Professional Documents
Culture Documents
Time Schedule
Time Schedule
Duration M M M O M O
MA J J A S O ND J FMA M J J A S O ND J FMA M J J A S O ND J F A J J A S N D J FMA J J A S N D J F M A M J J A S O N D JF
Vung Ang 1 Thermal Power Plant - Level II 0
OP1000 Unit 1 Reliability Run 30 27-Jun-12 26-Jul-12 Change Unit 1 Reliability Run
OP2000 Unit 2 Reliability Run 30 28-Dec-12 26-Jan-13 Change Unit 2 Reliability Run
Power Island
Islan 0
Boiler and S
Some Auxiliaries 924 03-Aug-09 A 01-Mar-13 01-Mar-13, Boiler and Some Auxiliaries
Procurement
Procurem 0 18-Jun-10 18-Jun-10 18-Jun-10, Procurement
H070 Award of Boiler and Some Auxiliaries 0 18-Jun-10 Award of Boiler and Some Auxiliaries
Detailed Engineering
E 167 03-Aug-09 A 30-Mar-10 30-Mar-10, Detailed Engineering
UHA010 Main Structure Boiler Design 210 03-Aug-09 A 27-Feb-10 change Main Structure Boiler Design
UHA030 Unit 1 Boiler Piling Dwgs IFC 0 30-Nov-09 A Unit 1 Boiler Piling Dwgs IFC
UHA035 Unit 1 Boiler Fdn Dwgs IFC 0 02-Mar-10 Unit 1 Boiler Fdn Dwgs IFC
BW005 Boiler & Aux Design, 240 03-Aug-09 A 30-Mar-10 Boiler & Aux Design,
Construction
Construct 715 01-Dec-09 A 12-Sep-12 12-Sep-12, Construction
UHA040 Unit 1 Boiler Foundation work 180 01-Dec-09 A 30-May-10 Change Unit 1 Boiler Foundation work
H020 Unit 1 Boiler Erection of Steelwork 235 18-May-10* 15-Feb-11 Change Unit 1 Boiler Erection of Steelwork
H060 Unit 1 Boiler & Aux Erection & Pre-commissioning 358 17-Nov-10 07-Jan-12 Unit 1 Boiler & Aux Erection & Pre-commissioning
H040 Unit 1 Steam Drum Lift 0 21-Feb-11 Unit 1 Steam Drum Lift
UHA200 Unit 2 Boiler Foundation work 180 01-Jan-10 A 23-Oct-10 Change Unit 2 Boiler Foundation work
UHA230 Unit 2 Boiler Erection of Steelwork 235 06-Jul-10 05-Apr-11 Change Unit 2 Boiler Erection of Steelwork
H220 Unit 2 Boiler & Aux Erection & Pre-commissioning 413 20-May-11 12-Sep-12 Unit 2 Boiler & Aux Erection & Pre-commissioning
H210 Unit 2 Steam Drum Lift 0 22-Aug-11 Unit 2 Steam Drum Lift
Precom & Commission 284 09-Jan-12 08-Feb-13 08-Feb-13, Precom & Commission
H100 Unit 1 Boiler & Aux Testing and Commissioning 162 09-Jan-12 14-Jul-12 Unit 1 Boiler & Aux Testing and Commissioning
H260 Unit 2 Boiler & Aux Testing and Commissioning 109 04-Oct-12 08-Feb-13 Unit 2 Boiler & Aux Testing and Commissioning
Detailed Engineering
E 399 17-Aug-09 A 10-Mar-11 10-Mar-11, Detailed Engineering
UMA020 Steam Turbine Building Design 155 01-Sep-09 A 07-Apr-10 Steam Turbine Building Design
UMA030 Steam Turbine Piling Dwgs IFC 0 01-May-10 A Change Steam Turbine Piling Dwgs IFC
UMA035 Steam Turbine Fdn Dwgs IFC 0 15-May-10 Change Steam Turbine Fdn Dwgs IFC
SA010 Air Con & Vent Sys Design, 300 27-Feb-10 11-Feb-11 Air Con & Vent Sys Design,
MK030 Turbine-Gen Design, 572 17-Aug-09 A 10-Mar-11 Turbine-Gen Design,
MA010 Turbine & Aux Design, 491 17-Aug-09 A 10-Mar-11 Turbine & Aux Design,
Construction
Construct 682 07-Apr-10 24-Nov-12 24-Nov-12, Construction
UMA040 Steam Turbine Piling and Foundation 208 07-Apr-10* 04-Dec-10 Steam Turbine Piling and Foundation
UMA060 Steam Turbine Steelworks 183 24-May-10 22-Dec-10 Steam Turbine Steelworks
UMA070 Steam Turbine Building Walls and Finishes 156 25-Aug-10 22-Feb-11 Steam Turbine Building Walls and Finishes
UMA080 Steam Turbine Building Roofings 155 11-Oct-10 08-Apr-11 Steam Turbine Building Roofings
SA040 Air Con & Vent Sys Installation & Pre-comm 365 05-Apr-11 02-Jun-12 Air Con & Vent Sys Installation & Pre-comm
MK060 Unit 1 T/G Bldg Base Mat & T/G Pedestal 313 16-Jun-10 15-Jun-11 Unit 1 T/G Bldg Base Mat & T/G Pedestal
MK080 Unit 1 Assemble & Align Turbine Generator 313 16-Jun-11 14-Jun-12 Unit 1 Assemble & Align Turbine Generator
MA040 Unit 1 Turbine &Aux Erection & Pre-commissioning 313 02-Apr-11 31-Mar-12 Unit 1 Turbine &Aux Erection & Pre-commissioning
MK210 Unit 2 T/G Bldg Base Mat & T/G Pedestal 313 27-Nov-10 26-Nov-11 Unit 2 T/G Bldg Base Mat & T/G Pedestal
