Professional Documents
Culture Documents
Framework 2
Framework 2
(AY2019/2020 Semester 1)
QRA Study on
Group 4
1|Page
Executive summary
In this project, a Quantitative Risk Analysis (QRA) study was performed on the Reinjection
(RI) Gas Compression System, which is one of the process modules on a Floating Production
Storage and Offloading (FPSO). The objective is to determine the fatality risk due to the RI
Gas Compression System. The inherent process hazard of this system is the compression of
highly flammable natural gas to a high discharge pressure of 382 barg before reinjection into
the subsea well.
HAZOP Study was first conducted to identify all credible accidents scenarios by using a
systematic approach. Loss of containment was determined to be the most severe consequence
from the HAZOP study.
Fault Tree Analysis (FTA) was then carried out which defines the loss of containment as the
top event in the Fault Tree. Fault tree was constructed based on the causes, consequences and
safeguards identified in the HAZOP study.
2|Page
Contents
Executive summary 2
1. Overview 5
1.1 Selected Process – RI Gas Compression System 6
1.2 Process Fluid 6
1.3 Equipment Description 6
1.4 Safety Systems 7
1.4.1 Emergency Shutdown System (ESD) 7
1.4.2 Blowdown System 8
1.4.3 Fire and Gas System (FGS) 8
1.4.4 Fire Fighting System 9
2 Hazard and Operability Study (HAZOP) 11
2.1 Objective 11
2.2 Methodology 12
2.3 HAZOP Results and Discussions 14
3. Analysis conducted 16
3.1 Fault Tree Analysis (FTA) 16
3.1.1 Fault Tree 16
3.1.2 Fault Tree MCS 19
3.1.3 Quantitative Analysis on Fault Tree 19
3.1.4 Qualitative Analysis on Fault Tree 22
3.2 Event Tree Analysis 24
4. Bow Tie Diagram 28
5. Consequence Modelling 30
5.1 Harm footprints and IR Modifiers 30
5.2 Impact Criteria 31
5.2.1 Impacts from Jet Fires 31
5.2.2 Impacts from Flash Fires 32
5.2.3 Impacts from Vapour Cloud Explosions (VCE) 32
5.3 Modelling assumptions 32
5.4 Case A: Isolation success and Blowdown Failure 33
3|Page
5.4.1 Jet Fire Modelling 33
5.4.2 Vapour Cloud Explosion Modelling 37
5.4.3 Vapour Cloud Flashfire Modelling 38
5.5 Case B - Isolation and Blowdown Failure 41
5.5.1 Jet Fire Modelling 41
5.5.2 Vapour Cloud Explosion Modelling 45
5.5.3 Vapour Cloud Flashfire Modelling 46
6. Risk Determination 49
7. Discussion and Conclusion 51
7.1 Comparing with NEA Criteria 51
7.2 Conclusion 51
References 52
Appendix A 53
Appendix B 56
4|Page
1. Overview
A Floating Production Storage and Offloading (FPSO) receives production from subsea oil
wells and is provided with facilities to process the fluids in order to meet the product
specifications.
The produced oil is separated from associated gas and water, stabilized and stored in hull
storage tanks prior to be metered and offloaded to shuttle tankers.
Produced water is separated and treated in the produced water treatment unit in order to
comply with the water specification for injection in the reservoir.
Produced gas is collected from oil treatment section and compressed and dehydrated in order
to be used as fuel gas and for gas lift purposes. The excess produced gas is re-injected in the
subsea injection wells.
For this project, we will be focusing on the Reinjection (RI) Gas Compression system, which
compresses the produced gas to high pressure for reinjection into the subsea well.
Gas from High Pressure (HP) compressor discharge header is routed to RI compressor via RI
compressor suction scrubber. The RI compressor suction scrubber is used to knock down any
liquid which will be sent back to HP Compressor suction scrubber. The RI compressor
compresses the gas from 169 barg to 382 barg. The discharge gas from is then cooled via RI
compressor discharge cooler by cooling water before it is routed for reinjection into the well.
The RI compression train is 2x100% configuration. Each train consists of the following
equipment:
• 1x100% RI compressor
5|Page
1.2 Process Fluid
The process stream at the inlet to RI Compressor Suction Scrubber is of vapour phase and
contains 74% mole of methane. It has a design flowrate of 79300 kg/hr, with operating
pressure of 168 barg and operating temperature of 35 deg. C.
The P&IDs for the selected process unit are attached in Appendix A of the report. The main
equipment description for the RI Gas Compression System are described in Table 1.1 below.
In the event of hydrocarbon release, ESD is provided to isolate segments of the process, and
thereby limit the inflow of hydrocarbons to the leaking sections.
The ESD System is organized in hierarchical shutdown levels and will initiate the following
levels of shutdown in the event of process upset or manual initiation.
6|Page
Level 0 – Abandon Shutdown (ASD)
o All ESD valves are closed and all gas inventories vented to flare
Level 1 – Emergency Shutdown for Confirmed Fire (ESD-1) and Gas (ESD-2)
The emergency shutdown with depressurisation can be activated by confirmed gas and fire in
process area and some critical utilities, or manual activation by local panel. ESD will initiate
complete FPSO shutdown with depressurisation of process units.
The blowdown system routes hydrocarbon fluids to flare which serves as a preventive
measure for the uncontrolled release of hydrocarbon from an equipment or piping failure.
Flaring will be done during emergencies, startup and post startup commissioning and restart
after planned or unplanned shutdown.
7|Page
1.4.3 Fire and Gas System (FGS)
The function of the FGS shall be to provide a fast and automatic means of detecting,
alarming, indicating the presence of a fire and combustible gas hazard and upon confirmed
detection of fire or gas, initiate the ESD to automatically isolate and depressurise process and
utility equipment, initiate appropriate firefighting measures and also isolate ignition sources
in the hazardous area.
The detection of fire and dangerous accumulations of combustible gases shall be achieved by
various types of Fire & Gas detection equipment whose selection and location shall be based
on the following criteria and shall be segregated by fire areas or zones:
A confirmed fire and gas incident (involving an actual fire or gas detection) in sufficient
quantities and concentrations shall typically initiate ESD-1 and ESD-2 respectively. Fire &
Gas related process shutdown (ESD-1 & 2) actions shall be executed by ESD based on the
Process Cause & Effect matrix.
In the event of detection of confirmed FIRE or confirmed GAS leading to actuation of ESD-1
and ESD-2 respectively, shutdown of all process and utilities within that particular fire zone
and automatic emergency depressurisation will take place.
