.M.Babu Narayanan is with Central Power Research Institute, 9448282321, kV) and associated LT (440 V) feeders, feeder wise
babu @cpri.in

450
Fifteenth National Power Systems Conference (NPSC), IIT Bombay, December 2008

consumption of energy by HT and LT consumers, all distribution companies as per their schedule is also formulated
recorded simultaneously for the same period of time. The to suit different class of consumers.
estimated losses will be dependable only if all the energy
meters are in good working condition. In reality, certain A. Estimation of energy supplied to the LT feeders with non-
percentage of meters at LT feeder and LT consumer may be functional DTR energy meters
non-functional [3] due to some reason or the other. While there
is no standard procedure followed by distribution companies to 1. For a HT feeder under consideration, from the energy
account for the unread energy input to the LT feeders, for HT recorded by the healthy DTR meters, the average
and LT consumers’ average consumption based on the previous energy sent out per KVA rating of the transformers
few month’s consumption is considered for billing. The same per hour are calculated separately for different ratings
data is also considered for loss estimation. As exact meter of the transformers in the feeder.
reading date and time is not generally recorded by distribution
companies, the conventional method does not account for the 2. The estimates for the energy sent out by transformers
non-simultaneous reading of the energy meters and assumes having non-functional energy meters are obtained
that the data is gathered for the same duration and hence by multiplying the transformer KVA rating by
suitable for loss estimation. respective average consumption per hour.

III. CONSTRAINTS IN B. Estimation of total energy consumed by consumers on LT


PRESENT PRACTICE feeder where some consumer meters could not be read

Field experience of the authors in gathering the energy There are some cases where individual LT consumption
and consumer consumption data shows that in most cases, could not be read using spot billing machine due to various
appreciable percentage of meters, mainly at the sending end of reasons for the period considered for loss estimation. In such
the LT feeders located at the secondary of the Distribution cases, the average LT consumption per KVA rating of a
Transformers (DTR) and consumer meters would be faulty at distribution transformer is calculated by considering the data of
any given point of time. In addition, though arrangements are successfully down loaded DT meters and their LT
available to record the HT and LT feeder inputs simultaneously, consumption, wherever both are available. The LT
by use of Load Survey type of electronic energy meters, the consumption corresponding to a transformer where some
individual HT and LT consumer consumption supplied by these consumer meters could not be read is calculated by multiplying
feeders are collected by different agencies at their own the average LT consumption per KVA with the KVA rating of
schedule, often convenient for billing. Adding to the the transformer under consideration.
complexity is the fact that it is not the practice of distribution
companies to collect and record the individual consumer C. Estimation of energy Consumed by un metered
consumption feeder wise. It is also observed that the set date Agricultural pump sets
and time in the HT and LT feeder meters are non-synchronized
either due to not taking care while commissioning or not setting LT Agricultural feeder consists of mix of agriculture and
it correctly after replacing the drained batteries providing power rural domestic consumers. Energy supply is restricted to a few
supply to the memory unit. Hence correlation between the hours per day to suit agricultural consumers. Some of the
energy input and consumption in a particular feeder for a fixed distribution companies do not provide energy meters to
duration of time is not possible. Obviously the losses estimated agricultural pump sets as the energy is to be supplied free as per
using this data would be erroneous. the policies of the government. Hence the consumption is to be
derived from one time measurement of the load current and
IV. THE NOVEL PROCEDURE average time for which the energy is supplied.

As none of the constraints mentioned in the previous Collection of field information showed that power supply
section could be readily overcome, in order to bring some is restricted to an average duration of 5½ hours/day to
acceptability to the estimated losses, procedures have been agricultural pump sets. An average power factor of 0.85 for the
formulated for reasonable estimation of (a) energy supplied to pump sets is found to be a reasonably good assumption.
the LT feeders with non-functional DTR energy meters, (b)
total energy consumed by consumers on LT feeder where some Therefore,
consumer meters could not be read and (c) energy consumed by
agricultural pump sets which are not metered. Consumption of an agricultural Pump set