MK220 Unit 2 Assemble & Align Turbine Generator 312 28-Nov-11 24-Nov-12 Unit 2 Assemble & Align Turbine Generator
MA100 Unit 2 Turbine& Aux Erection & Pre-commissioning 313 13-Sep-11 11-Sep-12 Unit 2 Turbine& Aux Erection & Pre-commissioning
Precom & Commission 293 04-Jan-12 16-Feb-13 16-Feb-13, Precom & Commission
SA060 Air Con & Vent Sys Testing and Commissioning 262 04-Jan-12 03-Nov-12 Air Con & Vent Sys Testing and Commissioning
MK120 Unit 1 Turbine Testing and Commissioning 72 28-Apr-12 20-Jul-12 Unit 1 Turbine Testing and Commissioning
MK140 Unit 1 T/G on Turning Gear 0 20-Jul-12 Unit 1 T/G on Turning Gear
MK260 Unit 2 Turbine Testing and Commissioning 72 26-Nov-12 16-Feb-13 Unit 2 Turbine Testing and Commissioning
MK280 Unit 2 T/G on Turning Gear 0 16-Feb-13 Unit 2 T/G on Turning Gear
Boiler Auxi
Auxiliaries 771 28-Dec-09 A 26-Oct-12 26-Oct-12, Boiler Auxiliaries
Procurement
Procurem 0 22-Jan-10 A 22-Jan-10 A 22-Jan-10 A, Procurement
EBC010 Award of Boiler Auxiliaries 0 22-Jan-10 A Award of Boiler Auxiliaries
Detailed Engineering
E 192 28-Dec-09 A 30-Sep-10 30-Sep-10, Detailed Engineering
EBC015 Coal Mill Sys Design, 238 28-Dec-09 A 30-Sep-10 change Coal Mill Sys Design,
Construction
Construct 386 03-Dec-10 28-May-12 28-May-12, Construction
EBC040 Unit 1 Coal Mill Sys Erection & Pre-commissioning 339 03-Dec-10 02-Jan-12 Unit 1 Coal Mill Sys Erection & Pre-commissioning
EBC250 Unit 2 Coal Mill Sys Erection & Pre-commissioning 339 29-Apr-11 28-May-12 Unit 2 Coal Mill Sys Erection & Pre-commissioning
Precom & Commission 214 03-Jan-12 26-Oct-12 26-Oct-12, Precom & Commission
EBC160 Unit 1 - Coal Mill Sys Testing and Commissioning 130 03-Jan-12 01-Jun-12 Unit 1 - Coal Mill Sys Testing and Commissioning
EBC260 Unit 2 - Coal Mill Sys Testing and Commissioning 130 29-May-12 26-Oct-12 Unit 2 - Coal Mill Sys Testing and Commissioning
Turbine/Generator BOP
Turbine/Ge 762 01-Oct-09 A 15-Oct-12 15-Oct-12, Turbine/Generator BOP
Procurement
Procurem 252 03-Nov-09 A 30-Oct-10 30-Oct-10, Procurement
LBA030 IFB Spec/ER/Scope of Work - Critical Piping & supports 0 03-Dec-09 A IFB Spec/ER/Scope of Work - Critical Piping & supports
LBG030 IFB Spec/ER/Scope of Work - Non-Critical Piping & Sup... 0 30-Oct-10 IFB Spec/ER/Scope of Work - Non-Critical Piping & Supports
LALC025 IFB Spec/ER/Scope of Work - Condensate Pumps 0 03-Nov-09 A IFB Spec/ER/Scope of Work - Condensate Pumps
LALC030 IFB Spec/ER/Scope of Work - Boiler Feed Pumps 0 03-Nov-09 A IFB Spec/ER/Scope of Work - Boiler Feed Pumps
LALB010 Award of Turbune/Gererator Auxiliaries 0 29-Jan-10 A Award of Turbune/Gererator Auxiliaries
Detailed Engineering
E 315 01-Oct-09 A 22-Jan-11 22-Jan-11, Detailed Engineering
LBA020 Main Piping Sys Design 343 01-Oct-09 A 03-Dec-10 Main Piping Sys Design
LBG010 Aux Piping Sys Design, 315 31-Dec-09 A 01-Jan-11 Aux Piping Sys Design,
BAA010 Duct IPB Design, 360 30-Nov-09 A 22-Jan-11 Duct IPB Design,
LALC020 Feedwater & Cond Sys Design 364 12-Oct-09 A 07-Dec-10 Feedwater & Cond Sys Design
Construction
Construct 420 07-Dec-10 17-Jul-12 17-Jul-12, Construction
LBA040 Unit 1 Main PipingSys Erection&Pre-commissioning 234 08-Mar-11 05-Dec-11 Unit 1 Main PipingSys Erection&Pre-commissioning
LBG040 Unit 1 Aux Piping Sys Erection&Pre-commissioning 236 18-Apr-11 17-Jan-12 Unit 1 Aux Piping Sys Erection&Pre-commissioning
BAA040 Unit 1 Duct IPB Installation & Pre-commissioning 236 12-Feb-11 14-Nov-11 Unit 1 Duct IPB Installation & Pre-commissioning
LALC040 Unit 1 Feedwater&CondSys Installation & Pre-comm 236 07-Dec-10 07-Sep-11 Unit 1 Feedwater&CondSys Installation & Pre-comm
LBA080 Unit2 Main Piping Sys Erection&Pre-commissioning 236 26-Jul-11 25-Apr-12 Unit2 Main Piping Sys Erection&Pre-commissioning
LBG080 Unit 2 Aux Piping Sys Erection&Pre-commissioning 236 17-Oct-11 17-Jul-12 Unit 2 Aux Piping Sys Erection&Pre-commissioning
