(CLIENT LOGO)

NEW AL MAZROUAH 300 SOLDIER BARRACKS PROLECT


(U0789)

PROJECT INFORMATION STATUS


Project Name: NEW AL MAZROUAH 300 SOLDIER BARRACKS Approved - A & B

Contractual Start Date:


Contractual Completion Date: SHOP DRAWINGS REGISTER Under review - UR

Revise&Resubmit - C

Date of Update: 08.MAR.20 Rejected - D

Revision: 0 Internally Returned - R

Precast Fabrication Panel


Status Code
Actual Submission
S/N REE Drawing Reference No. Description Disc Trade Level Area /Zone Plan Submission Date Date Return Date Review Period Remarks
Reference No. Received Date TR Ref A B C D UR

ELECTRICAL

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

Page 1 of 30
(CLIENT LOGO)
NEW AL MAZROUAH 300 SOLDIER BARRACKS PROLECT
(U0789)

PROJECT INFORMATION STATUS


Project Name: NEW AL MAZROUAH 300 SOLDIER BARRACKS Approved - A & B

Contractual Start Date:


Contractual Completion Date: SHOP DRAWINGS REGISTER Under review - UR

Revise&Resubmit - C

Date of Update: 08.MAR.20 Rejected - D

Revision: 0 Internally Returned - R

Precast Fabrication Panel


Status Code
Actual Submission
S/N REE Drawing Reference No. Description Disc Trade Level Area /Zone Plan Submission Date Date Return Date Review Period Remarks
Reference No. Received Date TR Ref A B C D UR

29

30

31

32

33

34

35

36

37

38

39

40

41

42

43

44

45

46

47

HVAC SYSTEM

GROUND FLOOR HVAC DUCTING LAY OUT DRAWING

FIRST FLOOR HVAC DUCTING LAY OUT DRAWING

SECOND FLOOR HVAC DUCTING LAY OUT DRAWING

THIRD FLOOR HVAC DUCTING LAY OUT DRAWING

PENT HOUSE & ROOF FLOOR HVAC DUCTING LAY OUT DRAWING

HVAC DUCTS SHAFT ARRANGEMENT LAY OUT

HVAC DUCTING SCHEMATIC LAY OUT DRAWING

GROUND FLOOR DX UNIT PIPING LAY OUT DRAWING

FIRST FLOOR DX UNIT PIPING LAY OUT DRAWING

Page 2 of 30
(CLIENT LOGO)
NEW AL MAZROUAH 300 SOLDIER BARRACKS PROLECT
(U0789)

PROJECT INFORMATION STATUS


Project Name: NEW AL MAZROUAH 300 SOLDIER BARRACKS Approved - A & B

Contractual Start Date:


Contractual Completion Date: SHOP DRAWINGS REGISTER Under review - UR

Revise&Resubmit - C

Date of Update: 08.MAR.20 Rejected - D

Revision: 0 Internally Returned - R

Precast Fabrication Panel


Status Code
Actual Submission
S/N REE Drawing Reference No. Description Disc Trade Level Area /Zone Plan Submission Date Date Return Date Review Period Remarks
Reference No. Received Date TR Ref A B C D UR

SECOND FLOOR DX UNIT PIPING LAY OUT DRAWING

THIRD FLOOR DX UNIT PIPING LAY OUT DRAWING

PENT HOUSE & ROOF FLOOR DX UNIT PIPING LAY OUT DRAWING

DX UNIT PIPING SHAFT ARRANGEMENT LAY OUT

DRAINAGE SYSTEM

UNDER GROUND DRAINAGE SYSTEM DRAWING

GROUND FLOOR DRAINAGE SYSTEM DRAWING

FIRST FLOOR DRAINAGE SYSTEM DRAWING

SECOND FLOOR DRAINAGE SYSTEM DRAWING

THIRD FLOOR DRAINAGE SYSTEM DRAWING

PENT HOUSE & ROOF FLOOR DRAINAGE SYSTEM DRAWING

DRAINAGE SYSTEM SCHEMATIC DRAWING

DRAINAGE SYSTEM SHAFT ARRANGEMENT DRAWING

WATER SUPPLY SYSTEM

GROUND FLOOR WATER SUPPLY SYSTEM DRAWING

FIRST FLOOR WATER SUPPLY SYSTEM DRAWING

SECOND FLOOR WATER SUPPLY SYSTEM DRAWING

THIRD FLOOR WATER SUPPLY SYSTEM DRAWING

PENT HOUSE & ROOF FLOOR WATER SUPPLY SYSTEM DRAWING

WATER SUPPLY SYSTEM SCHEMATIC DRAWING

FIRE PROTECTION SYSTEM

GROUND FLOOR FIRE PROTECTION SYSTEM DRAWING

FIRST FLOOR FIRE PROTECTION SYSTEM DRAWING

SECOND FLOOR FIRE PROTECTION SYSTEM DRAWING

THIRD FLOOR FIRE PROTECTION SYSTEM DRAWING

PENT HOUSE & ROOF FLOOR FIRE PROTECTION SYSTEM DRAWING

FIRE PROTECTION SYSTEM SCHEMATIC DRAWING

COORDINATION DRAWING

GROUND FLOOR MEP COORDINATION DRAWING

FIRST FLOOR MEP COORDINATION DRAWING

Page 3 of 30
(CLIENT LOGO)
NEW AL MAZROUAH 300 SOLDIER BARRACKS PROLECT
(U0789)