8|Page
The firewater supply from the duty and standby fire pumps are connected to the
header of firewater and foam ring main laid around the perimeter of main deck at
distance from process areas to maximize survivability from fire and explosion events.
The ring mains are designed to ensure operability in the event of damage to any one
part of the ring mains. The ring mains are size based on the maximum required
discharge from the fire pumps and adequate to meet the largest design firewater
demand.
2. Deluge system
Fixed deluge water system and foam deluge system are provided to protect specific
topsides equipment or to provide a general area coverage. The purpose of the water
deluge is to provide some cooling effects for equipment in fire events, and therefore
prevent or reduce the chance of escalation to another vessel or module. The purpose
of the foam deluge is to control the escalation for large hydrocarbon inventories and
to reduce radiation for personnel escape.
3. Foam system
Foam monitors are used to control or extinguish liquid pool fires in areas where a
fixed system cannot be fitted, such as open areas, or areas with no structure to support
a deluge system. Fixed foam systems are provided to protect the cargo tank storage
where hydrocarbons may accumulate, ignite and form a pool fire.
9|Page
10 | P a g e
2 Hazard and Operability Study (HAZOP)
2.1 Objective
The objective of Hazard and Operability Study (HAZOP) study is to identify all Hazards and
Operability issues that could have a significant impact on the design and operation of the
process system, if there is a process deviation away from the safe operating envelope. These
issues can be broadly classified into two categories which are Safety and Operability.
To identify/ analyse potential hazards and operability issues due to deviations from
normal process or operating conditions or intended design
To evaluate the adequacy of the existing safeguards with respect to safety and
operations
To identify additional safeguards required for the system under study to address the
causes and minimise the consequences of deviation.
11 | P a g e
2.2 Methodology
The steps involved in the HAZOP are illustrated in the below flowchart.
12 | P a g e
Guidewords combined with the process Parameters generates a list of Deviations that are
utilized for HAZOP analysis. These guidewords and parameters are listed in Table 2.1 below.
Applicable deviations were applied on each node to identify any safety or operability issues
associated with the process. Where a deviation leads to “no hazards identified” or “no
credible scenarios”, further analysis for that particular entry is not carried out.
13 | P a g e
2.3 HAZOP Results and Discussions
The HAZOP worksheet for RI Gas Compression system is attached in Appendix B of the
report. A total of 10 relevant process deviations were identified during the HAZOP. The
HAZOP study generated 17 recommendations/action items. The recommendations raised
include items for further review discussions and/or changes to the current design, which will
improve the safety or the operability of the facility.
From the HAZOP study, the most hazardous consequence has been identified to be loss of
containment. The causes for loss of containment and existing safeguards in place are
presented in Table 2.2 below.
1. No/Low Flow 1.6. (S) RI Compressor 1.6.7. (A) Potential 1.6.7.1. (K) Single check valve at discharge Cooler
Trips (All three overpressure of RI Compressor outlet.
compressors upstream suction due to reverse flow
(MP and HP) will also from the downstream discharge 1.6.7.2. (L) SDV3803A/B at discharge Cooler
trip as they are on header/ gas reinjection header outlet will close on Compressor trip.
common shaft)
Potential overpressure of 1.6.7.3. Single check valve provided at Suction
upstream HP Compressor Scrubber inlet
discharge piping.
1.7. (B) Strainer at 1.7.1. Loss of flow through 1.7.1.1. (N) PDI3832 with high alarm across
inlet of discharge Compressor leading to surge. strainer
Cooler plugged Anti-surge control will not
safeguard against this scenario.
1.8. (C) Discharge 1.8.1. Loss of flow through 1.8.1.1. (U) Strainer provided at inlet
Cooler plugged (This Compressor leading to surge.
is PCHE type with Anti-surge control will not
1.8.1.2. PDI3833 with high alarm across PCHE on
small diameter flow safeguard against this scenario.
gas side
path)
1.9. (D) SDV3803A at 1.9.2. Potential overpressure. 1.9.2.1. (P) PZAHH3814 at Compressor suction
discharge gets closed will trip the Compressor
or any downstream
blocked condition on 1.9.2.2. (Q) PZAHH3818 at compressor discharge
gas injection line. will trip the Compressor.
4. More/High 4.1. External Fire 4.1.1. Potential overpressure 4.1.1.1. (M) PSV3801 on suction Scrubber sized
Pressure around Suction for fire case.
Scrubber
14 | P a g e
4.3 (H) FCV3801 on 4.3.1. RI Suction pressure will
anti-surge open when increase, leading to increase in
not required (Fail open HP Compressor discharge
type) pressure. Potential surge in HP
Compressor. Potential increase
in upstream pressures. System
upset.
13. Others 13.2.(I) Seal failure 13.2.1. Potential Hydrocarbon 13.2.1.1. Provision for isolation and blow down of
leak to atmosphere Compressor. Single BDV3801 provided at the
discharge for the entire compressor loop including
the Scrubber.
Table 2.2 Causes for loss of containment and existing safeguards in place
15 | P a g e
3. Analysis conducted
Based on the HAZOP study, Loss of Containment was identified as the most severe of the
listed consequences. In this section, qualitative and quantitative analysis were conducted on
the Fault Tree with the top event: Loss of Containment. The Fault Tree was constructed from
the identified causes and safeguards in the HAZOP, with reference to the P&IDs in Appendix
A. The Fault Tree Analysis (FTA) methodology is summarized below
1. Construct Fault Tree with the top event: Loss of Containment, with the
causes/safeguards identified from HAZOP and P&ID.
2. Derive the Minimum Cut Sets (MCS) from the Fault Tree. The MCS is the smallest
number of cut set which represent the system failure mode. Failure of all the
components and its safeguard in the cut sets permits the occurrence of the top event.
3. Obtain the failure rates for the component and the probability of failure on demand for
the safeguard.
4. Calculate the failure probability for each of the MCS to determine the Safety Critical
Events (SCEs)
SCEs are determined by sorting the MCS failure probabilities and identifying the highest
failure frequencies that contributed to the occurrence of the top event. The reliability of the
system would improve significantly if additional safeguards were implemented on the MCS
of the SCEs. The top event: Loss of Containment outcome frequency is required for the
initiating event for Event Tree to be discussed in the next section of the report.