BAA080 Unit 2 Duct IPB Installation & Pre-commissioning 236 14-Jul-11 13-Apr-12 Unit 2 Duct IPB Installation & Pre-commissioning
LALC080 Unit 2 Feedwater&CondSys Installation & Pre-comm 236 19-May-11 17-Feb-12 Unit 2 Feedwater&CondSys Installation & Pre-comm
Precom & Commission 288 08-Sep-11 15-Oct-12 15-Oct-12, Precom & Commission
LBA060 Unit 1 Main Piping Sys Testing and Commissioning 65 06-Dec-11 18-Feb-12 Unit 1 Main Piping Sys Testing and Commissioning
LBG060 Unit 1 Aux Piping Sys Testing and Commissioning 77 18-Jan-12 16-Apr-12 Unit 1 Aux Piping Sys Testing and Commissioning
BAA060 Unit 1 Duct IPB Testing and Commissioning 78 15-Nov-11 13-Feb-12 Unit 1 Duct IPB Testing and Commissioning
Coal Handling
Handl Plant 660 03-Aug-09 A 27-Feb-12 27-Feb-12, Coal Handling Plant
Procurement
Procurem 68 03-Aug-09 A 17-Oct-09 A 17-Oct-09 A, Procurement
EA030 Tender Period 27 03-Aug-09 A 13-Aug-09 A Tender Period
EA050 Evaluation Period 55 27-Aug-09 A 17-Oct-09 A Evaluation Period
EA070 Award of Coal Handling System Contract 0 17-Oct-09 A Award of Coal Handling System Contract
Detailed Engineering
E 218 09-Nov-09 A 17-Sep-10 17-Sep-10, Detailed Engineering
UEA010 Coal Handling Jetty Topside Design, 270 09-Nov-09 A 17-Sep-10 Coal Handling Jetty Topside Design,
UEA030 Coal Handling Jetty Piling Dwgs IFC 80 01-Mar-10 A 31-May-10 Change Coal Handling Jetty Piling Dwgs IFC
UEA035 Coal Handling Jetty Topside Fdn Dwgs IFC 0 15-Jun-10 Change Coal Handling Jetty Topside Fdn Dwgs IFC
EAC010 Conveyor Sys Design, 265 09-Nov-09 A 13-Sep-10 Conveyor Sys Design,
EAD010 Stacker/Reclaimer Design 240 09-Nov-09 A 16-Aug-10 Stacker/Reclaimer Design
EAE030 Storage Area Piling Dwgs IFC 0 05-Mar-10 A Storage Area Piling Dwgs IFC
EAE035 Storage Area Fdn Dwgs IFC 0 15-Mar-10 Storage Area Fdn Dwgs IFC
EAE020 Storage Area Design 124 01-Apr-10* 02-Aug-10 Storage Area Design
Construction
Construct 463 25-Mar-10 10-Jan-12 10-Jan-12, Construction
UEA040 Coal Handling Jetty Piling and Deck Structure 372 30-Mar-10 05-Apr-11 change Coal Handling Jetty Piling and Deck Structure
UEA060 Coal Handling Jetty Topside Erection 116 29-Aug-11 10-Jan-12 Coal Handling Jetty Topside Erection
EAC040 Conveyor Sys Erection & Pre-commissioning 183 29-Apr-11 28-Nov-11 Conveyor Sys Erection & Pre-commissioning
EAD040 Stacker/Reclaimer Erection & Pre-commissioning 164 09-May-11 15-Nov-11 Stacker/Reclaimer Erection & Pre-commissioning
EAE040 Storage Area Piling 124 25-Mar-10 16-Aug-10 Change Storage Area Piling
EAE060 Storage Area Construction 569 01-May-10 20-Nov-11 Storage Area Construction
EAC060 Conveyor Sys Testing and Commissioning 78 29-Nov-11 27-Feb-12 Conveyor Sys Testing and Commissioning
EAD060 Stacker/Reclaimer Testing and Commissioning 78 16-Nov-11 14-Feb-12 Stacker/Reclaimer Testing and Commissioning
WTP and W
WWTP 715 08-Dec-09 A 13-Sep-12 13-Sep-12, WTP and WWTP
Procurement
Procurem 20 08-Dec-09 A 06-Jan-10 A 06-Jan-10 A, Procurement
WWTP020 Evaluation Period 26 08-Dec-09 A 06-Jan-10 A Evaluation Period
WWTP040 Award of Water & WasteTreatment System Contract 0 06-Jan-10 A Award of Water & WasteTreatment System Contract
Detailed Engineering
E 354 06-Jan-10 A 24-May-11 24-May-11, Detailed Engineering
GA010 Raw Water Sys Design, 300 06-Jan-10 A 21-Dec-10 Raw Water Sys Design,
GC010 Demin Water Sys Design, 280 06-Jan-10 A 27-Nov-10 Demin Water Sys Design,
GK010 Potable Water Sys Design, 270 14-Jul-10 24-May-11 Potable Water Sys Design,
RU010 Waste Water Sys Design, 320 06-Jan-10 A 13-Jan-11 Waste Water Sys Design,
Construction
Construct 596 20-Feb-10 A 12-Jun-12 12-Jun-12, Construction
GA040 Raw Water Sys Erection & Pre-commissioning 248 20-Jul-11 03-May-12 Raw Water Sys Erection & Pre-commissioning
GC140 Demin Water Sys Erection & Pre-commissioning 166 18-May-11 26-Nov-11 Demin Water Sys Erection & Pre-commissioning
GK040 Potable Water Sys Erection & Pre-commissioning 260 15-Aug-11 12-Jun-12 Potable Water Sys Erection & Pre-commissioning