PROJECT INFORMATION STATUS


Project Name: NEW AL MAZROUAH 300 SOLDIER BARRACKS Approved - A & B

Contractual Start Date:


Contractual Completion Date: SHOP DRAWINGS REGISTER Under review - UR

Revise&Resubmit - C

Date of Update: 08.MAR.20 Rejected - D

Revision: 0 Internally Returned - R

Precast Fabrication Panel


Status Code
Actual Submission
S/N REE Drawing Reference No. Description Disc Trade Level Area /Zone Plan Submission Date Date Return Date Review Period Remarks
Reference No. Received Date TR Ref A B C D UR

SECOND FLOOR MEP COORDINATION DRAWING

THIRD FLOOR MEP COORDINATION DRAWING

PENT HOUSE & ROOF FLOOR MEP COORDINATION DRAWING

MEP SHAFT COORDINATION DRAWING

MEP BUILDERS WORK

UNDER GROUND MEP BUILDERS WORK DRAWING

GROUND FLOOR MEP BUILDERS WORK DRAWING

FIRST FLOOR MEP BUILDERS WORK DRAWING

SECOND FLOOR MEP BUILDERS WORK DRAWING

THIRD FLOOR MEP BUILDERS WORK DRAWING

PENT HOUSE AND ROOF FLOOR MEP BUILDERS WORK DRAWING

Page 4 of 30
(CLIENT LOGO)
NEW AL MAZROUAH 300 SOLDIER BARRACKS PROLECT
(U0789)

PROJECT INFORMATION STATUS


Project Name: NEW AL MAZROUAH 300 SOLDIER BARRACKS Approved - A & B

Contractual Start Date:


Contractual Completion Date: SHOP DRAWINGS REGISTER Under review - UR

Revise&Resubmit - C

Date of Update: 08.MAR.20 Rejected - D

Revision: 0 Internally Returned - R

Precast Fabrication Panel


Status Code
Actual Submission
S/N REE Drawing Reference No. Description Disc Trade Level Area /Zone Plan Submission Date Date Return Date Review Period Remarks
Reference No. Received Date TR Ref A B C D UR

Page 5 of 30
(CLIENT LOGO)
NEW AL MAZROUAH 300 SOLDIER BARRACKS PROLECT
(U0789)

PROJECT INFORMATION STATUS


Project Name: NEW AL MAZROUAH 300 SOLDIER BARRACKS Approved - A & B

Contractual Start Date:


Contractual Completion Date: SHOP DRAWINGS REGISTER Under review - UR

Revise&Resubmit - C

Date of Update: 08.MAR.20 Rejected - D

Revision: 0 Internally Returned - R

Precast Fabrication Panel


Status Code
Actual Submission
S/N REE Drawing Reference No. Description Disc Trade Level Area /Zone Plan Submission Date Date Return Date Review Period Remarks
Reference No. Received Date TR Ref A B C D UR

Page 6 of 30
(CLIENT LOGO)
NEW AL MAZROUAH 300 SOLDIER BARRACKS PROLECT
(U0789)

PROJECT INFORMATION STATUS


Project Name: NEW AL MAZROUAH 300 SOLDIER BARRACKS Approved - A & B

Contractual Start Date:


Contractual Completion Date: SHOP DRAWINGS REGISTER Under review - UR

Revise&Resubmit - C

Date of Update: 08.MAR.20 Rejected - D

Revision: 0 Internally Returned - R

Precast Fabrication Panel


Status Code
Actual Submission
S/N REE Drawing Reference No. Description Disc Trade Level Area /Zone Plan Submission Date Date Return Date Review Period Remarks
Reference No. Received Date TR Ref A B C D UR

Page 7 of 30
(CLIENT LOGO)
NEW AL MAZROUAH 300 SOLDIER BARRACKS PROLECT
(U0789)

PROJECT INFORMATION STATUS


Project Name: NEW AL MAZROUAH 300 SOLDIER BARRACKS Approved - A & B

Contractual Start Date:


Contractual Completion Date: SHOP DRAWINGS REGISTER Under review - UR

Revise&Resubmit - C

Date of Update: 08.MAR.20 Rejected - D

Revision: 0 Internally Returned - R

Precast Fabrication Panel


Status Code
Actual Submission
S/N REE Drawing Reference No. Description Disc Trade Level Area /Zone Plan Submission Date Date Return Date Review Period Remarks
Reference No. Received Date TR Ref A B C D UR

Page 8 of 30
(CLIENT LOGO)
NEW AL MAZROUAH 300 SOLDIER BARRACKS PROLECT
(U0789)

PROJECT INFORMATION STATUS


Project Name: NEW AL MAZROUAH 300 SOLDIER BARRACKS Approved - A & B

Contractual Start Date:


