Professional Documents
Culture Documents
43) API 653 Day 6 Book (1 To 96) Indo
43) API 653 Day 6 Book (1 To 96) Indo
b. ± 4 inches
c. ± 1/8 inch
d. Inspector’s experience
10. 4 step UT thk Gage standardization bloclk has got thk steps____
a. 0.1, 02,03 & 0.4 inch
b. 10,20,40,40 mm
c. 0.25,0.50,0.75, 1 inch
d. Only 4 mm thk Disk
12. During calibration of an ammeter the unit shall not deviate by more than
________ of full scale.
a. 10%
b. 20%
c. 30%
d. 40%
15. During an internal inspection of a tank, pitting that measure 0.30 inches
deep was found in the shell (0.625 Thickness). The required thickness of the
shell in this area is 0.56 inches. Based on the above information should a
repair be made?
a. Yes
b. No
c. The inspector option
d. Repair contractor’s option
An inspection is performed on an AST 24’ tall, 22’ fill height, 94’ diameter, water
storage service, earth foundation. There is one area of general internal corrosion
on the south side of the shell 20” wide and 20” in vertical length. There is
evidence of bottom settlement.
16. Calculate the minimum thickness of the first course based on product alone.
a. 1.175”
b. 0.228”
c. 0.551”
d. 0.218”
17. Tank fill height 22’ & dia 94’ and material unknown Calculate the minimum
thickness for the third course, if each course is 4’ in height.
a. .122”
b. .100”
c. .275”
d. .132”
18. Tank fill height 22’ & dia 94’ and material unknown Calculate the “L” length
for an area of general corrosion found 10’ from the bottom on the south side
of the shell, T2=.125”.
a. 40”
b. 12.68”
c. 6.80”
d. 11.75”
19. Tank fill height 22’ & dia 94’ and material unknown There are three pits
aligned vertically on the north side of the tank, in the first course. The
diameter of the pits are 1.250”, 1”, and .500” in length along a vertical line 8”
long. Note: Assume pit depth of slightly less than one-half of the minimum
acceptable tank shell thickness, exclusive of the corrosion allowance.
a. Because the pits are aligned vertically no repair is required
b. Scattered pits may be ignored
c. If the pit is round, it may be ignored
d. A repair is required
20. Tank fill height 22’ & dia 94’ and material unknown Three circumferentially
scattered pits are located on the west side of the tank 18” from the bottom.
The pits measure 1.500”, .477” and .732” in diameter. Note: Assume pit
depth of one-half of the minimum acceptable tank shell thickness, exclusive
of the corrosion allowance.
a. Because the pits are scattered circumferentially no repair is required
b. All pits may be ignored
c. If the pit is round, it may be ignored
d. A repair is required
21. Tank fill height 22’ & dia 94’ and material unknown A bulge is found on the
tank floor, the diameter of the bulge is 36”. What is the maximum
permissible height for the bulge?
a. 11.1”
b. .555”
c. .962”
d. 1.11”
22. Tank fill height 22’ & dia 94’ and material unknown There was a bulge for 6 ‘
radius of inscribed circle and if the actual bulge measured is 2 inch, what is
your opinion
a. A more rigorous stress analysis must be performed
b. The area should be repaired
c. Sloped edge settlement is usually no problem
d. The area should be documented and checked during the next inspection.
23. What is the hydrostatic test height of this Tank (with fill height 22’ & dia 94’
and material unknown) based on a minimum thickness of 0.218 inch , as the
controlling thickness?
a. 24’
b. 34.2’
c. 18.6’
d. 21.9’
24. Tank fill height 22’ & dia 94’ and material unknown A depression is noted on
a section of the bottom near the middle of the east quadrant. The
depression measures 5/8” deep, with a diameter of 36 inches. Should a
repair be recommended?
a. Yes
b. No
c. Not enough information given
d. The tank holds water, no problem
25. Tank fill height 22’ & dia 94’ and material unknown If the liquid level in the
tank were to be lowered by 5’ what is the minimum thickness of the first
course?
a. 1.73”
b. .168”
c. .200”
d. No change from original design thickness
26. Using the data Or =10 year, , RTbc= 0.2 inch, RTup= 0.190 inch ,
StPr= .002 inch, UPr = .010 inch calculate (metal loss from the bottom side
corrosion).
a. .250
b. .070
c. .002
d. .10
27. Using the data, Or =10 year, , RTbc= 0.2 inch, RTup= 0.190 inch ,
StPr= .002 inch, UPr = .010 inch calculate minimum remaining thk
a. .250
b. .070
c. .002
d. .080
28. The weld ripples of reinforcement of butt-welded joints shall be _____ before
radiography.
a. Removed
b. Ground flush, with grinding direction parallel to the weld
c. Ground flush, with grinding direction perpendicular to the weld
d. Removed if irregularities mask discontinuities
29. What is the hydrostatic test height of an in-service welded AST built to API
650, 8th Edition, 82’ diameter, 40’ tall with a minimum first course thickness
of 0.197”. The material of construction is A-516, Grade 70 (A 516M Grade
485).
a. 40’
b. 36’ – 2”
c. 32’ – 8”
d. 31’ – 6”
30. For a single-wall material thickness, over 0.375” through 0.50”, what is the
hole-type designation for a source side penetrameter?
a. 15
b. 17
c. 20
d. 25
35. A new tank will hold a product with the specific gravity of 1.05; The
corrosion allowance is.10; The thickness of the first course is 1.25 inches;
Hydrostatic test stress 25,000 PSI. What is the thickness required for the
annular plate? (Note: Include corrosion allowance).
a. 5/16”
b. 11/16”
c. 3/8”
d. 7/16”
36. A leak is noted 1-1/2” away from the shell-to-bottom weld in the floor of an
existing welded tank. The hole in the floor is 4” in diameter. What type of
repair, in compliance with API 653, 3rd Edition, should be made?
a. Use RBI. Because the product might not contaminate the soil or waterways,
no repair is required.
b. Weld build-up the area.
c. Install a ‘tombstone’ shaped, welded-on patch plate, intersecting the shell-to-
bottom joint at approximately 90º.
d. Install a non-welded patch plate and fiberglass/epoxy to coat the area.