RU040 Waste Water Sys Erection & Pre-commissioning 260 15-Aug-11 12-Jun-12 Waste Water Sys Erection & Pre-commissioning
CIVC010 Water Treatment Plant - Civil Work - PVC 326 20-Feb-10 A 11-Jan-11 Water Treatment Plant - Civil Work - PVC
CIVC030 Waste Water Treatment Plant - Civil Work - PVC Scope 334 01-Mar-10 28-Jan-11 Waste Water Treatment Plant - Civil Work - PVC Scope
CIVC050 Tank Wall - Civil Work - PVC 263 01-Dec-10 20-Aug-11 Tank Wall - Civil Work - PVC
Precom & Commission 230 28-Oct-11 13-Sep-12 13-Sep-12, Precom & Commission
GA060 Raw Water Sys Testing and Commissioning 48 04-May-12 28-Jun-12 Raw Water Sys Testing and Commissioning
GC160 Demin Water Sys Testing and Commissioning 30 28-Oct-11 01-Dec-11 Demin Water Sys Testing and Commissioning
GK060 Potable Water Sys Testing and Commissioning 78 13-Jun-12 11-Sep-12 Potable Water Sys Testing and Commissioning
RU060 Waste Water Sys Testing and Commissioning 80 13-Jun-12 13-Sep-12 Waste Water Sys Testing and Commissioning
Procurement
Procurem 54 11-Dec-09 A 27-Feb-10 27-Feb-10, Procurement
BOP020 Tender Period 10 11-Dec-09 A 21-Dec-09 A Tender Period
BOP040 Evaluation Period 35 23-Dec-09 A 27-Feb-10 Evaluation Period
BOP010 REQUEST FOR BID REVISION 0 29-Jan-10 A REQUEST FOR BID REVISION
BOP060 Award of BOP Contract 0 27-Feb-10 Award of BOP Contract
Cooling Wa
Water System 515 15-Dec-09 A 14-Dec-11 14-Dec-11, Cooling Water System
Procurement
Procurem 0 15-Dec-09 A 15-Dec-09 A 15-Dec-09 A, Procurement
P010 Award Contract - Cooling Water Sys 0 15-Dec-09 A Award Contract - Cooling Water Sys
Detailed Engineering
E 239 15-Dec-09 A 20-Nov-10 20-Nov-10, Detailed Engineering
P020 Cooling Water Sys Design, 292 15-Dec-09 A 20-Nov-10 Cooling Water Sys Design,
Construction
Construct 390 15-Apr-10 20-Oct-11 20-Oct-11, Construction
CIVC020 Cooling Water System - Civil Work - PVC 329 15-Apr-10 09-Mar-11 Change Cooling Water System - Civil Work - PVC
P040 Cooling Water Sys Installation&Pre-commissioning 280 29-Nov-10* 20-Oct-11 Cooling Water Sys Installation&Pre-commissioning
P060 Cooling Water Sys Testing and Commissioning 48 20-Oct-11 14-Dec-11 Cooling Water Sys Testing and Commissioning
Heavy Fuel Oil Handling Plant 627 25-Feb-10 30-Jul-12 30-Jul-12, Heavy Fuel Oil Handling Plant
Detailed Engineering
E 197 19-Mar-10 28-Dec-10 28-Dec-10, Detailed Engineering
EN010 Heavy/Fuel Oil Sys Design, 244 19-Mar-10 28-Dec-10 Heavy/Fuel Oil Sys Design,
EN020 Heavy/Fuel Oil Sys Manufacture& Shipment 155 20-Sep-10 18-Mar-11 Heavy/Fuel Oil Sys Manufacture& Shipment
Construction
Construct 602 25-Feb-10 25-Jun-12 25-Jun-12, Construction
CIVB040 Havy Fuel Oil Storage Area (Bach Dang) 505 25-Feb-10 06-Oct-11 Havy Fuel Oil Storage Area (Bach Dang)
EN040 Unit 1 Heavy/Fuel Oil Sys Installation & Pre-comm 241 19-Mar-11 24-Dec-11 Unit 1 Heavy/Fuel Oil Sys Installation & Pre-comm
EN050 Unit 2 Heavy/Fuel Oil Sys Installation & Pre-comm 242 17-Sep-11 25-Jun-12 Unit 2 Heavy/Fuel Oil Sys Installation & Pre-comm
Precom & Commission 156 26-Dec-11 30-Jul-12 30-Jul-12, Precom & Commission
EN060 Unit 1 Heavy/Fuel Oil Sys Testing and Commissioning 30 26-Dec-11 28-Jan-12 Unit 1 Heavy/Fuel Oil Sys Testing and Commissioning
EN070 Unit 2 Heavy/Fuel Oil Sys Testing and Commissioning 30 26-Jun-12 30-Jul-12 Unit 2 Heavy/Fuel Oil Sys Testing and Commissioning
Inter-Plant Piping and Thermal Insulation 651 19-Mar-10 24-Sep-12 24-Sep-12, Inter-Plant Piping and Thermal Insulation
PIP020 Inter-Plant Piping Manufacture&Shipment 150 01-Oct-10 24-Mar-11 Inter-Plant Piping Manufacture&Shipment
Construction
Construct 304 25-Mar-11 23-May-12 23-May-12, Construction
PIP040 Inter-Plant Piping Installation & Pre-comm 365 25-Mar-11 23-May-12 Inter-Plant Piping Installation & Pre-comm
Precom & Commission 217 25-Nov-11 24-Sep-12 24-Sep-12, Precom & Commission
PIP060 Inter-Plant Piping Testing and Commissioning 261 25-Nov-11 24-Sep-12 Inter-Plant Piping Testing and Commissioning