Contractual Completion Date: SHOP DRAWINGS REGISTER Under review - UR

Revise&Resubmit - C

Date of Update: 08.MAR.20 Rejected - D

Revision: 0 Internally Returned - R

Precast Fabrication Panel


Status Code
Actual Submission
S/N REE Drawing Reference No. Description Disc Trade Level Area /Zone Plan Submission Date Date Return Date Review Period Remarks
Reference No. Received Date TR Ref A B C D UR

Page 9 of 30
(CLIENT LOGO)
NEW AL MAZROUAH 300 SOLDIER BARRACKS PROLECT
(U0789)

PROJECT INFORMATION STATUS


Project Name: NEW AL MAZROUAH 300 SOLDIER BARRACKS Approved - A & B

Contractual Start Date:


Contractual Completion Date: SHOP DRAWINGS REGISTER Under review - UR

Revise&Resubmit - C

Date of Update: 08.MAR.20 Rejected - D

Revision: 0 Internally Returned - R

Precast Fabrication Panel


Status Code
Actual Submission
S/N REE Drawing Reference No. Description Disc Trade Level Area /Zone Plan Submission Date Date Return Date Review Period Remarks
Reference No. Received Date TR Ref A B C D UR

Page 10 of 30
(CLIENT LOGO)
NEW AL MAZROUAH 300 SOLDIER BARRACKS PROLECT
(U0789)

PROJECT INFORMATION STATUS


Project Name: NEW AL MAZROUAH 300 SOLDIER BARRACKS Approved - A & B

Contractual Start Date:


Contractual Completion Date: SHOP DRAWINGS REGISTER Under review - UR

Revise&Resubmit - C

Date of Update: 08.MAR.20 Rejected - D

Revision: 0 Internally Returned - R

Precast Fabrication Panel


Status Code
Actual Submission
S/N REE Drawing Reference No. Description Disc Trade Level Area /Zone Plan Submission Date Date Return Date Review Period Remarks
Reference No. Received Date TR Ref A B C D UR

Page 11 of 30
(CLIENT LOGO)
NEW AL MAZROUAH 300 SOLDIER BARRACKS PROLECT
(U0789)

PROJECT INFORMATION STATUS


Project Name: NEW AL MAZROUAH 300 SOLDIER BARRACKS Approved - A & B

Contractual Start Date:


Contractual Completion Date: SHOP DRAWINGS REGISTER Under review - UR

Revise&Resubmit - C

Date of Update: 08.MAR.20 Rejected - D

Revision: 0 Internally Returned - R

Precast Fabrication Panel


Status Code
Actual Submission
S/N REE Drawing Reference No. Description Disc Trade Level Area /Zone Plan Submission Date Date Return Date Review Period Remarks
Reference No. Received Date TR Ref A B C D UR

Page 12 of 30
(CLIENT LOGO)
NEW AL MAZROUAH 300 SOLDIER BARRACKS PROLECT
(U0789)

PROJECT INFORMATION STATUS


Project Name: NEW AL MAZROUAH 300 SOLDIER BARRACKS Approved - A & B

Contractual Start Date:


Contractual Completion Date: SHOP DRAWINGS REGISTER Under review - UR

Revise&Resubmit - C

Date of Update: 08.MAR.20 Rejected - D

Revision: 0 Internally Returned - R

Precast Fabrication Panel


Status Code
Actual Submission
S/N REE Drawing Reference No. Description Disc Trade Level Area /Zone Plan Submission Date Date Return Date Review Period Remarks
Reference No. Received Date TR Ref A B C D UR

Page 13 of 30
(CLIENT LOGO)
NEW AL MAZROUAH 300 SOLDIER BARRACKS PROLECT
(U0789)

PROJECT INFORMATION STATUS


Project Name: NEW AL MAZROUAH 300 SOLDIER BARRACKS Approved - A & B

Contractual Start Date:


Contractual Completion Date: SHOP DRAWINGS REGISTER Under review - UR

Revise&Resubmit - C

Date of Update: 08.MAR.20 Rejected - D

Revision: 0 Internally Returned - R

Precast Fabrication Panel


Status Code
Actual Submission
S/N REE Drawing Reference No. Description Disc Trade Level Area /Zone Plan Submission Date Date Return Date Review Period Remarks
Reference No. Received Date TR Ref A B C D UR

Page 14 of 30
(CLIENT LOGO)
NEW AL MAZROUAH 300 SOLDIER BARRACKS PROLECT
(U0789)

PROJECT INFORMATION STATUS


Project Name: NEW AL MAZROUAH 300 SOLDIER BARRACKS Approved - A & B

Contractual Start Date:


Contractual Completion Date: SHOP DRAWINGS REGISTER Under review - UR

Revise&Resubmit - C

Date of Update: 08.MAR.20 Rejected - D

Revision: 0 Internally Returned - R

Precast Fabrication Panel


Status Code
Actual Submission
S/N REE Drawing Reference No. Description Disc Trade Level Area /Zone Plan Submission Date Date Return Date Review Period Remarks
Reference No. Received Date TR Ref A B C D UR

Page 15 of 30
(CLIENT LOGO)
NEW AL MAZROUAH 300 SOLDIER BARRACKS PROLECT
(U0789)