Procedure for indirect time synchronization between HT = ¥3 VLIL CosɎ * Nh*Nm , Wh / month
feeder input, LT feeder input , HT consumer consumption data
and LT consumer consumption data for the data collected by Where,

451
Fifteenth National Power Systems Conference (NPSC), IIT Bombay, December 2008

VL= line voltage c. The total DTR consumption (LT feeder input) is calculated
IL = line current by adding Normalized Distribution transformer
CosɎ = power factor consumption and projected normalized Distribution
Nh = No. of hours of power supply per day transformer consumption.
Nm = Period considered for loss calculation, days
Total DTR Consumption =
D. Procedure for Indirect time synchronization of feeder inputs
and consumer data Normalized consumptio n  Pr ojectedNor malizedDTR consumptio n

Feeder loss estimation requires time synchronized energy 2 .Time Synchronization at Consumer level
data for HT feeder input, LT feeder energy input and HT and
LT consumer consumption. This aspect will be presented in The procedure varies based on the category of the consumers in
detail while discussing field data collection for this work. the feeder. The following procedures are proposed for each category

In most of these estimates, a common time frame (average a. Urban feeder


duration) is to be evolved for all the measured and estimated In the case of urban feeders, LT consumer monthly billing
quantities. The experience of reading load survey data from HT data is available but time of reading is not available. However,
feeder meter, DTR meter, HT consumer and LT consumers is a it is a general practice that the meter reading is done from 08.00
time consuming process. On an average, it requires about 30 Hrs to 12.00 Hrs in the morning and again from 14.00 Hrs to
minutes to download a HT feeder meter, 48 hrs for DTR 18.00 Hrs in the afternoon on any scheduled meter reading day.
meters, 8 hrs for reading HT consumers data and about week to Therefore, the total duration is eight hours for billing per day
10 days to record all LT consumers consumption data. While i.e. 480 minutes in two parts of 240 minutes. The no. of meters
reading, the HT feeder meter and DTR meters, called CMRI corresponding to a distribution transformer (LT feeder) read
instrument is used .The data read by CMRI contains starting during morning half of the day and also during the afternoon
and ending time of the data recording in addition to the energy half are obtained from the billing section of the distribution
supplied. company. Similar information is collected for the whole period
of meter reading for that month for all the LT feeders. Average
In order to arrive at a common time frame for data time of successive meter reading is computed separately for the
synchronization the average of the reading times of the feeder meters read in the morning half and in the afternoon by
meter and DTR meters is taken as this provides some authentic dividing 240 minutes by the number of meters read during that
information on time. time. These are calculated for every meter read for both initial
reading and final reading after one month. The difference
Average Duration (Hrs): between the initial and final average time for individual
consumer meters gives reasonably accurate duration for which
the energy is supplied. From this, average energy consumed
FeederMeterrecording duration  SumofDTRme tersrecord ingduratio n per hour is calculated by dividing the billed energy by the
1  No.ofDTRs average time duration obtained as above.

1. Indirect time synchronization The individual consumer consumption is then


Between HT, LT feeder and HT consumer data normalized to the time duration arrived for LT feeder input in
Section D by multiplying the average energy consumed per
a. Normalization of HT & LT feeder energy input for feeder hour with the time interval considered for LT feeder input in
with functional meters hours. The sum of all such normalized consumptions for a
particular LT feeder will be the time synchronized LT
Normalized HT or LT feeder input Energy = consumption which is to be considered for loss estimation.

b. Industrial feeders
Re cordedFeederInputEnergyxAverageDuration
LT consumption reading, date and time are noted down
Actualrecordedduration(hrs )
manually for individual LT consumers in the case of Industrial
feeder and procedures similar to that described in section D are
b. Projected Normalized Energy of Non-functional
followed.
Energy (DTR) Meters is calculated as
c. Agricultural feeders
EstimatedE nergyasper D u AverageDur ationinHrs
There is no requirement for specific procedure in the case
of agriculture consumers as the time considered for estimating
the consumption in section C it self is average time. However,