The loss of containment from scrubber is caused by the failure of the protection of PSV-3801
(M) AND the intermediate event of reverse flow from compressor trip and the events of
FCV-3802 (G) and FCV-3801 (H) fail open. The reverse flow from compressor trip is caused
16 | P a g e
by the compressor tripping (S) AND the protection failure of check valve (K) and SDV-3803
fails to close (L).
The loss of containment from compressor high pressure discharge is caused by the protection
failure of Pressure HH alarm PZAHH-3814 (P) and PZAHH-3818 (Q), and the failure of
PSV-3811 (R) AND the intermediate events of block outlet due to Strainer plugged,
discharge cooler plugged and event of block outlet due to SDV-3803A fails shut (D). The
intermediate event block outlet due to strainer plug is due to compressor discharge strainer
plugged (T) AND Pressure differential HH alarm PDI-3832 fails (N). The intermediate event
block outlet due to discharge cooler plugged is due to compressor discharge strainer fails (U)
AND Pressure differential HH alarm PDI-3832 fails (O).
17 | P a g e
Figure 3.1: Fault Tree
Loss of Containment
Protection fails
Scrubber Overpressure
Compressor discharge line
overpressure
Reverse Flow from compressor trip FCV-3802 FCV-3801 PZAHH- PZAHH- PSV-
(A) 3814 3818 3811 (R)
fails open fails open
fails (P) fails (Q) fails
(G) (H)
Protection fails
Check SDV-3803
valve fails fails to
Strainer Strainer
(K) close (L)
plugged fails (U)
(T)
18 | P a g e
3.1.2 Fault Tree MCS
The Fault Tree MCS were derived from the Fault Tree shown in Figure 3.1. The cut sets are
first defined as shown below:
Cut Set = (S (K L) + G + H) M + I + J + (T N + U O + D) (P Q R)
Highlighted Blue is the safeguard or the protection for the component in black.
The cut set are then expanded out and rearranged to form the MCS as shown below:
MCS = S K L M + G M + H M + I + J + T N P Q R + U O P Q R + D P Q R = 8
There are 8 MCS, with each MCS consisting of failure components and their protections as
indicated in Blue. Failure of both the component and protection will result in the top event of
loss of containment. It is noted there are no protection for MCS = I and MCS = J. They are
the SPF of the compressor seal failure and pipe rupture as shown in the Fault Tree.
The hierarchy of obtaining the failure rates is first from UK HSE failure rates; Failure
Rate and Event Data for use within Risk assessment (28/05/2012); as indicated in the
NEA QRA Technical Guidance document.
OREA (1997) data is used as the failure rates are more accurate for offshore
equipment. FPSO are located offshore.
The rest of failures rates are obtained from UKAEA and CCPS.
The failure rates for per hour are converted to per year. It is assumed that the FPSO is
operated 365 days a year and 12 hours a day.
Failure per demand is calculated from the mean failure rate x repair time.
Reference 2
K Check valve fails 0.0022 3.5.1.2 Check valve (Fails to Check); mean
failure rate
Reference 2
M PSV-3801 fails 0.000212 4.3.3.2 Safety relief valve (Fails to Open on
Demand); mean failure rate
Reference 3
Compressor seal
I 0.00027 FR 3.1.3 Compressors; Small Hole (>25 mm –
failure
75 mm diameter)
Reference 3
FR 3.1.2 Above Ground Pipelines; Rupture
J Pipe Rupture 0.0000065
(>110 mm diameter)
Assumption of 1000 m of pipeline
20 | P a g e
Used in Offshore Operations
Pressure Sensor; mean failure rate and repair
time
Reference 2
R PSV-3811 fails 0.000212 4.3.3.2 Safety relief valve (Fails to Open on
Demand); mean failure rate
The MCS failure rate is calculated from the failure rates shown below:
l S K L M = lS x FDTK x FDTL x FDTM = 21.46 x 0.0022 x 0.03 x 0.000212 = 3.003 x 10-7/ year
From the MCS failure rate, the failure probability for this particular cut set can be calculated
as shown below:
The MCS failure rates and failure probabilities are calculated and then tabulated in Table 3.2
below:
3.003E-07 3.003E-07
MCS S K L M
1.060E-04 1.060E-04
MCS G M
1.060E-04 1.060E-04
MCS H M
2.700E-04 2.700E-04
MCS I
6.500E-06 6.500E-06
MCS J
1.496E-12 1.496E-12
MCS D P Q R
Total 4.888E-04
21 | P a g e
From the table, the top event: Loss of Containment hazard probability is summed up from all
the MCS failure probabilities calculated. The loss of Containment hazard probability of
occurrence is 4.888 x 10-4/year
22 | P a g e
Various flammable event outcomes may arise depending on each release conditions as well
as the timing, location and type of ignition (e.g. immediate or delayed). The Event Tree
Analysis provides a list of undesired outcome event and its probability of occurrence.
The probabilities used in the event trees are based on the relevant guidelines as reference
from recognized standards and guides. Based on the event tree analysis, all event outcome
frequencies are derived and summarised in the later section of the report.
Toxicity Probability
Toxicity can be categorised into IDLH (Immediately Dangerous to Life and Health) and
EPRG1, EPRG2 and EPRG3.
Ignition Probability
Ignition can be categorised into immediate or delayed ignition. Immediate ignition occurs
near the release point before the gas cloud disperses due to presence of ignition sources such
as sparks/static. Delayed ignition considers the drifting of gas cloud into an ignition source.
In this Event tree analysis, it is considered that an immediate ignition of the released gas can
result in a jet fire (for immediate ignition) and vapour cloud explosion or vapour cloud flash
fire (VCE, for delayed ignition).
Jet fire – a burning jet of gas or spray of atomised liquid release from high-pressure
equipment. This may be very damaging to equipment within the fire and lethal to personnel at
some distance from it.
Vapour Cloud Explosion – a burning gas cloud that develops high overpressures. This is
likely to kill anyone within it and may also severely damage high steel structures.
Vapour Cloud Flash Fire – a fire that propagates through a cloud of gas. This may be lethal
for anyone within it, but is unlikely to damage steel structures.
Each hydrocarbon leakage initiating event is developed into credible accident scenarios for
consequence analysis using Event Tree Analysis. The branches considered in developing the
final hazard scenarios are as follow:
- Immediate ignition
- Delayed ignition
- Explosion probability
- Isolation success
The term Isolation in the event tree refers to the activation of the ESD, which isolate the
compressor system, activate the ESD valves (Compressor inlet and discharge isolation
valves) and trip the compressor. The term Blowdown refers to the safe emergency
depressurisation after isolation of the system. Note that the blowdown valve is located at the
compressor discharge and it is able to depressurise the compressor inlet (Scrubber equipment)
through either the compressor surge valve and compressor recycle valve) per the line-up. See
Appendix A for the P&IDs.