37. A welder was Qualified to weld in accordance with one Qualified WPS. Is he
qualified to weld other qualified wps
a. Yes, Since all are qualified APS, Welder can weld other qualified WPS
b. No,he canot weld other qualified WPS
c. Yes he can weld other qualified WPS also if the welding process is the same
and within the limits of EV as QW 350
d. IF in the Certified welding inspector’s opinion, he is ok, The welder can do it
38. During a welder qualification test, for plate coupons, all surfaces (except
areas designated “discard”) shall _________.
a. Show complete joint penetration and complete fusion of weld metal and base
metal
b. Show no more than 1/3t inadequate penetration
c. Show no more than 1/3t nonfusion
d. be allowed one 5/32” crater crack
39. What is the hydrostatic test thickness for a new tank whose diameter is 150’,
and has a fill height of 40’? The shell material is A 36M.
a. 0.655
b. 0.611
c. 0.563
d. 0.500
40. In order to comply with API 650, the finished surface of a weld reinforcement
on plate ½” thick, horizontal butt joints, may have a reasonably uniform
crown not to exceed __________, for radiographic examination.
a. 1/4”
b. 3/16”
c. 1/8”
d. 1/16”
CLOSED BOOK
The second part of the exam is “Closed Book”
41. Who has the ultimate responsibility for complying with the provision of API
Standard 653?
a. API
b. Owner/operator
c. Inspector
d. Contractor/Builder
42. If cracks are suspected in nozzles or nozzle welds they should be checked
by _________.
a. Ultrasonic digital thickness gauge
b. MT or PT examination
c. Eddy current testing
d. Infrared thermography
43. Which for the following may produce physiological impairment with long
latency, such as cancer or pulmonary obstruction disease?
a. Water
b. Sweet Crude Oil
c. Benzene
d. Non-toxic substances
44. Per API 653, tanks shall have a formal visual inspection once every ____
years or RCA/4N years, whichever is less
a. Three
b. Four
c. Five
d. Seven
45. Monthly visual inspection of the external condition of in-service tanks may
be performed by ____.
a. API 653 inspectors
b. Owner/Operator personnel
c. NDE technicians
d. Plant Managers
46. According to API 650, which of the following types of connections shall be
stress relieved?
a. All Nozzles
b. All Group I, II, III or IIIA opening connection less than 12 inches
c. All Group IV, IVA, V or VI opening connections requiring reinforcement
d. All connection requiring reinforcement
47. The critical zone for repairs to tank bottom is that portion of the bottom or
annular plate within _____ inches of the inside edge of the shell.
a. 3
b. 6
c. 12
d. 24
48. What are the dimensions for a groove weld procedure specimen (face
bend)?
a. 3 inches long and ¾ inches wide
b. 6 inches long and 1 ½ inches wide
c. 12 inches long and 2 ½ inches wide
d. The inspector determines the dimensions
49. On a fixed-typed roof, planks long enough to span at least _________ roof
rafters should be laid and used as walkways
a. None allowed
b. 1
c. 2
d. 3
51. Toxic atmospheres may originate from ______ or from the material on which
hot work is being performed
a. Welding fumes
b. Oxygen cylinders
c. Stored product
d. Zinc coatings
52. During the reconstruction of a tank, welding operators, welders and welding
procedures must be qualified in accordance with _______.
a. API 650
b. ASME Section V
c. ASME Section IX
d. API 1104
53. Upon completion, the roof of a tank designed to be gas tight shall be tested
by which one of the following methods?
a. Magnetic particle testing of all welds
b. Application of internal air pressure not exceeding the weight of the roof plates
and applying a solution suitable for the detection of leaks
c. Penetrant testing the weld joints
d. Visual inspection of the weld joints
55. The tank surface that were in contact with gasoline ,should be scrapped to
the bare metal For a distance of minimum ------------ inches
a. 3 inch
b. 2 times the thk of thicker plate or 2 inch which is greater
c. 12 inch
d. 24 inch
58. For minor repairs to a tank bottom in otherwise good condition, first drill and
tap a hole for insertion of a carbon dioxide or other insert gas line _____
a. 6 inches from repair area
b. 12 inches from repair area
c. 24 inches from repair area
d. Adjacent to repair area
60. Which of the following tanks are used to reduce filling and breathing loss by
eliminating vapor space?
a. Cone roof tank
b. Umbrella-roof tank
c. Vapor-dome roof tank
d. Floating roof tank
61. Per API 650, external floating roof deck plates having support leg or other
rigid penetrations closer than __________ inches to lap weld seams must be
full fillet welded not less than 2 inches on 10 inch centers.
a. 6
b. 12
c. 14
d. 18
62. During lining of a tank that that been in services, State and Federal safety
regulations must be followed as well as the owner’s ________
a. Tank entry and or hot-work permit procedure
b. On-site meeting schedule
c. Attendance listing for tank inspectors
d. Verbal approval
64. When corrosion rates are not known and similar service experience is not
available, the actual bottom thickness shall be determined by inspections
within the next _________ years(s) of tank operating to establish corrosion
rates.
a. Five
b. Ten
c. Three
d. One
66. Calcining can occur when concrete has been exposed to __________
a. Chemical attack
b. Sulfate – type alkalis
c. Chlorides
d. High temperature
68. Upon completion of welding of the new tank bottom, the welds shall be
inspected by which one of the following methods?
a. Radiographs
b. Vacuum Box
c. Penetrant testing
d. Hammer testing
69. What preparation is required to base metal before welding on tanks that had
surfaces in contact with leaded gasoline?
a. Keep air mover to provide clean air
b. Scrape down to bare metal 2”
c. Abrasive blast any immediate areas affected
d. Use the air supplied respiratory equipment And do frequent air quality to
ensure that inside atmosphere during the hot work is safe
API 653 – DAY 6 Page 13
BOOK NO: 43
Southern Inspection Services
70. Tank plates being welded which do not have proper identification shall be
subjected to ________
a. Chemical analysis
b. UT thickness measurements
c. PT testing
d. RT testing
71. The maximum reinforcement thickness for vertical butt joints, less than or
equal to ½” thick is __________
a. 1/16”
b. 1/8”
c. 3/32”
d. 3/16”
73. ______ identifies a procedure for installing a nozzle in the shell of a tank that
is in service.
a. Repair
b. Alteration
c. Hot tap
d. Reconstruction
74. Annular bottom plates shall have a radial width that provides at least
________ inches between the inside of the shell and any lap-welded joint in
the remainder of the bottom.
a. 10
b. 30
c. 24
d. 18
75. For known materials, all shell plates and bottom plates welded to the shell
shall meet, as a minimum, the chemistry and mechanical properties of
material specified for the application with regard to thickness and design
metal temperature, per ________
a. ASM Requirements
b. ASME Requirements
c. API 650 Requirements
API 653 – DAY 6 Page 14
BOOK NO: 43
Southern Inspection Services
d. ASTMA 7 Requirements
76. What action should be taken after a flat spot is discovered in the second ring
of a 200’ diameter AST?
a. The shell distortion shall be evaluated
b. The area shall be cut out and replaced
c. Since no product is leaking out of the area, it may ignored
d. The inspector has the option to repair or ignore
77. Routine in-service visual inspections of the external condition of the tank
shall not exceed
a. One month
b. Six months
c. One year
d. Five years
79. When making major repairs on tank bottoms, water flood technique is used
______
a. To keep the floor cool when welding to prevent distortion
b. As a corrosion prevention technique
c. To prevent external dust from being sucked into the tank while the air mover
is operating
d. To displace flammable liquids beneath the tank floor
80. Minimum thickness for tank bottom plate, when there is no means of leak
detection and containment, is __________ inch.
