SIFAT CAMPURAN AGREGAT-ASPAL - METODE MARSHALL SEMEN

VMA VFA VIM


No. t a b c d e f g h i jeff jcur k l m n o p q r MQ Aa Ae Fi DP
(mm) (%) (%) (gr) (gr) (gr) (cc) (gr/cc) (gr/cc) (%) (%) (%) (%) (%) (%) (%) (kg) (kg) (mm) (kg/mm) (%) (%) (%) (Fi/Ae)
A 72,60 4,16 4,00 758,95 772,20 445,95 326,25 2,33 3,46 9,16 64,21 74,48 26,64 25,52 48,134 13,239 740,00 873,200 788,063 4,20 187,63 4,67 -0,49 4 -8,24
B 68,16 4,70 4,50 746,20 757,75 429,65 328,10 2,27 3,45 10,07 62,44 72,43 27,48 27,57 52,228 13,170 1210,00 1427,800 1275,025 6,30 202,38 4
Average 752,58 764,98 437,80 2,30 26,54609 50,181 13,204 1031,544 5,25 195,01
A 65,58 5,25 5,00 736,90 745,50 429,20 316,30 2,33 3,45 11,47 63,63 73,81 24,90 26,19 49,979 13,101 859,00 816,909 776,880 6,70 115,95 4,67 0,56 4 7,13
B 67,60 5,80 5,50 762,35 765,50 439,05 326,45 2,34 3,45 12,64 63,45 73,60 23,91 26,40 50,646 13,032 1345,00 1250,850 1163,291 5,85 198,85 4
Average 749,63 755,50 434,13 2,33 26,29763 50,313 13,066 970,085 6,28 157,40
A 67,60 6,36 6,00 766,20 769,30 442,60 327 2,35 3,45 13,85 63,38 73,52 22,77 26,48 51,048 12,963 1221,00 1440,780 1315,432 5,40 243,60 4,67 1,61 4 2,49
B 66,30 6,92 6,50 754,65 757,10 433,30 323,80 2,33 3,44 14,91 62,65 72,67 22,44 27,33 52,820 12,894 795,00 938,100 816,147 6,70 121,81 4
Average 760,43 763,20 437,95 2,34 26,905 51,934 12,928 1065,790 6,05 182,71

Keterangan :
t = tinggi benda uji (b.u), mm jeff = (100-b).g % n = rongga thd camp. (VIM) =
a = kadar aspal thd agregat, % B.J.agregat eff
b = kadar aspal (dan aditif) thd campuran, % o = nilai pembac. Arloji stabilitas
c = berat kering b.u. (sebelum direndam), gr jcur = (100-b).g % p = profing ring Suhu pencampuran : ± 160° C
d = berat kering b.u. keadaan SSD, gr B.J.agregat bulk q = stabilitas = p x koreksi tebal b.u., kg Suhu pemadatan : ± 140° C
e = berat b.u. didalam air, gr k = kadar rongga dalam camp. = (100 - i - jeff), % r = kelelehan plastis (flow), mm Suhu waterbath : 60° C
f = volume b.u. = d - e, cc l = kadar rongga dalam aggr. (VMA) = (100 - jcur), % MQ = Marshall Quotient, kg/mm
g = berat volume b.u. = c/f, gr/cc
h = B.J.maksimum teoritis, gr/cc m = rongga yg terisi aspal (VFA) = (VMA -VIM) x 100% B J. Aspal 1,016 (A)
i = volume aspal = bxg ,% (VMA) Campuran agregat
B.J.aspal B.J.bulk 2,999 (C)
B.J.semu 3,958 (S)
B.J.efektif 3,478 (E)