452
Fifteenth National Power Systems Conference (NPSC), IIT Bombay, December 2008

agriculture feeder also has domestic (rural) consumers whose Feeder Date of meter reading Dura- Energy
consumption is normalized using procedure in section D. First Second tion input to
(Hours) the feeder
(kWh)
d. HT Consumers Urban 3-7-06 7-8-06 840 1650835
Indus- 19-8-06 21-9-06 840 789288
The HT consumer billing data collected from Private agencies trial
Agric- 7-7-06 12-8-06 864 642054
with the permission of concerned utility officials .The data is ultural
normalized using procedure in section D.
Table 2: Details of energy input to HT feeders
V. DISTRIBUTION FEEDERS CONSIDERED FOR THE
LOSS ESTIMATION
The Table 3 and Table 4 shows details of measurement dates
Three typical 11 kV feeders are chosen representing the and energy input to feeders.
three common types of consumers, namely, urban, industrial
and agricultural. The details of these feeders are given in Table
1. HT Date of meter reading Average
Feeder First Second Duration
(Hours)
Type Lengt Distribution transformers and Urban 3rd July 2007 3rd Aug to 19th 16days
of h DTR meters in the feeder to 19th July Aug 07
feeder of Total Working % of 2007
11 kV meters meters Working Indus- 6th Sep07 13th Oct 07 1 day
feeder (No.) (No.) meters trial
(km) Agric- Rural 4July 07 to 14 days
Urban 5.39 51 39 76.47 ultural Consumer 17July 07
Agricultural 10th to 11th Aug 2 days
Indus- 7.10 24 20 83.33
consumer 07
trial
Agric- 15.2 55 21 38.18
ultural
Table 3: Details of dates of measurements of energy input
to LT feeders
Table 1: Details of distribution feeders chosen
HT Total energy input to LT feeders for the duration
for the study Feeder given in Table 3
(kWh)
It could be observed from the feeder data that the Measured for Estimated for Total
agricultural feeder is the longest and is evident that being rural LT feeders with LT feeders with
working meters faulty meters
feeder, may have received less attention in provide metering. Urban 746867 129074 875941
Indus- 770729.9 NA 770729.9
VI. COLLECTION OF ENERGY INPUT AND trial
CONSUMPTION INFORMATION Agric- 132331.9 480146.6 612478.5
ultural

A. Energy input to HT and LT feeders Table 4: Total energy input to LT feeders

B. HT and LT consumer energy consumption


Electronic Trivector meters provided at the input to HT
(sending end of the 11 kV feeders) and LT (output of
All distribution companies generally read HT and LT
distribution transformers) feeders record among other data,
consumer meters once a month except for agricultural (rural)
energy supplied by the feeder at every half hour interval along
feeder, whose meters are read once in two months. The LT
with date and time stamp for each data recorded. The energy
consumer meters are read geographical area wise and not feeder
meter memory in most cases is adequate to store the data for
wise by private agencies that are hired by the utility. These
minimum period of 36 days. The stored data is downloaded into
results in the LT consumer meters belonging to a LT feeder
Common Meter Reading Instruments (CMRI) at site in on line
read on different days and at different time contrary to the
mode at the end of a month.
requirement of simultaneous reading for loss estimation. The
LT consumer data is either read and recorded manually or
The content of the CMRI are transferred to a personal
keyed into a hand held Spot Billing Machines. The HT
computer using the software of the meter manufacturer for
consumers’ meters are read by the HT billing section of
storing and further analysis. Table 2 shows the energy input to
Distribution Company using the CMRI.
the HT feeder as recorded by CMRI.
The urban feeder chosen for the study supplied 3185
nos.of LT consumers and 11 nos. of HT consumers. The
reading was completed in 16 days during the period 3rd to 19th