a. .10
b. .075
c. .15
d. .05
83. The most likely point of occurrence of cracks in riveted tanks is around
_____
a. Internal piping
b. Flanged connections
c. Roof seals
d. Rivet holes
85. Qualified inspectors shall have education and experience equal to at least
one of the following:
a. A degree in engineering plus 1 year of experience in inspection of tanks,
pressure vessels or piping
b. Two years of experience in work related field
c. Two year certificate in technology from technical college
d. High school education
86. The maximum acceptable undercutting of the base metal for vertical butt
joints of the existing tank is ________
a. 3/32
b. 1/8
c. 1/64
d. 3/64
89. While work is being performed in and around an area with an inert
atmosphere _________
a. No monitoring is required
b. The area should be continuously flooded with water
c. The area should be continuously monitored with an oxygen analyzer
d. The welder must use a class Z49.1 filter type respirator
91. The minimum acceptable shell plate thickness for tanks with diameter equal
to or less than ____ feet shall be calculated using the following method: tmin
= (2.6DHG/SE)
a. 100
b. 150
c. 175
d. 200
92. All requirements of API 650, _____ shall be considered before changing the
service of a tank to operation at temperature above 200ºF.
a. Appendix M
b. Appendix J
c. Appendix C
d. Appendix K
a. API 650
b. ASME Article 4
c. AWS D1.1
d. API 1104
96. An entry permit shall be issued by a qualified person for all entries into a
tank. Employees may be allowed to enter a permit required confined space if
____________
a. Oxygen content is 19.5% - 23.5%
b. Flammable vapors are 30% LFL
c. Toxic substances are 30% PEL/TLV
d. Lead-in-air is .75 milligrams per cubic meter
98. Per API 653, what is the maximum allowable banding, using a vertical 36 »
sweep board?
a. 1”
b. ½”
c. 3/8”
d. 3/32”
99. A full hydrostatic test is not required after replacement of a door sheet if the
tank is otherwise exempt from hydrostatic testing and the spacing between
the shell-to-bottom weld and lower edge of the door sheet is such as
a. 24” or greater, if the tank is less than or equal to ½” thick
b. 12” or greater, if the tank is less than or equal to ½” thick
c. 6” or greater, if the tank is less than or equal to ½” thick
d. In compliance with table 9-1 of API 653, except is shall not extend to the floor
100. What is the extremely toxic, flammable gas that is encountered in the
production, storage and processing of sour crude oil?
API 653 – DAY 6 Page 18
BOOK NO: 43
Southern Inspection Services
a. Hydrogen sulfide
b. Leaded gas
c. Lead alkalines
d. Dust
101. The addition of manways and nozzles greater than 12-inch NPS or
increasing or decreasing the tank shell height is considered ___________
a. Reconstruction
b. Rebuilding
c. Reworking
d. Alteration
102. When bottom annular plates are required by paragraph 3.5.1 of API 650, the
radial joints shall be radiographed. For single welded joints using a backup
bar, one spot radiograph shall be taken on ________ percent of the radial
joints.
a. 10
b. 30
c. 50
d. 100
104. Atmospheric storage tanks are those tanks that have been designed to
operate in their gas and vapor space at internal pressure which approximate
______ pressure.
a. 16 Ibs. to 25 Ibs.
b. 12 Ibs to 15 Ibs.
c. More than 25 Ibs.
d. Atmospheric
106. Who is responsible for maintaining written procedure that cover work in
petroleum storage tanks?
API 653 – DAY 6 Page 19
BOOK NO: 43
Southern Inspection Services
107. Welder identification on roof welds and flange-to-nozzle neck welds shall
__________
a. Be hand or machine stamped
b. Be stamped every 3 feet
c. Be stamped on the top side of each nozzle an in every 3 feet of roof weld
d. Not require identification
108. Annular bottom plates must extend a minimum of _________ inches outside
the tank shell
a. 1 ½
b. 2
c. 3
d. 4
109. For penetrations using insert plates, how shall the completed butt welds
between the insert plate and shell plate be inspected?
a. 100% RT
b. Spot RT
c. MT
d. Visual
110. When making a perimeter repair, seal off all openings between the floor
plates and the tank foundation by packing them with ___________ or some
other suitable, non-corrosive material.
a. Asphalt
b. Liquid hydrogen
c. Mud
d. Graphite and grease
111. High Frequency transducer ( 10 Mhz or higher) can have the ability to
operate from thin sections of:
a. More than 1
b. Less than 0.025 inch
c. 0.005-0.009 inch
d. 0.050-1.000 inch
112. The maximum operating temperature for tanks constructed to API 650 (not
including appendices) is ___________
a. 500º F
API 653 – DAY 6 Page 20
BOOK NO: 43
Southern Inspection Services
b. 500º C
c. 200º F
d. 200º C
113. New ____________ for fixed roof support columns shall be installed when
replacing a tank floor.
a. Mud rings
b. Leg guides
c. Bearing plates
d. Support leg pins
114. Where does the new nameplate need to be attached to a reconstructed tank?
a. Adjacent to the existing nameplate
b. Does not need one
c. On the roof
d. Over the suction piping
115. The corrosion rate for an AST is 5 mils per year. Based on API 653
requirements when should the next external UT inspection be scheduled?
Note: Remaining Corrosion Allowance is 0.17 inches.
a. 17 years
b. 15 years
c. 20 years
d. 10 years
117. The maximum design liquid level for product shall be determined by
calculating the maximum design liquid level for each shell course based on
_________
a. Amount of product needed
b. The specific gravity of the product
c. Material coating
d. Number of penetrations in the first shell course
118. In order to be in compliance with API 2207, when must the work area be
monitored for oxygen deficiency and combustible and toxic atmospheres?
API 653 – DAY 6 Page 21
BOOK NO: 43
Southern Inspection Services
a. Every 4 hours
b. Every 8 hours
c. Every 12 hours
d. While work is in progress
119. You are adding a 6 inch blending nozzle to the bottom course, the shell is
5/8” thick ( it has not met the current design metal tem criteria). What size
insert plate is required when used with a reinforcement plate?
a. 12” diameter
b. 18” diameter
c. Three times the diameter of the penetration
d. The diameter of the reinforcement plate, plus 12”
120. Who is responsible for compliance with the API 650 standards?
a. Manufacturer
b. Purchaser
c. State Inspector
d. API 653 Inspector
121. _________ settlement occurs when the tank shell settles sharply around the
periphery, resulting in deformation of the bottom plate.
a. Uniform
b. Edge
c. Put-of-Plane
d. Rigid Body Tilting
123. Which type of tank settlement will rotate the tank in a titled plane?
a. Uniform settlement
b. Rigid body
c. Out-of-Plane settlement
d. Differential settlement
125. The minimum thickness of new roof plates shall be _____ inch, plus any
corrosion allowances, as specified in the repair specifications.
a. 1/2
b. 7/8
c. 3/16
d. 3/8
128. According to API 653, the bases for repairs and alterations shall be an _____
a. API Standard 650 equivalence
b. API Standard 2207 equivalence
c. ASME Section V equivalence
d. AWS D 1.1 equivalence
129. All new shell joints shall be ________ joints, with complete penetration.
a. Butt welded
b. Lap welded
c. Riveted
d. Chemically bonded
130. During the repair of an AST, one new vertical shell weld was installed. How
many radiographs are required on the vertical? (The shell is 1.25” thick)
a. One radiograph shall be taken in every vertical joint
b. 100% of the vertical joint
c. Two radiographs shall be taken in the vertical joint
d. No radiographs required
133. All bottom plates shall have a minimum nominal thickness of ________ inch,
exclusive of any corrosion allowance specified by the purchaser for the
bottom plates.
a. 49.8 kg/M2
b. .236 inch
c. 9.6 Lb/ Ft2
d. all
134. _________ means the work necessary to reassemble a tank that has been
dismantled and relocated to a new site.
a. Reconstruction
b. Rebuilding
c. Reworking
d. Alteration
135. Repairs shall not be attempted on a tank that is filled with __________ or on
a tank that has contained __________ until the tank has been emptied,
cleaned and gas freed in a safe manner.
a. Nitrogen
b. Oil
c. Water
d. Grain
136. According to API 653, a full hydrostatic test, held for 24 hours, shall be
performed on:
a. A new tank
b. An in-service tank
c. A reconstructed tank
d. An out-of-service tank
137. Misalignment in completed vertical joints over 5/8” shall not exceed what
percentage of the plate thickness?