Hydrogen S
System 710 19-Mar-10 15-Dec-12 15-Dec-12, Hydrogen System
Detailed Engineering
E 198 19-Mar-10 29-Dec-10 29-Dec-10, Detailed Engineering
R010 Gas Storage Sys Design, 245 19-Mar-10 29-Dec-10 Gas Storage Sys Design,
MKG010 Hydrogen Gen Plant Design, 235 19-Mar-10 17-Dec-10 Hydrogen Gen Plant Design,
R020 Gas Storage Sys Manufacture& Shipment 135 11-Oct-10 16-Mar-11 Gas Storage Sys Manufacture& Shipment
MKG020 Hydrogen Gen Plant Manufacture& Shipment 135 28-Sep-10 03-Mar-11 Hydrogen Gen Plant Manufacture& Shipment
Construction
Construct 313 04-Mar-11 15-May-12 15-May-12, Construction
R040 Gas Storage Sys Installation & Pre-comm 365 17-Mar-11 15-May-12 Gas Storage Sys Installation & Pre-comm
MKG040 Hydrogen Gen Plant Erection & Pre-comm 365 04-Mar-11 02-May-12 Hydrogen Gen Plant Erection & Pre-comm
Precom & Commission 162 03-May-12 15-Dec-12 15-Dec-12, Precom & Commission
R060 Gas Storage Sys Testing and Commissioning 184 16-May-12 15-Dec-12 Gas Storage Sys Testing and Commissioning
MKG060 Hydrogen Gen Plant Testing and Commissioning 184 03-May-12 03-Dec-12 Hydrogen Gen Plant Testing and Commissioning
Detailed Engineering
E 202 19-Mar-10 04-Jan-11 04-Jan-11, Detailed Engineering
SCA010 Compressed Air Sys Design, 250 19-Mar-10 04-Jan-11 Compressed Air Sys Design,
Construction
Construct 300 13-May-11 05-Jul-12 05-Jul-12, Construction
SCA040 Compressed Air Sys Installation & Pre-comm 360 13-May-11 05-Jul-12 Compressed Air Sys Installation & Pre-comm
Precom & Commission 120 28-May-10 16-Nov-10 16-Nov-10, Precom & Commission
SCA060 Compressed Air Sys Testing and Commissioning 148 28-May-10 16-Nov-10 Compressed Air Sys Testing and Commissioning
Electrostatic Precipitator
Electrostat 642 26-Jan-10 A 19-Jul-12 19-Jul-12, Electrostatic Precipitator
Procurement
Procurem 0 26-Feb-10 26-Feb-10 26-Feb-10, Procurement
QHO010 Award Contract - Electrostatic Precipitator 0 26-Feb-10* Award Contract - Electrostatic Precipitator
Detailed Engineering
E 193 26-Jan-10 A 03-Jun-11 03-Jun-11, Detailed Engineering
BWE010 Electrostatic Prec Design 235 26-Jan-10 A 03-Jun-11 change Electrostatic Prec Design
BWE020 Electrostatic Prec Manufacture& Shipment 320 26-Jun-10 04-Jul-11 change Electrostatic Prec Manufacture& Shipment
BWE030 U1 Electrostatic Precipitator Delivery 0 15-Mar-11* U1 Electrostatic Precipitator Delivery
BWE050 U2 Electrostatic Precipitator Delivery 0 15-Jul-11* U2 Electrostatic Precipitator Delivery
Construction
Construct 487 24-Feb-10 14-Jan-12 14-Jan-12, Construction
QHO040 U1 Electrostatic Precipitat Installation & Pre-comm 157 04-Jun-11 03-Dec-11 U1 Electrostatic Precipitat Installation & Pre-comm
QHO065 U2 Electrostatic Precipitat Installation & Pre-comm 157 16-Jul-11* 14-Jan-12 U2 Electrostatic Precipitat Installation & Pre-comm
QHO050 ESP Control building 0 24-Feb-10 Change ESP Control building
Precom & Commission 139 07-Jan-12 19-Jul-12 19-Jul-12, Precom & Commission
QHO060 U1 Electrostatic Precipitator Testing and Comm 30 07-Jan-12 10-Feb-12 U1 Electrostatic Precipitator Testing and Comm
QHO075 U2 Electrostatic Precipitator Testing and Comm 30 15-Jun-12 19-Jul-12 U2 Electrostatic Precipitator Testing and Comm
Procurement
Procurem 76 02-Dec-09 A 20-Mar-10 20-Mar-10, Procurement
HT010 REQUEST BID REVISION 1 02-Dec-09 A 29-Jan-10 A REQUEST BID REVISION
HT020 Tender Period 9 03-Dec-09 A 12-Dec-09 A Tender Period
HT040 Evaluation Period 39 12-Dec-09 A 19-Mar-10 Evaluation Period
HT060 Award of SWFGD Contract 0 20-Mar-10 Award of SWFGD Contract
Detailed Engineering
E 186 20-Mar-10 13-Dec-10 13-Dec-10, Detailed Engineering
HT070 SWFGD Design, 230 20-Mar-10 13-Dec-10 change SWFGD Design,
Construction
Construct 569 20-Mar-10 01-Jun-12 01-Jun-12, Construction
HT100 Unit 1 - SWFGD Erection & Pre-comm 330 25-Sep-10 14-Oct-11 Unit 1 - SWFGD Erection & Pre-comm
HT200 Unit 2 - SWFGD Erection & Pre-comm 330 14-May-11 01-Jun-12 Unit 2 - SWFGD Erection & Pre-comm