PROJECT INFORMATION STATUS


Project Name: NEW AL MAZROUAH 300 SOLDIER BARRACKS Approved - A & B

Contractual Start Date:


Contractual Completion Date: SHOP DRAWINGS REGISTER Under review - UR

Revise&Resubmit - C

Date of Update: 08.MAR.20 Rejected - D

Revision: 0 Internally Returned - R

Precast Fabrication Panel


Status Code
Actual Submission
S/N REE Drawing Reference No. Description Disc Trade Level Area /Zone Plan Submission Date Date Return Date Review Period Remarks
Reference No. Received Date TR Ref A B C D UR

Page 16 of 30
(CLIENT LOGO)
NEW AL MAZROUAH 300 SOLDIER BARRACKS PROLECT
(U0789)

PROJECT INFORMATION STATUS


Project Name: NEW AL MAZROUAH 300 SOLDIER BARRACKS Approved - A & B

Contractual Start Date:


Contractual Completion Date: SHOP DRAWINGS REGISTER Under review - UR

Revise&Resubmit - C

Date of Update: 08.MAR.20 Rejected - D

Revision: 0 Internally Returned - R

Precast Fabrication Panel


Status Code
Actual Submission
S/N REE Drawing Reference No. Description Disc Trade Level Area /Zone Plan Submission Date Date Return Date Review Period Remarks
Reference No. Received Date TR Ref A B C D UR

Page 17 of 30
(CLIENT LOGO)
NEW AL MAZROUAH 300 SOLDIER BARRACKS PROLECT
(U0789)

PROJECT INFORMATION STATUS


Project Name: NEW AL MAZROUAH 300 SOLDIER BARRACKS Approved - A & B

Contractual Start Date:


Contractual Completion Date: SHOP DRAWINGS REGISTER Under review - UR

Revise&Resubmit - C

Date of Update: 08.MAR.20 Rejected - D

Revision: 0 Internally Returned - R

Precast Fabrication Panel


Status Code
Actual Submission
S/N REE Drawing Reference No. Description Disc Trade Level Area /Zone Plan Submission Date Date Return Date Review Period Remarks
Reference No. Received Date TR Ref A B C D UR

Page 18 of 30
(CLIENT LOGO)
NEW AL MAZROUAH 300 SOLDIER BARRACKS PROLECT
(U0789)

PROJECT INFORMATION STATUS


Project Name: NEW AL MAZROUAH 300 SOLDIER BARRACKS Approved - A & B

Contractual Start Date:


Contractual Completion Date: SHOP DRAWINGS REGISTER Under review - UR

Revise&Resubmit - C

Date of Update: 08.MAR.20 Rejected - D

Revision: 0 Internally Returned - R

Precast Fabrication Panel


Status Code
Actual Submission
S/N REE Drawing Reference No. Description Disc Trade Level Area /Zone Plan Submission Date Date Return Date Review Period Remarks
Reference No. Received Date TR Ref A B C D UR

Page 19 of 30
(CLIENT LOGO)
NEW AL MAZROUAH 300 SOLDIER BARRACKS PROLECT
(U0789)

PROJECT INFORMATION STATUS


Project Name: NEW AL MAZROUAH 300 SOLDIER BARRACKS Approved - A & B

Contractual Start Date:


Contractual Completion Date: SHOP DRAWINGS REGISTER Under review - UR

Revise&Resubmit - C

Date of Update: 08.MAR.20 Rejected - D

Revision: 0 Internally Returned - R

Precast Fabrication Panel


Status Code
Actual Submission
S/N REE Drawing Reference No. Description Disc Trade Level Area /Zone Plan Submission Date Date Return Date Review Period Remarks
Reference No. Received Date TR Ref A B C D UR

Page 20 of 30
(CLIENT LOGO)
NEW AL MAZROUAH 300 SOLDIER BARRACKS PROLECT
(U0789)

PROJECT INFORMATION STATUS


Project Name: NEW AL MAZROUAH 300 SOLDIER BARRACKS Approved - A & B

Contractual Start Date:


Contractual Completion Date: SHOP DRAWINGS REGISTER Under review - UR

Revise&Resubmit - C

Date of Update: 08.MAR.20 Rejected - D

Revision: 0 Internally Returned - R

Precast Fabrication Panel


Status Code
Actual Submission
S/N REE Drawing Reference No. Description Disc Trade Level Area /Zone Plan Submission Date Date Return Date Review Period Remarks
Reference No. Received Date TR Ref A B C D UR

Page 21 of 30
(CLIENT LOGO)
NEW AL MAZROUAH 300 SOLDIER BARRACKS PROLECT
(U0789)

PROJECT INFORMATION STATUS


Project Name: NEW AL MAZROUAH 300 SOLDIER BARRACKS Approved - A & B

Contractual Start Date:


Contractual Completion Date: SHOP DRAWINGS REGISTER Under review - UR

Revise&Resubmit - C

Date of Update: 08.MAR.20 Rejected - D

Revision: 0 Internally Returned - R

Precast Fabrication Panel


Status Code
Actual Submission
S/N REE Drawing Reference No. Description Disc Trade Level Area /Zone Plan Submission Date Date Return Date Review Period Remarks
Reference No. Received Date TR Ref A B C D UR