138. New or altered reinforcing plates of shell penetrations shall be given a(n)
______ test, In accordance with API Standard 650
a. Diesel
b. Air leak
c. Stress
d. Gas
141. Any specific design considerations, other than normal product loading, shall
be specified by ____________
a. Owner/operator
b. Contractor
c. Engineer
d. Welding foreman
b. Anode
c. Cathode
d. Electrolyte
145. ______________ occurs when two metals with different compositions (thus
different electrolytic potentials) are connected in an electrolyte (usually soil).
a. Scattered metal growth
b. Scattered metal blistering
c. Galvanic corrosion
d. Erosion
147. All tanks shall be given a formal visual external inspection by an inspector
qualified in accordance with API 653, Paragraph 4.10 at least every ________
years.
a. 10
b. 7
c. 6
d. 5
149. The rules given in API 653 ___________ for tank inspection, repairs,
alterations and reconstruction.
a. Minimum requirements
API 653 – DAY 6 Page 26
BOOK NO: 43
Southern Inspection Services
b. Maximum requirements
c. Guidelines requirements
d. Suggested requirements
ANSWWERS
Q1. b (Par. T-620) ASME V
L = 3.7√ (Dt2)
L = 3.7√ 25) Values substituted
L = 3.7√ (11.75)
L = 3.7 X 3.428
L = 12.68"
d1 + d2 + d3 … < 2”
Solution: Use the formula, Internal Bottom Settlements or Bulges. Edge settlement is
calculated in the same fashion.
B = 0.37R
B = 2.22"
Solution: Use the formula, Hydrostatic test height for welded tank shells.
Ht = (StEtmin/2.6D)
Ht = (5659.28) / (44.4)
Solution: Use the formula, Internal Bottom Settlements or Bulges. Edge settlement is
calculated in the same fashion.
B = 0.37R
Solution: Use' the formula, Minimum Thickness Calculation for Welded Tank Shell.
t
min = 2.6(H-1) DG / SE
t
min = 2.6 (17-1) (94)(1) / 23,595(1 ) Values substituted
t
min = 3.910.4 / 23,595
t
min =0 .168"
Solution: Use the formula, Minimum Thickness for Tank Bottom Plate.
Metal loss from Bottom side = Bottom side corrosion raate x Number of years
Solution: Use the formula, Minimum Thickness for Tank Bottom Plate.
MRT = .070
Solution: Use the formula, Hydrostatic test height for welded tank shells.
Ht = (6501\ 213.2)
Tt = 2.6D(H-1) / St
Tt = (15.210) / 24,900
9. A hot tap in a 1.25” thick tank with a minimum metal temperature of 650ºF
at time of hot tap, without having material toughness data is
a. Not permitted
b. Permitted
c. Not enough information
d. Not addressed by the code
11. A liquid penetrant examiner must have vision to enable him to read Jagger
Type 2 standard chart at a distance of not less than 12 inches and is
capable of distinguishing and differentiating contrast between colours
used. Examiners shall be checked ______ to ensure that they meet these
requirements
a. Quarterly
b. Semi-Annually
c. Annually
d. Bi-Annually
13. A radiography is made using an X-ray source and two films in each film
holder. For composite viewing, each film of the composite shall have a
minimum density of
a. 4.0
b. 1.8
c. 2.0
d. 1.3
14. A reconstructed tank with a total height of 25’ has been determined to
have an out-of-plumb ness of 2-3/4 “. This is
a. Acceptable
b. Unacceptable
c. Not covered by the code strengthening
d. Corrected by eternal
15. A riveted tank shell with a butt joint has 3 rows. What is the joint
efficiency?
a. 0.75”
b. 0.85”
c. 0.90
d. 0.91
19. A single film technique was used to make a radiograph using a cobalt 60
source. The minimum permitted density in the area of interest is
a. 4.0
b. 1.8
c. 2.0
d. 1.3
25. A welder may deviate from the parameters specified in WPS if they are
nonessential variable
a. Provided authorization from inspection is documented
b. Provided the welding supervisor approves
c. No
d. Nonessential variables only apply to PQRs
29. A welding procedure qualified on ¼ inch thick plate can be used to weld
groove welds in materials from to
a. 3/16 to ¾
b. 1/16 to ¾
c. 3/8 to ¾
d. 1/16 to ½
30. A welding procedure qualified on 3/8” thick plate can be used to weld
groove welds in materials
a. 3/16 to ¾
b. 1/16 to ¾
c. 3/8 to ¾
d. 1/16 to 3/8
31. A welding procedure qualified under the 1965 ASME Code Section IX
a. Is obsolete
b. Is still application
c. Must be re-qualified every 3 years when code is re-issued
d. Is not addressed by the code
38. At what design metal temperature must impact tests be made for all weld
metal and procedures to be used?
a. Below 32ºF
b. Below 20ºF
c. Below 15ºF
d. Below 10ºF
40. Base metals are grouped into groupings according to their welding
characteristics
a. F-number
b. AWS
c. A-number
d. P-number
46. Bottoms exceeding 100’ diameter in tanks operating above 200ºF shall
have
a. Butt-welded annular bottom plates
b. Be made of a group IV, V or VI material
c. Have a modulus of elasticity of 30,000,000
d. All of the above
52. Determine the exact interval for ultrasonic thickness measurement for a
tank with 17 mils of the original 25 mils corrosion allowance still remaining
after 15 years?
a. 5 years
b. 15 years
c. 23.875 years
d. 31.875 years
53. Determine the maximum allowable height for a 90 foot diameter tank based
on a maximum shell plate thickness of 0.5 inch and maximum allowable
stress of 21,000 psi with a joint efficiency of 0.85, and no corrosion
allowance
a. 29.6
b. 35.3
c. 39.1
d. 43.9
65. Find the capacity of a small tank, with a joint efficiency of 0.85, specific
gravity = 1.0, no corrosion allowance, diameter is 40 feet, height is 30 feet
with 5 completed 72” courses.
a. 5,370
b. 5,140
c. 6,710
d. 7,350
68. For a 30 inch shell manhole, 0.5 inches thick shell and reinforcing plate,
what minimum neck thickness is required?