Event Tree
The event tree is illustrated in Figure 3.3 and Figure 3.4 below for the release of hydrocarbon
due to the main causes of loss of containment as indicated in the earlier sections of the report:
Safety protection systems such as early detection, fire and gas detectors were not considered
in the calculation of event frequency, as it is conservatively judged that the delay before these
emergency intervention action can be taken is sufficient for the hazardous scenario to occur
(based on the calculated probabilities).
Based on the 3 cases of events, outcomes resulting from liquid hydrocarbon were not
considered due to single gaseous phase. Hence, events such as pool fire, BLEVE, fireball etc.
were not considered in this consequence analysis. Events from the release of gas such as jet
fire, vapour cloud explosion, vapour cloud flash fire, and toxic vapour cloud were considered
to be a probable and realistic approach for this section of analysis.
24 | P a g e
From the fault tree table, the top event: Loss of Containment hazard probability is summed up
from all the MCS failure probabilities calculated. The loss of Containment hazard probability
of occurrence is 4.888 x 10-4/year
Frequency of Probability Detection Isolation Probability Probability of Outcome Description of end event
Gas Mixture of Immediate Success Success of Delayed Explosion Per Year
release Ignition Ignition
25 | P a g e
Isolation Success
Jet Fire, Fire Detection
N Success and Isolation Fail
Jet Fire, Fire Detection and
N No Isolation
Figure 3.3: Template for Event Tree for the Largest Possible Release of Gas Mixture
Frequency of Probability Detection Isolation Probability Probability of Outcome Description of end event
Gas Mixture of Immediate Success Success of Delayed Explosion Per Year
release Ignition Ignition
26 | P a g e
1.34E-10 Jet Fire, Fire Detection and
0.0058 No Isolation
Figure 3.4 Probabilities Event Tree for the Largest Possible Release of Gas Mixture
The gas ignition probabilities which is used to calculate the frequency of a jet fire
(immediately ignited) or vapour cloud explosion/vapour cloud explosion (delayed ignition)
are obtained from A Guide to Quantitative Risk Assessment for Offshore Installations, Centre
of Marine and Petroleum Technology (CMPT). Probabilities of isolation and blowdown
success are also referred from CMPT based on historical data. The probability of delayed
ignition leading to explosion is conservatively prescribed at 0.3. Summary on the initial
release rates for ignition is as shown in Table 3.3 below.
The Toxic Vapour Cloud probabilities to calculate the frequency of reaching IDLH or PEL
are obtained from… Probabilities of flange leakage, pipeline leak, and valve packing leak are
referred from ODECO/CMPT based on historical data. The probability of reaching IDLH is
conservatively prescribed at 0.3. Summary as shown below.
From the event tree, we have identified catastrophic events as events resulting from isolation
success and blowdown failure, and events resulting from isolation and blowdown failure.
From the quantitative analysis of the event tree, we have identified vapour cloud flash fire
due to isolation success and blowdown failure to have the highest probability of occurrence
of 3.99x10-6 /year. This result will be used in our risk assessment.
28 | P a g e
4. Bow Tie Diagram
The bow tie software that we have used for this project is Thesis, ABS Consulting software.
The software allows a graphical representation of threats which can cause a top event to
happen, leading to possible consequences. Barriers in between are the prevention and
mitigation controls which relates to each threat and consequence. It can also be used as a tool
to assist in the quantitative risk management of safety critical systems.
In this bow tie diagram, it is recognised that the threats highlighted in blue are relevant to the
minimum cut sets as determined in the previous part of the report. Further, early detection
and fire and gas detectors are also added into the mitigation layers.
29 | P a g e
Figure 4.1: Bow Tie Diagram
30 | P a g e
5. Consequence Modelling
From the results of the frequency analysis, the following fire and explosion scenarios were
deemed to be credible, and will be further analysed through consequence modelling in
ALOHA:
- Jet Fire
- Vapour Cloud Explosion (VCE)
- Vapour Cloud Flash Fire
For the purpose of this report, footprint boundary dimensions (isotherms) are determined as
per table indicated below (reference from Table 6 of NEA Technical Guidance).
37.5kW/m2 ~ 100%
10psi
For the fire and gas dispersion modelling, the weather conditions that are considered are,
31 | P a g e
as per 6.2.2 of NEA Technical Guidance.
The severity determined by the hole size of the release, and the following representative hole
size used in this QRA (as per 4.1.1.1 of NEA Technical Guidance) is presented in table
below:
Small <10 10
Medium 10-22 25
Large 22-75 75
The consequence modelling is categorised into 2 cases – A and B. Case A where we consider
the consequences are due to isolation success and blowdown failure and Case B where the
consequences are due to isolation and blowdown failure.
Probability of failure of Flanges in the inlet and outlet piping of Scrubber are high so when
there is a successful isolation, the Impact due to fires and explosions are less.
For each of the fire and explosion scenarios modelled, the physical effects arising from fires
are analysed with respect to thermal radiation loads. For vapour cloud explosion scenarios,
blast overpressure loads are considered.
4 kW/m2 – no effects, provided personnel can take normal escape action. The thermal
radiation level of 5.0 kW/m2 is sufficient to cause pain to personnel if unable to reach
cover within 30 seconds; however, blistering of the skin (second degree burns) is
likely; 0% fatality.
15.3 kW/m2 – escape routes are treated as ‘impaired’, meaning that personnel will not
enter this zone. personnel in this zone may use escape routes, providing this allows
them to leave the area within a few seconds, find safe refuge, or jump into the sea, but
they suffer second degree burn injuries. Otherwise they must take emergency action,
such as seeking safe refuge or jump into the sea.
32 | P a g e
37.5 kW/m2 – immediate fatality for all personnel and sufficient to cause damage to
structures and process equipment.
Personnel being exposed to the flammable cloud, i.e., within the LFL, in the instant of a
delayed ignition of the flammable cloud would have a 100% probability fatality either by the
inhalation of hot combustion gases or from severe burns.
Flash Fires do not generate severe structural or equipment damage, and only superficial
damage to insulation and cables.