Page 22 of 30
(CLIENT LOGO)
NEW AL MAZROUAH 300 SOLDIER BARRACKS PROLECT
(U0789)

PROJECT INFORMATION STATUS


Project Name: NEW AL MAZROUAH 300 SOLDIER BARRACKS Approved - A & B

Contractual Start Date:


Contractual Completion Date: SHOP DRAWINGS REGISTER Under review - UR

Revise&Resubmit - C

Date of Update: 08.MAR.20 Rejected - D

Revision: 0 Internally Returned - R

Precast Fabrication Panel


Status Code
Actual Submission
S/N REE Drawing Reference No. Description Disc Trade Level Area /Zone Plan Submission Date Date Return Date Review Period Remarks
Reference No. Received Date TR Ref A B C D UR

45

45

45

45

45

45

Page 23 of 30
CONSULTANT : GHD
MAIN CONTRACTOR : UCC
ELECTRICAL SHOP DRAWING SUMMARY CLIENT: PRIVATE ENGINEERING OFFICE

FOR P1 FORMAL MAJLIS & DAILY PROJECT NAME & NO : DESIGN AND BUILD LUSAIL PALACE
MEP CONTRACTOR : RADIANT ENGINEERING ENTERPRISES
Last Update : 11-Mar-20

Code A Code B Code C Code D Code UR


Item (per Sheet) (per Sheet) (per Sheet) (per Sheet) Code E (per Sheet)
Total No Actual Drawings Balance from 1st Balance from Remarks for Balance 1st submission
System Description Drawings Submitted Submission ReSubmission Drawings
Approved as
No Approved Noted Revise & Resubmit Rejected UCC Return Under Review

Drwg No. % No. % No. % No. % No. % No. % No. % No. % No. % Expected date of Completion

1 Earthing & Lighting Protection Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508

2 Lighting Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508

3 Power Containment Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508

4 Small Power Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508

5 Electrical Details (DB, ELE Room & Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508
SLD)

6 Fire Alarm Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508

TOTAL ELECTRICAL : Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508

TOTAL MECHANICAL: #REF! Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 #REF! #REF! Err:504 Err:504

TOTAL CO &BW: #REF! Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 #REF! #REF! Err:504 Err:504

OVER ALL TOTAL : Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508

Prepared by: oliver


CONSULTANT : DAR
MAIN CONTRACTOR : UCC

MECHANICAL SHOP DRAWING SUMMARY CLIENT: PRIVATE ENGINEERING OFFICE

FOR P1 FORMAL MAJLIS & DAILY PROJECT NAME & NO : DESIGN AND BUILD LUSAIL PALACE
MEP CONTRACTOR : RADIANT ENGG. ENT.
Last Update : 11-Mar-20

Item Code A Code B Code C Code D Code E Code UR


Total No Actual Drawings (per Sheet) (per Sheet) (per Sheet) (per Sheet) (per Sheet) Balance from 1st Balance from Remarks for Balance 1st submission
System Description
Drawings Submitted Submission ReSubmission Drawings
No Approved Approved as Revise & Resubmit Rejected UCC Return Under Review
Noted
Drwg No. % No. % No. % No. % No. % No. % No. % No. % No. % Expected date of Completion

1 HVAC #REF! Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 #REF! #REF! Err:504 Err:504

2 FIRE FIGHTING #REF! Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 #REF! #REF! Err:504 Err:504

3 DRAINAGE #REF! Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 #REF! #REF! Err:504 Err:504

4 WATER SUPPLY #REF! Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 #REF! #REF! Err:504 Err:504

5 CHILLED WATER SUPPLY #REF! Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 #REF! #REF! Err:504 Err:504

6 MECHANICAL DETAILS #REF! Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 #REF! #REF! Err:504 Err:504

TOTAL MECHANICAL: #REF! Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 #REF! #REF! Err:504 Err:504

TOTAL ELECTRICAL : Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508

TOTAL CO &BW: #REF! Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 #REF! #REF! Err:504 Err:504

OVER ALL TOTAL : #REF! Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 #REF! #REF! Err:504 Err:504

Prepared by:Oliver
CONSULTANT : DAR
MAIN CONTRACTOR : UCC

COORDINATION / BUILDERS WORK DRAWING SUMMARY CLIENT: PRIVATE ENGINEERING OFFICE

FOR P1 FORMAL MAJLIS & DAILY PROJECT NAME & NO : DESIGN AND BUILD LUSAIL PALACE
MEP CONTRACTOR : RADIANT ENGG. ENT.
Last Update : 11-Mar-20

Item Code A Code B Code C Code D Code E Code UR


Total No Actual Drawings (per Sheet) (per Sheet) (per Sheet) (per Sheet) (per Sheet) Balance from 1st Balance from Remarks for Balance 1st submission
System Description
Drawings Submitted Submission ReSubmission Drawings
No Approved Approved as Revise & Resubmit Rejected UCC Return Under Review
Noted
Drwg No. % No. % No. % No. % No. % No. % No. % No. % No. % Expected date of Completion

1 MEP BUILDERS WORK #REF! Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 #REF! #REF! Err:504 Err:504

2 MEP COORDINATION DRAWING #REF! Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 #REF! #REF! Err:504 Err:504

TOTAL CO & BW: #REF! Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 #REF! #REF! Err:504 Err:504