a. 3/16
b. 3/8
c. 1/2
d. 5/16
69. For an existing 150 foot diameter storage tank, which has been in service
for 28 years, known joint efficiency is 1.0, contents have been the same,
with a specific gravity of 1.0, material yield of plate is 30,000 and tensile
strength is 55,000, liquid fill level is 50 feet, calculate the minimum
allowable thickness for the second course:-
a. 0.6789
b. 0.7962
c. 0.8056
d. 0.8156
70. For New butt-welded joints in which the thinner shell plate is 3/8 inch or
less, how many spot radiographs shall be taken in the first 10 feet of
completed vertical joint of each type and thickness welded by each welder
or welding operator?
a. One
b. Two
c. Three
d. Four
71. For dome roofs that are flanged, the radius of curvature is limited by the
depth of the roof, including the crown and knuckle depth. What is the
maximum roof depth for a shop assembled cone roof 10 feet in diameter?
a. 2.0”
b. 3.5”
c. 5.5”
d. 8.0
72. For impact testing materials, what is the minimum traverse value of Group
IV materials, 1.5” thick?
a. 13 foot – pounds
b. 15 foot – pounds
c. 20 foot – pounds
d. 25 foot – pounds
73. For impact testing materials, what is the minimum Longitudinal value for a
1.8” thick A-516-70 as rolled material for a WPS?
a. 50 foot – pounds
b. 15 foot – pounds
c. 42 foot – pounds
d. 40 foot – pounds
74. For new or repaired shell horizontal joints, how many radiographs shall be
taken for each 50 feet of horizontal joint, not including those required at
intersections of vertical and horizontal joints?
a. 1
b. 2
c. 3
d. 5
75. For Vertically oriented welds that attach nozzles, manholes, cleanout
openings and permanent attachments, undercut shall not exceed _______
inch.
a. 3/32
b. 1/8
c. 3/16
d. 1/64
76. Foundations of relocated tanks specified as true to horizontal plane
without ringwalls shall be true:-
a. + 1/8” in any 30’ and + 1/4” in the total circumference
b. + 1/8” in any 30’ and + 1/2” in the total circumference
c. + 1/8” in any 10’ and + 1/2” in the total circumference
d. + 1.4” in any 30’ and + 1/2” in the total circumference
77. From what type of material should shims be fabricated when they are to be
used to radiograph welds?
a. Malleable materials capable of being drilled
b. From the same heat number as the material being inspected
c. Fabricated of radiographically similar material to the object to be inspected
d. All of the above
78. Generally, Which is a major consideration while selecting tan bottom lining
a. cost
b. down time
c. Thickness of coating
d. Hygroscopic nature over time
81. How does the calculation of minimum thickness for a riveted tank shell
differ from that of a welded tank shell
a. The formula for the calculation of minimum thickness of a riveted tank
shell is the same as for a welded tank shell except that the maximum
allowable stress (S) is 21,000 lbs / sq. inch and the efficiency equals 1 for
the shell plate 6 inches away from rivets;
b. The formula for the calculation of minimum thickness of a riveted tank
shell is exactly the same for a welded tank
c. The formula for the calculation of minimum thickness of a riveted tank
shell is the same as for a welded tank shell except the minimum allowable
stress (S) is 21,000 lbs / sq. inch and the efficiency equals 0.85 for the
shell plate 6 inches away from the rivets.
d. API does not set minimum thickness.
82. How many equally spaced measurement are required for the thickness
averaging technique?
a. 2
b. 5
c. 4
d. 3
83. How many impact specimens must be broken for an average value for P1
Group 1, 2, 3 material?
a. 2
b. 3
c. 4
d. 6
84. How many inches must project beyond the outside edge of the weld
attaching the bottom sketch plate to the shell plate?
a. Atleast 1/12 inch
b. Atleast 2 inches
c. Atleast 3/8 inch
d. Atleast 1.0 inch
85. How many settlement measurement points are required for a tank that
measures 200 ft. in diameter?
a. 30
b. 8
c. 20
d. 10
86. How many specimens and impact tests must be performed from a single
test coupon or test location?
a. 1
b. 2
c. 3
d. 4
87. How many specimens must be broken for an average value for P1, Group
1, 2, 3 materials?
a. 2
b. 3
c. 4
d. 6
90. If penetrameters are not placed adjacent to the welds, what rules apply?
a. The penetrameter should be placed on the source side of the material
being radiographed
b. The penetrameter may be placed on the film side of the material being
radiographed
c. Lead letter “F” alleast as high as the identification number is placed
adjacent to the film side penetrameter
d. All of the above
92. In a riveted tank shell, a butt joint has 3 rows. What is the joint efficiency?
a. 0.75
b. 0.85
c. 0.90
d. 0.91
94. In general, if shell thickness does not exceed ______ inch, it does not
require further assessment for brittle fracture:-
a. 0.25
b. 0.75
c. 1.00
d. 0.50
107. Letters and numerals on nameplates shall not be less than inch high.
a. 5/32
b. 5/16
c. 3/16
d. 1/8
111. Minimum spacing between toes of welds for a radius (R) on a penetration
and other welds of 1.25” plate must be:-
a. 6”
b. 7.5”
c. 3”
d. 1.25”
112. Minimum thickness calculation for shells of tanks 200 ft. or less in
diameter shall be done using ________:-
a. The variable design point method for API 650
b. ASME section VII, div. 1:
c. The formula given in API 653
d. Either (a) or (c) may be used
114. Of the following welding processes, which one is not permitted for welding
on above ground storage tanks:-
a. SMAW
b. GMAW
c. OFW
d. SAW
115. On plates more than 3/16 inch thick, the fillet weld thickness shall not be
less than 1/3 the thickness of the thinner plat at the joint and shall be
atleast:-
a. 1/2 inch
b. 1/4 inch
c. 3/16 inch
d. 9/32 inch
116. On the drawing that the manufacturer shall furnish the purchase, you
would except to see which of the following information:-
a. The required shell thickness for both the design condition (including
corrosion allowance) and the hydrostatic test condition
b. The nominal thickness used
c. The material specification and allowable stresses
d. All the above
119. Per API 650, calculation of shell thickness by the 1 – foot method cannot
be used for tanks:-
a. Under 200 ft. in diameter
b. Over 200 ft. in diameter
c. Under 150 ft. in diameter
d. Of any size
120. Pinhole leaks or porosity in tank bottom joints may be repaired by:-
a. Grinding and out area
b. Penning over affected are
c. Applying additional weld bead over area
d. Mechanical caulking
122. Plate material thicker than _______ inches shall be normalized or quench
tempered, killed, made to fine grain practice and impact tested:-
a. 2.00
b. 1.75
c. 1.50
d. 1.00
123. Plates found to be thinner than those in the course above it are:-
a. Not allowed
b. Permitted
c. Permitted provided they were so designed
d. Need to be calculated for suitability for service
128. Reinforcement pads shall be tested by applying pressure between the tank
shell and reinforcement plate using the telltale hole. How much pressure
is used to perform this inspection:-
a. 15 psig hydrostatic pressure
b. 15 psig pneumatic pressure
c. 5 psig hydrostatic pressure
d. 5 psig pneumatic pressure
131. Rewelding vertical joints requires cutting horizontal welds back form the
joint a minimum of _______ inches:-