5 psi: Most buildings collapse and Serious injuries are common, fatalities may occur.
7 psi: Loaded train cars overturned. More possible for fatality to occur.
The weather conditions follows NEA conditions per guidelines, and is located in open
water.
Release due to overpressure from Scrubber is modeled as a pipe release, as the release
is likely from the vessel connecting flanges. The representing hole sizes for pressure
vessel release per section 4.1.1.1 of the QRA Technical Guidance document is used.
33 | P a g e
For Case A: Isolation success and Blowdown failure, the source term is based on
isolated inventory of 4400 kg (Calculated based on the volume of the vessels and
interconnecting pipelines) and the settle out pressure of 251.5 atm. The unbroken end
of the pipe is closed off and the pipe length is iterated to obtain 4400 kg.
For Case B: Isolation failure and Blowdown failure, the source term is based on the
unbroken end connected to infinite source and assumed worst case at compressor
discharge pressure of 376.2 atm.
For Jet Fire: Gas escapes from Piping is Burning (jet fire)
For VCE: Hazard analyzed was Blast Area of vapour pressure with LOC as
Congested and Ignited by Spark or flame
The length of a jet flame is primarily a function of the mass release rate of the fuel. When
ESD is successfully initiated, the jet flame lengths will decay with time as the system
pressure decreases and the flammable inventory is depleted.
The initial and maximum jet flame lengths obtained from ALOHA are summarised in the
table below for various hole size.
34 | P a g e
Event Weather Initial Jet Flame Length 4kW/m2 Contour Distance
Conditio (m)
n
10mm 25mm 75mm Full Bore
Loss of F1 0 22 83 337
Containment of
Hydrocarbons B2 0 22 83 337
C3 0 22 83 337
Loss of F1 0 12 44 178
Containment of
Hydrocarbons B2 0 12 44 178
C3 0 12 44 178
Loss of F1 0 0 28 116
Containment of
Hydrocarbons B2 0 0 28 116
C3 0 0 29 116
The maximum distances along the axis of the frustum to thermal radiation levels of 37.5,
15.3, and 4 kW/m2 are determined by relation with the fractions of the flame lengths for
different hole size and wind speed. Calculation of the thermal radiation contours was done
using the ALOHA software.
10 mm 25 mm
35 | P a g e
F1
B2
C3
36 | P a g e
F1
B2
C3
Figure 5.2: Jet Fire contour for hole sizes 75 mm and full bore
37 | P a g e
achieved through the acceleration and non-linear deceleration of the flame front as it passes
over and around obstacles such as adjacent piping, equipment and structures.
5 821
VCE
38 | P a g e
5.4.3 Vapour Cloud Flashfire Modelling
Gaseous or liquid hydrocarbon discharged into atmosphere can lead to the formation of a
flammable gas cloud. The size of the gas cloud is influenced by the properties of the
gas/vapour and the prevailing wind conditions. Flash fires can occur due to a delayed ignition
of the flammable gas cloud at unconfined/uncongested areas.
Flash fires are characterized by transient front of flames travelling through the cloud
generating a potentially intense flame causing serious effects on people engulfed by the
flammable cloud. However, with a short duration, it would not cause any structural or
equipment damage, and only superficial damage to insulation and cables.
10 mm 25 mm 75 mm Full Bore
Table 5.7: Maximum Flash Fire (LFL) Distances at different wind speed
39 | P a g e
10 mm 25 mm
F1
B2
C3
Figure 5.4: Vapour cloud Flash Fire Contour for hole sizes 10 mm and 25 mm
40 | P a g e
75 mm Full Bore
F1
B2
C3
Figure 5.5: Vapour cloud Flash Fire Contour for hole sizes 75 mm and full bore
41 | P a g e
5.5 Case B - Isolation and Blowdown Failure
The length of a jet flame is primarily a function of the mass release rate of the fuel. When
ESD is successfully initiated, the jet flame lengths will decay with time as the system
pressure decreases and the flammable inventory is depleted.
The initial and maximum jet flame lengths obtained from ALOHA are summarised in the
table below for various hole size.
Loss of F1 0 22 83 337
Containment of
Hydrocarbons B2 0 22 83 337
C3 0 22 83 337
Loss of F1 0 12 44 178
Containment of
Hydrocarbons B2 0 12 44 178
C3 0 12 44 178
42 | P a g e
Event Weather Initial Jet Flame Length 37.5kW/m2 Contour
Conditio Distance (m)
n
10mm 25mm 75mm Full Bore
Loss of F1 0 0 28 116
Containment of
Hydrocarbons B2 0 0 28 116
C3 0 0 29 116
The maximum distances along the axis of the frustum to thermal radiation levels of 37.5,
15.3, and 4 kW/m2 are determined by relation with the fractions of the flame lengths for
different hole size and wind speed. Calculation of the thermal radiation contours was done
using the ALOHA software.
43 | P a g e
10mm 25mm
F1
B2
C3
44 | P a g e
F1
B2
C3
Figure 5.6: Jet Fire contour for hole sizes 75 mm and full bore
45 | P a g e
5.5.2 Vapour Cloud Explosion Modelling
Delayed ignition of a flammable cloud within a confined and/or congested area will most
likely result in significant overpressures. It would then be termed as a Vapour Cloud
Explosion (VCE). In order to generate a significant explosion load, the flame-front of the
flammable cloud is required to transition from laminar to turbulent flow. This is typically
achieved through the acceleration and non-linear deceleration of the flame front as it passes
over and around obstacles such as adjacent piping, equipment and structures.
5 487
VCE
46 | P a g e
5.5.3 Vapour Cloud Flashfire Modelling
Gaseous or liquid hydrocarbon discharged into atmosphere can lead to the formation of a
flammable gas cloud. The size of the gas cloud is influenced by the properties of the
gas/vapour and the prevailing wind conditions. Flash fires can occur due to a delayed ignition
of the flammable gas cloud at unconfined/uncongested areas.
Flash fires are characterized by transient front of flames travelling through the cloud
generating a potentially intense flame causing serious effects on people engulfed by the
flammable cloud. However, with a short duration, it would not cause any structural or
equipment damage, and only superficial damage to insulation and cables.
For this study, the flash fire is assumed to cover the distance reached by the 100% Lower
Flammable Limit (1.0 LFL).