CIVC60 SWFDG civil work 251 20-Mar-10 25-Nov-10 SWFDG civil work
HT300 SWFGD Control Building 0 09-Sep-11 SWFGD Control Building
Precom & Commission 362 10-Nov-11 29-Mar-13 29-Mar-13, Precom & Commission
HT120 Unit 1 - SWFGD Testing and Commissioning 236 10-Nov-11 10-Aug-12 Unit 1 - SWFGD Testing and Commissioning
HT220 Unit 2 - SWFGD Testing and Commissioning 236 28-Jun-12 29-Mar-13 Unit 2 - SWFGD Testing and Commissioning
Fire Protec
Protection System 333 01-Mar-10 16-Jun-11 16-Jun-11, Fire Protection System
Procurement
Procurem 43 01-Mar-10 29-Apr-10 29-Apr-10, Procurement
SGA030 REQUEST BID REVISION 0 01-Mar-10 REQUEST BID REVISION
SGA040 RECEIVE NEW BIDS 0 31-Mar-10 RECEIVE NEW BIDS
SGA060 Evaluation Period 10 15-Apr-10 26-Apr-10 Evaluation Period
SGA080 Award of Fire Detection & Prot Contract 0 29-Apr-10 Award of Fire Detection & Prot Contract
Detailed Engineering
E 97 29-Apr-10 15-Sep-10 15-Sep-10, Detailed Engineering
SGA090 Fire Detection & Prot Design 120 29-Apr-10 15-Sep-10 change Fire Detection & Prot Design
SGA100 Fire Detection & Prot Manuf & Shipment 125 08-Jun-10 30-Oct-10 change Fire Detection & Prot Manuf & Shipment
SGA110 Delivery of Fire Protection System 0 01-Dec-10 Delivery of Fire Protection System
Construction
Construct 131 01-Nov-10 05-May-11 05-May-11, Construction
SGA120 Fire Detection & Prot Erection & Pre-comm 160 01-Nov-10 05-May-11 Fire Detection & Prot Erection & Pre-comm
SGA140 Fire Detection & Prot Testing and Commissioning 36 06-May-11 16-Jun-11 Fire Detection & Prot Testing and Commissioning
Ash Handling
Handli Plant 667 02-Dec-09 A 03-Jul-12 03-Jul-12, Ash Handling Plant
Procurement
Procurem 48 02-Dec-09 A 10-Feb-10 A 10-Feb-10 A, Procurement
HDA010 REQUEST BID REVISION - ASH HANDLING 0 02-Dec-09 A REQUEST BID REVISION - ASH HANDLING
HDA020 RECEIVE NEW BIDS - ASH HANDLING 0 12-Jan-10 A RECEIVE NEW BIDS - ASH HANDLING
HDA060 Evaluation Period 15 12-Jan-10 A 10-Feb-10 A Evaluation Period
HDA080 Award of Ash Handling & Disposal Sys Contract 0 10-Feb-10 A Award of Ash Handling & Disposal Sys Contract
Detailed Engineering
E 220 10-Feb-10 21-Dec-10 21-Dec-10, Detailed Engineering
HDA090 Ash Handling & Disposal Design, 270 10-Feb-10 21-Dec-10 change Ash Handling & Disposal Design,
Construction
Construct 220 02-May-11 02-Mar-12 02-Mar-12, Construction
Miscellaneous Works
Miscellaneo 59 29-Jan-10 A 30-Apr-10 30-Apr-10, Miscellaneous Works
Procurement
Procurem 59 29-Jan-10 A 30-Apr-10 30-Apr-10, Procurement
OTH010 REQUEST BID REVISION - MISC WORKS 6 29-Jan-10 A 05-Feb-10 A REQUEST BID REVISION - MISC WORKS
OTH020 RECEIVE NEW BIDS - MISC. WORKS 14 08-Feb-10 A 25-Feb-10 RECEIVE NEW BIDS - MISC. WORKS
OTH030 EVALUATION - MISC WORKS 21 26-Feb-10 26-Mar-10 EVALUATION - MISC WORKS
OTH040 CONTRACT NEGOTIATION - MISC WORKS 16 27-Mar-10 14-Apr-10 CONTRACT NEGOTIATION - MISC WORKS
OTH050 Award of MISC WORKS Contract 0 30-Apr-10* Award of MISC WORKS Contract
Vehicle and Mobile Equipment 130 30-Apr-10 03-Nov-10 03-Nov-10, Vehicle and Mobile Equipment
Fire Engine and Accessories 453 30-Apr-10 01-Feb-12 01-Feb-12, Fire Engine and Accessories
Construction
Construct 323 03-Nov-10 01-Feb-12 01-Feb-12, Construction
SG040 Fire Fighting Equipment - Installation 391 03-Nov-10 01-Feb-12 Fire Fighting Equipment - Installation
Worshop and
a Laboratory Equipment 453 30-Apr-10 01-Feb-12 01-Feb-12, Worshop and Laboratory Equipment
Construction
Construct 323 03-Nov-10 01-Feb-12 01-Feb-12, Construction
STA040 Workshop Equipment - Installation 391 03-Nov-10 01-Feb-12 Workshop Equipment - Installation
STG040 Laboratory Equipment - Installation 391 03-Nov-10 01-Feb-12 Laboratory Equipment - Installation
Procurement
Procurem 18 07-Oct-09 A 25-Dec-09 A 25-Dec-09 A, Procurement
SW020 RECEIVE NEW BID - SWYD AND TRANSFORMERS 0 07-Oct-09 A RECEIVE NEW BID - SWYD AND TRANSFORMERS
SW040 Evaluation Period 10 08-Oct-09 A 29-Oct-09 A Evaluation Period
