RENCANA ANGGARAN BIAYA ( RAB )

HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT.
SATUAN HARGA
( Rp. ) ( Rp. )
1 2 3 4 5 6

A LAPANGAN TENIS
1 Penambahan cor 7cm 29.89 m3 750,000.00 22,417,500.00
2 Penambahan cor 17cm 29.08 m2 750,000.00 21,810,000.00
3 Floor Hardener 598.40 m2 60,000.00 35,904,000.00
4 Net jaring 1.00 bh 1,000,000.00 1,000,000.00
5 Cat 598.40 m2 35,000.00 20,944,000.00
JUMLAH 102,075,500.00
B LAPANGAN FUTSAL
1 Penambahan Cor 10cm 18.49 m3 750,000.00 13,867,500.00
2 Laveling 427.00 m2 50,000.00 21,350,000.00
3 Cat 612.00 m2 35,000.00 21,420,000.00
4 Gawang 2.00 bh 5,000,000.00 10,000,000.00
JUMLAH 66,637,500.00
JUMLAH TOTAL 168,713,000.00