C3 19 63 115 225
Table 5.12: Maximum Flash Fire (LFL) Distances at different wind speed
47 | P a g e
10mm 25mm
F1
B2
C3
Figure 5.8 Vapour Cloud Flash Fire Contour for hole sizes 10 mm and 25 mm
48 | P a g e
F1
B2
C3
Figure 5.9: Vapour Cloud Flash Fire Contour for hole sizes 75 mm and full bore
49 | P a g e
6. Risk Determination
For the purpose of this project, we have limited the QRA study to the RI gas compression
system only, hence limited data are available for an overview calculation of the risk. In this
regard, the conservative approach that we have adopted in determining the Individual Risk
(IR) Fatality is based on the below equation:
Where
the probability of hazardous event is selected from the catastrophic events which have
the highest probability of occurrence;
worst case scenario and the probability of death is assumed to be 1 by considering the
harm level which gives 100% fatality i.e. thermal radiation of 37.5 kW/m2 for jet fire
case, and 100% LFL for flash fire case.
The table below shows the IR (fatality) calculated for the different catastrophic events and
their corresponding contour distance.
50 | P a g e
From Table 6.1, it can be shown that it is lethal being at a distance of 42m from the point of
ignition in an event of a jet fire, with a probability of 6.52x10-7/year and a distance of 786m
from the point of ignition in an event of a vapour cloud flash fire, with a probability of
3.99x10-6/year. These risk figures are acceptable based on recognized offshore standard from
UK HSE where the tolerable range is greater than 1x10-4/year. As for an event of vapour
cloud explosion, even though there is a probability of occurrence of the event as indicated
from the event tree analysis. However, based on consequence modelling where actual
inventory of the process were factored into, it proves that on a realistic point of view, there
will not be any fatality for an event of explosion as it is negligible for a pressure of greater
than 5psi.
51 | P a g e
7. Discussion and Conclusion
From the QRA study, we note that the IR (fatality) calculated is considered low. NEA criteria
for IR (fatality) in fixed installation within the boundary is 5x10 -5. We have assumed that the
IR (fatality) on FPSO which is out in the sea is limited to the boundary of the FPSO only.
Based on Table 6.1, we note that the highest IR (fatality) calculated in our facility is 3.99x10 -
6
, which is tolerable and within NEA criteria.
7.2 Conclusion
As this QRA study is restricted to only IR compression study, the IR is considered low. A full
scale QRA on the FPSO which considers all the hazards present (process related hazards
from other modules on the FPSO and non-process related hazards such as Ship Collision
Analysis, Non Flammable Hazard Analysis and Dropped Object Study) will give a more
representative value on the IR (fatality).
To acquire an even representative value on individual risk, it is recommended that the risk
figures due to the hazard for various consequences can be calculated by considering different
groups of personnel on board the vessel, amount of time spent by each personnel at location
of concern. The formula is as follows:
IRPA= IR x Manning Factor
52 | P a g e
References
1. Mannan Sam; Lees’ Loss Prevention in the Process Industries; Hazard Identification,
Assessment and Control – Appendix 14 Failure and Event Data
2. Center for Chemical Process Safety; Guidelines for Process Equipment Reliability
Data with Data Tables – Chapter 5 CCPS Generic Failure Rate Data Base
3. UK Failure Rates – Failure Rate and Event Data for use within Risk Assessments
(28/06/2012)
4. NEA QRA Technical Guidance
5. NEA QRA Criteria Guidelines
6. A Guide to Quantitative Risk Assessment for Offshore Installations, Centre of Marine
and Petroleum Technology (CMPT)
53 | P a g e
Appendix A
54 | P a g e
55 | P a g e
Appendix B
Process section: Reinjection Compressor including inlet and outlet Study Date: 01 / 10 / 2017
Gas from HP Compressor discharge Cooler is routed to RI Compressor suction Scrubber to knock down any liquid. The Gas is then routed to the RI Compressor
Design intent
suction where it is Compressed and routed for reinjection into the well.
1. No/Low Flow 1.1. Loss of flow to Compressor 1.1.1. Less flow to Compressor leading to 1.1.1.1. Capacity control provided through FCV3802.
due to upset upstream. potential surge. Potential damage to
Compressor. 1.1.1.2. Compressor anti-surge control will open the recycle valve
FCV3801 across Compressor.
1.2. Less flow to Compressor 1.2.1. Less flow to Compressor leading to 1.2.1.1. Capacity control provided through FCV3802.
due to turndown operation or potential surge. Potential damage to
during later years when overall Compressor. 1.2.1.2. Compressor anti-surge control will open the recycle valve
gas flow may be less. Low flow FCV3801 across Compressor.
case may also occur if only
heavy oil is flowing without
light oil. 1.2.1.3. PZALL3814 at suction will trip Compressor turbine.
1.3. Less flow during heavy oil 1.3.1. At this flow rate, there may not be 1.3.1.1. Capacity control provided through FCV3802. 1. Check for heavy oil operation
only operation. any gas flow to HP & RI section while MP only, whether MP Compressor
may continue to run and supply to fuel can be operated o either consume
gas. the gas or reinject the gas without
need for flaring. Also check HP
1.3.1.2. Compressor anti-surge control will open the recycle valve & RI Compressor operation for
FCV3801 across Compressor. this case.
56 | P a g e
1.4. SDV3802A at suction gets 1.4.1. Loss of flow to Compressor leading 1.4.1.1. Compressor anti-surge control will open the recycle valve
closed to potential surge. Potential damage to FCV3801 across Compressor. This recycles downstream of the
Compressor. suction SDV.
1.5. Compressor suction 1.5.1. Potential loss of flow to Compressor 1.5.1.1. PDI3816 with high alarm across strainer
strainer plugged leading to surge. Loss of anti-surge
protection. 1.5.1.2. Low low pressure trip downstream of strainer at compressor
suction nozzle (PZALL3814)
1.6. RI Compressor Trips (All 1.6.1. Pressure build up in upstream 1.6.1.1. PC3729 on MP Compressor suction header will relieve to
three compressors upstream vessels leading to upset. HP Flare. This is sized for full flow of MP Compressor.
(MP and HP) will also trip as
they are on common shaft) 1.6.1.2. Upstream vessels have individual relief to flare for blocked
condition.
1.6.2. Loss of HP fuel gas to power 1.6.2.1. Provision for switch over to diesel
turbine.
1.6.3. Potential loss of LP fuel gas for flare 1.6.3.1. Gas may be routed directly to low pressure fuel gas users
purge and pilots. from MP Compressor suction cooler outlet to Fuel Gas Scrubber.