453
Fifteenth National Power Systems Conference (NPSC), IIT Bombay, December 2008

August 2006. The HT consumer meters were read in one day on


31st August 2006. From the results, it is seen that the % loss of urban feeder is
higher than Industrial feeder and Agricultural feeder .In
The industrial feeder supplied 25 LT consumers and 12 contrast, the % losses in normal practice are more in
industrial consumers at HT level. The initial LT and HT Agricultural feeder than urban and industrial feeder.
consumption readings were taken in one day on 6th September
2006 and the second reading was taken again in one day on 13th B. Results from Proposed Method
October 2006. The readings were taken on 6th September
between 12.00 Hrs and 17.00 Hrs and on 13th October it was
The % losses at HT level, LT level and total losses are shown in
from 16.00 Hrs to 19.00 Hrs.
Table 6 for the same feeder and with modified procedure.
There were 132 irrigation pump sets and 1570 rural URBAN FEEDER
domestic consumers in the rural feeder, all supplied at LT Sr.No Category Losses % losses
voltage level. In this distribution company the supply for of loss (kwh)
irrigation pump sets are not metered. Hence the line currents of 1 HT Level 49050.935 3.06%
all the 132 irrigation Pump sets were measured on 10th and 11th 2 LT Level 90186.95 8.38%
August 2006 to assess the energy consumed. 3 Total 139237.88 12.37%
losses
VII. CALCULATION OF HT & LT LOSSES INDUSTRIAL FEEDER
Sr.No Category Losses % losses
The data is normalized as per procedure given in clause of loss (kwh)
4.4 at HT level as well as at LT Level. The total losses are 1 HT Level 9173.7 1.21%
calculated using this data at HT level by subtracting the sum of 2 LT Level 5860.31 13.811%
the energy output of DTRs from the energy input to the HT 3 Total 15034.01 15.021%
feeder. The percentage losses are calculated by dividing the losses
total losses by Input energy. RURAL FEEDER
Sr.No Category Losses % losses
Similarly, Total LT Losses with Normalization of date of loss (kwh)
and time: (Input Energy to LT feeder with normalization data- 1 HT Level 37533.02 5.76%
Consumer consumption with normalized data) 2 LT Level 59263.02 9.66%
3 Total 96796.04 14.87%
losses
VIII. RESULTS & DISCUSSION Table 6: Results from Novel Method

A. Result from Conventional Method In this case, as observed from the results, the % loss in urban
feeder is considerably lower compared with the loss estimated
The % losses at HT level, LT level and total losses are shown in with conventional method.
Table 5 for the three classes of feeder considered.
C. Comparison of Results from the Two Methods
URBAN FEEDER
The various percentage losses estimated with data received
Sr.No Category of Loss % Loss
loss (kwh) from utility is compared with that obtained with normalized
1 HT Level 102272.48 6.2% data with proper date and time in Table 7.
2 LT Level 197849.2 18.425%
3 Total losses 300121.63 25.52% The results clearly indicate that the loss estimated
INDUSTRIAL FEEDER without normalization of data is in general higher.
Sr.No Category of Loss % Loss
loss (kwh) URBAN FEEDER
1 HT Level 18558.1 ( 2.35%) Sr. Voltage Difference Difference
2 LT Level 7392.9 ( 14.02%) No. Level in in % Loss
3 Total losses 25951 (16.37%) loss (kwh)
RURAL/AGRICULTURE FEEDER 1 HT Level 53221.905 (3.14%)
Sr.No Category of Loss % Loss 2 LT Level 107662.25 (10.045%)
loss (kwh) 3 Total losses 160883.745 (13.15%)
1 HT Level 37415.59 ( 5.76) INDUSTRIAL FEEDER
2 LT Level 71099.20 (11.61) Sr. Voltage Difference Difference
3 Total losses 108514.79 (16.70) No. Level In Loss in % Loss
Table 5: Results from Conventional Method (kwh)