a. ½
b. 1
c. 2
d. 12
139. Tack welds shall be made using a procedure qualified in accordance with
ASME Section IX:-0
a. Fillet weld
b. Groove or fillet weld
c. Special
d. Butt weld
142. Tests for leaks in reinforcing plate welds require ______ psig:-
a. Upto 2.5
b. Upto 15
c. Upto 21
d. Upto 30
143. The “critical zone” for tank bottom repairs is the area within the annular
plate ring, within inches of the shell or within inches of the inside edge of
the annular plate ring:-
a. 6
b. 9
c. 3
d. 12
144. The “L” in actual thickness determination for each shell course:
a. May be greater than 40”
b. Is valid only when corroded area is less than 40”
c. Applies even if corroded area is greater than L
d. Requires converting “D” from feet to inches
146. The API 653 standard covers the maintenance inspection, repairs,
alteration, relocation and reconstruction of tanks constructed to which one
of the following standards:-
a. ASME
b. API 651
c. API 65
d. API 650
147. The assessment period for inspection of tank bottom integrity is:-
a. Is always 5 years
b. Is fixed by corrosion rate
c. Less than or equal to the appropriate internal inspection interval given in
API-653 4.4.2
d. Determined by the designer
148. The complete or partial removal and replacement of more than 12 inches
of a vertical weld joining shell plates beneath the design liquid level is
considered a:-
a. Minor alteration
b. Minor repair
c. Minior shutdown
d. Major repair
150. The determining factor for intervals between internal and external
inspections
a. Change of service to a higher specific gravity
b. Tank service history provided earlier inspection is not required by special
reasons
c. Corrosion activity either known or suspected
d. Governmental regulations
160. The maximum acceptable undercutting for base metal in vertical welds is:-
a. 1/64”
b. 1/32”
c. 1/16”
d. 1/8”
161. The maximum interval between internal inspections shall not exceed
______ years:-
a. 10
b. 20
c. 5
d. 15
162. The maximum spacing between settlement measurement points shall be:-
a. 30 ft
b. 20 ft
c. 40 ft
d. 25 ft
163. The minimum dimension for replacement shell plate is 12 time t or ____
inches:-
a. 8
b. 18
c. 6
d. 12
164. The minimum interval for external inspection by a qualified inspector is
years or at the quarter corrosion-rate life of the shell, whichever is less:-
a. Twenty
b. Five
c. Ten
d. Fifteen
166. The minimum thickness of an annular plate ring is usually greater than:-
a. 0.10
b. 0.25
c. 0.0625
d. 0.1875
167. The permissible exposure limit (PEL) is the maximum _______ time-
weighted average of any airborne contaminant to which an employee may
be exposed:-
a. 8 hour
b. 24 hour
c. 4 hour
d. 1 hour
168. The proper method for dismantling tank bottoms that are to be reused
shall be cut by:-
a. Deserning of lapwelds
b. Cutting alongside remaining welds at a minimum of 2 inches from existing
welds
c. Cutting alongside remaining welds at a minimum of 3 inches from existing
welds
d. Both (a) and (b) are acceptable
169. The purchaser has not specified the use of 1-foot method for calculating
thickness and L/H < 2, therefore, what is the shell plate thickness for the
first course for the following tank design?
Height = 40 feet
Diameter = 260 feet
Stress @ test condition = 30,000 psi
Specific gravity = 1.0
Course Length = 8 feet
Corrosion Allowance = 0
Joint Efficiency = 0
a. 1.209”
b. 1.171”
c. 0.856”
d. 1.038”
171. The root opening for square grooves for butt-welded bottom plate shall not
be less than:-
a. 1/2 inch
b. 1/4 inch
c. 3/16 inch
d. 9/32 inch
175. The thickness to be used for each shell course when checking the tank
design after reconstruction shall be based on measurements taken within
_____ days prior to relocation:-
a. 45
b. 90
c. 180
d. 360
178. The variable design point method shall be used for tanks greater than
_____ in diameter:-
a. 50’
b. 200’
c. 150’
d. 200’
180. Thickness readings taken on a tank shell after 5 years of service show a
minimum thickness of 0.420 inches. The data sheet shows the original
thickness as 0.5 inches. What is the corrosion rate for the tank:-
a. 0.008
b. 0.0016
c. 0.016
d. 0
181. Three different methods of conducting “Visual Examinations” (VT):-
a. Direct, indirect and previously recorded
b. Translucent, direct and previously recorded
c. Direct and indirect or (remote visual examination)
d. All of the above
184. To be certified under the program which of the following educational and
experience requirements must be met:-
a. A degree in engineering plus 6 months of experience in inspection of
tanks, pressure vessels, or piping
b. A two-year certificate in engineering or technical college and two years of
experience in construction, repair, operation, or inspection of tanks,
pressure vessels, or piping
c. The equivalent of a high school education and three years of experience
in construction, repair, operation or inspection of which one year must be
in inspection of tanks, pressure vessels or piping
d. Four years of experience in the inspection of above ground storage tanks
in petroleum / chemical industries
187. Top decks of external floating roofs (double deck or pontoon type) which
are designed with are designed with a permanent slope for drainage shall
have a minimum slope of ___ inch in 12 inches
a. 1/64
b. 1/2
c. 1/4
d. 3/8
188. Underun on plate not more than inch from the computed design thickness
or minimum permitted thickness is acceptable:-
a. 0.01
b. 0.02
c. 0.03
d. 0.04
191. Vertical welds must be fully radiographed if the shell thickness exceeds
inches:-
a. 3/4
b. 1
c. 1 1/4
d. 1 1/2
193. Welded joints that have experienced metal loss due to corrosion :-
a. Must be X-Rayed prior to further use
b. May be repaired by welding
c. May be repaired by grinding
d. All of the above
197. Welding filler metals are grouped into groupings based on their AWS
classification:-
a. P-numbers
b. F-numbers
c. Z-numbers
d. ASTM spec
201. What are the two general approaches for determining minimum thickness
of tank bottom plate and briefly describe their differences
a. Deterministic and Probabilistic
b. Probabilistic and Actualistic
c. Actualistic and Deterministic
d. Variables design and Actual thickness determination
203. What diameter bolt circle is required and how many bolts for a 24 inch roof
manhole?
a. 26.0 inch diameter bolt circle and 18 bolts
b. 25.5 inch diameter bolt circle and 20 bolts
c. 27.5 inch diameter bolt circle and 16 bolts
d. 27.5 inch diameter bolt circle and 20 bolts
208. What is the 42 gallon barrel capacity of a tank 110 feet in diameter, 24 feet
high, joint efficiency is 0.85, specific gravity = 1.0, corrosion allowance = 0
a. 34,303
b. 38,309
c. 39,910
d. 40,656
209. What is the allowable stress at root of anchor bolt threads for a tank with a
design pressure upto 2500 psig? Uplift is based on tank design pressure
and wind
a. 15,000
b. 20,000
c. 25,000
d. 30,000
210. What is the capacity of a tank 110 feet in diameter, 24 feet high, joint
efficiency is 0.85, specific gravity is 1.0, corrosion allowance = 0?
a. 34,303
b. 38,909
c. 39,910
d. 40,656
211. What is the distance from the centre pipe to shell for a 3 inch nominal pipe
size, 36 diameter drawoff sump, which is 18 inched deep?