This line remains open and will flow when Fuel Gas Scrubber
pressure falls.
1.6.4. Potential reverse flow from Gas 1.6.4.1. Single check valve provided at Compressor discharge
Injection Header leading to damage nozzle.
1.6.5. Potential surge during coast down 1.6.5.1. Anti-surge safeguard for Compressor.
57 | P a g e
1.6.6. Potential increase in Compressor 1.6.6.1. Compressor suction designed higher than settle out
suction pressure due to settle out condition pressure.
Compressor trip.
1.6.7. Potential overpressure of RI 1.6.7.1. Single check valve at discharge Cooler outlet. 2. Review the overpressure
Compressor suction due to reverse flow safeguards for the RI Compressor
from the downstream discharge header/ 1.6.7.2. SDV3803A/B at discharge Cooler outlet will close on suction against discharge check
gas reinjection header Compressor trip. valve leakage case. Similarly
review the overpressure
Potential overpressure of upstream HP safeguard for the HP Compressor
1.6.7.3. Single check valve provided at Suction Scrubber inlet discharge piping against
Compressor discharge piping.
downstream check valve leakage
1.6.7.4. SDV3802A/B at Suction Scrubber inlet will close on case. The requirement for double
Compressor trip. check valve and PSV sizing for
check valve leakage case to be
reviewed in addition to closure of
SDVs.
1.6.9. On loss of gas lift, heavy oil flow 1.6.9.1. Preservation procedure in case of Heavy oil line shut off.
lines may stop flowing leading to stagnant
condition. Potential plugging.
1.7. Strainer at inlet of 1.7.1. Loss of flow through Compressor 1.7.1.1. PDI3832 with high alarm across strainer 3. Review the requirement for hot
discharge Cooler plugged leading to surge. Anti-surge control will bypass across the Compressor
not safeguard against this scenario. nozzles, considering the potential
for blockage in discharge cooler
and consequent loss of anti-surge
flow. This is to be checked with
vendor. This action is applicable
for MP, HP and RI Compressor.
58 | P a g e
1.7.2. Potential damage to strainer leading 1.7.2.1. PDI3832 with high alarm across strainer 4. Provide trip of Compressor on
to debris carryover to Cooler. high differential pressure across
strainer at the inlet of MP
Compressor discharge cooler.
1.7.3. Potential overpressure at 1.7.3.1. PZAHH3818 at compressor discharge will trip the
Compressor discharge. Compressor.
1.8. Discharge Cooler plugged 1.8.1. Loss of flow through Compressor 1.8.1.1. Strainer provided at inlet 5. Review the requirement for hot
(This is PCHE type with small leading to surge. Anti-surge control will bypass across the Compressor
diameter flow path) not safeguard against this scenario. nozzles, considering the potential
1.8.1.2. PDI3833 with high alarm across PCHE on gas side for blockage in discharge cooler
and consequent loss of anti-surge
flow. This is to be checked with
vendor. This action is applicable
for MP, HP and RI Compressor.
1.9. SDV3803A at discharge 1.9.1. Loss of flow through Compressor 1.9.1.1. Anti-surge safeguard for Compressor.
gets closed or any downstream leading to surge.
blocked condition on gas
injection line. 1.9.2. Potential overpressure. 1.9.2.1. PZAHH3814 at Compressor suction will trip the
Compressor
59 | P a g e
3. Reverse/ 3.1. No issue
Misdirected Flow
4. More/High Pressure 4.1. External Fire around 4.1.1. Potential overpressure 4.1.1.1. PSV3801 on suction Scrubber sized for fire case.
Suction Scrubber
5. Low Pressure 5.1. Compressor turbine speed 5.1.1. Suction pressure will fall. Potential 5.1.1.1. Compressor anti-surge control will open.
control malfunctions and surge due to high head across the
increases the speed. Compressor although surge point may
move due to higher flow. Potential stone 5.1.1.2. Over speed safeguard for the turbine.
wall condition at high flow if delta P does
not increase.
5.3. HP Compressor recycle 5.3.1. Less flow to RI Compressor leading 5.3.1.1. Compressor anti-surge control will open.
valve opens. to surge.
6. More/High 6.1. Loss of Cooling Water to 6.1.1. Potential high temperature gas to RI 6.1.1.1. TC3809 with high alarm. Credit for this taken where any
Discharge Cooler due to supply compressor suction when operating on element of this loop is not the cause of malfunction.
Temperature failure recycle mode. Potential increase in
Compressor discharge temperature leading 6.1.1.2. TZAHH3808 at Cooler outlet will trip the Compressor
to damage.
6.1.1.3. TZAHH3804 at RI Compressor discharge will trip the
Compressor.
6.1.2. High temperature gas will flow to 6.1.2.1. TC3809 with high alarm. Credit for this taken where any
gas injection system. Potential damage to element of this loop is not the cause of malfunction.
gas injection piping, swivel joint and risers
60 | P a g e
due to exceedance of design temperature. 6.1.2.2. TZAHH3808 at Cooler outlet will trip the Compressor
7. Low Temperature 7.1. More cooling due to 7.1.1. No significant drop in temperature is
TC3809 malfunction in expected. No significant issue.
Discharge cooler.
7.2. Blow down operation 7.2.1. Potential low temperature in the 6. To confirm based upon the
blow down valve outlet to flare. Potential Low temperature study the
Hydrate formation. Potential low requirement to connect BDV
temperature in the system due to blow discharge to Low Temperature
down. HP flare header, the material
suitability for the system (for
which blow down is provided) as
well as any requirement for
hydrate inhibitor.
7.3. Pressure let down across 7.3.1. Potential low temperature at the 7. Compressor capacity control
capacity control valve valve and downstream and antisurge control downstream
FCV3802 or anti-surge valve piping material to be checked for
FCV3801 lowest temperature expected due
to pressure let down. Currently
CS material is shown. This action
is applicable for both HP
Compressor and RI Compressor.
61 | P a g e
8. High Level 8.1. SDV3801 at Suction 8.1.1. Level build-up in Scrubber. Possible 8.1.1.1. LC3802 with high alarm. Credit for this taken where any
Scrubber liquid outlet gets liquid carry-over leading to Compressor element of this loop is not the cause of malfunction.
closed. Normally no liquid damage.
expected. 8.1.1.2. LZAHH3804 on Scrubber will trip the Compressor.