454
Fifteenth National Power Systems Conference (NPSC), IIT Bombay, December 2008

1 HT Level 9384.4 (1.14%) In Industrial feeder, the difference in percentage of losses at HT


2 LT Level 1532.5 9 (0.209%) level is 1.14 where as the difference at LT level is 0.209 and the
3 Total losses 10916.99 (1.349%) overall difference is 1.349 .The consumption (two sets) readings were
RURAL/AGRICULTURE FEEDER taken in the month of Aug, 06 and Sep, 06 within one day at HT level
Sr. Voltage Difference Difference as well as at LT level. The time interval of meter reading at HT level is
No. Level InLoss in % Loss two days and the time interval of meter reading for LT consumers is
(kwh) just six hours, hence the difference between the losses estimated with
1 HT Level -117.43 (0%) normal practice and with proposed new method is very less.
2 LT Level 11836.18 (1.95%)
3 Total losses 11718.7478 (1.83%) In rural/agriculture feeder, difference in % losses at HT level is
zero (actually a negative value, but within the error limit of energy
Table 7: Difference in Results from the two methods
meter used at DTRs), where as, the difference at LT level is 1.95. The
overall difference in percentage losses for two methods is 1.83%.
It is observed that in urban feeder , the difference in
percentage losses at HT level is 3.14, where as, the difference at However in the case of rural feeder in addition to non metering of
LT level is 10.045 . The overall difference is 13.15 which are agriculture pump sets, a large number of DTR meters were found
high. The % error at HT level is less than at LT level because defective (34 out of 55 DTR meters).Hence, there is a possibility that
the Load survey data was downloaded for feeder and the estimated consumption of agricultural loads and LT consumption
Distribution transformers within a day i.e. on 3rd July, 2006 for on the same feeder could be inaccurate and these renders the
one set of readings and on 7th Aug, 2006 for second set of comparison difficult and no meaningful conclusion can be drawn.
readings after one month at LT level of urban feeder .It has Hence , the new novel method also could pose some limitation if large
no. of DTR meters are not working .It is observed that with about 80%
taken 16 days to complete all the LT consumers meter reading
of DTR meters working in a feeder, the new method is useful for
both on july ,06 and aug,06.Hence it is evident that the loss meaningful estimation as shown for urban and industrial feeder in this
estimate without normalization of data results in higher paper .
estimate for LT loss .

IX . CONCLUSIONS
X. ACKNOWLEDGEMENT
1. Estimation of HT & LT losses for urban, industrial and
rural feeder was attempted by collecting field data on The authors wish to thank management of CPRI for
consumption & supply. granting permission to publish this paper .The authors are also
thankful to Smt.J.Sri Devi, E.O.IV and S.Shyamsundar, EO IV of
Power System Division of CPRI for their help during the field work
2. Loss estimation was carried out with data received from and the authors also thank Prof.Atmanand for his valuable inputs in
field as followed by utilities. the dissertation .

3. Time synchronization of data was found to be a major XI. REFERENCES


source of error in the estimated losses
1. www.powermin.nic.in
4. A new method was proposed for normalization of field
data to arrive accurate loss estimation 2. Prabhakar. C, SriDevi.j, Bala Subramanyan P.V, Babu Na
rayanan. M.M (2004), Estimation of technical Losses in
5. It is concluded that normalization or time synchronization Transmission and Sub Transmission network of Andhra
of data is highly essential for accurate loss estimation Pradesh, NationalPowerSystemConference (NPSC) at
and to avoid reporting erroneous loss levels in Chennai, December 27-30, P.no.946
distribution utilities.
3. Shyam Sundar, Sridevi J, Aradhya R.S.S, Raghunatha,
6. It is also seen that estimated loss with the new method Sujatha Sub hash (2006), Energy Metering for Distribution
is influenced by the number of non available Loss Estimation –problems and solution paper
DTR/Consumer meter reading and possibly these could accepted for 14thNationalPowerSystem Conference
be a maximum limit on the number of un metered faulty (NPSC) is being hosted by the IIT, rourkee during
DT meters beyond which the proposed method may not be December,27 to 29.
simple.
4. Chandra Sekhar P.(2006) , Evaluation of 11kV and LT
7. The new method proposed here can be employed by the Losses in SPDCL using a novel Method, A dissertation
utilities to carry out energy accounting and audit in Submitted in Partial fulfillment of the requirements for the
distribution system award of PGDEM at MDI, Gurgaon.

455

You might also like