TOTAL ELECTRICAL : Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508

TOTAL MECHANICAL : #REF! Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 #REF! #REF! Err:504 Err:504

OVER ALL TOTAL : #REF! Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 #REF! #REF! Err:504 Err:504

Prepared by:Oliver
CONSULTANT : DAR
MAIN CONTRACTOR : UCC

MECHANICAL SHOP DRAWING SUMMARY CLIENT: PRIVATE ENGINEERING OFFICE

FOR P1 - MOSQUE & GUEST HOUSE PROJECT NAME & NO : DESIGN AND BUILD LUSAIL PALACE
MEP CONTRACTOR : RADIANT ENGG. ENT.
Last Update : 11-Mar-20

Code A Code B Code C Code D Code UR


Item (per Sheet) (per Sheet) (per Sheet) (per Sheet) Code E (per Sheet)
System Description Total No Actual Drawings Balance from 1st Balance from Remarks for Balance 1st submission
Drawings Submitted Submission ReSubmission Drawings
No Approved Approved as Noted Revise & Resubmit Rejected UCC Return Under Review

Drwg No. % No. % No. % No. % No. % No. % No. % No. % No. % Expected date of Completion

1 HVAC #REF! Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 #REF! #REF! Err:504 Err:504

2 FIRE FIGHTING #REF! Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 #REF! #REF! Err:504 Err:504

3 DRAINAGE #REF! Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 #REF! #REF! Err:504 Err:504

4 WATER SUPPLY #REF! Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 #REF! #REF! Err:504 Err:504

5 CHILLED WATER SUPPLY #REF! Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 #REF! #REF! Err:504 Err:504

6 MECHANICAL DETAILS #REF! Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 #REF! #REF! Err:504 Err:504

TOTAL Mosque & Guest House


MECHANICAL: #REF! Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 #REF! #REF! Err:504 Err:504

CONSULTANT : DAR
MAIN CONTRACTOR : UCC

ELECTRICAL SHOP DRAWING SUMMARY CLIENT: PRIVATE ENGINEERING OFFICE

FOR P1 - MOSQUE & GUEST HOUSE PROJECT NAME & NO : DESIGN AND BUILD LUSAIL PALACE
MEP CONTRACTOR : RADIANT ENGG. ENT.
Last Update : 11-Mar-20

Code A Code B Code C Code D Code UR


Item (per Sheet) (per Sheet) (per Sheet) (per Sheet) Code E (per Sheet)
System Description Total No Actual Drawings Balance from 1st Balance from Remarks for Balance 1st submission
Drawings Submitted Submission ReSubmission Drawings
No Approved Approved as Noted Revise & Resubmit Rejected UCC Return Under Review

Drwg No. % No. % No. % No. % No. % No. % No. % No. % No. % Expected date of Completion

1 Earthing & Lighting Protection #REF! Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 #REF! #REF! Err:504 Err:504

2 Lighting #REF! Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 #REF! #REF! Err:504 Err:504

3 Power Containment #REF! Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 #REF! #REF! Err:504 Err:504

4 Small Power #REF! Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 #REF! #REF! Err:504 Err:504

5 Electrical Details (DB, ELE Room & SLD) #REF! Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 #REF! #REF! Err:504 Err:504

6 Fire Alarm #REF! Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 #REF! #REF! Err:504 Err:504

TOTAL Mosque & Guest House ELECTRICAL: #REF! Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 #REF! #REF! Err:504 Err:504

Prepared by:Oliver
COORDINATION / BUILDERS WORK DRAWING SUMMARY FOR P1 FORMAL
ELECTRICAL SHOP DRAWING SUMMARY FOR P1 FORMAL MAJLIS & DAILY CONSULTANT :
MAJLIS & DAILY
MAIN CONTRACTOR :
CLIENT:
SHOP DRAWING SUMMARY PROJECT NAME & NO :
MEP CONTRACTOR :
Last Update :

Code A Code B Code C Code D Code UR


Item
Total (per Sheet) (per Sheet) (per Sheet) (per Sheet) Code R (per Sheet) Balance from 1st Balance from
System Description Actual Submitted Remarks
Drawings Submission ReSubmission
No Approved Approved as Noted Revise & Resubmit Rejected UCC Return Under Review
Drwg No. % No. % No. % No. % No. % No. % No. % No. % No. %

1 ELECTRICAL #REF! Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 #REF! #REF! Err:504 Err:504

2 HVAC #REF! Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 #REF! #REF! Err:504 Err:504

3 PLUMBING #REF! Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 #REF! #REF! Err:504 Err:504

4 FIRE FIGHTING Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508

TOTAL #REF! Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 Err:504 #REF! #REF! Err:504 Err:504

Page 28 of 30
LP-P1 - SHOP DRAWING REVISED PLAN SUBMISSION - 4-DEC-18

Total
S.no Drawings Total Submitted 15-Dec-18 31-Dec-18 15-Jan-19 31-Jan-19 15-Feb-19 28-Feb-19 15-Mar-19 30-Mar-19 Total Sheets
Sheets

