PTGGP-00-PL-CAL-004 - 0 Pipeline Buoyancy and Stability Calculation Grissik-Pusri
PTGGP-00-PL-CAL-004 - 0 Pipeline Buoyancy and Stability Calculation Grissik-Pusri
NO part of this document may be reproduced, in any form or by any means, except as permitted by
PT. PERTAMINA GAS
FRONT END ENGINEERING DESIGN (FEED)
PEMBANGUNAN PIPA GAS
GRISSIK-PUSRI
Lembar Revisi
COMMENT SHEET
Komentar
No. Referensi / Paragraf / Kalimat Catatan
PT. Pertamina Gas
1 3.2 Definition Revise Definition Revised
3 Attachment Revised
DAFTAR ISI
1. PROJECT OVERVIEW .................................................................................................... 5
2. OBJECTIVES ................................................................................................................... 6
3. MEASUREMENT UNITS, DEFINITIONS AND ABBREVIATIONS .................................... 6
3.1. Measurement Units................................................................................................ 6
6. METHODOLOGY ........................................................................................................... 10
6.1. Minimum SG ........................................................................................................ 10
ATTACHMENT ...................................................................................................................... 13
FRONT END ENGINEERING DESIGN (FEED)
PEMBANGUNAN PIPA GAS
GRISSIK-PUSRI
1. PROJECT OVERVIEW
PT Pertamina Gas (Pertagas) plans to build new pipelines to support the plan of
distribution of gas for fertilizer, where the pipeline will deliver gas sourced from Grissik
Processing Plant heading to PUSRI Plant at Palembang.
A pig launcher will install in ConocoPhillips area and power source will provide via solar-
cell. This pig launcher will design for intelligent pig. Liquid drain from pig launcher will be
collected using dedicated portable drum. Nitrogen system will provided to operate SDV
and fusible plug for fire detection. Venting will be directed to Jambi-Merang facilities,
which will be EPCI scope of work. Drains will be disposed periodically by vacuum truck.
The project location is the construction site of the new gas pipeline. Pictures of these
locations can be seen on the following map. Pipeline planned through 3 (three) route, i.e.
Right of Way (ROW) ConocoPhillips, ROW PERTAGAS and ROW Jalan Raya
Palembang-Jambi. About 70 MMSCFD gas will transfered 171 km via 20” pipeline and
LBCV will be installed along this pipeline. Nitrogen from bottle also used for SDV and
fusible plug at this area. Pipeline will protected from corrosion with cathodic protection.
Outside the fence of Pusri area there will constructed receiving facilities that consist of
Pig Receiever, Slug Catcher and Gas Metering (ultrasonic type) and Instrument Air
System. Drain from the receiving facility will be disposed periodically by vacuum truck.
Venting from this facility will be routed to safe area. The required of electrical power will
be supplied from PT PUSRI fertilizer plant.
2. OBJECTIVES
The objectives of this document is to calculate pipeline stability and buoyancy for 20”
Onshore Gas Pipeline API 5L – X65 from Grissik to Pusri, to ensure negative buoyancy
in swampy areas.
3.2. Definitions
3.3. Abbreviations
AFC Approved For Construction
API American Petroleum Institute
BOPD Barrels of Oil Per Day
BPD Barrels Per Day
BWPD Barrels Water Per Day
CV Curriculum Vitae
°C Celcius degree
EPC Engineering, Procurement and Construction
DSS Design Submission Schedule
°F Fahrenheit degree
FRONT END ENGINEERING DESIGN (FEED)
PEMBANGUNAN PIPA GAS
GRISSIK-PUSRI
All Work shall be performed in accordance with the following order of precedence of
the following codes and standards:
Any latest amendments / new additions to the standard and regulation shall be
incorporated.
6. METHODOLOGY
6.1. Minimum SG
A pipeline located in submerged or swampy areas shall have a specific gravity
(SG) that is higher than that of the surrounding water or fluidic soil (mud). The
submerged pipe SG is calculated by the following equation.
FRONT END ENGINEERING DESIGN (FEED)
PEMBANGUNAN PIPA GAS
GRISSIK-PUSRI
𝑊𝑝
𝑆𝐺 =
𝐹𝑠
where:
Fb = buoyancy (N/m)
6.3. Assumptions
The assumptions made during calculation are:
1. Pipeline sinking settlement is considered unlikely.
2. Field joint coating for corrosion coating is to be the same as the mill coating itself.
FRONT END ENGINEERING DESIGN (FEED)
PEMBANGUNAN PIPA GAS
GRISSIK-PUSRI
ATTACHMENT
Calculation Result
CLIENT : PT Pertagas BY: BYN
i := 0 .. 1
ρg :=
i Length per Joint Lp := 12.2m
Pipe content density
(CASE 1 Empty) −3
0kg⋅ m Concrete Cut-back Lcb := 300mm
Pipe content density −3
29.17kg⋅ m
(CASE 2 Gas)
−3
1000kg⋅ m
−3
1000kg⋅ m
3.0 Calculation
1 of 2
Lp − 2 ⋅ Lcb
wcon tcon , i := ⋅ ODtotal tcon ...
π 2
Concrete coating weight ( 4
) ( ) ⋅ ρconi⋅ g ⋅ Lp
+ − OD + 2 ⋅ t + t 2
cor ins ( )
π 2
Weight of content wg := ⋅ ID ⋅ ρg ⋅ g wg =
i 4 i i
N
0 ⋅
m
50.956
π ⋅ ρ ⋅ g⋅ OD 2
Buoyancy (
FL tcon , i := ) 4 f i ( total( tcon) ) (
FL tcon , i = )
N
2.035·103 ⋅
m
2.035·103
Required weight ( ) (
wreq tcon , i := SG⋅ FL tcon , i − wdown tcon , i ) ( ) (
wreq tcon , i = )
N
305.852 ⋅
m
254.895
−1
Weight required check wchk :=
i
(
"YES" if wreq tcon , i > 0N⋅ m )
"NO" otherwise
Given
(
wdown tcon , i )
SG = tcn( i) := Find tcon ( )
(
FL tcon , i )
−1
tc :=
i
(
"NO" if wreq tcon , i < 0N⋅ m )
tcn( i) otherwise
Total Download Weight Total Buoyancy with
with Concrete Concrete (Uplift)
(
wp tcn( i) , i + wg )
SGfinal( i) :=
i ( )
wp tcn( i) , i + wg =
i (
FL tcn( i) , i = )
(
FL tcn( i) , i ) N N
2.426·103 ⋅ 2.205·103 ⋅
m m
2.395·103 2.177·103
4.0 Result
Additional weight required: Concrete coating thickness required: SG using concrete thickness :
SGfinal( i) =
"YES" 10.55 1.1
wchk = tc = ⋅ mm
"YES" 8.82 1.1
2 of 2