SW060 Award of Switchyard & Transformers Contract 0 25-Dec-09 A Award of Switchyard & Transformers Contract
Detailed Engineering
E 115 25-Dec-09 A 31-May-10 31-May-10, Detailed Engineering
Construction
Construct 272 15-Apr-10 09-May-11 09-May-11, Construction
UAA040 SWYD Foundation and Concreting works 390 15-Apr-10* 09-May-11 Change SWYD Foundation and Concreting works
BAT920 Switchyard Erection & Pre-comm 104 10-Dec-10 23-Mar-11 Switchyard Erection & Pre-comm
Precom & Commission 130 23-Mar-11 20-Sep-11 20-Sep-11, Precom & Commission
BAT960 Switchyard Testing and Comm 156 23-Mar-11 20-Sep-11 Switchyard Testing and Comm
Main Transformers
Trans 696 25-Dec-09 A 16-Jul-12 16-Jul-12, Main Transformers
Detailed Engineering
E 275 25-Dec-09 A 15-Mar-11 15-Mar-11, Detailed Engineering
BAT000 Main XFMRs Design, 135 25-Dec-09 A 31-May-10 Main XFMRs Design,
BAT020 Main XFMRs Manuf & Shipment 340 06-Feb-10 A 15-Mar-11 Main XFMRs Manuf & Shipment
Construction
Construct 497 11-Feb-10 A 16-Jan-12 16-Jan-12, Construction
BAT120 Unit 1 Main XFMRs Erection & Pre-comm 124 15-Mar-11 05-Aug-11 Unit 1 Main XFMRs Erection & Pre-comm
BAT220 Unit 2 Unit and Main T/Fs Erection & Pre-comm 136 11-Aug-11 16-Jan-12 Unit 2 Unit and Main T/Fs Erection & Pre-comm
CIVB060 Main transformer, aux. transformer foundations 455 11-Feb-10 A 16-May-11 Main transformer, aux. transformer foundations
Precom & Commission 246 06-Aug-11 16-Jul-12 16-Jul-12, Precom & Commission
BAT160 Unit 1 Main XFMRs Testing and Comm 156 06-Aug-11 03-Feb-12 Unit 1 Main XFMRs Testing and Comm
BAT260 Unit 2 Unit and Main T/Fs Testing and Comm 156 17-Jan-12 16-Jul-12 Unit 2 Unit and Main T/Fs Testing and Comm
Electrical B
BOP & Communication & Security Syst... 78 25-Jan-10 A 16-Apr-10 16-Apr-10, Electrical BOP & Communication & Security System
Procurement
Procurem 78 25-Jan-10 A 16-Apr-10 16-Apr-10, Procurement
ELE010 REQUEST BID REVISION - eBOP 0 25-Jan-10 A REQUEST BID REVISION - eBOP
ELE020 RECEIVE NEW BIDS - eBOP 0 02-Feb-10 A RECEIVE NEW BIDS - eBOP
ELE030 Evaluation Period 24 02-Mar-10* 29-Mar-10 Evaluation Period
ELE050 Award of Electrical Balance of Plant 0 16-Apr-10* Award of Electrical Balance of Plant
Electrical B
Balance of Plant 693 16-Apr-10 19-Dec-12 19-Dec-12, Electrical Balance of Plant
Detailed Engineering
E 235 16-Apr-10 18-Mar-11 18-Mar-11, Detailed Engineering
AT010 T/F Aux Design, 230 16-Apr-10 08-Jan-11 T/F Aux Design,
MJ010 Diesel Generator Design, 250 16-Apr-10 01-Feb-11 Diesel Generator Design,
CAB015 Cabling Design, 230 16-Apr-10 08-Jan-11 Cabling Design,
BB015 MV Switchgears Design, 150 25-Sep-10 18-Mar-11 MV Switchgears Design,
BF015 LV Switchgears Design, 270 16-Apr-10 24-Feb-11 LV Switchgears Design,
BT-BR010 DC & UPS Equipment Design 250 16-Apr-10 01-Feb-11 DC & UPS Equipment Design
Construction
Construct 351 14-Jan-11 19-May-12 19-May-12, Construction
AT040 Unit 1 T/F Aux Erection & Pre-comm 313 14-Jan-11 22-Nov-11 Unit 1 T/F Aux Erection & Pre-comm
AT120 Unit 2 T/F Aux Erection & Pre-comm 313 05-Feb-11 04-Feb-12 Unit 2 T/F Aux Erection & Pre-comm
MJ040 Diesel Generator Erection & Pre-comm 234 08-Apr-11 05-Jan-12 Diesel Generator Erection & Pre-comm
CAB040 Cabling Installation & Testing 364 05-Feb-11 04-Apr-12 Cabling Installation & Testing
BB040 MV Switchgears Erection & Pre-comm 130 19-Mar-11 17-Aug-11 MV Switchgears Erection & Pre-comm
BF040 LV Switchgears Erection & Pre-comm 313 21-May-11 19-May-12 LV Switchgears Erection & Pre-comm
BT-BR040 DC & UPS Eqpt Installation & Pre-comm 234 18-Mar-11 15-Dec-11 DC & UPS Eqpt Installation & Pre-comm
Precom & Commission 350 18-Aug-11 19-Dec-12 19-Dec-12, Precom & Commission
AT080 Unit 1 T/F Aux Testing and Comm 156 22-Nov-11 25-Apr-12 Unit 1 T/F Aux Testing and Comm
AT160 Unit 2 T/F Aux Testing and Comm 156 06-Feb-12 04-Aug-12 Unit 2 T/F Aux Testing and Comm
MJ060 Diesel Generator Testing and Comm 77 06-Jan-12 04-Apr-12 Diesel Generator Testing and Comm