1 Earthing & Lighting Protection 8 0 - 2 2 4 - - - - 8

2 Lighting 36 24 - 7 2 1 - 2 - - 36

3 Power Containment 40 20 - 9 4 0 2 5 40

4 Small Power 34 21 - 5 4 4 34

5 Electrical Details (DB, ELE Room & SLD) 6 6 - - - - - - - - 6

6 Fire Alarm 34 0 4 9 9 5 7 - - - 34

7 HVAC 64 10 4 6 6 11 13 12 2 - 64

8 FIRE FIGHTING 46 8 1 12 11 8 6 - - - 46

9 DRAINAGE 50 24 3 3 16 4 - - - - 50

10 WATER SUPPLY 48 11 1 5 4 5 13 9 - - 48

11 CHILLED WATER SUPPLY 43 8 7 5 4 7 5 7 - - 43

12 MECHANICAL DETAILS 25 0 0 2 16 7 - - - - 25

13 MEP BUILDERS WORK 89 34 0 4 5 16 16 14 89

14 MEP COORDINATION DRAWING 54 0 2 9 10 13 7 10 3 54

Total 453 95 22 55 81 76 67 52 5 0 453


LUSAIL PALACE - (PACKAGE 1)

SHOP DRAWINGS SUBMITTAL REGISTER FOR FORMAL MAJILIS & DAILY MAJLIS

MECHANICAL WORK
CONSULTANT : GHD Discipline : MECHANICAL
MAIN CONTRACTOR : UCC Run Date : 11-Mar-20
MEP CONTRACTOR : RADIANT ENGINEERING ENTERPRISES Revision : 0
Action By Status Code
S/N REE Drawing Ref No. Drawing Description Latest Packag Level Disc Trade/ Area /Zone Plan date Actual Date Plan Date Actual Date Latest Status Remarks
Rev. e No. Type submission Draftsman Submission Approvals Return A B C D UR

1 LP-UCC-REE-P1-FM-GN-SD-1B-BW-0003 1 OF 10 BASEMENT FLOOR SLAB MEP BUILDERS WORK LAYOUT OVER ALL SHEET 1 OF 10 P1 1B MEP BW FM Not Submitted

2 LP-UCC-REE-P1-FM-GN-SD-1B-BW-0003 2 OF 10 BASEMENT FLOOR SLAB MEP BUILDERS WORK LAYOUT SHEET 2 OF 10 P1 1B MEP BW FM Not Submitted

3 LP-UCC-REE-P1-FM-GN-SD-1B-BW-0003 3 OF 10 BASEMENT FLOOR SLAB MEP BUILDERS WORK LAYOUT SHEET 3 OF 10 P1 1B MEP BW FM Not Submitted

4 LP-UCC-REE-P1-FM-GN-SD-1B-BW-0003 4 OF 10 BASEMENT FLOOR SLAB MEP BUILDERS WORK LAYOUT SHEET 4 OF 10 P1 1B MEP BW FM Not Submitted

5 LP-UCC-REE-P1-FM-GN-SD-1B-BW-0003 5 OF 10 BASEMENT FLOOR SLAB MEP BUILDERS WORK LAYOUT SHEET 5 OF 10 P1 1B MEP BW FM Not Submitted

6 LP-UCC-REE-P1-FM-GN-SD-1B-BW-0003 6 OF 10 BASEMENT FLOOR SLAB MEP BUILDERS WORK LAYOUT SHEET 6 OF 10 P1 1B MEP BW FM Not Submitted

7 LP-UCC-REE-P1-FM-GN-SD-1B-BW-0003 7 OF 10 BASEMENT FLOOR SLAB MEP BUILDERS WORK LAYOUT SHEET 7 OF 10 P1 1B MEP BW FM Not Submitted

8 LP-UCC-REE-P1-FM-GN-SD-1B-BW-0003 8 OF 10 BASEMENT FLOOR SLAB MEP BUILDERS WORK LAYOUT SHEET 8 OF 10 P1 1B MEP BW FM Not Submitted

9 LP-UCC-REE-P1-FM-GN-SD-1B-BW-0003 9 OF 10 BASEMENT FLOOR SLAB MEP BUILDERS WORK LAYOUT SHEET 9 OF 10 P1 1B MEP BW FM Not Submitted

10 LP-UCC-REE-P1-FM-GN-SD-1B-BW-0003 10 OF 10 BASEMENT FLOOR SLAB MEP BUILDERS WORK LAYOUT SHEET 10 OF 10 P1 1B MEP BW FM Not Submitted

11 LP-UCC-REE-P1-FM-GN-SD-GF-BW-0004 1 OF 10 GROUND FLOOR SLAB MEP BUILDERS WORK LAYOUT OVER ALL LAYOUT SHEET 1 OF 10 P1 GF MEP BW FM 22-Nov-18 Not Submitted

12 LP-UCC-REE-P1-FM-GN-SD-GF-BW-0004 2 OF 10 GROUND FLOOR SLAB MEP BUILDERS WORK LAYOUT SHEET 2 OF 10 P1 GF MEP BW FM 24-Nov-18 Not Submitted

