Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

TEST METHOD WA 312.

1 – 2016

BALL EMBEDMENT

1 SCOPE (c) Rest the base of the standard hammer on the ball
and apply one blow of the falling weight. Remove the
This method describes the procedure for determining hammer and ball.
the embedment of a standard ball under the impact of a
standard load into a road surface which is to be treated (d) Repeat Procedures 4 (b) and 4 (c) at another nine
with a bitumen seal coat. locations within the sample site.

2 SAFETY (e) Zero the cumulative dial gauge or digital


embedment meter.
This method does not attempt to address all of the
safety concerns, if any, associated with its use. It is the (f) Place the cumulative dial gauge or digital
responsibility of the user of this method to establish embedment meter so that its feet are situated
appropriate occupational health and safety practices approximately evenly around a ball indentation.
that meet statutory regulations. Register the depth of embedment to the nearest 0.01
mm.
3 APPARATUS
NOTE: The indentations in the road surface should not
(a) Standard Marshall compaction hammer, or be subjected to traffic flow before the depth of
standard imperial heavy soils compaction hammer embedment is registered.
(sliding mass 4.535 ± 0.020 kg, 457 ± 1 mm free fall).
(g) Repeat Procedure 4 (f) at the remaining nine ball
(b) A 19 mm ball (steel ball bearing of diameter 19.00 indentations to obtain a cumulative depth of
± 0.05 mm). embedment.

NOTE: The steel ball bearing may be welded to the (h) Determine the average ball embedment using
standard compaction hammer for use in Procedure 4.1 Procedure 4 (h) (i) for the cumulative dial gauge or
(c) provided the sliding hammer mass is adjusted Procedure 4 (h) (ii) for the digital embedment meter.
accordingly. The ball bearing should be measured
regularly for wear on its lower hemisphere. (i) Record the total accumulated depth of
embedment from the 10 locations. Divide the total
(c) Thermometer with a range of approximately 0° C by 10 to obtain the average ball embedment for the
to 100° C, readable to at least 0.5° C. sample site.

(d) Cumulative dial gauge or digital embedment (ii) Obtain a printout of the data from the 10
meter (50 mm travel in 0.01 mm units). locations. The average ball embedment for the
sample site will be shown on the printout. Identify
4 PROCEDURE the sample site of road tested on the printout and
attach the printout to the worksheet.
(a) Select a sample site typical of the road surface to
be sealed. (i) Record the average ball embedment (E) to the
nearest 0.01 mm.
NOTES:
(j) Record the temperature of the road surface (T)
i. Embedment tests should normally be carried out in within the sample site to the nearest 0.5°C.
the wheel path as seal design is based on this
measurement. Testing may be carried out between 5 CALCULATIONS
wheel paths however these results should be
considered to represent a different lot and should not (a) Determine the standard summer road surface
be combined with wheel path results but reported temperature (Ts) of the sample site using Figure 1.
separately.
Where the sample site lies between median values
ii. A sample site would typically be no more than 2 m shown in Figure 1 determine the summer road surface
in length. temperature by linear interpolation.
Page 1 of 4

(b) Site the ball within the sample site. NOTE: Linear interpolation is achieved by scaling
between the median value lines shown in Figure 1.

MAIN ROADS Western Australia Document 71/04/312.1 Issue Date: 02 November 2016
D16#693144
TEST METHOD WA 312.1 – 2016

(b) Determine an appropriate temperature


susceptibility of penetration (K) for the sample site
using the criteria shown below:

• Finished Basecourse 0.00 mm/°C

• Single and multiple seal (not fatty) 0.04 mm/°C

• Primed surfaces (not fatty) 0.06 mm/°C

• Fatty roads and premix surfacing 0.08 mm/°C

(c) Correct the average ball embedment of the road


surface at the temperature of test to the standard
summer temperature for the sample site using the
following formula:

𝐸𝑠 = 𝐸 − 𝐾(𝑇 − 𝑇𝑠 )

Where:

𝐸𝑠 = embedment depth at standard summer road


surface temperature (mm).

𝐸 = average embedment depth at the time of test


(mm).

K = temperature susceptibility of penetration


(mm/°C).

T = temperature of the road surface at the time of test


(°C).

Ts = standard summer road surface temperature of


sample site (°C).

6 REPORTING

Report Es for each sample site to the nearest 0.1 mm


and record whether the measurements were carried
out in or between the wheel paths.

Page 2 of 4

MAIN ROADS Western Australia Document 71/04/312.1 Issue Date: 02 November 2016
D16#693144
TEST METHOD WA 312.1 – 2016

7 FIGURES AND DRAWINGS

Page 3 of 4

SUGGESTED MAXIMUM ROAD TEMPERATURES


IN DEGREES CELSIUS
FIGURE 1

MAIN ROADS Western Australia Document 71/04/312.1 Issue Date: 02 November 2016
D16#693144
TEST METHOD WA 312.1 – 2016
8 ISSUING AUTHORITY

Document Owner Delegated Custodian

Manager Materials Engineering Pavements Manager

9 REVISION STATUS RECORD

Revision
Page No. Section
Description / Reference

All All Format Revision and Re-issue of Test Method

2 5 (b) Updated for Primed Surfaces and Finished Basecourse

Page 4 of 4

MAIN ROADS Western Australia Document 71/04/312.1 Issue Date: 02 November 2016
D16#693144

You might also like