a. 2.1875’
b. 3.2343’
c. 5.0000’
d. 5.3780’
212. What is the distance in inches, that both a roof plate or a shell bottom
must be cut from the weld when dismantling a shell tank:-
a. One
b. Two
c. Four
d. Six
213. What is the expected service life for a properly applied tank bottom lining?
a. 5-10 years
b. 10-15 years
c. 10-20 years
d. 20-30 years
214. What is MDMT for A 516 M 415 as rolled, Killed and fine grained if Thk is
20 mm
a. – 20 Deg F
b. – 22 Deg F
c. – 23 Deg F
d. 10 Deg F
217. What is the maximum allowable edge settlement for the settled areas of 4
feet dia of 60 feet dia tank With Bottom lap joints Approximately Parallel
to the shell
a. 6.6”
b. 3.2
c. 4.07”
d. 2.035”
218. What is the maximum depth of bottom settlement if the radius of the
inscribed circle in the bulged area of local depression from the inside of
the shell to the bend point of the depression is 10 feet?
a. 2.59”
b. About 93 mm
c. 0.37 inch
d. 31.08”
220. What is the maximum out-of-plumbness of a new tank from the top of shell
relative to the bottom of the shell?
a. 1/100 of the total tank height
b. 1/50 of the total tank height
c. 1/60 of the total tank height
d. 1/200 of the total tank height
223. What is the maximum thickness of weld reinforcement for a 0.5625 inch
plate?
a. 1/16
b. 3/32
c. 1/8
d. 3/16
224. What is the minimum acceptable shell plate thickness for a tank shell
made of A 283 grade C material, 70 feet in diameter and 50 feet high?
Specific gravity of contents is 0.8. Original joint efficiency was 100%.
a. 0.356
b. 0.339
c. 0.480
d. 0.304
225. What is the minimum allowable density through the image of the
penetrameter for radiographs made with a 2000 kv tube?
a. 1.8 – 4.0
b. 1.3 – 2.8
c. 2.0 – 4.0
d. 1.3 – 1.8
227. What is the minimum nominal shell thickness required when the normal
tank diameter is less than 50 feet?
a. 3/16
b. 1/4
c. 5/16
d. 3/8
228. What is the minimum nominal thickness for bottom plates, exclusive of
any corrosion allowance?
a. 3/16 inch
b. 1/4 inch
c. 5/16 inch
d. 7/16 inch
230. What is the minimum permissible design metal temperature for a 280 foot
diameter tank, 75 feet high, tank radius is 1,680 inches, plate material
ordered is 1.125” (including corrosion a allowance) A 516 – 555 as rolled,
killed fine grain practice without impact testing:-
a. +8
b. 0
c. -4
d. All material must be impact tested
233. What is the minimum thickness of bolting flange and cover plate for a 24 x
24 size flush-type cleanout to be installed in a tank having maximum
height of 53 feet:-
a. 5/8
b. 9/16
c. 3/8
d. 5/16
234. What is the calculated minimum thickness of shell plates from the stress
on vertical joints for a field-erected small capacity tank, which has a
diameter of 30 feet, height of 36 feet, joint efficiency is 0.85, specific
gravity is 1.0, with a corrosion allowance of 0.125?
a. t = 0.1529
b. t = 0.1875
c. t = 0.2779
d. t = 0.3125
235. What is the minimum weld length that must be shown on each radiograph?
a. 2 inches
b. 3 inches
c. 4 inches
d. 5 inches
236. What is the most common protective cushion for aboveground storage
tanks?
a. Clean sand
b. Clay
c. Gravel
d. Carbonaceous
237. What is the nominal shell thickness required when the nominal tank
diameter is less than 50 feet?
a. 3/16 inch
b. 1/4 inch
c. 5/16 inch
d. 3/8 inch
238. What is the radii tolerance measured at 1 foot above the shell to bottom for
a reconstructed 125 foot diameter tank?
a. +/- 1/2
b. +/- 3/4
c. +/- 1
d. +/- 1 1/4
240. What must be done to the tank prior to dismantling to insure proper
alignment after the tank is reconstructed?
a. At least four sets of matching centre punch marks should be placed at the
top and bottom edges of each shell plate.
b. At least two sets of matching centre punch marks shall be placed the top
and bottom edges of each shell plate
c. At least three alignment tabs shall be tack welded to the top and bottom
edges of the each shell plate
d. At least two sets of matching centre punch marks may be placed at the
top and side edges of each shell plate
241. What are NDE methods and to what extent shall they be used for the
examination of repairs to butt welds?
a. MT and PT over full length
b. MT and PT spot
c. UT and RT over full length
d. UT or RT over full length
242. What of the following are not principal causes of shell distortion
a. Thinning caused by corrosion
b. Foundation settlement
c. Over-or under-pressuring
d. High wind
244. What size diameter cover plate is required for a 20 inch roof manhole?
a. 22 inch
b. 24 inch
c. 26 inch
d. 28 inch
245. What size penetrameter is required for RT of a tank 0.75 inches thick?
a. 17
b. 20
c. 25
d. 1
246. What spacing must be used for a settlement survey of a 100’diameter tank
a. 31.4
b. 30
c. 32.56
d. 31..