13 LP-UCC-REE-P1-FM-GN-SD-GF-BW-0004 3 OF 10 GROUND FLOOR SLAB MEP BUILDERS WORK LAYOUT SHEET 3 OF 10 P1 GF MEP BW FM 26-Nov-18 Not Submitted

14 LP-UCC-REE-P1-FM-GN-SD-GF-BW-0004 4 OF 10 GROUND FLOOR SLAB MEP BUILDERS WORK LAYOUT SHEET 4 OF 10 P1 GF MEP BW FM 28-Nov-18 Not Submitted

15 LP-UCC-REE-P1-FM-GN-SD-GF-BW-0004 5 OF 10 GROUND FLOOR SLAB MEP BUILDERS WORK LAYOUT SHEET 5 OF 10 P1 GF MEP BW FM 30-Nov-18 Not Submitted

16 LP-UCC-REE-P1-FM-GN-SD-GF-BW-0004 6 OF 10 GROUND FLOOR SLAB MEP BUILDERS WORK LAYOUT SHEET 6 OF 10 P1 GF MEP BW FM 2-Dec-18 Not Submitted

17 LP-UCC-REE-P1-FM-GN-SD-GF-BW-0004 7 OF 10 GROUND FLOOR SLAB MEP BUILDERS WORK LAYOUT SHEET 7 OF 10 P1 GF MEP BW FM 4-Dec-18 Not Submitted

18 LP-UCC-REE-P1-FM-GN-SD-GF-BW-0004 8 OF 10 GROUND FLOOR SLAB MEP BUILDERS WORK LAYOUT SHEET 8 OF 10 P1 GF MEP BW FM 6-Dec-18 Not Submitted

19 LP-UCC-REE-P1-FM-GN-SD-GF-BW-0004 9 OF 10 GROUND FLOOR SLAB MEP BUILDERS WORK LAYOUT SHEET 9 OF 10 P1 GF MEP BW FM 8-Dec-18 Not Submitted

20 LP-UCC-REE-P1-FM-GN-SD-GF-BW-0004 10 OF 10 GROUND FLOOR SLAB MEP BUILDERS WORK LAYOUT SHEET 10 OF 10 P1 GF MEP BW FM 10-Dec-18 Not Submitted

21 LP-UCC-REE-P1-FM-GN-SD-1B-BW-0006 1 OF 10 BASEMENT FLOOR BLOCK WALL MEP BUILDERS WORK OVER ALL LAYOUT SHEET 1 OF 10 P1 1B MEP BW FM 30-Dec-18 Not Submitted

22 LP-UCC-REE-P1-FM-GN-SD-1B-BW-0006 2 OF 10 BASEMENT FLOOR BLOCK WALL MEP BUILDERS WORK LAYOUT SHEET 2 OF 10 P1 1B MEP BW FM 1-Jan-19 Not Submitted

23 LP-UCC-REE-P1-FM-GN-SD-1B-BW-0006 3 OF 10 BASEMENT FLOOR BLOCK WALL MEP BUILDERS WORK LAYOUT SHEET 3 OF 10 P1 1B MEP BW FM 3-Jan-19 Not Submitted

24 LP-UCC-REE-P1-FM-GN-SD-1B-BW-0006 4 OF 10 BASEMENT FLOOR BLOCK WALL MEP BUILDERS WORK LAYOUT SHEET 4 OF 10 P1 1B MEP BW FM 5-Jan-19 Not Submitted

25 LP-UCC-REE-P1-FM-GN-SD-1B-BW-0006 5 OF 10 BASEMENT FLOOR BLOCK WALL MEP BUILDERS WORK LAYOUT SHEET 5 OF 10 P1 1B MEP BW FM 7-Jan-19 Not Submitted

26 LP-UCC-REE-P1-FM-GN-SD-1B-BW-0006 6 OF 10 BASEMENT FLOOR BLOCK WALL MEP BUILDERS WORK LAYOUT SHEET 6 OF 10 P1 1B MEP BW FM 9-Jan-19 Not Submitted

27 LP-UCC-REE-P1-FM-GN-SD-1B-BW-0006 7 OF 10 BASEMENT FLOOR BLOCK WALL MEP BUILDERS WORK LAYOUT SHEET 7 OF 10 P1 1B MEP BW FM 11-Jan-19 Not Submitted

28 LP-UCC-REE-P1-FM-GN-SD-1B-BW-0006 8 OF 10 BASEMENT FLOOR BLOCK WALL MEP BUILDERS WORK LAYOUT SHEET 8 OF 10 P1 1B MEP BW FM 13-Jan-19 Not Submitted

29 LP-UCC-REE-P1-FM-GN-SD-1B-BW-0006 9 OF 10 BASEMENT FLOOR BLOCK WALL MEP BUILDERS WORK LAYOUT SHEET 9 OF 10 P1 1B MEP BW FM 15-Jan-19 29-Jan-19 Not Submitted

30 LP-UCC-REE-P1-FM-GN-SD-1B-BW-0006 10 OF 10 BASEMENT FLOOR BLOCK WALL MEP BUILDERS WORK LAYOUT SHEET 10 OF 10 P1 1B MEP BW FM 17-Jan-19 31-Jan-19 Not Submitted

Page 30 of 30