9. Low Level 9.1. LC3802 malfunctions 9.1.1. Gas blow-by to HP Suction 9.1.1.1. LZALL3804 will close SDV3801 9. SDV3801 at RI Compressor
leading to wide opening of Scrubber. Under Compressor running Suction Scrubber to close on
LCV on liquid outlet of Suction case, this will lead to gas being recycled. Compressor trip or stop signal.
Scrubber. No significant issue. Under Compressor
trip case, this may lead to overpressure of
HP Suction Scrubber.
9.1.1.2. On Compressor trip, RI Compressor suction Scrubber liquid 10. Check the requirement for
outlet SDV will close. sizing PSV3601 on HP
Compressor suction Scrubber for
the case of gas blow-by from RI
Compressor Suction Scrubber.
9.1.1.3. PSV3601 on HP Compressor Suction Scrubber. This is 11. Check if the medium is dense
designed for fire case. phase and whether level sensor
will act in dense phase and if
control need to be automatic.
10. Composition 10.1. H2S in Compressor feed 10.1.1. No issue for Compressor operation
Change / gas stream. This may occur in or metallurgy.
Contamination / later years and if H2S
Additional Phase / Scavenger is not effective or 10.1.2. In case of seal failure, this can 10.1.2.1. Provision for isolation and blow down of Compressor.
Loss of Phase operational. result in H2S leak to atmosphere
10.1.2.2. H2S detectors will be installed in the field when H2S will
be detected in later years.
10.2. Compressor operates on 10.2.1. Anti-surge control valve and 12. Anti-surge control valve and
recycle mode Capacity control valve inlet may have two Capacity control valve across HP
phase flow due to hydrocarbon & RI Compressor to consider
condensing. It may also contain water in impact of water content at inlet to
case of wet gas flow from Dehydration the valve for both the case of
Column. Potential impact on control valve. normal water content and as well
as for the case of wet gas flow
due to upset in Dehydration
62 | P a g e
Column.
10.3. Wet gas from Dehydration 10.3.1. Potential hydrate formation where 10.3.1.1. Online Dew point Analyzer AI3201 at Dehydration 13. Review the impact of wet gas
column outlet. This may occur there is gas let down. Potential impact on Column outlet. However under the start-up and upset condition, wet flow to HP Compressor and
during start-up as well as during gas injection well. Also potential increased gas flow will continue. Reinjection Compressor and
any upset such as loss of TEG corrosion in the piping as these are CS downstream well injection,
flow. material. including impact on BDV,
compressor recycle valves for
anti-surge etc. Review the
requirement for corrosion
inhibitor injection in Dehydration
Column overhead. Review the
requirement for Hydrate inhibitor.
Also review the requirement for
venting of gas to flare or
recycling if required.
12. Start-up Shutdown 12.1. Re-start of Compressor 12.1.1. No issue since gas turbine can be
/ Maintenance after settle out run at minimum speed.
13. Others 13.1. Tube rupture in Discharge 13.1.1. Gas will leak into the Cooling 13.1.1.1. PSV3831 on Cooling water side designed for plate leak
Cooler water system. Potential overpressure of the and will relieve to HP flare header.
cooling water side of exchanger .
13.1.2. Gas will leak into the Cooling 13.1.2.1. Cooling Medium Vessel is designed for 18 barg while
water system. Potential gas build-up in PSV is set at 8 barg for fire case.
Cooling Medium Vessel. Potential
overpressure. 13.1.2.2. PZAHH6703 at Cooling Medium circulation pump
discharge will trip the pump.
63 | P a g e
medium vessel (internal gas detection)
13.1.3. High pressure gas leak into the low 13.1.3.1. PI6701 on Cooling Medium Vessel with high alarm. 14. In case of any hydrocarbon
pressure cooling medium may lead to leak from PCHE in the
gradual drop in cooling medium compressor circuit to the cooling
temperature. In the worst case, gas may medium, action to be taken to
displace the liquid and vent through stop the Compressor and blow
PSV3831 which may get blocked due to down.
hydrate if temperature is lower than 0 deg
C.
13.1.3.2. AI6701 with high alarm for hydrocarbon in Cooling 15. Consider PI with high alarm
. medium vessel (internal gas detection) on cooling water side at each
PCHE to alert operator in case of
any leakage. This action is
applicable for all PCHE in high
pressure gas system.
13.2. Seal failure 13.2.1. Potential Hydrocarbon leak to 13.2.1.1. Provision for isolation and blow down of Compressor.
atmosphere Single BDV3801 provided at the discharge for the entire
compressor loop including the Scrubber.
13.3. Operation of SDV by-pass 13.3.1. Potential low temperature when 16. Check the low temperature
across Compressor suction and by-pass SDV is operated for pressure requirement for the by-pass SDV
discharge SDV equalization under high differential and the downstream by-pass
pressure. piping at Compressor suction and
discharge where high differential
may occur resulting in low
temperatures when the by-pass is
operated for pressure
equalization. This is particularly
applicable for HP Compressor
discharge as well as RI
Compressor suction and
discharge.
13.4. Compressor suction and 13.4.1. Potential damage due to sudden 13.4.1.1. PDI with inhibit signal to inhibit open of the main SDV on
discharge SDV opened under high flows high differential pressure
high differential pressure
13.5. Blockage in RI 13.5.1. Since piping is derated 17. Review the design pressure
Compressor Suction Scrubber downstream of LV3802, plugging in the for the piping downstream of
64 | P a g e
liquid outlet piping downstream piping can lead to overpressure and can LV3802 in RI Compressor
of LV3802. This may occur in cause loss of containment Suction Scrubber liquid outlet.
case of hydrate formation, This action will also apply for the
particularly during start-up or piping downstream of the
upset condition when gas may LV3603 on HP Compressor
be wet. suction Scrubber liquid outlet and
for piping downstream of
LCV3705 on MP Compressor
discharge Scrubber liquid outlet.
These piping may be designed for
the same pressure as the LV
upstream pressure upto the return
nozzle of the downstream
equipment.
13.6. Drain valve to Closed 13.6.1. Potential overpressure of the 13.6.1.1. 6" vent to flare on Closed Drain Drum with Lock Open
drain system opened Closed drain drum and the header. (LO) valves but may not be sufficient. Also this will not protect the
inadvertently during normal header in case of any blockage.
operation.
13.6.1.2. Procedures to ensure drain valves to closed drain header
are closed and spaded closed during normal operation. They are to
be opened only after depressurisation of the equipment, for
maintenance.
65 | P a g e