248. When alternative inspection intervals are selected, the owner / user
a. Shall document the procedure and make it part of the permanent record
b. Alternative are not allowed
c. Alternative method shall include method for determining bottom plate
thickness
d. Both (a) and (b)
249. When calculating the maximum liquid level for reconstructed tanks, the
required corrosion allowance shall be
a. Deducted from the actual thickness before calculating maximum liquid
level
b. Added to actual thickness before calculating maximum liquid level
c. Not be considered when calculating maximum liquid level
d. Deducted from the original design thickness
251. When concrete ringwalls are provided under the shell, the top of the
ringwall shall be level with ____________ inch in the total circumference
measured from the average elevation
a. ¼
b. 1/8
c. 3/8
d. 5/16
253. When evaluating roof supports systems, special attention should be paid
to
a. Rafters
b. Prior repairs
c. Distortions
d. The possibility of serve internal corrosion of pipe columns
256. When preparing the surface for lining, the abrasive blasting should not be
performed if the temperature of the steel surface is less than
______________ above the dew point or if the relative humidity is greater
than ____________ %
a. 10degrees, 75%
b. 5 Degrees, 80%
c. 10 Degrees, 80%
d. 5 Degrees,75%
258. When required, a set of charpay V-notch impact specimens shall be taken
a. Before heat treatment
b. After heat treatment
c. Either before or after
d. Both before and after heat treatment
260. When reusing the entire bottom in the intact condition, the shell cut shall
be a minimum of ________________ inch(es) above the top of the bottom
plate
a. ½
b. 6except where crossing existing welds
c. 12
d. 12 is the maximum
261. When reviewing a radiograph, a dark image of the letter B can be seen on
the film
a. This is cause for rejection
b. This is not cause for rejection
c. This is the same as a light letter B
d. An unusual safety hazard existed during the exposure
262. When the corrosion rate is not known or determinable from similar service
experience, actual bottom plate thickness shall be determined by
inspection within the next ________________ years of operation
a. 10
b. 7
c. 5
d. 3
263. When the tank is out of service, additional bottom plate examination
includes
a. Ultrasonic
b. Hammer testing
c. Turning of coupons
d. All of the above
264. When two (2) welders weld opposite sides of the same butt joint
a. 2 spot radiographs shall be taken
b. Heat generated by twin arc removes the need to radiograph
c. Shall be inspected by ultrasonics
d. 1 spot radiograph shall be taken
265. When two or more tanks are installed concurrently in the same location for
the same purchase
a. Spot radiographs to be taken is based on each tanks footage of the welds
b. Spot radiographs may be omitted in tank # 2 if no defects were found in
tank # 1
c. Spot radiographs may be taken based on the aggregate footage of the
welds of the same type and thickness
d. Spot radiographs to be taken be based on the aggregate footage of the
welds regardless of weld type and thickness
268. When vacuum testing is performed, a partial vacuum of atleast psig should
be used
a. 2
b. 3
c. 4
d. 5
269. Which below best describes how surface shall be prepared for ultrasonic
examination
a. The finished contact surface shall be free from weld splatter and any
roughness that would interfere with free movement of the search unit or
impair the transmission of ultrasonic vibrations
b. The weld surface shall be finished so they cannot mask or be confused
with reflections from defects, and should merge smoothly into the surface
of the adjacent base materials
c. The volume of bases material through which the sound will travel in angle
beam examination shall be completely scanned with a straight beam
search unit to detect reflectors which might affect interpretation of angle
beam results
d. All of the above
270. Which below option Thin-film lining system shall be used for the following
service conditions: Temperature 200 degrees F, product contents are
distillates
a. Coal tar epoxy
b. Epoxy amine
c. Epoxy polyamide
d. Epoxy Polyamidoamine
279. Which of the following is not a factor in determining suitability for service
of shell tanks
a. Internal corrosion due to the product or water bottoms
b. Location relative to other thanks
c. Chemical analysis and mechanical properties of the materials of
construction
d. Tank foundation, soil and settlement conditions
282. Which of the following is not true regarding dismantling of the shell
a. Temporary attachments welds must be ground flush
b. Shell stiffener rings, including wind girders and top angles, may be
removed
c. Shell stiffener rings, including wind girders and top angles, may be left
attached
d. Temporary attachments welds need not be ground flush
283. Which of the following is not true regarding small punctures in a floating
roof plate
a. May be ignored if they have been determined to be non-critical
b. Shall be repaired
c. Hall have affected sections replaced
d. Is considered a change from the original condition
284. Which of the following types of welds do not need welder identification?
a. Shell vertical welds
b. Roof plate welds
c. Flange-to-nozzle-neck welds
d. Both (b) and (c)
285. Which thin-film lining system shall be used for the following service
conditions Temperature 200 degrees F, product contents are distillates
a. Coal tar epoxy
b. Epoxy amine
c. Epoxy polyamide
d. Epoxy polyamidomine
288. Who is responsible for qualifying the welders used to repairs an above
ground storage tank?
a. The tank manufacture
b. The repair concern
c. The inspector
d. The test laboratory
289. Who is responsible for standing the design metal temperature (based on
ambient temperatures) the design specific gravity, the corrosion allowance
(if any), and the design wind velocity?
a. PURCHASER
b. FABRICATOR
c. INSPECTOR
d. ERECTOR
290. Widely scattered pits may be ignored provided that the sum of their
dimensions along any vertical line does not exceed 2 inch in an 8 inch
length and no pit depth results in a shell thickness of less than of the
minimum thickness exclusive of corrosion allowance
a. 5/8
b. ¾
c. ½
d. 2/3
41 A 6.33.1
42 C 653 4.3.3.1
43 B 653 2.1
44 D Fig 5.8 API 571
45 B 12.1.6.1 API 653
46 A APX M 4.1 API 650
47 B 3.2.33 API 2015
48 B 7.2.1 API 651
49 D 4.5.1.2 API 653
50 C 6.8.1 API 653
51 B T 673.3 SEC V ART 2
52 B 653 6.3.3 API 653
53 C 4.3.3.2 API 653
54 D B 2.2.3 of API 653
55 C 4.5.3 of API 653
56 B API 650 5-6.32
57 A 653 12.5.1.2
58 C QW 432 SEC IX
59 C QW 251.2 SECIX
60 B 8.3.2.4 API 650
61 C 8.1.3.1 API 650
62 B 5.4.1 API 650
63 B 4.3.1.2 API 653
64 C 7.3.1 API 575
65 C A-1b of API 650 or
66 C 12.3.2.5.1 a API 653
67 C H 5.4 API 650
68 D API 650 Table 5.4
69 D API 8.4 or 4297
70 A 650 8.1.2.2
71 C Table J1
72 C 650 Table 4.4
73 C 650 Table 4.4
74 A 650 801.2-3
653 12.2.1.2
75 D 8.5.1.b of API 650
76 C 653 10-5.6.2
77 C T 277.3 SEC V ART 2
78 D 6.1 2nd Para API 652
79 C 9.4. 1.2 & 1.4& 1.5 API 653
80 D 4.2 API 2015
81 A 653 4.3.4.1
82 B 653 4.3.2.1 C
Last Line
83 B API 650 9.2.25
84 C 5.4.2 of API 650
API 653 – DAY 6 Page 90
BOOK NO: 43
Southern Inspection Services
85 C 653 12.5.1.2
86 C API 653 9.2.25
87 B API 650 9.2.2.5
88 B C 4.5.1.3 & 4.5.1.5 of API 571
89 C 653 12.3.1
90 D T 277.1 SEC V ART 2
91 A T 232.A ,B SEC V ART 2
92 B 653 Table 4.3
93 B T 232 SEC V ART 2
94 D 653 5.3.5
95 B 653 Fig B 11 X axis
96 D GK
97 A 6.8.3 of API 653
98 D 6.3.3.3 of API 653
99 B ,4.43.5 API 653
100 B 6.3.1.3 API 653
101 D 6.3.2.2 API 653
102 D 10.4.1 API 651
103 C 6.4.1.1 a API 653
104 D 6.4.1.1 a API 653
105 A 6.4.1.1 a , b & c
106 C API 651 Table 6.4.2.1 & 2.2
107 A 10.1.1 of API 650
108 B 8.4.3 –API 650
109 A 8.2.1 API 650
110 B 9.3.2 API 652
111 B Fig 9.1 API 653
112 D 5.6.4 API 650 & 4.3.1 API
653
113 D 12.1.1.1 API 653
114 C 7.2.1.1 PI 650
115 C 5.1.3.3 API 650
116 D 7.2.1.1 API 650
117 C Table 5.6a note & 577.2.1
API 650
118 C ??? 575
119 B 5.6.3.1 API 650
120 C 9.10.1.4 API 653
121 D 7.2.10 2nd para API 575
122 C Fig 4.1 a API 650
123 A 5.6.1.3 a API 653
124 D 11.1.2 API 650
125 D 8,3.2.3 API 650
126 D 5.3.2 API 651
127 A 8.1.5 API 650
128 B 7.3.4 API 650
API 653 – DAY 6 Page 91
BOOK NO: 43
Southern Inspection Services