BB060 MV Switchgears Testing and Comm 183 18-Aug-11 17-Mar-12 MV Switchgears Testing and Comm
BF060 LV Switchgears Testing and Comm 183 21-May-12 19-Dec-12 LV Switchgears Testing and Comm
BT-BR060 DC & UPS Eqpt Testing and Comm 79 16-Dec-11 16-Mar-12 DC & UPS Eqpt Testing and Comm
Detailed Engineering
E 86 16-Apr-10 17-Aug-10 17-Aug-10, Detailed Engineering
CX020 SCADA Design, Manuf & Shipment 86 10-May-10 17-Aug-10 SCADA Design, Manuf & Shipment
CYA020 Tel, Internet & PABX Manuf & Shipment 50 16-Apr-10 12-Jun-10 Tel, Internet & PABX Manuf & Shipment
Construction
Construct 85 18-Aug-10 18-Dec-10 18-Dec-10, Construction
CX040 SCADA Installation & Pre-comm 106 18-Aug-10 18-Dec-10 SCADA Installation & Pre-comm
CY040 Telecom Installation & Pre-comm 106 18-Aug-10 18-Dec-10 Telecom Installation & Pre-comm
CYA040 Tel, Internet & PABX Installation & Pre-comm 106 18-Aug-10 18-Dec-10 Tel, Internet & PABX Installation & Pre-comm
Integrated C
Control and Monitoring System 850 30-Jul-09 A 15-Nov-12 15-Nov-12, Integrated Control and Monitoring System
Procurement
Procurem 0 30-Jul-09 A 30-Jul-09 A 30-Jul-09 A, Procurement
CJ020 Award of ICMS Contract 0 30-Jul-09 A Award of ICMS Contract
Detailed Engineering
E 393 20-Aug-09 A 05-Mar-11 05-Mar-11, Detailed Engineering
CJ030 DCS Design, 485 20-Aug-09 A 05-Mar-11 DCS Design,
Precom & Commission 291 06-Oct-11 15-Nov-12 15-Nov-12, Precom & Commission
CJ180 Unit 1 DCS Testing and Comm 30 06-Oct-11 09-Nov-11 Unit 1 DCS Testing and Comm
CJ190 Unit 1 ICMS Testing and Comm 180 01-Nov-11 28-May-12 Unit 1 ICMS Testing and Comm
CJ280 Unit 2 DCS Testing and Comm 30 17-Feb-12 22-Mar-12 Unit 2 DCS Testing and Comm
CJ290 Unit 2 ICMS Testing and Comm 180 20-Apr-12 15-Nov-12 Unit 2 ICMS Testing and Comm
Procurement
Procurem 71 13-Nov-09 A 26-Feb-10 26-Feb-10, Procurement
UHN010 REQUEST BID REVISION - STACK 0 13-Nov-09 A REQUEST BID REVISION - STACK
UHN020 RECEIVE NEW BIDS - STACK 0 27-Nov-09 A RECEIVE NEW BIDS - STACK
UHN030 Evaluation Period 26 27-Nov-09 A 16-Feb-10 A Evaluation Period
UHN050 Award of Stack Contract 0 26-Feb-10* Award of Stack Contract
Detailed Engineering
E 369 26-Feb-10 04-Aug-11 04-Aug-11, Detailed Engineering
UHN080 Stack Design & Constuction 450 26-Feb-10 04-Aug-11 Stack Design & Constuction
Other Civil Works 921 30-Jul-09 A 26-Feb-13 26-Feb-13, Other Civil Works
Procurement
Procurem 0 30-Jul-09 A 30-Jul-09 A 30-Jul-09 A, Procurement
SITE020 Award of Civil Detail Design 0 30-Jul-09 A Award of Civil Detail Design
Detailed Engineering
E 454 03-Aug-09 A 14-May-11 14-May-11, Detailed Engineering
UZJ50 Fence and Gate 120 02-Oct-09 A 10-Feb-10 A Fence and Gate
UZJ70 Admin Building Design 0 30-Jun-10 Change Admin Building Design
UCA020 Main Control & Anc Buildings Design 234 03-Aug-09 A 03-Jul-10 Main Control & Anc Buildings Design
CIV050 Road & Drainage Dwgs IFC 0 12-Oct-10 Road & Drainage Dwgs IFC
UZA070 Permanent Road and Drainage 200 02-Nov-09 A 01-Apr-10 Change Permanent Road and Drainage
UZK070 Landscaping 225 02-Oct-10 14-May-11 Landscaping
Construction
Construct 921 03-Aug-09 A 26-Feb-13 26-Feb-13, Construction
SITE030 Clearance and Levelling 182 03-Aug-09 A 14-May-10 Clearance and Levelling
SITE050 Temporary Facilities 261 30-Nov-09 A 29-Oct-10 Temporary Facilities
UZJ060 Fence and Gate 236 26-Feb-10 A 26-Mar-11 Change Fence and Gate
UZA080 Permanent Road and Drainage 707 24-Nov-10 26-Feb-13 Permanent Road and Drainage
UCA040 Main Control & Anc Buildings Piling & Foundation 123 20-May-10 09-Oct-10 Main Control & Anc Buildings Piling & Foundation
UCA060 Main Control & Anc Buildings Construction 335 15-Sep-10 15-Aug-11 Main Control & Anc Buildings Construction
CIV170 Adminnistration & service area 579 01-Jun-10 31-Dec-11 Change Adminnistration & service area
CIV120 Infrastructure 782 12-Aug-10* 08-Feb-13 Infrastructure
CIV180 Landscaping 262 10-Apr-12 08-Feb-13 Change Landscaping